Dear Experts,
I have a question on setting the req. delivery date and plan order finish date relationship. Now, I want the plan order finish date is one day before the req. delivery date, is it possible to set it in configuration? Please advised! Many thanks!
Regards,
Matt Yim
Matt,
Please use a schedule margin key(SMK) in the material master MPR2 view which has float after production defined as 1day.
If there are no SMK with that defination then you can define you own in customisation and assign the same in the material master. (SPRO--->Production ->MRP->Planning ->Scheduling and Capacity Parameters->Define Floats).
Regards,
Prasobh
Similar Messages
-
MRP Planned order finish Date calculation (Planned delivery + GR Proc.time)
Dear Gurus,
Currently in our system, when MRP runs, Planned orders are created and the order finish date is calculate based on Purchasing processing time OMEW + Planned Delivery time from Material Master + GR processing time from material Master.
My business requirement is that, system has to take only Planned Delivery time + GR Processing time and exculde Purchasing PRocessing time.
I cant make it Purchasing Processing time as ZERO - because this is used for other Purchase orders and KPI will be affected for procurement department
Now we are going to Automate the Purchase orders for Materials - if outline agreement exist.
How to make system settings for a MRP run, the Planned order finish date - should consider only Planned delivery time from Material master + GR Processing Time ( it should exculed Purchasing PRocessing time). Is it posssible? if not by any user exit, ABAP coding should be done?
gurus please advice!
BADI : MD_PLDORD_CHANGE - is this can be used?
Please advice
Regards
RS
Edited by: RS on May 18, 2010 10:22 AM
Edited by: RS on May 18, 2010 10:33 AM
Edited by: RS on May 18, 2010 1:34 PMLet me check, if I can find a way to paste /afs/md04 (AFS Envirnoment) screen shot . But in the mean time following are the
details
IHPT - 12 days
GRPT - 0 days
SMK - 000 (Op Period, Float After Prod., Float Before Prod.,Release Per. - 0 days)
Thanks, -
Delivery date and sales order creation date
Dear all
Can you please explain the relation between delivery date and sales order date. In my case i can create delivery with delivery date as before the sales order date... how it is possible that i can create delivery before the sales order date.??
Please explain.........
Warm Regards
Inder PalHi,
Sales order date: Date on which the customer officially places an order to your company.
All the commitment and product allocation counting starts with reference to this date.
e.g. customer says that the goods are required from 20 days of placing order, then from this date the calculation starts.
Delivery date: Date on which after the system goes through material availability date, replenishment time, calculates the date on which physically the goods can be delivered to the customer.
e.g. customer orders 100 qty of material X in 15 days, you will hve to check this delivery date through availability check which can be done in sales order and also delivery.
payment date is based on this delivery date.
regards,
Siddharth. -
Actual Goods Issue date and Planned Goods Issue date
Dear All
we are loading the january,08 sales invoice from the legacy system to SAP system through BDC program.
for this at the time of PGI we are using Actual GI date as month of January, 08 and keeping planned GI date as the system date and at the time of creating sales order, delivery, we are not changing the material available date, loading date, delivery date, at the item level and system taking automatically based on the current date
when doing PGI system accepting and creating PGI document and billing also creating based on this delivery.
But dose it give problem in Inventory managements and FI in future, then what would be the right procedure to uploading the back dated invoices in the system.
Please give me solution for this issue, or what we are doing is the right procedure.
Thanks In advanceFor those who might come across this note, the design issue was solved by incorporating Rule Groups.
Problem:
Need to have 2 different Date references for 0calday, based on the key figures. For example for Sales key figure date it would reference to Actual GI Date. But, for Intake key figure I needed the date reference to be Planned GI date.
Solution-- applied to the transfer rules of the desired cube:
1. In the starndard rule group delete the transfer rule for the appropriate key figures. in this case (sales key figure)
2. In the same rule group map all time characteristics from the cube to Planned GI date from DSO
3. Create a new rule group in the transfer rule between the DSO and the Info Cube
4. In the new rule group, create a new rule for the appropriate key figure i.e. sales
5. In the new rule group, Map the date/week/month/fiscal period to Actual GI date
6. save/activate
This solution eliminates the need for changing the data model, which makes everything almost transparent to the report users.
Hope this helps someone.
Edited by: Babak Shafiei on Dec 12, 2008 5:23 PM
Edited by: Babak Shafiei on Dec 12, 2008 5:24 PM -
Material Availability Date and Corresponding Basic finish date
Hi experts,
I have one requirement from my Business for updating Basic Finish date based on the Material availability date
Requirement goes like this, When we enter a Component of 100 qty in the service order , if stock is not available we get system status as MSPT and IWBK we can see how much quantity confirmed
But i dont see any table or report which shows when this material can be available for further delivery. Based on the next available material date i have to change the basic finish date in the service Order
Please let me know if you any report available for this or any standard approach. I want to know if any exist to leverage this functionality and logic how to get this accomplished
thanks
sarvanSarvan,
You would need to perform this check when saving the work order as there could be multiple components all with differing ATP dates.
But a development could do something like:
Read all active/open components/materials on the work order
Determine the availability data for each component/material
Determine the latest of the above dates
Apply this date to the order Basic Finish Date
You would need to ensure your scheduling parameters do not set this date back to its original value (OPU7).
You could achiev the above through user-exit IWO10009 (SMOD) or BADI WORKORDER_UPDATE (SE18).
PeteA -
How to fetch post goods issue date and sales order creation date
Hi All,
How to find out the difference between SD Sales Order Item Creation Date and final Post goods issue Date. I would like to know how to fetch those dates and what is the relationship between the tables from which i will get the dates.
Please let me know the solution .
Thanks in advance.Hi,
Sales order creation date is when u raise a sales order in favor of the customer using VA01.......using ATP logic system purposes the material availability date....
after saving ur sales order...when u raise the Delivery using VL01n w.r.t to OR...than u have to perform picking ....In the picking Tab...specify the amount to be picked than press Post Good Issue....means the goods left the company premises ..
You can the fetch the values using tables- Use T code SE12 or SE16
Vbak-----order header
Vbap-----order item
Vbek-----order schedule line
Likp-----Delivery header
Lips----Delivery item -
Difference between P.O.date and P.O.created date
Hi,
Could you tell me difference between purchaseing doucment date and purchase order creaed date.
Because some time in my org. po created after GR means in past date. So there is difference between
po date and po created date. where this po created date is maintained in purchase order
Thanks and Regards
AnilDear Anil,
Please check table EKKO with ta SE11.
Created Date => EKKO-AEDAT
Date on which the record was created
Document date => EKKO-BEDAT
Date on which the purchasing document was created
EKKO-AEDAT = Date on which the record was created
and also "Created By" also recorded automatically
by system.
Document date or EKKO-BEDAT normally default as
today when you create the PO via ME21N. This field
appear at top right of the screen. However this date
can be change to any date that required.
Thanks
Loke Foong -
How Production Order finish date and time is being comptued by SAP?
Hello Expert,
How Production Order finish date and time is being comptued by SAP? for example, we create a Production Order via CO01, the basic start date is 29.09.2008 and time is 04:00 it gives us basic finish date is 29.09.2008 and time is 13:28.
how does SAP compute the time 13:28 as it finished time
Please explain me briefly.
Thanks
RyanHello Guys,
When we create Production Order in R/3 the time is calculated by routing but it is extended at SetUp machine time. It is not correct?. SetUp imachines time used only for first Production Order for the same product and it is plan manually, for others Production Order we need calculate time for production without SetUp machine time being pick up to compute finish time. how could we achieve this? only those Machine time will be check.
thanks -
Basic dates and production dates in planned order
Dear all,
I have a planned order (for material A) which has "order finish date" same as "End of production date".
I have another planned order (for material B) where "End of production date" is eariler than "order finish date".
Scheduling margin key is same in both the cases.
Why they are different? Can you please help?
Regds.,
ChaitanyaDear
Please Check in the MRP 2 And SchedMargin key it defines the floats
SCHEDULING MARGIN KEY
Takes effect only for Lead Time Scheduling
Configure scheduling horizon OPU5
which lead time scheduling and capacity planning should be carried out. scheduling horizon is the period in working days. If a planned order has its basic start date within this period in future, lead time scheduling is carried out using the selected routing.
The production times are calculated from the float times of the scheduling margin key in the material master record and the time from the individual operations.
If the planned order has its basic start date further in the future than this scheduling horizon, the basic dates are calculated from the in-house production times in the material master and are transferred to the production times
with Regards
Pushpalas -
Process Orders and Planned Orders data
Hi,
I am working on extracting process order and Planned Orders data into BW. I could not find any standard DataSources available for my req, so I want to develop generic extractor. the main key figures are Actual Labor and Machine Hours, Target Labor and Machine hours.
Please help me if there are any standard datasource available or ECC tables to pull the data or any standard function modules available.
Thanks,
ReddyHi Sanath,
Thanks for your reply. I want to pull Actual Machine hours, Target Machine hours, Actual Labor hours and Target Labor hours.
these fields are not there in PLAF table.
I am looking for a table or datasource which can give those details.
Thanks,
Reddy -
SNP planned order availability date difference between APO and ECC
Hi,
I have observed that SNP Planned order availability date is not matching between APO and ECC. Details are as follows.
I ran SNP Optimizer with bucket offset of 0.5. After publishing the optimizer created planned orders to ECC, only start date is matching.
Example:
I am using PDS as a source of supply.
Fixed production activity in SNP PDS is 1 day.
GR processing time: 3 day
After running optimizer planned order is created with dates explained below.
Start date/time: 09.05.2011 00:00:00
End date/time: 12.05.2011 23:59:59
Availability date: 16.05.2011 00:00:00
Because of bucket offset defined as 0.5 optimizer planned order availability is start of next monday.
After publishing this planned order to ECC dates on the planned order is as follows.
Start date: 09.05.2011
End date: 09.05.2011
Availability date: 12.05.2011
I have not maintained any scheduling margin key in ECC. Also if I dont define the GR processing time, planned dates between APO and ECC always match. Can anyone explain the impact of GR time on the availability date.
Regards,
VenkatHi Venkadesh,
What's "state stamp"? Do you mean different time zone?
note : 645597 mentioned by Nandha is very helpful:
In standard, CCR will use duedate - "the available date of the output product".
Nandha's words "In SAP APO, if the receipt date of the primary product deviates from the
end date of the last activity of the order, the receipt date
always identifies this as inconsistent. You cannot rectify
inconsistencies of this type by using CCR."
I guess in your PDS or PPM, the output product is not assigned to the End of the last activity. Someone changed it?
Please CIF the PDS or PPM again.
If you really want to apply a note, please use note 815509 as you're using planned order,
and system will use order end date in CCR instead.
GR time is always considered. BR/Tiemin -
Fieldes planned delivery date and actual good recipt date for SAP QUERY
Hi Gurus
I am changing sap query. I need to find two fieldes : planned delivery date and actual goods recipt date
I dont know MM tables, do you know wrhere are?
in table EKPO i don't find the fieldes.
Thanks in advanceThank a lot!
Regards -
MRP run - misalignment for planned order between Date and Production Date
Hi All,
We've just integrated SAP for a new plant.
The MRP runs based on Routing Lead Time for Make materials instead on Material Master Lead Time, for Capacity Assessment purpose.
When requirements dates lay in the past, MRP performs forward scheduling starting from current date and properly defines Production End Date according to Routing.
By checking MD04, for the proposed Planned Order, the basic date is same as Current Date (= same as Requirement Date) instead of being same as Production Date.
It works as it if checks stil the MAterial MAster LEad time instead of Routing. In fact if I updated the LT of MM the MD04 provides the right Date.
For future requirements, the MRP works properly, by having basic dates (both start and end date) aligned with Production Dates of Planned Order.
How can I do the alignment w/o updating In House Production LT?
Thanks,
DHi Caetano,
we have already done this configuration in OPU5 but it doesn't provide any benefit.
Below how we configured it:
Scheduling level: Via detailed scheduling
Adjust dates: adjust basic dates, adjust dep. reqmts to operation date
For capacity scheduling: Always basic dates, dep. reqmts to operation dates
Scheduling type: Backwards.
Regards,
D. -
Hi,
We have created a Intra plant STO (plant to plant in the same company code). The planned delivery date is 4 days. So if I create a STO today (27th march), the delivery date is 31st march (excl Saturday and Sunday).
During delivery creation, the loading date, transportation date and planned date are also coming as 31st march. The route determination for the given shipping point and route shows 2 days for transit and 4 hours for pick pack. There is no loading time maintained for the given combination.
Can you please advice why are the dates coming the same as delivery date during delivery creation without considering the duration maintained in route determination ?
Thanks!!!
AnujaHi,
This is a standard behavior of SAP in case of Stock Transfer PO.
If you want that the delivery date of receiving plant be transferred to supplying plant, please use BADI MD_STOCK_TRANSFER.
Hope this helps.
Regards,
Prashant -
Planned order start date & finish date
Dear All ,
I am running MRP for finished material ,
But i am getting Planned order start date & finish date are coming same (todays date ). But when i am converting the order then proper scheduled dates are coming .
Why for the Planned order the scheduled dates are not coming ?
RegardsHi Venky,
Pls try to understand how MRP works
After MRP planned orders are created for the requirement(in house)
In the planned order stage -basic dates are deteremined
For the determintaion of basic dates system check the in house production time/replenishment lead time maintained in the material master
For your requirement you maintain lot size dependent in house production data in the work scheduling view & check
You have to key in data in set up time,processing time ,base qty etc
Hope it is clear
Rgds,
SVP
Maybe you are looking for
-
In Classic Scenario SRM 5.0 with ECC 6.0, how can I create an ECC Contract with a requirement from the Purchaser's Worklist ? Do I use the Global Outline Agreement? If so, what are the config steps ? Full points assured. Thx. Raja
-
Why is Quick Selection Tool taking forever on MACBOOK PRO
Just recently my quick selection tool is obnoxiously slow. It's driving me crazy. Nothing has changed on my computer and I optimized my preferences as in another thread regarding this issue but on a windows computer. I'm not sure what's going on b
-
Dear Experts, We have a datasource in R/3 i.e 0FI_AP_4. The extract structure is DTFIAP_3. We have enhanced this datasource with some fields & have written some ABAP code in cmod to fetch the data into the enhanced fields.In this process some request
-
SD Customer Order Extraction:
Hi, 1) what to take better for SD Customer Order Extraction: SD Order Header Status 2LIS_11_VASTH, SD Order Item Status LIS_11_VASTI, SD Sales: Order Delivery 2LIS_11_V_SSL, or: 2LIS_11_VAHDR-Sales Order-Header Data 2LIS_11_VAITM-Sales Order-Item Dat
-
Srervice Market Place System list not found
Dear All, IN service market place i can not found system list when i am going to put a message to SAP, but i can see system list in Data Administration. so i can not put message on service market place, please guide me, Thanks, Bhavesh