PR Delivery date as project finished date

HI,
When user is generating Service PR from project system, its delivery date is taken as a Finished date of the project. Further SAP is not allowing to edit this date.
Can anyone let me know why it is happening. My user do not want delivery date as finished date of the project, he would like to put his own delivery date.
Kindly  suggest
regards
Sanjay Karnekar

Hi,
I think that the date comes from the scheduling of the network activity. Go to the project builder and then display the material. On the Purchasing Data tab change the settings from 'Align the finish date' to the 'Manual requirements date'.
If you'd like to change this setting globally, you need to maintain the customizing under
Dates -> Scheduling of networks -> Specify scheduling parameters
Cheers, Aleksandra

Similar Messages

  • Update SharePoint list with project finish date on Project.Updated event

    Hello,
    I want to update a column in a SharePoint list with the project finish date when a project is updated on Project Server. My OnUpdated event handler is being called ok, but if I change the project start date Project Server runs an asynchronous republishing
    on the project, and my event handler ends up being called before the finish date is update by the republishing job, so the code writes the "old" finish date on the SharePoint list. The solutions I could think of are:
    Identify the republishing job on Project Server queue, pool the queue waiting for it to finish, then read the finish date and update the list item in SharePoint.
    Include a custom job on Project Server queue after the republishing job, that reads the finish date and update the list item in SharePoint.
    I don't know if any of the solutions are feasible and how to implement them. Has anyone coded something like this and/or have a better solution?
    Thanks,
    GB

    I vote for the option 1.
    I did for one of my event handler..Did you try "on published" event?
                projectSvc.QueueUpdateProject(jobUid, SessionUID, projectDss, false);
                //WaitForQueue(q, jobUid);
                jobUid = Guid.NewGuid();
                projectSvc.QueuePublish(jobUid, e.ProjectGuid, false, string.Empty);
                jobUid = Guid.NewGuid()
    Cheers. Happy troubleshooting !!! Sriram E - MSFT Enterprise Project Management

  • Req. delivery date and plan order finish date relationship

    Dear Experts,
    I have a question on setting the req. delivery date and plan order finish date relationship. Now, I want the plan order finish date is one day before the req. delivery date, is it possible to set it in configuration? Please advised! Many thanks!
    Regards,
    Matt Yim

    Matt,
    Please use a schedule margin key(SMK) in the material master MPR2 view which has float after production defined as 1day.
    If there are no SMK with that defination then you can define you own in customisation and assign the same in the material master. (SPRO--->Production ->MRP->Planning ->Scheduling and Capacity Parameters->Define Floats).
    Regards,
    Prasobh

  • Scheduling as per given project finish date

    I need to know if it is possible to arrange the project structure to do below described scheduling.
    Urgent reply will be highly appricated..
    thanks,
    he.
    I would like to give the "project finish date " ;
    I would like p6v7 would schedule such that ;
    - project finish date would be the date that I gave,
    - all activity dates would be defined accordingly even if they should have been start and/or finish before project start date.
    I should say that there is not any resource / cost assignment. Just activities/ original durations/ and relationships have been entered.

    user9166529,
    By you saying "project finish date" I have to assume that you have some sort of mandatory completion date such as a contract deadline.
    Or do you mean that you want to add a date constraint to the project finish date such as "must finish on or before" your date of completion?
    If needed, you could even apply a "mandatory finish" date constraint (not highly recommended).
    On the other hand, by building your initial schedule you will be able to determine your planned finish date by tracing your longest path. If this completion date does not meet your needs you then would need to adjust your scheduled activities (durations) to fit within your planned finish date.
    After settling on your initial schedule, save it as a baseline (copy) in order to perform periodic comparisons between your original (baseline) and the current (real time) schedules. The result of performing these comparisons will produce your schedule variance data.
    Hope this helps,

  • Change delivery date on sales order -- change of Billing date on item

    Hi,
    We are trying to change a delivery date for a sales order's item, if we do so normally the billing date on that item's billing tab will change automatically also.
    Now, for a specific sales order the billing date in the billing tab is not changing.
    We compared 2 sales orders .. the same statusses - no blocks - ... and with one it works (changing of the billing date) and with the other it does not work..
    Please help !
    thanks a lot!

    Hi,
    Check the following.
    If invoice dates are defined for the customer, the system proposes the billing date from the invoice date calendar. If no invoice dates are agreed, then the actual goods issue date is formed on the basis of delivery related billing. In order related billing, the billing date of the order forms the basis of the billing date.
    If you are billing services, the system proposes the date of services rendered. You can change the date manually in the sales document.
    If you are using a billing plan to bill a project, the system can propose billing dates for the billing plan on the basis of planned or actual dates in the corresponding milestone.
    In a billing plan for a maintenance or rental contract, you can specify rules by which the system determines billing dates on the basis of other dates in the contract.
    Regards
    Nadarajah Pratheb

  • Unable to change requested delivery date in the sales order at item level.

    The issue is when I create order with one material (linked to network and project is created automatically in the background), I am able to change (in change mode) req delivery date for an item, but when I create order with 2 materials (linked to network and project is created automatically in the background), I can not change (in change mode) the req delivery date of any item. Req delivery date is then copied from the header req delivery date.
    Is this a standard SAP functionality or a defect?

    Req del date is the date requested by customer and  can be changed at item level. Probably the confirmed date in the schedule line is derived from the network scheduling after ATP check. (ATP check is not activated in this case)
    I am able to change the req del date at item level if there is only one item (Linked to network) and not when there are two line items (Both are linked to 2 diff networks belonging to same project)
    I tried to change the date in the network, scheduled and saved but that didnt change the date in the sales order. On the contrary, if I run ATP check, netowrk dates get back to original dates derived from sales order.

  • Sales Order - How to make Delivery Date default to Lead Time?

    My scenario is this:
    - We have items that go thru several production stages before it is a finished item that can be sold.
    - Each production item has its lead time loaded.
    - I would like the delivery date of a finished item to equal the sum of the productions items lead times.
    I dont want my sales people to have to look at calendars are calculate how long until something is ready for delivery.
    I would like my sales orders delivery date to default to a date that sales people can use.
    Is this possible? I would think this would be part of core functionality but I do not see this.
    Thank you,
    John Sefton

    John,
    Knowing what Items are added to the Sales Order at the time of entry would not be possible without SDK since the line level details are stored internally in temp location.
    Only on Submitting the Sales Order would it be possible to calculate the date.
    Let me know how you would want to move on this
    Suda

  • PR Delivery Date Issue from Maintenance Order

    Hi All,
    We have a scenario -
    - Create Maintaince Order (IW31)/Assign Basic Start Date and Basic Finish Date.
    - Auto PR Generated from Maintenance Order but the delivery date in PR is Basic  Finish Date.
    My client's requirement is Auto PR will pick up the Delivery date as Basic Start Date. What settings do we need to Do for this scenario and on wht basis the delivery date is decided in PR wrt to Maintenance Order?
    Regards
    Pankaj

    Hi SAP Gurus,
    Any updates how to solve this issue?
    Regards
    Pankaj

  • Delivery date as per requirement

    We have MRP configured for Finished goods External procurement
    MRP is happending as per defined parameters but the problem is "Required Delivery date" is coming as per Lead time.
    In case the product is required early, system is just asking for Rescheduling IN
    We want "Required delivery date" should be as per material requirement,
    If requirement is in August
    and lead time is 60 days, if we enter the Independent demand in July and run mrp system on 5th July system generates PR with delivery date as 5th of Sept  , as per lead time, and gives exception message to reschedule the same on 1st Aug
    We want this to be having Delivery date as 1st August in PR itself
    Please guide which settings are to be changed

    Dear Sir,
    This is standard functioanlity to give the   delivery date on the basis of RLT (Replensih Lead Time)/
    However , i think you can manuualy chnage the date of delivery date in purchase order itself
    Regards
    Bhupendra Singh

  • Confirmed delivery date on sales order

    Dear specialists,
    I have a problem and I don't know how to solve it ...
    When we create an order, we automatically create purchase requisitions ... The confirmed delivery date on the order-item is calculated by adding the value of field eban-plifz to the delivery date ... We manually change the value of eban-plifz in user-exit ZXVVAU16 and the confirmed delivery date is (re-)calculated automatically ... This works fine, except when we create a new order-item and go through the logic for the first time ... The first time we press enter and we see the screen 'Purchase order scheduling', the date is wrong ... I found that the value of eban-plifz is refreshed in function ME_REQUISITION_PRESTEP in the form neue_pos_banf - bezugsquelle_3 ...
    My question is if there is a possibility to change the value again in a user-exit before we get the screen 'Purchase order scheduling' ???
    Hopefully someone can give me an answer ?
    Greetz,
    Kurt.

    Hi,
    i have a similar problem. You talk about user-exit ZXVVAU16, but this is the project (CMOD), don't?. Can you tell wich enhancement do you use to change availability sales order???
    Thanks
    Edited by: RODRIGO PEREZ on Feb 20, 2009 2:24 PM

  • Material availability date can not be after the delivery date

    Dear Experts,
    we are using the following scnario,
    1. Once the user creates the sales order, automatically system creates PO in the background.
    we have created Bapi program for creation of Background PO in SD User Exit.
    The following issue occurs in Prd, DS1, QS1 server, We have done Technical upgradation project, Now when we creates sales order automatically po created with error message of Material availablity date can not be after the delivery date. even sales order no also not updated in the PO.
    QAS server (without technical upgrade) i refered the same input parameter and used the same and create the sales order system generates PO automatically without error message.
    Does any one can through lights on this issue,
    Thanks and Best Regards,
    Muralidharan S

    Hi
    The dates are determined due to shipping and transportation scheduling settings. So check whether the shipping and transportation scheduling is being performed as per the cofiguration settings after Technical upgrade. Since the MAD date should not be after Delivery date but it seems that the dates are not determined properly.
    Also check the Transit  time, Loading time, Pick/Pack time and Lead time are retained as same as before the technical upgrade. Use the QAS server settings to validate the settings in other servers.
    Regards
    Rajkumar K

  • Delivery date in PR created through MO

    Dear PM guys,
    When I create PR for Exetrnal services/Non-Stock through ME51,on saving system will give information Can delivery date be met? and we can change the date if needed.When I try to create PR through MO,system is not giving any info on delivery date and its taking Basic finish date as delivery date.Is there is any way to enter/change the delivery date while creating PR through MO.
    Regards
    ISWARI

    hi iswari
    you can have different dates for PR,but it is based on your settings in customization ( you have to deselect the collective PR req for the order type, so that system will create individual PR to individual operation or non stock material)
    then as i said before make the schdulling parameters as Adjust basic dates to the operation ,then in the maintenance order create 2 operation and assign each one to different materials and in the operation detail screen specify the dates required.hence system will create individual PR for each operation/material and dates will be picked from the operation
    regards
    thyagarajan

  • Userexit which determine the confirm delivery date in order creation

    Hi,
    I need to obtain the ATP details which contain confirm delivery date of all the lineitem. The BAPI BAPI_MATERIAL_AVAILABILITY determine the material availability date but not the Confirm delivery date. But I require the Confirm delivery date which will be calculated based on picking, working day ...
    Is there any userexit available to determine the Confirm delivery date from the material available date.
    Pls help..urgent..
    Thanks
    Suresh Kumar

    Hi,
    The userexits related to the material availability during sales document processing are:
    User Exits For Availability Check
    The user exits named here are planned for projects that are to be carried out in agreement with SAP development as they may only be used in consultation with SAP. SAP provides no guarantee if they are used without our advice!
    USEREXIT_PLANT_SELECTION in program RV03VFZZ is an exception to this rule (see below).
    User exits in program FV45VFZZ
    USEREXIT_ADD_FIELD_TO_HEADER
    USEREXIT_ADD_FIELD_TO_LINE
    User exits in program FV45VFZY
    USEREXIT_DELIVERY_GROUPS
    USEREXIT_MVERF_INIT
    USEREXIT_QUOTA_KEY_VALUE
    User exits in program RV03VFZZ
    USEREXIT_AVAILABILITY_IN
    USEREXIT_AVAILABILITY_OUT
    USEREXIT_DARA_REFRESH
    USEREXIT_PLANT_SELECTION
    This might be of some use.
    Thanks and regards,
    Satya

  • Use BAPI_SALESORDER_CREATEFROMDAT2 with delivery date in Header

    Hi all,
    In my current project I try to use BAPI_SALESORDER_CREATEFROMDAT2 to create the SO ,
    I can create the SO without setting delivery date in header.
    but after I set the delivery date like following, the error message occured. Could someone help me?
    ORDER_HEADER_IN-REQ_DATE_H = '20110330'
    ORDER_HEADER_IN-DATE_TYPE = '1'
    I try to add the requirment delivery date in schedule line ,but fail too.
    ORDER_SCHEDULES_IN-REQ_DATE =  '20110405'
    ORDER_SCHEDULES_IN-DATE_TYPE =  '1'

    Nothing special,
    TYPE: e
    ID: V4
    NUMBER: 219
    MESSAGE :Sales document  was not changed
    I  try to see the log in ST22 too. but nothing in there.
    I also try to use BAPI_SALESORDER_SIMULATE to generat SO ITEM to fill
    the ORDER_ITEMS_IN (after some data formate translated) but, still got the same result.
    My codes in VS as following:
    when without delivery date setting, the SO is OK, So I belive the data transport is fine.
    The promble is mainly occur in BAPI.
                   IRfcFunction function = repo.CreateFunction("ZCMT_RFC_SO_CREATE2");
                    //importing parameter
                    IRfcStructure salehd = function.GetStructure("ORDER_HEADER_IN");
                    IRfcStructure salehdx = function.GetStructure("ORDER_HEADER_INX");
                    //Tables
                    IRfcTable returntable = function.GetTable("RETURN");
                    IRfcTable item = function.GetTable("ORDER_ITEMS_IN");
                    IRfcTable itemx = function.GetTable("ORDER_ITEMS_INX");
                    IRfcTable partner = function.GetTable("ORDER_PARTNERS");
                    IRfcTable schedule = function.GetTable("ORDER_SCHEDULES_IN");
                    IRfcTable schedulex = function.GetTable("ORDER_SCHEDULES_INX");
                    //IRfcTable condition = function.GetTable("ORDER_CONDITIONS_IN");   //commented
                    //IRfcTable conditionx = function.GetTable("ORDER_CONDITIONS_INX");   //commented
    //* Build order header
                    salehd.SetValue("DOC_TYPE", "ZOR");       
                    salehd.SetValue("SALES_ORG", "2011");    
                    salehd.SetValue("DISTR_CHAN", "01");     
                    salehd.SetValue("DIVISION","00");       
                    salehd.SetValue("REQ_DATE_H", "20110412");
                    salehd.SetValue("DATE_TYPE", "1");
                    salehd.SetValue("PURCH_NO_C", "test");       
                    salehd.SetValue("PRICE_DATE", "20110331");
                    salehd.SetValue("PMNTTRMS", "0002");       
                    salehdx.SetValue("UPDATEFLAG", "I");       
                    salehdx.SetValue("DOC_TYPE","X");       
                    salehdx.SetValue("SALES_ORG","X");    
                    salehdx.SetValue("DISTR_CHAN","X");     
                    salehdx.SetValue("DIVISION","X");       
                    salehdx.SetValue("REQ_DATE_H", "X");
                    salehdx.SetValue("DATE_TYPE", "X");
                    salehdx.SetValue("PURCH_NO_C", "X");       
                    salehdx.SetValue("PRICE_DATE", "X");
                    salehdx.SetValue("PMNTTRMS", "X");       
    //* Build order item(s) - Only 1 is used in this example
                    item.Append();
                    item[0].SetValue("ITM_NUMBER", "000010");       
                    item[0].SetValue("MATERIAL", "HMS690C-T002-A1");       
                    item[0].SetValue("PLANT", "2011");      
                    item[0].SetValue("TARGET_QTY", "3.000");      
                    item[0].SetValue("SALES_UNIT", "PCS");      
                    itemx.Append();
                    itemx[0].SetValue("UPDATEFLAG", "I");       
                    itemx[0].SetValue("ITM_NUMBER", "000000");       
                    itemx[0].SetValue("MATERIAL", "X");       
                    itemx[0].SetValue("PLANT", "X");      
                    itemx[0].SetValue("STORE_LOC", "X");  
                    itemx[0].SetValue("TARGET_QTY", "X");      
                    itemx[0].SetValue("SALES_UNIT", "X");      
                    schedule.Append();
                    schedule[0].SetValue("ITM_NUMBER", "000010");
                    schedule[0].SetValue("SCHED_LINE", "0001");
                    schedule[0].SetValue("REQ_QTY", "3.000");
                    schedule[0].SetValue("REQ_DATE", "20110331");
                    schedule[0].SetValue("DATE_TYPE", "1");
                    schedulex.Append();
                    schedulex[0].SetValue("UPDATEFLAG", "I");
                    schedulex[0].SetValue("ITM_NUMBER", "000010");
                    schedulex[0].SetValue("SCHED_LINE", "0001");
                    schedulex[0].SetValue("REQ_QTY", "X");
                    schedulex[0].SetValue("REQ_DATE", "X");
                    schedulex[0].SetValue("DATE_TYPE", "X");
    //* Build partner information
                    partner.Append(2);
                    partner[0].SetValue("PARTN_ROLE", "AG");       
                    partner[0].SetValue("PARTN_NUMB", "C10006");       
                    partner[1].SetValue("PARTN_ROLE", "WE");       
                    partner[1].SetValue("PARTN_NUMB", "C10006");

  • Loading time - Delivery date question

    Hi,
    My delivery date is Loading date + 1 day even though I have specified the loading time hours to be zero for my shpping point.
    All of the finished products in my company require 15 minutes or less to load so how can I make the Loading date = Delivery date?
    Please help.
    Sincerely,
    Puja

    Puja,
    Lead time in VOV8 only affects the proposed REQUESTED delivery date in the main screen of VA01.  It has no impact on the actual scheduling of the shipment and the delivery.
    I will assume that you are not using APO for shipment or delivery scheduling.
    Your screen print indicates that you have zero days allowed for picking, packing, loading a shipment.  You screen print indicates that no route was determined.
    Your request to have loading date = delivery date is uncommon.  Delivery date is generally accepted to be the date that you deliver the parts to the destination (customer location).  I suppose if the customer is next door, it is not much of an issue.  In this case you could just turn off Transportation scheduling altogether.
    Check out all the configuration under Logistics Execution> Shipping>Scheduling>Delivery Scheduling and Transportation Scheduling.  Examine each item in this block for details of how your dates are being determined.  Make changes to fit your business requirements.
    There are a number of factors that can affect transportation duration (difference between loading time and delivery time). Most of these are pretty well covered in https://service.sap.com/sap/support/notes/547961.  
    Rgds,
    DB49

Maybe you are looking for

  • Thunderbird crashes every time I try to attach a file

    Every time I try to attach a file Thunderbird crashes as does Firefox when I try to use the online e-mail program at Yahoo O/S is windows 7 below is the error report. escription: A problem caused this program to stop interacting with Windows. Problem

  • IPhone 4 randomly restating after updating to iOS 6.0.1

    When I updated to iOS 6.0.1, from iOS 6.0, my iPhone 4 started to reboot randomly. I have tried a restore, and I am not willing to start as a new iPhone either. It doesn't reboot often, just randomly, and when it does it takes 5-10 seconds to restart

  • Screen enhancement through enhancement framework

    Hi to all  experts, I have question can screen enhancements can be done using enhancement framework technology in ECC 6.0 Any link will help ALready searched in SCN couldnt find anything

  • Photoshop download trial

    Hello, I am also having trouble downloading the photoshop trial to my Macbook Pro. I can click on the download button but nothing happens - I have tried signing out and back in. I am not sure what's the best way to get the trial to commence downloadi

  • Creating an Invoice and generating and IDoc

    Hi All Can anyone let me know what are the prerequisites for creating an invoice, the transaction for creating an invoice and steps to create an Invoice using the transaction. I also want to know how to generate an Idoc from the Invoice related trans