Hi,
We are in to IT distribution business; in our nature of business we donu2019t know shipment cost at Purchase Order, we can have various options
As per Our business requirement we want to take the MAP cost as basis of our Sales Price considering very low profit margin, so  for every shipment( partial GR) the freight cost  are not on proportionate basis, it will vary widely depending on the facts like
A.     Mode of transport(Air / Ship /Road )
B.     Size of Truck load/ Ship Container
C.     Number of Partial Shipment
D.     Shipment for Multiple Purchase order.
Further we want the freight cost  to be automated based on above variations.
Problem:
We need to incorporate both the partial delivery cost (Elucidated below) at Goods receipt point for each and every shipment (Partial Delivery).
We want automated price component should flow to Good receipt on partial delivery basis considering both components mentioned below.
For understanding kindly refer to the below mentioned example.
Case 1:
We placed one Purchase Order Qty 1000 to Vendor HP on Inco term Ex Works Taiwan,
This Quantity of Material will be shipped partially to Our Plant at Dubai; We will out sourced Freight forwarder for picking the material from HP factory to Dubai Sea Port
We have different components as below
Fixed      $  115.00      Per Bill of Lading / Shipment
Variable 1 and/or      $  235.00      Per 30 CBM / 20" FT Container
Variable 2 and/or      $  200.00      Per 60 CBM / 40" FT Container
Variable 3      $  200.00      Per 70 CBM / 40" FT HC Container
Again the Shipment will be transferred from Sea Port to Our Plant through road, this may be a
Variable     From 1 to 8 CBM --> $ 19     3 Tonn
     More than 8 CBM --> 19 CBM --> $38     7 Tonn
     More than 19 CBM --> 43 CBM --> $52     40" Trailer
Any concept or solution will be acknowledged..
Thanks & Regards
Sudhansu
Edited by: sudhansu satapathy on Jan 27, 2011 9:50 AM
Edited by: sudhansu satapathy on Jan 27, 2011 2:02 PM

Hi,
Quick answer will be
As you do not know delivery cost at the time of PO creation , you can post delivery cost in MIRO with a option to a particular G/L account & need to active in following path:
SPRO > Materials Management > Logistics Invoice Verification > Incoming Invoice > Activate Direct Posting to G/L Accounts and Material Accounts > Here Activate "Dir.posting to G/L acct = active" and save. 
OR
Try for rebate / subsequent settlement.
Regards,
Biju K

Similar Messages

  • Purchase order is created with less amount than the shipment cost amount.

    Hi All,
    Shipment has got 2 stages but the system wants to split the shipment cost to 3 parts (33% each) If we add the amount with manually to shipment cost document and we transfer it the PO will be created only for 2/3 (66%) part of the shipment cost.
    What could be the reason?

    from http://help.sap.com/saphelp_40b/helpdata/fr/dd/2d547bb435d1118b3f0060b03ca329/content.htm
    User exit M06E0004 is provided to enable you to adapt the release strategy determination process to meet your requirements.
    This user exit allows you to change the communication structure for determining the release strategy for purchasing documents.
    The following user fields are available:
    USRC1
    USRC2
    USRN1
    USRN2
    In addition, communication structure CEKKOZZ is available, allowing you to use your own fields.

  • How to add the shipment costs in to material costs

    Dear friends
    I am implenting the transportation module.
    In purchase process and STO processes, the client requirement is received material cost should be added with shipment cost.
    I mean the material cost is 1000/-
    The shipment cost is 100/-
    Client Requirement: Freight liability should get loaded on the inventory being it is part of purchase cost.
    Now the material cost: 1000+100
    We are not entering the freight costs in PO.
    We are creating the shipment cost documnets for calculating the ship.costs.
    When we do the MIGO/Inbound delivery the system need to capture whole amount as a material cost.
    With regards
    Lakki

    Dear Vinod,
    Already  i created the shipment cost document with reference to inbound delivey document.
    Now the ship.cost value is 100/-
    The material cost is 1000/-
    But i want to show the accounting document for meterial document with 1100/-(Material cost and ship.cost)
    But when we do the PGR, sys will generate the accounting document with material cost only, sys should not add the ship.cost. Because we didnot enter any ship.cost value in PO or delivery.
    We are maintaining the ship.cost in saperate documents.
    How to do that?
    With regards
    lakki

  • Define the shipment cost

    Dear All
    How to define the shipment cost by the material which from Outbound delivery.thanks very much

    hi,
    use the conditon type HD00 if you want give the freight at header level or kf00 if you want to give it at the item level in the pricing procedure and maintain the condition records.
    Please reward the points if the answer is helpful
    Regards,
    Murali

  • Cannot transfer the shipment cost on PO

    Hi Guys,
    Im trying to transfer the shipment cost on a PO. But I the PO creation cannot be successfully created due to the following error:
    "No PO item was generated for shipment cost item 0000XXX 00XX,
    Please enter an overall limit or allow unlimited"
    Do you guys have an idea on how to solve this issue??
    Thanks!

    What is the combination of Item Category and Account Assignment you are using? You should be using K and D or U and D.
    You are trying to create a limit PO.
    Check what is the account assignment assiged to the Item category in the cost in T_56.
    Please also check the below.
    SPRO - Logistics Execution - Transportation - Shipment Costs - Settlement - Assign Purchasing Data

  • Pass the shipment costs to billing document

    Hi All,
    I want to transfer the shipment costs to billing document.
    But i don't want to transfer to customer. I want to post it as accruals.
    What are the settings need to do in SD and transportation module for copying the shipment costs to billing documenbt.
    Do we require to maintain any special config.
    Please help me to solve it out.
    Thanks
    Lakki

    Hi
    Maintain the Pricing procedure for the shipment cost document,in which place a Frieght condition type suppose fb00 which also has to be placed in your billing document pricing procedure for the last step with stastical check so that from shipment ,frieght will be copied but the value will not be inclued in the netvalue for ur customer.for frieght condition type maintaian req-51 with base cal -51in ur shipment pri.proc.   Apart from this maintain in copy control from delivery-billing price source as 'F'.
    Hope this will help u.
    Sujith.

  • Multiple delivery condition in the shipment cost

    Hi,
    How to handle multiple  condition in the shipment cost?
    For example , if  the single consigment contains following conditions
    1.Freight
    2.Insurance
    3.Custom clearing (these condition value to be added in the material cost at the time GR process).
    It is working fine for the single condition  but not working for mutiple condition.
    Regards,
    Renuga.A

    Hi,
    This is answered by standard SAP.
    Standard condition types are avlb (freight, Insurance). Create condition types for additional delivery costs. Use it in pricing procedure as per calculation matrix. Assign the pricing procedure to vendor and purchasing org.
    While creating PO, use these conditions at line item level in condition type. You can have few costs are PO header level. Tick the header indicator in condition type.
    All these costs will be calculated at the time of goods receipt except customs duty. Customs duty will be applicable after posting bill of entry.
    Anand

  • Billing the Shipment Costs to the Customer

    Hi,
    In my scenario, I had created shipment document & shipment cost document, now what ever be the cost in that I want to charge to customer in addition of material price.
    I had created condition type say KF00 in shipment & made it statistical. same condition is in my pricing procedure in SD.
    In front of procing procedure I had made tick mark i.e. Transaction speciefic price procedure
    In copy controll LF to F2, at item level I selected price source as shipment cost.
    But still cost is not flowing in the billing document.
    Please suggest what to do
    Thanks,
    kapil

    Hi,
    Refer this [http://help.sap.com/saphelp_erp60_sp/helpdata/en/d5/2285347860ea35e10000009b38f83b/frameset.htm]
    and [Re: sap sd Transportation;
    please check the copy control for Billing in the SAP Hep link
    Regards,

  • Problem in clearing the shipment costs to transporter

    Hellow,
    Scenario:
    Step1:
    1. I created on PO and I did one inbound delivery with reference to PO.
    2. Then i did inbound shipment, and shipment cost document.
    3. Shipment costs calculated based on weight of the delivery material, Here Weight is 3 To with 300/- per TO.
    Total amount is 900.
    3. Then i did MIGO with reference to inbound delivery.
    4. Now system copied shipment costs to material costs.
    5. Then i did MIRO for planned delivery costs(900/-) with reference to PO.
    Step2:
    1. same way i did one more inbound delivery for open items
    2. Shipment document with reference to Inbound delivery.
    3. Shipment cost document created, Here also only 3 To weight, but the freight rate is 200/- per TO, total cost is 600 only.
    4. I did MIGO with reference to Inbound delivery
    5. When i do the MIRO with reference to same PO for remaining 600/- planned delivery costs, system is not copying the 600/- from PO. It is copying the average on 900+600 for remaining delivery costs.
    If we go with same freight rates this kind of problem is not happening. In different rate situation only this problem is occuring.
    Can i have any solutions please?
    With regards
    Lakki

    Hi Lakki,
    May I know what's the condition type for the freight charges involved so that we could proceed to help you further.
    Thank you.
    Best regards,
    HC.

  • Replicate breakdown cost from the Shipment cost document (VI01) to the PO

    CASE:
    Currently we are creating the SCD with reference to the shipment number. This SCD creates a Service purchase order and a Service Entry sheet automatically.
    The SCD has several conditions types to store different types of costs: Freight, fuel, accessorial, package, etc.
    The purchase order has only one value, instead the several values in the SCD. We want to replicate all condition types from the SCD  to the PO.
    Example:
    SCD condition types:
    Freight           $80
    Fuel           $15
    Accessorial     $5
    Total          $100 USD
    Automatic service PO conditions
    Price(Limit)          $100
    We want to have the same breakdown cost in both documents. Do you know how to do this?
    CD

    No possible.
    OSS note 427944

  • Transportation cost calculation based on the Shipment duration

    Dear all members,
    Now I work on the IS-Oil system. I try to calculate the shipment cost for the shipment duration.
    1. The requirement here is when we complete the delivery confirmation (shipment status is 6), the system doesn't calculate the actual total duration of this shipment. I saw there is a field for total duration in the TD shipment (in the Maintain Stages tab), but it is blank. Do you know how to config this system so that it can auto update this field?
    2. I want to calculate this shipment cost base on this shipment duration. Do you know which condition type or how to customize the condition type so that we can calculate the shipment base on the shipment duration? I try to work with Scale technique, it works when I set the price for 9999 day. But it doesn't make sense  if the customer asks us the reason why we need scale for this problem. This problem seems to be very simple, I want to maintain condition record for 1 truck of 1 vendor, the price will be 50 USD/ day for this truck. And the shipment cost document must get the (shipment duration) * (50 USD).
    Thanks in advance!

    Hi Thado
    You need a have routine on the shipment cost document pricing procedures condition type, there you need to get the actual shipment start date and end date which are available in Shipment status, and condition value can be calculated from there based on Number of Days *eg 500.
    Thanks
    Sudhakar

  • Shipment cost condition not copied in the billing document

    hi
    I have created shipment for the delivery and compelted the shipment cost as well , however when i create the billing document the shipment cost conditions are not copied in to the billing document.
    i have already set up pricing source as F in copy control from Delivery to billing document ,
    what are the other settings to be done to copy the shipment cost condition types to billing document  ?
    Regards
    Dinesh

    You migth include it on copy control frome delivery to invoice.
    Regards,
    RP

  • VI01 - Shipment Costs (combining Deliveries from the Shipment)

    Hello experts
    Do you know how to combine (consolidate) the shipment costing line item (VI01) when there are more than one Delivery to the same customer in the Shipment document?
    E.g. I have a Shipment with 58 Deliveries and for a specific customer has 2 Deliveries, the Shipment Costing (VI01) must to create just one line item consolidating the 2 Deliveries for that customer, not to split 2 lines (one line for each Delivery).
    Any help will be highly appreciated.
    Best regards...
    Marcelo Boccia - SAP SD

    Hi,
    As per my best knowledge shipment cost document item is not created based on delivery, it is created from shipment header or shipment stages:
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/93/7440ac546011d1a7020000e829fd11/frameset.htm
    Shipment cost items
    The items refer either to a shipment header or a shipment stage. The items contain general data for shipment costing and settlement, such as service agent, pricing date and settlement date, tax amount and tax basis as well as organizational data such as company code, plant and purchasing organization.
    There is an individual status at item level for each of the shipment costing, account assignment and forwarding to FI functions.
    As you can see delivery is not mentioned.
    At shipment cost sub-item level you may have deliveries.
    Isn't it possible that your deliveries belong to different stages? Is any related development in your system?
    Please check your shipment and report us on the result.
    Thanks,
    Csaba

  • Default the Tax Code on a Shipment Cost Document

    How do I set the tax code to default in the Shipment Cost Document under the Tax tab?  We're seeing different behavior depending on whether we're shipping from US to Canada or the other way around.  It must be configurable but I can't find it.  Please help as I've read many existing posts and can't find a resolution.
    Here's what's happening:
    B/L 122252 was shipped in Company 2000 from CA to US.  When I settle the cost document for these types of shipments, I have to delete the Tax Jurisdiction (US0000000) before I can complete it.  The Tax Code is also blank, when it should be I0 (Tax Exempt).
    2.    B/L 122325 is in Company 1000, and is the reverse of the one above (US to Canada shipment). It has a Canadian Tax Jurisdiction with the Tax Code of I0, and it works fine. The Jurisdiction does not have to be deleted.
    It seems that the issue with the Company 2000 shipments would be the Tax Code of I0 not being populated, when the shipment cost document is created.

    I was able to add a record to the Condtions' table that solved half my problem.  The Tax Exempt code (I0) is now being added to the Canadian record like it is for the US record.  However, the Tax Jurisdiction field is still being populated and we want it to be blank.  Where does this field come from?    It's not in the condition record, and it's something different for the US ship cost doc than the Canadian record, so something's telling it what to put there.

  • Shipment Cost Condition Type

    Dear Gurus,
    Is there any standard system condition type in the shipment cost who calculate the cost in the below behavior.
    If product weight is in b/w 1 to 10 tons cost is $10,000.
    and if weight is more than 10 tons lets say 11tons system calculate the value per ton. (10,000/10 ton = $ 1,000/ton * 11 tons = $11,000).
    Please advise.
    Looking forward for the response.
    Regards,
    Imran khan

    Hi,
    Dear Imran,
    You have posted this question twice and there is no such condition
    You have to maintain scale and if need to develop routine and that I already suggested to you.
    Kindly do not post 1 question many time
    Kapil

Maybe you are looking for

  • DVD keeps popping out.  How do I get it to play???

    DVD keeps popping out.  How do I get it to play??

  • Songs arent showing on ipod but are on computer

    Ive recently synced my ipod & ripped 6 cd's which was fine! The next time i ripped 10 cd's & these dont show on my ipod but they are showing up on my computer! How do i get them from my computer to my ipod?

  • How to export and import only data not table structure

    Hi Guys, I am not much aware about import ,export utility please help me .. I have two schema .. Schema1, Schema2 i used to use Schema1 in that my valuable data is present . now i want to move this data from Schema1 to Schema2 .. In schema2 , i have

  • Change details of attachments

    Hi Friends, In create mode we attach 3 documents (say A, B,C) in CV01N, with status CT. Say document no is 1001 We removed a attachment  (B) in change mode and change the status to IW. Now the document 1001 has two attachmnets only i.e. A & B. Can we

  • Ad-Hoc between MBP's still a G network!