Hi,
HRA = (Basic salary __ 1000 rupees) %10.
Example:- Basic is 10000 rupees, so system shoul deduct 1000 rupees from basic automatically and calculate HRA 10 percent on 9000 rupees.
How to do this? pls help me
Can anybody help me please
Edited by: Mudupu123 on Mar 17, 2010 9:44 AM
if you want this one at the infotype level
i think useing the User exit is the best option
or else try to make the percnetage as 10 % on basic at infotype and - the Rs 1000 at schema level
but i feel you are looking at the ifnotype level if yes check the option of useing User Exit
Similar Messages
-
Pricing procedure mm Packing and forwarding to be calculated on Basic price
Hi experts
we are having one pricing procedure where in details are as follows.
basic price 100
excise 12.36
total 112.36
P & F 2 % 0n (112.36) 2.24
total 114.60
Vat 5 % 0n (114.60) 5.73
Grand total 120.33
Now we require new pricing procedure wherein Packing & forwarding to be calculated on basic price & not on basic + excise
so can we change in same pricing procedure or we have to create new ?
Can you elaborate with the configuration steps ? Any changes required in Tax procedure also or not ?
Thanks in advance
regardsHi,
No need you can add the condition type to the pricing procedure at spro--mm---purchasing--pricing procedure ---calculation schema with proper calculation to get the percentage on base price and add to the total .
Regards, -
Calculation of basic dates and schedule dates
I update material master from routing with CA97 to material master
work scheduling data with base quantity 1000
When MRP running, planned order for 54000 PCS is schedule with work scheduling data.
when i schedule planned order (change)
the calculation basic date & schedule date differs for 19 days
cause basic start shift
why is this happend?
is this cause by rounding when transforming minute from routing to days in material master?
is this because i used shift sequence and scheduling with breaks?
some strage case again is
for base qty 1000 processing time is 0.97
for base qty 10000 processing time is 6.93
is there any solution for this case?
please help.
Best regards,
Freddy Hai forgot i used overlapping
sorry -
Calculation of basic date and schedule date
I update material master from routing with CA97 to material master
work scheduling data with base quantity 1000
When MRP running, planned order for 54000 PCS is schedule with work scheduling data.
when i schedule planned order (change)
the calculation basic date & schedule date differs for 19 days
cause basic start shift
why is this happend?
is this cause by rounding when transforming minute from routing to days in material master?
is this because i used shift sequence and scheduling with breaks?
some strage case again is
for base qty 1000 processing time is 0.97
for base qty 10000 processing time is 6.93
is there any solution for this case?
please help.
Best regards,
Freddy Ha
Edited by: Freddy Halim on Jan 28, 2010 7:40 AMHi,
Yes. The schedule date is generated considering your factory calender also in addition to the routing data. For eg.. Suppose if Saturday and sunday are holidays, the schedule date will be extended to 2 days.
Pl. check the unit in your routing for the second query.
Pl. refer the link
http://help.sap.com/saphelp_47x200/helpdata/en/b1/c042b7439a11d189410000e829fbbd/frameset.htm
Madhava -
Rebate calculation from Basic Price PR00
Hi,
This query is related to rebate conditions. At present the rebate base is calculated from the subtotal, that is Basic price - discount(The subtotal 7 is assigend to the step 300).
As per the requirement from the business, the rebate should be calculated from the 'Basic Price'. They don't want the discount value should be considered in the rebate calculation. I explained them regarding the burden which company has to bear, but the business still want to go with the changes.
My plan is to create another step in the pricicng procedure right after the basic price and assign subtotal 7 to it and delete the exting reabte subtotal step, and assign the new step number to rebate conditions, so the reabte will be calculated based on this.
My questions are:-
1. Can I edit the existing pricing procedure to make these changes?
2) Will there be any impact on the existing rebate agreements (open) and its settlements on a later date?
3) Will there be any impact on the process of billing of open sales orders/deliveries (not billed) after the change in pricing procedure?
Please guide me.
Regards,
SAMHi Ivano,
Thnak you very much for your suggestion.
As the note says, the best way is to copy the existing pricing procedure and create another and assign it in OVKK.
Will there be any effect for partially billed delivery items? (at the time of creation of billing document for the unbilled items in the delivery)
OR
when we create a billing document from the delivery (in the case of sales order and delivery created with old pricing procedure and the billing document is getting created after the assignment of new pricing procedure)
Your valuable suggestions will be highly appreciated.
Regards,
SAM -
Urgent : TDS - Cess Calculation on Basic + Surcharge
< MODERATOR: Message locked. Please read the [Rules of Engagement|https://www.sdn.sap.com/irj/sdn/wiki?path=/display/home/rulesofEngagement] before posting next time. >
Hi Sirji
I am trying to configure the following in tds
basic rate ( A1)
surcharge ( A2 )
cess ( A3 ) &
ecess ( A4 )
but the problem is cess is on basic + surcharge
and surcharge is applicable after 1,00,00,000.
so how to built the condition taking this value consideration.
I tried with "Define formulas for calculating Withholding tax" but didn't work.
my requirement is
If invoice value = 10,00,000
basic tds = 2,00,000
surcharge = 0
cess = 2000
ecess = 1000
If invoice value = 20,00,00,000
basic tds = 4,00,00,000
surcharge = 40,00,000
cess = 8,80,000
ecess = 4,40,000
kindly let me know if anything can be done on this.
my mob is 9821050905
thanks in advanceHello Kambli,
First you need to configure wht types and codes for
- TDS
- Surcharge
- Cess
- Edu. Cess
Then after do the following settings
FA>****>wht>ewht>calculation>wht base amount>portray dependencies between wht types.
- Here you will give surcharge wht type no to tds wht type
- You will give cess wht type no to tds + surcharge wht types
- You will give edu. cess wht type no to tds + surcharge wht types
Try this if u have any querry pl revert
If useful pl assign points
Thanks
Para -
dear all experts
i have one issue as
in a month there are 30 days & 26 days are working days
now
employee takes two unpaid leaves & two paid leaves(1PL&1CL)
of the 4 wt in it 0008 ,two r to be calculted on the basis of 24 days & remaining two wagetypes on the basis of 22 days(physically present)
kindly help me with the solution
thnkxThat is the factoring. for your requirement IBP1 rule is enough may be. If it is suitable for your requirement write the rule. Get the total days from TADIVI and get the paid and unpaid asences from the TSAP** and TSAU**.
Good luck
Devi -
Production order Basic start date calculation
Hello PP Sapperu2019s,
I have an production order for total qty - 865,00.This production order created on 11.08.2011 and I could able to see the Basic start date as 26.06.2011.Please let me know how this basic start date gets calculated. I mean what are all the parameters included for calculating this basic start date.
My Observation:
I have checked in OPU3 for the respective plant and order type the scheduling type mentioned as Backward.
SMK u2013 903 (ie, opening period for planned order u2013 3 days)
In Routing we have two operations.
Requesting from forum people to give me the detailed calculation part on how this basic start date gets calculated / arrived.
Please let me know if you need any more inputs.
Cheers,
Kumar.SHi Kumar,
As per my understanding this is all decided/maintained through scheduling parameters which are defined in Customizing per order type, plant and production scheduler (from the material master) (Customizing for Shop Floor Control, by choosing Operations > Scheduling > Define Scheduling Parameters). In what follows the parameters are described that affect the scheduling of a production order. Further control parameters are described in the course of this section.
According to your query I suggests ,In Customizing you can specify that an order is rescheduled as soon as it is a certain number of days late (Start in the past indicator). The system then automatically carries out today scheduling when the basic start date of the order is more than the given number of days in the past. This scheduling is a type of forward scheduling starting from todayu2019s date and where the necessary reduction measures are applied .
Else you can also specify that a production order is to be rescheduled automatically whenever it is saved (indicator Automatic scheduling). If changes relevant to scheduling are made in the order and this indicator is not set then the order is given the status NTER (dates not current).
Hope this would be useful for you at some extent.
Please revert if required .
Regards
Chandra -
Error while entering Basic Pay 0008
Hi Experts ,
In Transaction code PA40, while hiring an employee, In Basic Pay 0008 Info type, Following Wage types are to be entered
1001 -Basic Pay 4000 INR
2000 conveyance
2005 House Rent Allowance
2010 Transport Allowance
2015 City compensatory Allowance
W. Type 2000, 2005, 2010, 2015 are based on PRZNT of Basic Pay
i.e. Different % valuations for these wage types
In Table T539J , the % weightage has been entered for wage type 2001, 2005,2010 & 2015 & other wage types.
The value of the wagetypes based on PRZNT should be calculated based on Basic Pay 1001 wagetype.
But, the following error is displayed IndVal of wage type 2005: No entry in table T7INA9 for key 40E2M12005A on 20070820 Message no. RP032
In Table T7INA9 , the entries of Wage types 2000 to 2018 (PRZNT based) is not there. Do I need to enter the other wage types in Table T7INA9.
Allowance Grouping has been defined.
Pls advice ,
Thanks in anticipation
PratikDear All,
Thanks a lot for the support, some changes were required in Table T539J
which i made and now i am getting desired entries.
The position of two wagetypes to be entered in the table was in wrong manner
ie; HRA 2001 PRZNT Basic 1001 10%
II had entered in a opposite way. now
AFTER CHANGING THE ERROR IS RECTIFIED
Also in RAP changes were made.
Thanks for the support given
Regards
Pratik -
Hi everyone
Hoping that there is an easy workaround to the below
I am calculating GM at a SKU level, however would like to be able to present the data at a product category and/or customer channel level
However when I drag in my calculated field of GM per SKU it recalculates GM at a average product category level and uses that new calc to determine GM achieved, rather than summing the GM per product catergory.
I basically want the GM to calculate at a SKU level but be able to present the data at an aggregate level,
In excel the formulas would look like this:
GM per SKU = ytd sales/ ytd sales quantity
GM achieved for day per SKU = GM per SKU*qty delivered for the day
GM achieved per category = sum(GM achieved for all SKUs in category)
It looks like BO recalculates GM per SKU depending on what product field I drag in ie if my table to calculate GM had product catergory rather than SKU I am getting GM per category, which then impacts my final calculation
I basically want the calcs to keep running at a SKU level but be able to present totals at an aggregate level, rather than aggregating data then calculating GM
Hope this makes sense. Can attched screenshots if required.Hi,
What you describe sounds very similar to the user guide's definition of the calculation contexts. Read the chapter "Understanding calculation contexts" and make sure that you get to know the input and output calculation contexts:
http://help.sap.com/businessobject/product_guides/sbo41/en/sbo41sp3_ffc_user_guide_en.pdf#page=16 -
Dear Experts,
When the user is paying Basic adjustment for employee the PF contribution is calculated correctly (BasicDABasic Adjustment) x 12% but for the pension calculation the system is calculating only Basic+DA x 2% and Basic adjustment is not included. T539J is configured for Basic adjustment against pension wage type for 2 % but still getting the same difference. Please guide me
Thanks in Advance
UpenUpen it means Basic Pay Adjustments were not included in the the Pension Caluculatioin right ?
-
Creation of a PCR for calculation of LTA
Hi Experts,
I have an India Payroll requirement where i need to write a PCR with the below conditions:
1) The Employees would be eligible for the LTA from the very first month of their Service as per below conditions:
a) All active employees in a given month are eligible for LTA for that given month.
b) All employees joining the Organization on or before 15th of the month are eligible for LTA of that particular month.
c) All employees leaving the Organization on or after 15th of a particular month are eligible for LTA of that particular month.
2) Calculation:
Latest Basic Salary in the month of March *No of months worked in a particular financial year(step2)*LTA Percentage
For this i would need a wage type which i can use as a counter for the entire financial year.So what model wage types i can use to create a counter wage type which would get stored in CRT and can be used as a factor at the end of the financial year to calculate LTA.
Thanks & Regards,
Punam JhaHello Punam,
Please go through the documentation of payroll function INLTA in your system and then create your schema.
Best Regards,
Deepak.. -
New Condition type of freight on basic+excise duty
Hi experts,
I have a requirement of new Condition as "State Freight" which will be calculated on basic + exciseE.CessSECess.
Request you to send complete steps for the same.
regards,Hi,
Tocreate a new condition, go to tax procedure, select tax code ,create new condition ("State Freight"). Write a coding, which should calculate on basic + exciseE.CessSECess .This taotal should reflect into the condition State Freight. This program needs to assign to condition. The need of writing code is not to disturb the standard schema. I hope it will resolve your issue. Thanking you. -
Tax calculation (excise duty and purchase tax) issue
Hi friends,
we want to automate MIRO.
we are using BAPI ( BAPI_INCOMINGINVOICE_CREATE ).
while posting that does not propose excise duty ( Modvat ) amount and
sales tax component is calculated on basic price instead of Basic plus Excise.
we are using BAPI in calculate tax mode.
( BAPI_INCINV_CREATE_HEADER-CALC_TAX_IND = 'X'. )
In MIRO:
Basic price - 100.00
Excise duty - 16.32
(16.32%) -
Total1 - 116.32
sales tax - 4.65
( 4% Total1 )
Total - 120.97 - Invoice amout
In BAPI
basic price - 100
Excis duty - 0 - Since not proposing while posting
Sales tax - 4
(4% on basic) -
104
hence difference is Excise - 16.32 + Tax component on Excise 0.65
total difference is 16.97.
please give me the solution for this problem.Hi Experts,!!
Kindly let me know How to use Multiple vendor in BAPI_INCOMINGINVOICE_CREATE.
We have a requirement that in PO multiple vender will be maintained, we have to create individual wise invoice for multiple venders.
I have tried to create it is posing to one main vendor only.
pls. Give some solution
Regards
Sathish J -
Excise duty an VAT Calculation
Dear SAP Gurus,
I want to calculate the price for the PO with excise duty, education cess and sec edu cess for which VAT/CST is applicable.
Please clarify how this calculation work, as per my understanding ED is calculated on basic price say
basic price - discounts = X
X * ED (8%) = Y.
Y * edu cess (2%)
Y * sec edu cess (1%)
In condition records how do we define/alculate edu cess on ED and sec edu cess on ED.
This will amount to price with excise duty. On this we need to add VAT (4%) or CST (12%) + Freight cost. This will be the final cost of the PO.
Kindly clarify the above calculation if its correct and if you please give me the condition type for all and how to map the same in the config setting. And also VAT/CST we define in the calculation procedure in M/03 or we need to define the same in condition records(FV11) or in Tax code maintenence (FTXP).
Please help.
Regards,
Prashanth PaiThe tax code in PO follows the FI pricing in OBQ3, TAXINN...
it is been maintained as u have described..
first create tax code in FTXP say F1= 8.24% excise and 4% vat
then maintain conditions records for the above tax code if FV11
for JMOP( BED) = 8
JEC1(ECESS) = 2
JSEP(SECESS) = 1
JMX1(BED % CREDIT) = 100
JEX1(ECESS% CREDIT) =100
JHX1(SECESS% CREDIT) = 100
JVRD(VAT CREDIT) = 4
then assign tax code to company code in tax on goods movement < basic setting < calculation based
the check the condition type please try OBYZ...
Maybe you are looking for
-
Upgrade from 7.1.2 to 9.3.1
Hi All, I have a query regarding the migration of Essbase applications from 7.1.2 to 9.3.1. I have been able to migrate the apps with the outline, rule files, and calc scripts. But I am stuck up in migration of security. Can anyone please let me know
-
How can you change the bubble color in the message app on the iphone 5
How can you change the bubble color in the message app on the iphone 5?
-
Call Centre???
Hi, I have been asked to suggest an SAP solution to this: Log calls/requests to HR from employee's (e.g. leavers, absence, Leave, transfers....normal HR processes). Basically, the requirement is a call centre and the SAP Solution would be CRM but we
-
I have a Creative Labs 73PD0000000 webcam. Where can I find this driver? If It is possible I'd like to download the Windows XP's webcam driver! Thank you!
-
Apache/linux PathTrim failing
wl-510/sp5 apache 1.3.12 http://server/HelloWorld.jsp works http://server/servlet/Servlet does not work I should note that I took the weblogic.properties from a working system (albeit solaris). I get this in my