Problem in Project progress

Hi,
I am facing problem in Project progress report CNE5.
System is calculated 300 % poc in Adjusted aggregated actual POC & Aggregated actual POC field only after full confirmed the activity (Degree of Processing is showing in report as 100%).
If I confirmed 50 % then system is showing above value 0% .
Also while CNE1 system is taking default method as :SAP 0-100, so i changed it into activity by 00006 (Work) then system calculate the Progress but only after full confirmation, but again it is 300%. which should not.
The configuration settings are as
1. Progress Version: -
Progress Version : 100
Plan Version          : 0
EV Basis                 : 1 ( Cost Plan)
POC weighting      : 4 Work, Basic ( Active Project)
2. Group of Progress version:-
Controlling Area & 1
3. Assign Progress Versions to Group Progress Versions:-
Controlling Area, 100 & 1
4. Define Statistical Key Figure for Percentage of Completion:-
                                                 Usage               SKF (with unit of measurement= %)
       Controlling area                   1 10
       Controlling area                    2 20
       Controlling area                    3 30
5. Define Measurement Methods:-
Measurement method :0000000006 (Work)
Meas. technique  : E ( Degree of Processing)
Max POC                : 100
6. Define Measurement Method as Default Value
Progress version(100),  Object Type (2:Activity, Internal Processing), Plan/ Actual( 1 &2 :both), Method (00000006 :Work)
7.Maintain Assignment of Cost Element Group
Cost element (PS) , Default selection( Yes) & cost element group(PS_PROP)
I hope above information is sufficient.
My problem is system is calculating poc only after full confirmation but i want at partial confirmation. Also after full confirmation poc is showing 300% which i want 100%.
Regards,
AVI

Hi Experts,
I am waiting for your valuable inputs.
Regards,
AVI

Similar Messages

  • Problem with the progress line in MS Project

    Hi there,
    I have a question about the progress line in MS Project. 
    My boss asked me to see how far we were with the work, so I inserted the column '% Complete' and then the progress line.
    Now my boss has a problem with the layout and I don't know how the fix it. The problem is at line 43 and 44, where the progress line indicates that we are behind on that group of tasks. But is it possible for the progress line to not indicate it on lines
    43 and 44 but only on lines 45 to 50? So my question is if it's possible to make the progress line go down (vertically) over line 43 and 44 instead of jumping to the back? 
    It would be much more simple if I could insert lines 43 ad 44 as text but not as a task, so that it just counts as a title of some tasks but nothing more than that. Is that possible in Project?
    (Lines 45 to 50 are subtasks for line 44, and 44 is a subtask for 43. So line 43 is the main task.)
    Normally there was a picture here but I couldn't upload it because my account is not yet verified... So hopefully you can understand the problem with the text. 
    If anyone could give my some advice or the solution, that would be great!
    Thanks in advance!

    Hi Thunderbal66--
    Basically your activity 43 is late because the sub tasks are also late. Thus MS Project shows the situation by moving the progress line backward. The progress line is automatically displayed based on your project progress, there is no way to manually change
    it unless you update your project.
    I think the question is not there. This is more a matter of project governance and transparency: why not showin that a project is late when it is late and taking the appropriate corrective actions?
    Hope this helps,
    Guillaume Rouyre, MBA, MVP, P-Seller |

  • Project Progress Catch-up Plan

    Dear PS Friends,
    I would like to know if any of you have worked on Project Progress Catch-up Plan.
    Basically, it is the third dashed-curve which comes in a project progress graph of plan vs actual to cover u2013up the delay.
    Below is an example to explain this.
    M3 being the current month.
    Months     M1     M2     *M3*     M4     M5     M6     M7     M8     M9
    Plan PoC     0%     12%     20%     35%     42%     52%     60%     72%     90%
    Actual PoC     2%     7%     12%                              
    Catch-up               12%     18%     24%     40%     52%     72%
    If yes, please let me know and also how we can implement in SAP PS.
    Thanks in advance for your help!
    Regards,
    Aparna

    Hi Abdul,
    We are using the planned dates and actual dates spread over duration to calculate the monthly PoC.
    Now, if there is a delay i.e. there is a variance between planned and actual, then we need to reschedule   or u2018crashu2019 the project .
    This in turn will give us a new planning curve that would need to be followed  in order to make up for the delay.
    But the problem is that if we reschedule, the original plan is overwritten and hence, the u2018baselineu2019 vanishes.
    So the requirement is that in CNE1 , we should be able to calculate three set of dates u2013 original planned PoC ,actual Poc till date, rescheduled PoC.
    Given that progress version  supports  only  two set of dates, is there any way to achieve this ?
    Regards,
    Aparna

  • Problems using projects created in older versions of iMovie

    I have a few projects created in older versions of iMovie, as far back as version 2 as well as more recent versions. Most of those projects are finished and I want to burn them to DVD again, but a couple of them could bear a little touch up editing. These projects are precious movies of our kids and hard to replace. Although I could probably find the original video, I put many hours of work into creating these projects.
    In any case, when I open up an old project, I get a warning that goes something like this: "The project was saved with an older version of iMovie. Opening it in this version will cause it to be upgraded, which will make it unreadable by older versions. Are you sure you want to open it?"
    I clicked okay, thinking "sure, I don't need to play it in an older version. I have iMovie HD."
    However, now when I play my old iMovie project, there are a few problems. For example, one original movie's title was over black. When I play the movie, I get a completely white screen and no title. Also, in another movie, when viewing the movie in full screen, the transitions were replaced by a black screen (although the transitions were there when I viewed the movie in the iMovie window). Basically, there are problems cropping up here and there.
    I need to do some more experimenting with all this to more fully understand how many problems there are. I don't know if the projects I opened in iMovie HD are now "broken" since I "upgraded" them with iMovie HD (when prompted to save the project's changes when quitting, I said NO, don't save changes).
    I don't know if I should use older versions of iMovie to view and burn to DVD these projects. (I still have iMovie 2 and 3, but not 4 or 5. I don't know if older versions would even work on my Quad G5 with OS 10.4.7.) I also don't know if the older versions of iMovie would work with the current version of iDVD. How can I tell which version of iMovie was originally used for a given project? How can I find iMovie 4 or 5 if I need it?
    I also wonder if projects I make with iMovie HD can be opened by future versions of iMovie, or if I should export them as Quicktime or something to be safe.
    As I start to look into this further, I would appreciate any comments, suggestions, and experiences that you may be able to offer. I need to get these movies back to their former selves, when they looked good!
    Message was edited by: Anthony M Kassir MD

    (when prompted to save the project's changes when
    quitting, I said NO, don't save changes).
    Excellent! That should leave you in pretty good shape. More below.
    I don't know if I should use older versions of iMovie
    to view and burn to DVD these projects. (I still have
    iMovie 2 and 3, but not 4 or 5. I don't know if older
    versions would even work on my Quad G5 with OS
    10.4.7.)
    The old versions of iMovie will run just fine in today's OSX. (But not iMovie 2 if it was the version that ran in Classic instead of Mac OSX.)
    I run versions 2,3,4,5 and 6 today. Problems are minimal.
    I also don't know if the older versions of
    iMovie would work with the current version of iDVD.
    That's not a problem unless your old iMovie projects contain chapters. If you tell iMovie 3 to create a new iDVD project, it might not work. You might not be able to transfer the chapter information to the newer version of iDVD.
    (I just tested iMovie 3 to iDVD 6 and everything worked just fine.)
    Except for iMovie 2, all old versions of iMovie stored a small QuickTime reference movie in the project folder. If you can't get an old version of iMovie to play nice with iDVD, drag that movie into the iDVD window.
    How can I tell which version of iMovie was originally
    used for a given project?
    Drop the project file (discussed below) onto the TextEdit icon in the Dock. The version of iMovie that last saved the project is shown in the first few lines of the project file.
    iMovie 5 used an entirely different project file format, the pList format. The top of the project file will look like this in TextEdit:
    <?xml version="1.0" encoding="UTF-8"?>
    <!DOCTYPE plist PUBLIC "-//Apple Computer//DTD PLIST 1.0//EN" "http://www.apple.com/DTDs/PropertyList-1.0.dtd">
    <plist version="1.0">
    <dict>
    How can I find iMovie 4 or
    5 if I need it?
    eBay?
    I also wonder if projects I make with iMovie HD can
    be opened by future versions of iMovie, or if I
    should export them as Quicktime or something to be
    safe.
    We can never assume any new version of iMovie will be able to understand all features of a older project. It's always smart to make a backup.
    There can be problems Apple can't anticipate. There may be third-party software used to create titles, transitions and special effects, plug-ins not installed with the new version or (more often, incompatible). The fonts installed on our Mac may have changed too. There's lots of features that can't be anticipated. I've never had a problem converting projects, but I never use third-party add-ons and special fonts.
    As I start to look into this further, I would
    appreciate any comments, suggestions, and experiences
    that you may be able to offer. I need to get these
    movies back to their former selves, when they looked
    good!
    My guess is it should be possible to restore the projects back to their original state.
    Note that when imovie 5/6 converts an older project, it does NOT create a true iMovie HD project. Instead of creating an iMovie package, it retains the project FOLDER format. It places new iMovie HD elements inside the old project folder instead of converting it to a package.
    When converting the project it changes the old project file name to "Sample Project Name.iMovie2Project", then creates a NEW project file with the plist format, having the name "Sample Project Name.iMovieProj". (There may NOT be the .iMovieProj extension.) When you save the new project, it adds a new project file "Sample Project Name.~iMovieProj". Note the tilde. The tilde file is a backup of the project file as it was when last saved in iMovie HD.
    For our purposes, ignore the iMovie HD project files. We'll use the file ".iMovie2Project" to restore the project. (The extension is the same for all old versions of iMovie, not just iMovie 2.)
    • In the Finder, Duplicate the entire project folder. Work on the copy.
    • Open the project folder in the Finder.
    • Discard the "Cache" folder, the "Shared Movies" folder, the "Audio Waveforms" folder and the two iMovie HD project files. (Some of those items may not yet exist yet because you didn't save the converted project.)
    • Drop the "Sample Project Name.iMovie2Project" file onto the TextEdit icon in the Dock to get the version. Close it.
    • Remove the ".iMovie2Project" extension, if you want.
    • Launch that version of iMovie. Drop the "Sample Project Name.iMovie2Project" file icon on the iMovie icon in the Dock. With luck, the project should open normally. It's possible any third-party plug-ins used to create the project may not be available. If they aren't available, there might still be problems.
    • Move your unconverted projects to folders that say which version of iMovie created them. To open them in the future, drop the project icon on the appropriate version of iMovie.
    If all this fails, there is another way to do the editing you want. That is to import the project.mov file that's inside the converted project folder to a new iMovie HD project. That will deliver the video and audio of the original project as a single clip. Use that to re-edit the project. The name of the movie is "Sample Project Name.mov".
    (The movie is a QuickTime reference movie, with no video and audio of its own, just pointers to the files in the Media folder. So long as the Media folder hasn't changed, it can play the original project as last saved.)
    Importing the project.mov won't work with iMovie 2 projects, however, for iMovie 2 didn't store a project.mov file in the project folder.
    Even if you end up importing the project.mov, you still may want to "unconvert" the project as described above.
    Hope I haven't skipped a step. Let me know if you bump your head on something.
    Karl

  • HT204370 I downloaded an HD movie onto my laptop from i-tunes.  It plays fine on my laptop, but when I plug in my HD projector, the movie quits.  When I unplug the projector, the movie starts again. I have never had a problem with projecting an itunes mov

    I downloaded an HD movie onto my laptop from i-tunes.  It plays fine on my laptop, but when I plug in my HD projector, the movie quits.  When I unplug the projector, the movie starts again. I have never had a problem with projecting an itunes movie before this. Someone told me that i-tunes changed something so that movies can no longer be projected.  We have a home theatre and have watched movies this way quite regularly, so it would be a drag if Apple will prevent us from doing this in the future. 

    I don’t know about projection, but I’m unable to watch HD content in iTunes because my Apple 30-inch Cinema Display is not HDCP-compliant (which is part of an HD copy-protection scheme).
    The other movies you’ve projected, were they HD as well? If not, it could be the same problem: your projector is not HDCP-compliant.

  • Error in Project Progress Config and process steps

    Hi experts,
    I am implementing PS for Asset procurement, in this i will procure material against material component which is added in Internal activity. I am using scheduling also. Now My client requirement is that he want project progress report on cost basic.
    I am using CJ40, CJ30 and CJ32.
    IN IMG i have configured like given below
    1. I have created Progress version 100
        EV base - Cost Plan ( active Proejct, Annual Value)
        POC weighting - Weight
        Planning type - Basic dates
        Early/Late - Earliest Possible
        Actual method and Ref plan method tick.
    2. Measurement method -
       for cost based report i have selected - Cost proportional
    3. Default value for measuremnt method -
        100 -WBS element - Plan - Cost proportional
        100 - WBS element - Actual - Cost proportional
        100 - Acitvity ( int)- Actual - Cost proportional 
        100 - Acitvity ( int)- Actual - Cost proportional 
    I have put this in CJ20N. I followed following steps
    1. CNE1
    2. CNE5
    but it is showing 0 value in all tabs such as Aggregate planned percentage of completion, Non-aggregated planned percentage of completion
    can anyone tell me the total process to get this report perfectly. It is very urgent need so please help me guys.
    Thanks,

    Hi,
    1) in wbs goto progress tab for enter version plan ,give ur method and actual also give your method  poc weightage give 1
    2) in activity go to progress tab enter your version, give your method for plan and actual give the work measurement method and weightage give 1
    3) now confirm the activities if partial confirmation enter the degree of processing (%).
    4) goto progress calculation screen and give your project number and select with hierachy and with orders. enter the month and year.
    5) excute,
    6) goto the report and check the report.
    if still not working send screen shot of the report.
    Thanking you
    Vengaiah Chowdary

  • Capacity check problem in Project system

    hi,
    i have some questions for the Capacity check problems in Project System.
    1. if one Person is assigned to diffierent Work Centers, for example,  person A is assigned to Work Center 01 under Plant 01, and Work Center 02 under Plant 02, how can i do the Capacity check?
       if i want to use A of Work Center 01 in the Project, the System will only check the Capacity of  01, or both of 01 and 02?
    2.  What is the Pooled Capacity?
    Rgds,
    Liang

    hi,
    1.Capacity check takes place at plant level itself..
    2.Pooled capacity:- This is created separately in [u wil find in PP] and this capacity can be used by different work centers.
    regards
    pushpa

  • Need information on project progress

    Hello All
    We have a ETO scenario and to determine the progree of the project .
    I want to know what all are the type of project progress available in SAP
    If any one can help me on this.
    Thanks in advance

    Hello
    For the geting the information on project progress go through the following link
    http://help.sap.com/printdocu/core/Print46c/EN/data/pdf/PSPRG/PSPRG.pdf
    if this help kindly give the point
    thanks
    alok

  • Problem with the progress bar

    I've have a problem with the progress bar of my ipod. I bought a 5th generation ipod about 8-9 months ago. Now its progress bar stuck so it only shows the 5 dots. It doesn't show both scrubber bar and song time bar. When I press the center button, the 5 dots dissappear from the screen and then reappear but it doesn't show the other bars. Do you know what is the problem and How can I fixed it?

    have you tried resetting ipod, cause as far as i know, this is sometimes just a temporary glitch, mine does this.

  • Milestone Configs in Project progress

    Hi Friends,
    Pls. Send me the Usage of Milestone in Project progress and Milestone trend analysis.
    What are all the config. has to do?
    Looking for your speedy response.
    Regards
    Prabu K

    This can be configured using Milestone Billing.
    1. Create New Sales Order Type, say ZOR (Copy of OR) through T.Code: VOV8
    Maintain Delivery Type as LF & Billing Type As 'F1' - Order Related / 'F2' Delivery Related.
    IMG > Sales and Distribution > Sales > Sales Documents > Sales Document Header > Define Sales Documents Types
    2. Assign New Sales Document Type to Sales Area, For Eg:
    1000 (S.Org) / 10 (D.Channel) / 10 (Division) / ZOR (S.O Type)
    IMG > Sales and Distribution > Sales > Sales Documents > Sales Document Header > Assign Sales Area to Sales Document Type
    3. Create New Item Category, say ZTAN - Copy of TAN (For delivery Related) / ZTAD - Copy of TAD (For Order realted) / ZTAS - copy of TAS (For Third Party)
    Maintain as under (others remaining same)
    Billing Relevance: I
    Billing Plan Type: 01
    IMG > Sales and Distribution > Sales > Sales Documents > Sales Document Item > Define Item Category
    4. Assign Item Category, for ex (assuming Usage & higher level item category as blank):
    Sales Document Type | Item Category Group | Default Item Category
    ZOR | NORM | ZTAN
    ZOR | DEIN | ZTAD
    ZOR | BANS | ZTAS
    IMG > Sales and Distribution > Sales > Sales Documents > Sales Document Item > Assign Item Category
    Note: In the above Billing Type '01' plays the main controller for milestone billing.  In Sales order, at item level, we require to maintain the billing plan.
    Follow the Sales cycle as normal sales cycle for particular Scenarios
    Regards,
    Rajesh Banka
    Reward point if Helpful

  • Problems opening project if I 'log on' with new id

    Someone told me that my problem may be fixed if I logged on as a new user. I assume because they thought the problem might go away if I did so. But now when I'm logged on as a new user, I can't open the project. I get the forever beach ball???
    Maybe I'm just not waiting long enough, but it seems to be crashing my system.
    Any advice??
    Bryce

    The log in as a different user manuever is intended to determine if the FCP application itself , not any particular project, is at issue. This manuever involves only logging in as a different user and then starting FCP. If you get an un named project and normal start-up, that tells you at least that FCP is working OK. In turn that informs you that the preferences used as the "real" user may be the problem. If the project you are working on is not available to the "different" user and the different user tries to open it,an assignment that has to be made in advance of the switch, you could get a beachball and learn very little. You would have to make all components of the project(everything) available to the different user to try to start the project.
    But the search for problems within projects are not revealed in this manuever.

  • 10.1.3 - Compiler problem rebuilding projects

    I found a problem compiling projects.
    Until 10.1.2 when I compiled a project and I got some errors correct classes where compiled and stored, now only if all is correct compilation succeds and compiled classes are stored.
    Is it possible to avoid that odd behaviour ?
    Tks
    Tullio

    Cannot confirm your observation.
    I believe it really depends on the location of the error.
    With 9.0.5.2 (!), depending on the location of the error, the amount of class files written differs enormously. Sometimes, it seems all class files are written except the ones with error. Sometimes almost no class files make it to the disk.
    If that's the odd behaviour you're talking about then this already existed in 9.0.5.2.
    Sascha

  • Project Progress Calculation

    Dear All,
    I have query for project progress calculation.
    As you know that we have std project progress reports( CNE1/ CNE5), In these reports , project progress are calculated monthwise because as per the prerequisite of CNE1 report, input parameter is period ( month, year). If client wants project progress report on a specific date e.g. 15.11.2008 then system gives the progress report , considering plan poc by the end of the month Nov i.e. 30.11.2008, not upto 15.11.2008.
    If you faced such scenario, please share your experience.
    Regards,
    Ashok Sangal

    Ashok,
    I am not sure but this information may give some hits / helpful to you. plese refere link...
    http://help.sap.com/printdocu/core/Print46c/en/data/pdf/PSPRG/PSPRG.pdf
    Regards
    Nitin

  • Project Progress

    Dear All,
    Please suggest in case of my following scenario:
    If I want to measure the project progress on the basis of work completed on each activities under several wbs and then total of project under which these WBS come.
    I am using progress version with basis as Work. Assigning Degree of completion as measuring method to actual method in Progress Tab of each activity(Both Internal and external).
    In CNE5 i get the correct % of work and weight for each activity.
    But when I assign weight to the WBS above these activities and suppose there are three parallel WBS like this then I canot access the work done for each WBS.
    As SAP does not allow % of work done for WBS.
    Can somebody suggest something please.
    Thanks in advance
    Regards
    Maneesh

    None

  • Project progress vs % Work complete

    Hi,
    As far as I've read the %Complete field doesn't state the progress of the project. I would like to see how much work has been done (% Work complete) and compare it against a percentage that's the same as days past since beginning divided by total duration
    times 100%. So in a project lasting 100 working days, I want this project progress at 50% after 50 working days and compare it against the % Work complete. Is there an option to do this?
    If this function isn't available by default, I would have to use some custom fields in which is calculated:
    The number of working days passed since the startdate of the project
    The total number of working days (equals duration)
    Divide the days passed by the days total * 100%

    Hi Jan,
    Thanks for the quick response! Can see you work with a Dutch version of MSP. ;) Are you in Belgium? 
    In the meantime I was trying myself to accomplish it. I did it like this:
    Custom Duration 1: ProjDateDiff([Project Start];Date();"Standard")
    Custom Duration 2: ProjDateDiff([Project Start];[Project Finish];"Standard")
    Custom Text 1: Round([Duration1]/[Duration2]*100) & " %"
    Starting to like MS P!! :)
    Is there any possibility to only show this for the Project Summary (ID 0)?