Process order scheduling

Hello ,
I am working on PP-PI.
When i am creating a process order manualy thru t/c cor1 , the order is not scheduled as per the recipe.
The orders start time and end time calculated is same for any date.
I have maintained the schduling parameters in 'OPUZ' and also 'order dependent parameters ' in COR4.
The capacity in resource is also maintained.
What settings more i need to do ?
In resource i am using 'resource category ' as '0001 - machine ' and not '0008 - processing unit' , is this causing the error .
Regards
ShankarR

Hi,
The in house production time in material master is ' 0 ' .As i wanted to do lead time
scheduling i did not maintain it.
For Lead Time scheduling System conciders the Recipe time that's true but for Basic Start and End Date system considers the In House Prod. Time so there is no problme in maintain it.
Now regarding your Problme.
Problem is Order start and End time both as same 24:00.
In your Master Recipe (Check Scheduling Result of your Recipe - C202 )
Problme may be due to
-  Control Key assign to the orders. Scheduling should be active.
-  Scheduling Formula used in Resource.
Regards,
Dhaval

Similar Messages

  • Process Order Schedule Finish date before Schedule Start date

    On rare occasions, the process order Schedule Finish date is before the Schedule Start date.  This causes an error on the APO system when the process order is CIF to APO.  Does anyone have any ideas how this occur?
    Thanks.
    Best regards,
    Sandy

    Rajesha, thank you for your reply but it doesn't solve my problem.
    Let me restate my scenario:
    I start a process order and both the basic and scheduled finish dates are the same, June 1.
    At some point, shop floor tells me they will be late and cannot deliver until June 15.
    I need to update a date in the system so the ATP and the MRP planning runs have correct information for promising customers, I will update the Basic Finish date with June 15.
    I also need to keep the original June 1 date in order to measure the shop floor performance to the production schedule to measure how early or late the  order was delivered. How can I keep the original finish date or how can I measure if a process order is early or late??
    Thank you for your help,
    Greg

  • Problem  with Process Order Scheduling..

    Dear Experts,
    i'm stucking with the scheduling of a process oreder.
    I've maintained all scheduling parameters into OPUZ except "selection ID" for detailed scheduling as it is grey & not allowing to fill any entry into it.
    I've also maintained production scheduler and other relevant settings into master recipe & resource regarding scheduling .
    Still i'm getting the error"Scheduling parameters for process orders have not been entered" message no CT609.
    Kindly help me out , where i'm wrong
    Thanx in advance...

    Dear Dennis,
    Ensure the scheduling parameters in OPUZ for the order type,plant combination and for all (* )scheduler you have maintainied
    the scheduling type,the check box for scheduling and generate capacity requirements under detailed scheduling is set.
    Check and revert back.
    Regards
    Mangalraj.S

  • Process order schedulling

    Hello friends,
    In process order, when i click  on 'scheduling tab', system gives massage that  scheduling is carried out. But in actual no scheduling takes place. What may be the reason?

    Hi,
    Please check the control key it should active for scheduling?
    And also chcek the scheduling parameter for order type, are marked for scheduling or not?
    Regards,
    R.Brahmankar

  • Process order scheduling based on in-house production time.

    Hello!
    I have following problem. My SAP system is configured in that way that process oedrs are schedulled based on times saved in master recipies. When I input data to in-house production time in master data for materials and make new process order, this time is not
    taken into account.
    Where I have to change configuration to use in-house production time from material master data to make scheduling process orders.
    Regards
    Bogdan

    Dear
    Process Order /Production Order scheduling ( Lead Time Scheduling )  based on the Operation timings in the routing not based on the Material Master In house Production Time in Work Scheduling View .
    If you are loking for Basic Date Scheduling then it will happend based on material master , scheduling margin key  at material master level .
    It depends the selection of Schedueling indicator while excetion of MRP in MD02 .
    In case of Process order specifically , you need  to schedule the Master Recipe and check whether operations are getting scheduled, if it is not then you need to first the problem, which may be because of wrong "Forumla" or paramater assigned in resource or the resource is not maintained for Finite scheduling (capacity header).
    Master reciepe can be schedule in the change transaction C202, and from menu you would find the option to schedule the recipe .
    Also  check the OPU3/OPU5-Define scheduling parametres wether scheuling , adjust scheduling , scheuling type , logs all are in place .
    Check and revert
    Regards
    JH

  • Process Order Scheduling dates.........

    Hi there,
                 For the process order where we can do the configuarion in SPRO so that the opreation starts on the basis of earlier dates or the latest dates...
    Thanks
    Kaushik

    Using OPUZ transaction you can Specify Scheduling parameters to operations in the Process Orders.
    Use the following path via SPRO
    Production Planning for Process Industries --> Process Order --> Operations -->Scheduling --> Specify Scheduling Parameters
    Specify Scheduling Parameters
        In this step you define the parameters for scheduling process orders for
        each plant, order type and production scheduler. It comprises
        maintenance of
        o   scheduling levels (detailed-, production-rate and rough-cut
            scheduling)
        o   date adjustment when deadlines are exceeded
        o   scheduling control for detailed scheduling
        o   reduction
    Hope this helps you.

  • Process order schedule

    Hi gurus
    I am working for process industries with ECC 6.0 version.
    In my configuration part i was done all schedule part. I given target qty in master recipe as 150 kg / 60 min and set up time is 15 min. But at the time of process order creation, the process order basic finish date was not calculated depending on the qty entered. but scheduling carried out message was showed.
    so tell anybody where i missed the configuration.
    regards
    balachandar

    Hi
    I know this is a very old thread, however wanted to know if you remember the solution for this thread, as I am facing the same error.
    In addition the Actual data menu option is disabled for me!
    Can you please share the solution if you found and remember that.
    Thanks in advance
    Rahul

  • Process order scheduling type

    Hi Team,
    While scheduling the process ord (COR1) , with scheduling type"No scheduling", when we enter any future date in schedule start & finish date, system changes these dates to "future date-1" & time to 24:00. We need that system should not change the date provided by the user ie keep the date as provided by the user.
    Awaiting your suggestions,
    Thanks in advance.
    Regards,
    Jack

    Please refer following notes, 151503
    In that
    In-house production time is larger than 0 days:
               For material-related orders, the system interprets the order finish date as a requirements date for the material. Therefore, the following rule applies: If an in-house production time greater than 0 days has been defined in the material master, the requirements date is at the beginning of the day, that is, the order finish date is set to 00:00. In this case, the order finish date of the production finish date differs by one day from the order because the production must have already been finished on the previous day so that the material is available at the beginning of the next day.
    With an in-house production time equal to 0 days, it is assumed that the material can be produced at any time of a day. For this reason, the order finish date is set to 24:00

  • Sched.start date not allowing on week-ends for fwd scheduling process order

    Hello Experts,
    For a process order & scheduling typr forward/in time if I take sat or sunday as a start date then if I click on schedule, system changes it to previous workin day (friday). But however if i select backward/in time scheduling type & put week ends as finish day then system does not change this date.
    How can I make system to allow schedule start date on week ends also for forward/in time scheduling type. in a factory calendor sat & sunday are holidays. while for work center, calender sat & sunday are marked as working days.
    Thanks for advance,
    Vijay.

    Hi
    it depends upon client requirement.you must have defined the holiday calender as well.if you select the public holidays in your factory calender.then system will allow you to do your daily transctions on public holidays as well and vice versa.so better go with all options selected .and plz check at your end
    plz revert back if it works
    Regards
    Anupam Sharma

  • Problem: Scheduling Process Orders.

    Hi,
    I have a problem in PPPI with scheduling in Master recipe and with the process order in CM25. Can you help me?
    In Master Recipe:
    I create a capacity category 0025 to display for a resource the setup formula and Processing formula in the Scheduling Tab (as the capacity category 0001 - I also tried to let the capacity category 0001 be used in application C - Master recipe and didn´t work).
    In OP40, I created and assigned in applications to C Recipes
    Afterwards, I ordered the views in OP13.
    When im creating a resource, i prove the formula and i have no problem. But when I assigned it to the recipe and the recipe to the production version to make a process order, neither the master recipe or process order schedules the order.
    When I create a resource with a capacity category 0008 (standard) the scheduling works just fine in the process order.
    Scheduling in CM25:
    Also when Im trying to schedule the order in CM25, I see two lines of the same order (i guess are the 2 phases 0010 and 0020), is there anyway to just see the second to avoid misunderstanding?
    Thanks in advance!
    AM

    Dear,
    For FIFO you can use the Characteristic  LOBM_LFDAT for FIFO if is LOBM_VFDAT then in plant storage data 1 view maintain the SELD then assign these Characteristic to class in CL02 then assign this calss to material master.
    Then craete sort rule in CU70 withCharacteristic  LOBM_LFDAT or LOBM_VFDAT
    then assign it to serch strategy in MBC1 or COB1 with selction criatoria.
    In OPL8 assign this serch procedure.
    Then create the order and check the result.
    Regards,
    R.Brahmankar

  • BAPI_PROCORD_CHANGE for process order operation level change

    Hi,
    Can any buddy tell me how to change operation dates in process order with following requirement:
    Process order scheduling type is 'Forward',
    1st step, read operation start dates 'Earliest Dates' and 'Latest Dates',
    2nd step, change operation 'Earliest Dates' and 'Latest Dates' directly, this step can't be done in foreground,
    Can use BAPI_PROCORD_CHANGE to update operation dates directly?
    Best Regards
    Amy

    Hi Amy
    BAPI_PROCORD_CHANGE cannot be used to change operations.
    According to note 1694267 you can use the remote-enabled function module CO_SE_PRODORD_CHANGE that is released by the customer to change the order header, sequences, operations and production resource/tool. See the detailed documentation for the function module.
    BR
    Caetano

  • Material Availability in Process Order

    Hi Gurus,
    In process order, (scheduled in Current date) before release I was checked availability of in-put materials.
    System thrown a message that Allchecked materials are availble.
    But, in actual  one material is shortage in stocks.
    I checked the controls in COB1 all are OK
    Please any body help me in this
    with regards,
    Anand.M (Hyderabad)

    Hi Anand,
    It depends on  Checking criteria maintain in your  checking rule in T.code OPJJ.
    - First of all select your order type and plant in along with Transaction type (1 creation or 2 Release) and find out which checking rule you have maintain in it.T.code is OPJK
    - Then go to t.code OPJJ and find the checking criteria for that Checking rule.
    Regards,
    Dhaval

  • How does the GR processing time affect the scheduling of the process order & the latest start date in the operation.

    Hi
    Can anyone explain  how does the GR processing time affect the scheduling of the process order & the latest start date in the operation overview.

    Hi
    GR processing time means number of workdays required after receiving the material in storage.
    Check this link:GR Processing time
    Regards,
    Anupam Sharma

  • Scheduling Time in process order

    Dear All
    While creating process order system is not picking scheduling time as per maintained in recipe because of this capacity is not being load on WC & showing zero reqmnt. Whreas date are properly calculating as per inhouse time maintained. In OPUZ i had ticked both scheduling & capacity reqmnt.
    In resource i had maintained all parameter in capacity & capacity is showing as 24 Hr. Scheduling & Capacity fromula had aslo maintain. Wht could be other reason for nt calculating time as per recipe.
    Thanks & regards

    Rashid,
    So is the dates getting populated correctly after scheduing function? If so then probably you current system design it to perform scheduling manually. You can use the "Production Scheduling profile" to perform this automatically. You need to assign a production scheduling profile defined for automatic Scheduling at the creation stage to you materil master "Work Scheduling" view
    Regards,
    Prasobh

  • Scheduling in Process order

    Dear All
    While creating process order system is not picking scheduling time & date as per maintained in recipe after clicking scheduling tab, because of this capacity is not being load on WC & showing zero reqmnt.
    When i checked scheduling at recipe level there also it is happening.
    In OPUZ i had ticked both scheduling & capacity reqmnt.
    In resource i had maintained all parameter in capacity & capacity is showing as 24 Hr. Scheduling & Capacity fromula had aslo maintain. Finite scheduling is ticked.The control key assigned to the phase, is also defined with "Scheduling and Capacity requirments".
    Wht could be other reason for nt calculating time & date as per recipe.
    Thanks & regards
    Abhijit Gautam

    Hi,
    Refer below thread,
    [Thread |No reqmt/capacity exist or not relevnt for finite scheduling: Mesage: CY298;
    Regards,
    Dhaval