Hi
If  QUALITY PLAN  is assigned to any material then it should appear in QA32 that is quality lot must be created.The problem is such that during starting of new period i.e. every month starting Inspection lot is not getting genrated for already asssigned Quality Plan materials.The problem gets normal after 4 -5 days after the month start.
Please suggest any solution
Regards
Pallab
+91 9960331816,Pune

Hi Anup,
The thing is like that we generally maintain qulaity plan to any inprocess/incomming material.Now for the entire month the in process material after productuion order confirmation will get appear in QA32 then results recording is done then UD.
Now in the starting of every mionth when new periods opens for couple of days the in process material give errors that inspection plan is not maintained.Where as these are those materials which responded Ok in the last month with inspection
plan maintained.Also after couple days of starting of the month things become normal
Regards
Pallab
+91 9960331816(Pune)

Similar Messages

  • Inspection lot not getting generated after PurcGR

    Hi,
    Inspection lot not generated after doing GR for a purchase order. what could be the reasons?
    for the first 2 puchase orders, Inspection lot was created. however, for the 3rd Purchase order of 100qty, i did GR for 50 qty only. after then for new purchase orders, the material status has become unrestricted and directly going to stock.
    Inspection type 01 is mainted in material master
    QM info record has been maintained.
    please clarify

    Hi Nagaraj,
    Try the following.
    1. Check the inspection set up in the Material Master record for inspection type 01 whether 'post to inspn stock' is selected. If not, select it.
    2. Check in Customizing for 'QM in Procurement' in 'Define QM system' activity, 'certified QM system - skip' is marked(Actual QM system). If this indicator is selected no inspection lot is created even if there is an active inspection type. This is valid if you maintain a target QM system in QM view of Material Master (Purchase data).
    3. Check in IMG set up :
    Quality Inspection -> Inspection lot creation -> Inspection for goods movement  - whether inspection lot origin 01 is specified for movement type 101 and also ensure that QM is active for this movement type.
    Please revert after trying these options.
    Regards,
    Swati

  • Inspection lot not getting generated by Z inspection type

    Hi,
    I created a inspection type Z1 , copying the inspection type 01. I guess I maintained all the required configurations or conditions.
    I maintained the inspection type Z1 in the QM view of a material with status Active, but I am not able to do MIGO, neither the stock type is coming as Quality Inspection automatically in both the Purchse Order creation and MIGO. As a reslut, the inspection lot is not getting generated.
    I am also not able to create a manual lot but QA01, Its giving error as "Inspection type Z1 not maintained for material X" .
    Thanks in advance for your valuable suggestions.
    Regards
    Kunal

    Dear check preffered inspection type in material master QM view and do the GRN.
    Check and Revert.
    Cheers
    KK

  • Inspection lot not getting generated for schedule in stability study

    Dear All,
    Need your urgent help to solve a issue. I need to perform inspection of material after specified interval of time for which i am using stability study process. Following are the steps which i have followed :
    1) Create initial sample (physical sample created)
    2) Confirm initial sample
    3) Initial test inspection lot( Inspection lot created )
    4) Complete initial test
    5) Specify storage conditions (Physical sample created with CRTD status)
    6) Create testing schedule( Maintenance schedule is created )
    7) I have scheduled maintenance plan through IP10 tcode. All the calls are getting generated.
    Now i have given manual call in IP10, but inspection lot is not generating.
    Please help to solve this issue ASAP.

    Dear Craig,
    Yes i have activated inspection type 16 to material master.
    Actually issue is solved now, I have missed one step " Store stability Sample".
    Now the lots are getting generated.
    i am closing this thread now.

  • Inspection lot not getting generated during SD delivery

    Hi QM experts,
    I am working on QM in SD function. I activated inspection type 10 in the material master in QM view as shown below.
    I created a QM info record SD through QV51 for the combination of customer and Sales organization and assigned the material and quality inspection as before delivery as shown below.
    Now I created a sales order for the material with sales organization and when I making the delivery system is allowing delivery and no inspection lot is generated and delivery is also not stopped. am i missing something..can u please guide..
    Thanks
    Kumar

    Hello,
    You have activated 10 and 11 both , any specific reason ?
    If you activated 10, then system will allowed you delivery check QM customization---> During Shipping. have you assigned inspection type against Delivery type in customization ?
    Regards

  • 09 inspection lot not getting generated

    Hi Friends ,
    I have one material batch for which next inspection date is 7.6.2014 . I have activated 09 inspection type in material master . Now when I am executing QA07 for the material  with checkbox " To insp. stock at lot creation" selected and with initial run in days = 4 . System shows following msg in green :
    "No batches found for processing"
    But it should create a lot for the above batch because inspection date is 7.6.2014 . Stock also exist
    Regards

    Please go through the following steps & maintain the same
    > Batch management should be active against material.
    > Next inspection date should be maintained.
    > Inspection interval should be maintained according to next inspection date.
    > UD must be completed for the previous inspection lot.

  • Inspection Lot not generated, with MIGO 561

    Hello All,
    Please help me with this issue.
    WHen i do MIGO with 561, inspection lot is not generated.
    So there is a setting in spro, if we check that, inspection lot wont be generated.
    So now in my IDES, i tried to uncheck that box.
    When i save this setting, I get the following error.
    "Fill table key for table T156Q only up to position 010".
    Please help with this issue.
    Regards,
    Piyush

    To load initial inventory in Quality stock and release it using Inspection lot  UD,   use movement type 563 instead of 561.
    With 561 movement stock is directly posted to un-restricted status. So there is nothing to be released from Quality stock.

  • Inspection lot not generated after goods reciept?

    Dear SAPIENTS,
    Inspection type 01,0101,08,89 and all activated in material master but then allso inspection lot not generated after goods reciept. Can anybody suggest here that what could be the reason.
    Regards,
    Kaushal Rai

    Hi Kaushal,
    For Inspection lot from GR, 01 Inspection type is enough.
    - Ensure 01 Insp type is active and Post to Inspection stock indicator is active for that inspection type.
    - Ensure the QM is active for 101 Movement type, SPRO>Quality Management>Quality Inspection>Inspection Lot Creation>Inspection for Goods Movements>Deactivate Quality Inspection for a Movement Type
    Regards,
    Keerthi.

  • Lot not show in MMBE quality insspection

    Dear expert
    i make planing for halb material  against 04 origin and also active inspection 04 or lot will be generated against 101 movement type. Now lot will be show on QA32 but not shown in MMBE in Quality inspection its quantity show only unrestricted stock.
    i want to show this quantity in quality for MMBE
    Because quality inspector take decision
    Please guide me
    Regards
    Priya
    Edited by: sapqm01 on Aug 26, 2010 12:57 PM

    Dear Vishal
    Thanks a lot. Now i understand thanks again and again
    regards
    priya sharma

  • Inspection lot 03 type not get generated

    Dear All
    I have set 03 inspction type in material master and checked lot origin of 03 in configuration also there with N task list type is assigned. but problem is inspection lot not genrated when i realsed production order,
    what should i check to find out this cause
    Regards
    Pravin

    I
    Dear
    I tell you the scenario,
    As here in prodution, they combine number of orders having  same material no.  into One Comboorder having different Order type for ex combo order having ZCOM order type and child order having PP04 order type.
    For Ex
    Combo order(50025)
            i
            i
    i              i                  I
    10029    10030        10031
    as given above structure
    we have developed on Z transction which combine all child orders and made one combo order with total of three, but order type of combo order is different and child orders having different order type.and when combo order released child order also get released but problem is inspection lot generated for combo order only  not child orders
    what would be the reason
    Regards
    Pravin

  • Inspection lot not generated via CO07

    Hi QM Gurus,
    Does anyone know how we can generate inspection lot via CO07 (production order without material number)?
    I have done the steps below:
    Customized inspection type 03 in order type PP03 (OPL8).
    Created Reference Operation Sets 50000008.
    Created Inspection plan for ROS 50000008 and assign IMC in the operation.
    OSS note 675643
    Anything I missed?
    Any help would be appreciated.
    Cheers,
    Sun

    Hi,
          I think the problem is no material will be maintained. The background is user reference operation set & CO07 to create production order without material. Generally, oritinal insp. type should be maintaind in MM02 QM Tab, then 03 insp. lot can be created while Pro Order released. But now, as no material master is maintained, so we can not trigger 03 in QM TAB, and no insp. lot will be generated.
          I made the moderation like Sun listed, but no insp. lot can be generated. What the note says,it will take the material number from the superior order, conflicts with our purpose (without material).
           So my question is:
          1) whether SAP can generate insp. lot from Pro. order without material
          2) What's the superior order mean?
          Thanks
    Edited by: Margaretji on May 4, 2009 4:22 AM

  • Spool file not being generated in production server

    Hello
    Our end users are using automatic payment program F110 to print multiple cheques.
    The settings in SPAD are identical in Quality and Production Server,but some how
    spool file is not being generated in production.
    Test printing is fine in Quality server.
    Printer being used is Epson LQ 300.Device type is EPESCP2.
    We are using z custom page size ,and it is assigned to printer device Type as well
    Would be very great if some can can comment on which settings to check,as SPAD setting is
    same in both server ,yet no spool.Very Very urgent.
    Iam not sure ,whose domain is it now-BASIS or ABAP.
    Thanks a lot
    Nouman

    If there is a problem with the spool, the variant that is being in F110 parameters.
    As you are saying the quality system is working fine, please compare both the variants in Production and Quality systems.
    This should solve your situation.

  • Previews not being generated

    When I first set Aperture up during the trial, I left all the in the iPhoto library and referenced them. Since then I bought Aperture and now have it managing almost all of my masters (JPEG only at present).
    Like some others on the forum, I noticed that I was having problems with images showing up in the 'Aperture library' in iWork/iLife. It seems that only the imported example projects (with previews already) are showing up.
    I originally just entered the Serial Number into the Trial version but have since tried:
    0) Rebuilding the library via Command-Option on launch
    1) Updating Previews at various times both for the whole Library and for individual projects. If I delete all previews first then I can't even see the example projects in iLife/iWork.
    2) Reinstalling from 1.5.1 on DVD and using Software Update
    3) Removing Aperture, deleting all the receipts and reinstalling again
    4) Repairing permissions
    5) Deleting the library and recreating it from a Vault
    6) Adjusting the preview size and quality and currently have it at 1280x1280 at 6
    7) Importing the library as a different user: lots of time 'generating previews' but no more success.
    During this process, I decided to investigate properly inside my Aperture library and noticed that it does not seem to generate previews at all for me (despite 'Processing previews' in the 'Task list' window). ApertureData.xml seems to only contain ImagePath entries for the example projects (unless I deleted their previews during the troubleshooting process)
    At one stage I wondered whether it was connected with my camera as pictures from my (and other people's) Canon A95 seem to need to be imported via iPhoto before Aperture will read them properly. However, photos from a different (JPEG) camera do not form previews and nor do the IR RAW files mentioned recently on this forum (and generating all new previews from the example projects does not work).
    Except for the previews (and the Fullscreen filmstrip window popping up over other windows when in workspace layout, but that's another issue) my experience so far with Aperture has been very positive.
    Can anyone suggest anything else to try? TIA.
    I notice that every time I start Aperture it claims to be processing all my previews. If I try a slideshow, it seems to get stuck 'Rendering Previews' as the progress bar does not advance (including an example project with previews deleted). Of course, the slideshow works for the example projects with their original previews intact.

    That I would accept as the reason if it weren't for the fact that they generate the thumbnail preview inside the 'get info' panel for the file (and I have seen these thumbnails generated by Finder in the past inside Finder windows and on my desktop).
    What I see going on here is that files that have been 'claimed' in launch services by either Emacs.app or DrScheme.app display this problem and scheme files did generate the proper thumbnail previews in the past and continue to do so today... I just looked at a scheme file in 'get info' and watched the twirling icon twirl and then be replaced by the preview thumbnail:
    http://imgur.com/21iRo.png
    There seems to be no technical difficulty in generating the thumbnail preview in the 'get info' panel.
    Unfortunately, I don't have a machine with a fresh install of the OS lying around, so I can't verify my memory of seeing these previews being attached to the file types in question. I'll have to wait and see next time I get a new mac (I won't wipe my current set up just to do this... the icon problem doesn't bother me that much)!

  • Purchase Requisition are not getting generated for External Procured Materi

    Hello PP Guru,
    The is a issue which the client is facing.
    The requirement is as follows
    There is material which is externally procured.
    They do the MRP run by using MDBT.
    Now the problem is Planned orders are getiing generated instead of Purchase requisition.
    It should always generate PR instead of planned Order.
    When the check in ME57 the PR is not reflecting, but when the check in MD16 the planned orders are getting reflected.
    Every time they have to convert the Planned order to Purchase Requisition in MD16.
    So can you please let me know as to why is this problem.
    Thanks & Regards
    Nilesh

    In the variant which you use in MDBT, modify the value for Create purchase req. to 1. Now if you execute MRP with the new / modified variant system will always trigger PR irrespective of the opening period.
    But if you want PR within opening period & outside of it should be planned orders, then maintain 2.

  • BPM alert not being generated

    Hi guys,
    I'm having quite a little trouble in doing one thing which has been done for several times but which is giving  me a hard time...
    I've created a bpm process which in an error condition will trigger a simple alert.
    I've tested the process and everything goes allright, except the alert. What is happening? Well, the alert is not being sent to my inbox. Why? Maybe because the alert is not being generated.
    I've went to sxmb_moni_bpe and everything is OK. I can see the message of the alert being fired. After that I went to slg1 to see if my alert is being generated, and the answer is no. It's not being generated....
    I've gone through Michal's blogs and everything was checked...The question is, if I execute RSALERTTEST with my alert category, the alert is generated and send to my inbox. Do you have any ideas?
    Thanks a lot for your attention

    Hi,
    Yes the job scheduling is needed only for Sp14 and below.
    Can you recheck if the Alert is actually getting triggered or not in the BPM in the control step? Make sure that you have given the correct Alert Category in your Control Step and also, make sure that the recipient in your alert as well as the Alert Inbox entry you are seeing is the same.
    Finally, refresh the Alert Inbox.
    Regards,
    Bhavesh

Maybe you are looking for

  • Help Rgd. BAPI for Creation of Inbound delivery Document

    Hi all, I need a Bapi to create inbound delivery document without using PO reference. I have seen the below BAPIs. i) BAPI_IBDLV_CREATE_FROM_OBDLV,  ii) BAPI_GOODSMVT_CREATE. I am not sure whether they are for creating inbound delivery document witho

  • Reading the data from web

    Hi guys , I am new to j2me ,i am going to start a project named onlineNews for this project i need to read the data from web.can anyone help me with a sample code for reading a data from web thank u for spending your precious time

  • Windows 7 Pro 64 bit - WIA service won't stay "on"

    I have to install a Brother AIO printer/scanner using a network connection.  Using a brand new Acer Veriton X275 with 4gB RAM, new HDD, built in graphics card.  The printer driver went in, it prints.  The scanner though isn't working.  Brother (the A

  • Multiple Hierarchy Use in EVDRE

    Hi, How to use the PARENTH2 hierarchy in Evdre report. I need that always the report opens with H2 hierarchy instead of using H1. Tried using MEMBERS(H2) but does not work. Please advice... Regards, Abhinav

  • POSTSCRIPT PRINTER FOR WIN7 PRO 32

    Which  HP  printers with PostScript emulation are supported fofr Windows 7 (pro 32-bit)?. It seems the Color Laser Jet 3800,  which did fine in both PCL and PS on my XP, are not- except with Universal PS dirver, which is so slow that timeouts occur.