Project Code to be included in Depreciation run

Hi Friends,
Previously, the Cost Center was mandatory for all assets. Now, they want the depreciation to flow to either a cost center or to a project code. In accordance with the requirement, I had made Cost Center optional, along with Maintenance Order. Previously Cost Center was mandatory and Maintenance Order was not shown in the asset class master data configuration screen.
Hi Friends,
Find below the description of the issue faced.
Previously, the Cost Center was mandatory for all assets. Now, the depreciation HAS to flow to either a cost center or to a project code. In accordance with the requirement, I had made Cost Center optional, along with Maintenance Order. Previously Cost Center was mandatory and Maintenance Order was not shown in the asset class master data configuration screen.
Further, there was a validation which checked that each asset master had a Cost Center field filled in and a substitution which filled the Cost Center field with a default Cost Center. I have changed the validation to reflect that either a Cost Center or a Maintenance Order is filled in. I have modified the Substitution to reflect either a Cost Center or a Maintenance Order.
Before the above changes were made, the Depreciation run was being executed without any error. After the above changes were made in the system, the Depreciation Run is ending with an error "Account 551100 requires an assignment to a CO object - Message no. KI235"
Even prior to the error, the Default Account Assignment tab in the relevant Cost Element was empty.
I have checked the Field Status Variant and Cost Center is only optional in that.
Can you suggest any further config. settings that have to be changed? Two SAP Notes, ‘827363’ and ‘98778’ have suggested patches, which have already been applied to SAP.
Regards,
GV Shivakkumar

Answered .thanks

Similar Messages

  • Single depreciation run for multiple company codes

    Hi experts,
    How can I carry out a depreciation run for multiple company codes in one transaction? I thought about creating a variant and running a batch job but you can only select the run for one company code at a time. Am I missing something here. Kindly provide explanation of how this can be done.
    Thanks.
    Ben

    Use the program RAPOST2010. There is no transaction for this program, but you can create your own if necessary, for example ZAFAB.
    Please not that there is a separate forum for asset accounting.

  • Depreciation run not included the asset

    I have already taken the depreciation run in period 12 of f.y.2009. Now a new asset is puchased & I want to charge dep. for one month, then system don't post the deprection for that month.
    How can I do for post the depreciation on new asset in last month of fiscal year?

    Hi,
    generally, if you change depreciation relevant parameters, it effects all open fiscal years (all open periods).
    Since ERP2005 you can enter a interval for a new depr. key.
    AS02
    -> depr. areas
    -> double click on area
    -> Press Button "More intervals"
    regards Bernhard

  • Depreciation run for Business area

    Hi all
    We design some business areas are belong to 1 company code.IF each BA want to depreciation run by itself
    How to depreciation run independent for each BA. If anyone know it, please teach for me.
    Thanks all
    Tora86

    Thanks Sridevi
    I know that depreciation run at companycode level. But my project have some difficult problems, So I want to find way depreciation run at BA level. we can config or customize anything?
    Thanks all
    Tora86

  • Posting an unplanned depreciation run for the previous period

    Hi SDN forum,
    May I just ask if it's possible to run an unplanned posting run for a previous period wherein the depreciation run has already been executed?
    The scenario is more like a "repeat unplanned posting run"
    I can't seem to include this unplanned depreciation whenever I select the repeat run for the previous period.
    Please help.
    Thanks

    Hi
    Through T.Code: ABAA  you can able to post unplanned dep for previous period.
    Executing AFAB for previous
    1 - open FI Periods (OB52)
    2 - Post Unplanned Dep T.Code: ABAA
    3 - Run AFAB with Repeet run & Test run
    you feel it is ok with test run execute production run
    Regards
    Viswa

  • Depreciation run issue.......

    Hi,
        I am trying to re run the depreication as it calulated wrongly for last 2 months. Now when i am executing it through AFAB T.code, it is giving me an error that posting period is not open for period 1. Our fiscal year start in Oct and ends in Sept. I checked the OB52 settings and there it is shoiwng that currently period 3 is open.
    So is there any other way through which i can re run the depreciation posted. I don't think business will agree to open the closed period.
    Please suggest.
    Regards....

    Hi
    To post an acconting document in a particular period, that period should be opened. And in case of depreciation run also, accounting document is generated by the system. So it's necessary to open the period to execute depreciation.
    Otherwise you can correct the incorrect depreciation in current period if it's ok as per your management.
    Rajib

  • FI-AA : Problem in Depreciation Run and Year end closing.

    i am doing asset year end closing and new fiscal year open, i followed the steps as followings..
    Step 1 Did depreciation run using T-code AFAB- no error
    step 2 checked depreciation run in AFAR was correct(no error)
    step 3.did actual run of new fiscal year open using tcode AJRW.
    step 4 : did actual fiscal year closing t-code AJAB.
    but now the problem is still i am not able to see any asset reports when open the report meg. says "fiscal year change not done for company code xxxxx"
    problem due to  is any patch need to be executed? or due to any other application error?, pls advice to solve this my issue.
    with best regards,

    Hello
    Choose Periodic processing ® Fiscal year change.
    Enter the company code and the new fiscal year.
    Choose Program ® Exec. in background.
    Process the assets with errors that were identified during the fiscal year change (Tools ® Assets with errors).
    Reg
    *Assign points if useful

  • Freight - Marketing Documents Assign a Project Code

    Hi All,
    I have a customer that uses project codes and profit center functionality in SAP Business One. They flag transactions to record the relevant project codes and profit centers for extended reporting requirements. So far we have had no issues but we have encountered one lack in functionality which I can't seem to configure in SAP Business One. The issue is that we cannot assign a project code when recording additional charges / freight during a marekting document in SAP Business One. However you are able to assign a profit center? Is this a limitation of the product and if so will this be addressed in future versions? Does anybody know?
    Any feedback / ideas will be greatly appreciated!
    Thanks
    Andre Pienaar

    Hi
    Whole Marketing Document can be assigned to project, even freight is having separate  profit center.
    If u want to include more features in B1 pls post ur queries here:
    Forum: SAP Business One Product Development Collaboration:/community [original link is broken]
    Giri

  • Project Code in recurring journal postings

    Hi All,
    Does anyone know whether SAP plans to include the option of using project codes on recurring journals in future versions as it's been flagged up a few times by our customers?
    Kind Regards,
    Matt

    Hi Matt,
    Based on the road map for the new version, I have not seen this detailed new feature. It might be include already. However, this is too detailed function. It is no document to prove up to now.
    Thanks,
    Gordon

  • Project Code in J.E.

    Dear All,
    Please let me know even when the Project Code is mentioned in the Marketing document, why is this Code not updated in the J.E.???? Because of this when the Ledger of that Account is viewed as per Project Code it does not show any implications of the entry.
    Thanks & Regards

    Hi Binita,
    In Business One at the moment when a project code is assigned at header
    level in a marketing document then it will only be assigned to the credi
    tor or debitor in the journal entry.
    If the project code is assigned to the item on row level in the
    marketing document then it will also be assigned to the
    revenues account in the jounral entry.
    Similarly, when in the journal entry if the project code is entered in
    the header of the journal entry then  the project code will be entered
    for all rows in the journal entry including the vat row.
    This is the system behaviour.
    Please refer to note 875291 for further information.
    If you want just to put the project code in the revenues row of the
    journal entry a formatted search can be set up on the "project" field on
    row level in the marketing document.
    Query to use:
    SELECT T0.PrjCode FROM OPRJ T0 where T0.PrjCode = $$157.1.0
    Save this as a formatted search behind the "project code" field on row
    level. Everytime a bp with a project code is used this formatted search
    will copy its project code to row level.
    Hope this will help.
    Regards,
    Gagan Thareja
    SAP Business One Forums Team
    Edited by: Gagan Thareja on Mar 19, 2009 3:01 PM

  • Project code scenario

    Hello Experts,
    I create B1 to B1 synch Project code scenario (object id 63),
    The process runs immediately to the DB queue monitor and stays there,
    It's not running in to failure and I can't understand what seems to be the problem.
    Best regards
    Nir

    Hi Nir,
    local object id 63 belongs to a B1 service object called "ProjectsService".
    In B1iSN you need to create a special B1 object for Service Call ( B1iSN Tools --> Development Tools --> Object Type Generate ):
    Therefore the first field Category needs to be filled with ObjectType Definition for B1 Service Calls.
    The ServiceCall details need to be maintained behind the "Details" button.
    Best regards
    Bastian

  • Depreciation Run for closed fiscal year

    Hi All,
    We bought some assets on 2005 through direct purchase and these assets are in under operation, but not having the asset master record in the SAP system.
    Now we have decided to bring these assets into the system as the capitalised date is 10 Nov 2005 and for this purpose, we had created the asset master record and applied the t.code: ABNAN to post the values to these assets.
    <b>"My concern is about how to provide the depreciation run to these assets for the closed fiscal year from 2005 to until Nov 2007.The present closed period in the production system is 2006".</b>
    I request you to all kindly give your values on the above mentioned issue.
    Thanks with regards,
    Ran

    Hi
    Just give the dep start date as 10 Nov 2005 and run the dep for the current posting period the depreciation will get posted for the year 2005 and upto the current period,in the current posting period.
    As the past reriods are all closed you cannot post dep in the year 2005.
    You will have the whole dep for that particular asset posted in the current posting period.
    Hope this helps
    Good Luck
    Hari

  • Unable to post depreciation run - AFAB

    Dear All,
    I have a AUC with capitalisation date 16.06.2011. On 4.02.2011, I have wrongly depreciated the AUC. On realising my mistake, I changed the Depreciation key to 'MANU' from '0000' and posted a transaction with Transaction Type '640 - Unplanned depreciation on prior-year acquisitions. Now when I try to execute the depreciation run for period 1 - 2012, which was terminated, I am still getting the error - 'Account 'Accumulated dep. account unpl. deprec.' could not be found for area 01'.
    Diagnosis
    When creating the accounting document, the system could not find account 'Accumulated dep. account unpl. deprec.' in depreciation area 01 for company code XXXX.
    Procedure
    Enter this account in the account determination for Asset Accounting.
    Since this is an AUC account, account determination to a GL is not appropiate.
    Kindly suggest how to proceed, as I am unable to complete my depreciation run.
    Thanks
    Rosalyn

    Hello Konnipati,
    Issue is not yet resolved.
    The details of the issue are as follows:
    1) The user has changed the depreciation key from '0000 to 'MANU' in
    one of the AUC and posted unplanned dep. in ABSO transaction.
    2) The dep.run was executed for the month end close on the same day.
    3) The dep run got terminated with the error
    message: 'Account 'Accumulated dep. account unpl. deprec.' could not be
    found for area 01' Message no. AU133.
    4) The user realised the mistake and reversed the unplanned
    depreciation document immediately.
    5) Then they tried to execute the 'RESTART' dep. run. But the system is
    still showing the same error message.
    6) We changed the dep.key from 'MANU' to '0000' in AUC master.
    We replicated this scenario in Quality. We tried to resolve the error
    by transfering the AUC to new AUC in the same Asset Class.
    The values of the AUC got posted to the new AUC without any
    depreciation and the old AUC got deactivated.
    We then executed the RESTART depreciation run, but we still get the
    same error.
    6) Since this is a AUC, we cannot assign any GL accounts.
    Please let us know your suggestions to resolve the error message in the
    depreciation run.
    Thanx
    Rosalyn

  • Depreciation Run Error (Message no. AA693)

    Hi,
    User has posted an entry to transfer an asset from one companyh code to the new company code into last FY 2010 in P13. This new company code do not have any asset prior to this. When perfomring the depreciation run, an error message was encounter as per below.
    Only an unplanned posting run is possible in this fiscal year.
    Message no. AA693
    Diagnosis
    You have already posted in fiscal years that come after 2010.  This means that you can only post in the last posting period 012 in fiscal year 2010. Or you can post to a special period, if one is set up. Since you have not posted yet in this fiscal year, you must specify that the depreciation posting run is unplanned.
    Procedure
    Please check the fiscal year entered.  If you are certain you want to post to fiscal year 012, you must start the depreciation posting run in the last posting period (or in the special period).  Be sure to indicate that this posting run is unplanned, since it falls outside of the normal posting cycle.
    User has tried the various method (Planned, repeat, restart and unplanned) but still got the same message.
    Can someone advise urgently ?
    Thanks in advance
    Ang.

    Hi,
    I assume you have in 2010, no entry in the table TABA,  because you have made no depreciation run in 2010.
    I suppose you have already made a depreciation run in 2011 - right?
    In this case you can not post in 2010,
    In this case we make a dummy entry in the table TABA in 2010 for period 12.  Then you can post in the special period in 2010.
    regards Bernhard

  • Depreciation run for each business area

    Hi all,
    In case all business areas are belong to 1 company code.
    So how to run depreciation for each business area separately?
    I mean business area A can run depreciation for itself, and not affect other business areas in the same company code.
    Any suggestion would be highly appreciate!
    Thanks in advance any help!
    HuyenTT

    no, this is not possible, as the depreciation run needs to be executed for the whole company code.
    Blaz

Maybe you are looking for