Quota between inhouse Manufactured & external procured materials in APO

Hello All,
Scenario is like this:
I have semi-finished material. Suppose it is 'AX'. Now this 'AX' material I am manufacturing & procuring from external sources also. Material 'X' is APO material(MRP Type='X0'). Now I transferred MM scheduling agreement of same part in APO also through Integration Model, to get schedule lines as well as manufacturing orders after Heuristic run. When I checked in APO, MM scheduling agreement was transferred to APO but the Quota  which I maintained in R/3 in MEQ1(% between in-house production & external procurement) was not in APO. Now in this case if I do the Heuristic run I got only Planned Orders(manufacturing orders), not any schedule lines against the MM Sch. Agreement. Now at this moment I was able to convert any planned order into MM Schedule line.
After this I created the quota in APO itself. After creating the quota I was able to get the planned orders as well as MM schedule lines based on maintained quota.
Regarding the above scenario I have some doubts. Please answer:
1. Is it a correct practice, what i did ?
2. I was very confused that when we maintains each Master Data of APO materials in R/3 why we need to create the same quota in APO also.
3. Is there any way to transfer this quota from R/3 to APO ? If yes please tell me the steps. This will save a lot of my stuff. 
Thanks in Advance !

Hi,
1. Yes, as per the scenario mentioned and since the planning is taking place in APO, quota is needed to be maintained in APO itself.
2. This is because planning needs to input like proporational planning to to find out the right sources using quota and transportation lanes. But its master data intensive.
3. In other way, I would see no need of maintaining the quota in R3, instead you maintain the quota only on APO. (if I understand requirement correctly).
there is one way, you can avoid quota maintenance in APO. Here you need to use CIF user exit (APO outbound, C5) to modify the the procurement proposals of APO while getting transferred frm APO to R3 based on the quota maintained in the R3 side. This seems to be bit complex.
Hope this helps
Regards
Venkat DR

Similar Messages

  • For Externally Procured Materials (ex - ROH) - SG's are maintained or not?

    Hello
    Do I need to maintain SG's ( like SG10, 40, 70) for ROH as these are externally procured?
    As I see since ROH are externally procured, no need to maintain the SG (10, 40, 70,etc) in MRP 3 view of the ROH* material master as SG's (10, 40, 70)* are meant for maintianing PIRS & PIRs means it is inhouse production
    Iam not limiting myself to SG's (10,40, 70) for ROH, instead any SG need not be maintained for ROH (externally procured) 
    If I want to see that ROH materials get consumed by  the FERT then maintain SG 40/70 for the FERT/HALB (inhouse production) that should consume the ROH (externally procured)
    Questions:
    Q.For externally procured materials do I need to maintain the SG?
    Q. If no need to maintain SG's for externally procured materials then what fields do I need to maintain to see that externally procured material which are used in the finished product gets consumed by sales orders?
    Please clarify
    Thank You

    Pradeep
    Thank you for your reply & time
    If the component is semifinished & is externally procured, then following settings needs to be maintained
    Procurement Type : F
    Special Procurement Key : 30 (subcontracting)
    But Subcontracting(30) is used when we want semifinshed product to be manufactured outside the company from a raw material issued by the company
    & control key we maintain is PP02
    In above scenario, then we go for subcontracting or else we need not maintain the subcontracting
    Please clarify
    In your answer (" u have to set Individual/coll = 1 or blank at MRR of Down level material.")
    what does MRR stand for
    Due points have been assigned

  • MRP - Create Planned Orders only for Externally Procured Materials

    Dear All,
    We have a scenario that our client gives us the daily requirement schedule for the current month and a monthly forecast for future months so that we can plan our externally procured materials based on the forecast.
    Now I only want the MRP run to create Planned Orders for HALB and FERT based on my current months daily schedule and planned orders for ROH (Externally Procured) based on the next months forecast (monthly).
    I dont want the system to create planned orders for HALB and FERT from the forecast. The requirement for the ROH are however derived from the Finished Good BOM and the forecast is also given for the FERT material. I know its a long shot but is there a possibility in the system to do such a thing or a work around?

    Your business case is not clear; MRP will create planned orders for inhouse produced materials, and either planned orders or purchase requisitions for external procurement.
    You can choose to convert or release external procurement for a long time ahead (eventhough taht if you have proper lead times defined you can release by lead time), but convert inhouse planned orders to production orders only for next period (week, month). Actually this is common practice.
    So I fail to understand your problem.

  • Parallel MRP run for Internally and Externally procured materials

    Hello all,
    we want to run MRP with different settings for externally procured materials (create purchase Requisition) and internally produced materials. The choices provided my MRP run is either create planed order or Requisitions when run background. Is the activation of user exit M61X0001 the solution to this issue?  I can recall that we had done this is some project in the past, not 100% sure to be sincere. Can anyone help on this?
    Thank you for any help.
    Edited by: Ioannis Salichos on Aug 11, 2010 11:51 PM
    Edited by: Ioannis Salichos on Aug 11, 2010 11:57 PM

    you are right, this is the user exit that can be used to control this.
    see an excellent "how to use"  from R Brahmankar
    in this thread:
    Re: mass MRP run

  • ATP for manufactured and procured materials

    We have a scenario that we have essentially a make-to-order process but occassionally, due to setup costs, manufacture more than what is needed to satisfy the sales order line item that triggered the planned/production order.
    In other words, when sales order ATP executes, we would like  to first check for unrestricted inventory to supply the order.  If there is available inventory, it should be used on the sales order line item.
    If there is no inventory on hand, we want MRP to run and create an order using the Make-to-order process.
    Can someone help wtih this?
    Thank you,
    bak

    Hi Bak,
    The only way i have seen this done in the past is to create two materials codes for the sames material one is the stock item and the second is MTO, so when you have stock you can use the stock material code or there is none in stock to use the MTO material code.
    The second option is too have one material that is MTO but when the order is placed to check if there is available stock and then to do a Stock to sales order stock material transfer. then when you run the ATP check the stock is available and no production is generated

  • Bom for External procured materials

    Hi, my bom is as follows. in top level semi product is F procurement type and next to this is 2 roh components of F procurement type. when i run md02, no pr generated for bottom level materials. pls advise why it is not generating the pr's for the same.

    Run MRP (MD02) for lower level materials as well, then you will get PRs. If you want PRs at all levels, then run MD01 in NETCH mode.

  • Price valuation with standard price in case of external procurement

    Dear All,
    I have the following scenario with my client.
    All the materials will be valuated with price control S, whether procurement type is E or F. We don't have any problem if procurement type is E. But where as if procurement type is F and price control indicator is S, the system calculating the moving average price and as well as standard price is also updating for some materials. For some materials there are not moving average prices.
    1. Can any one tell me when SAP calculates both moving average price and standard price? is there any setting to be done.(procurement type F and price control S)
    2. there are differences between moving average price and standard price, ofcourse there may be a difference, but in some cases the difference is more and higher than the standard price, this may cause financial loss to the company. How can solve this.
    full marks will be awarded.
    thanks & regards,
    Ramesh Balivada

    Hi
    Moving average is updated for External purchases although price control is standard price in all cases where there are movements in materials i.e., when they are purchases...
    Check for the materials where there are no updation of moving average and externally procured materials, there might not be any purchases..
    There would be no losses as even though it is calculating mov avg price, the stock, consumption is calculated with std price only.
    Check both the cases where there are std prices and check for cases where there are both prices getting updated.
    Regards,
    Suraj

  • Cross Plant Planning for External procured Material in MRP with their stock

    Dear Gurus,
                 I have one requirement my client want Cross plant planning in MRP. this plants are only site plants no Manufacturing. All materials in these plants are Externally Procure Materials(F). Now they want cross plant planning  for Externally Procure Materials or cross plant planning  for Externally Procure Materials  with consider all plant stock details while planning.
            can you tell me procedure for this,
    Thanks in advance,
    Regards,
    Devraj

    Hi,
    In R/3 you cannot consider all plants in planning, you have to use SAP APO to achieve your goal (if your goal is to optimize the procurement in your plants). When you execute MRP run in R/3 it will only consider the details of one single plant.
    I mean if you have several plants used for external procurement, and you want to make an optimal decision considering all the stocks and open transactional data, requirements in those plants, it is not possible in R/3 as per my knowledge - multi site/plant planning won't give you such optimal solutiion.
    http://help.sap.com/saphelp_47x200/helpdata/en/f4/7d2d4d44af11d182b40000e829fbfe/frameset.htm
    http://help.sap.com/saphelp_apo/helpdata/en/7e/63fc37004d0a1ee10000009b38f8cf/frameset.htm
    Regards,
    Csaba
    Edited by: Csaba Szommer on Nov 17, 2008 10:27 AM

  • External procurement for inhouse material

    Dear All,
    I have maintained 0 as the external procurement status for the material type inhouse. But my client want's to send this material for sub contracting which is not exactly external procurement. but the system is not allowing me to do so giving error blocked for exterrnal procurement
    How to reslove this. is there any exit for this issue.
    Please help

    Hi,
    Please check in material master >> Purchasing view >> Any block indicator is exists for external block.
    If yes please remove it
    Regards,
    Mahesh Wagh

  • Quota for External Procurement

    Hi,
    Can any One please tell me how to create quota arrangement for external procurement relationships using BAPI.
    Thanks In advance.
    Thank you..

    You can always use BAPI BAPI_QTASRVAPS_SAVEMULTI2
    Go to SE37 and test out the BAPI. Ensure there are T Lanes and mode for creating the inbound QA for external Proc.

  • External Procurement with MRP based on sales demand w/o Production unit.

    Dear Friends,
    Plant AAAA is a central warehouse (Distribution center),from where materials are dispatched to other storage locations.
    AAAA is non manufacturing unit and is dealing only with FG's.
    Sales demand will come from different storage locations,based on which external procurement of FG's will be started.
    1.,how the sales demand can be turned into external procurement through MRP?.
    2.Please provide the customization settings to achieve the same.
    Regards,
    Venkatesh

    Hi Venkat,
    Try to use the functinality SOP, where you can maintain the demand in the system by T-code MD61 after getting all the sales demand from various locations,
    When you run the MRP, this demand will be considered & accordingly procurement proposal will be generated by the MRP run.
    Also you can go through below links sublinks for understanding about SOP,
    SOP basics

  • Capacity Planning for External Procurement Material

    Hi, I have the following requirements.
    MRP Scheduling is getting executed material level (material no, plant) with scheduling type 2 which means lead time scheduling using MD02 Transaction Code. This is works fine for the Inhouse Product. In order to achieve lead time the functional team has maintained the necessary routing/workcenter configs.
    The business needs the same functionality "Capacity requirements calculation" for the external procurement material. Business is willing to maintain routing/workcenter config.
    Currently standard program (MD02) is not considering the Capacity planning for the external Procurement material.
    Could you please suggest is it can be controlled through programming.
    Kindly suggest the function modules for Capacity Planning - materialwise, plantwise.
    Please suggest.
    Thanks
    Giri

    Hi Giri
        I think the requirement is not mentioned clearly. Capacity is required only if the material is assembled/produced in house.
    Anyway try this. Set the Procurement type to X in the MRP views in material master. You might have to define your custom material type so that it does not force the procurement type to F. Try the feature called "Quota arrangement". The idea is to define the material in such a way that it can be procured externally or produced in house. With quota arrangement you can say what % has to be bought and what % to be produced in house. If it is produced in house then you can have capacity requirements.
    Regards
    Pragnesh

  • MD02 - Capacity Requirement Plan for External Procurement Material

    Hi, I have the following requirements.
    MRP Scheduling is getting executed material level (material no, plant) with scheduling type 2 which means lead time scheduling using MD02 Transaction Code. This is works fine for the Inhouse Product. In order to achieve lead time the functional team has maintained the necessary routing/workcenter configs.
    The business needs the same functionality "Capacity requirements calculation" for the external procurement material. Business is willing to maintain routing/workcenter config.
    Currently standard program (MD02) is not considering the Capacity planning for the external Procurement material.
    Could you please suggest is it can be controlled through programming.
    Kindly suggest the function modules for Capacity Planning - materialwise, plantwise.
    Please suggest.
    Thanks
    Giri

    Hi Giri
        I think the requirement is not mentioned clearly. Capacity is required only if the material is assembled/produced in house.
    Anyway try this. Set the Procurement type to X in the MRP views in material master. You might have to define your custom material type so that it does not force the procurement type to F. Try the feature called "Quota arrangement". The idea is to define the material in such a way that it can be procured externally or produced in house. With quota arrangement you can say what % has to be bought and what % to be produced in house. If it is produced in house then you can have capacity requirements.
    Regards
    Pragnesh

  • Schdelung for externally procured material.

    Dear Gurus,
    We have defined planned delivery time for externally procured material. After MRP run system is generating delivery dates for that.
    We want if there is capacity constraint at supplier's end then how to handle this issue in MRP run.
    Example -
    PR generated after MRP run for XXX material code for 5000 kg and required date is 15/06/2009.
    Supplier's manufacturing capaicty of this material is 500/day i.e. from today he will be produced only 3500kg.
    In case shop floor plan will not executed due to shortage of supplies.
    How to map this scenario in SAP so that MRP controller will come know that the said material will not be available on required date and he will have plan some thing else during that period.
    Regards,
    Abhay

    Have you tried with Lot SIze Data in MRP 1 view
    you can give 500 in Maximum Lot Size
    and lot size as per your business need for example 7 days no split quota something like that
    After MRP run, your planner can see the next material expected availablity and plan the production
    otherwise, if company permits for surplus inventory , then keep some buffer as Safety stock and plan accordingly
    Edited by: deshamol on Jun 9, 2009 12:59 PM

  • Difference between repetative manufacturing and discreate manufacturing

    Hi,
    Guru's
    What is the difference between repetative manufacturing and discreate manufacturing in product costing.

    Dear Manish,
    Repetitive Manufacturing 
    In repetitive manufacturing, master plans are typically created on a period and quantity basis (reduction in individual lot and
    order-specific processing). A quantity of one product is manufactured over a certain period. The product is processed in a constant flow and interim products are generally not stocked. In repetitive manufacturing, you usually find that the effort required for production control is significantly less than is required for single lot and order-based production control and the recording of actual data is kept simpler. Repetitive manufacturing can be used for various industries, such as the
    consumer packaged goods industry, the electronic industry, packaging industry, for example.
    You can use Repetitive Manufacturing purely for make-to-stock production, or in a sales order-oriented environment, such as found in the automotive industry.
    Discrete Manufacturing
    Discrete manufacturing is characterized by requirements that occur on an irregular basis and a workshop-oriented process.
    The Discrete Manufacturing scenario can be used in different variants, production by lot size, make-to-order production and assembly processing. The variants differ mainly in the type of planning conducted before-hand and in the relation to the sales order. Production by lot size is identified by the grouping of requirements into lots during requirements planning, and by planning with existing basic data. Production by lot size is independent of a particular sales order. Make-to-order production describes the production of a material with reference to a particular sales order. The manufactured quantities are managed, in terms of stock, directly for the individual sales order. They cannot be exchanged with the stock of other sales orders. Starting from the sales order, single-item planning can be allowed as far down the bill of material (BOM) structure as you like. Assemblies and
    components can also be procured for the sales order that generates the requirements, and managed in stock for this sales order. If the product is a configurable product, the system chooses a variant for the customer based on the characteristics that he or she selects. A sales order BOM can then be generated for the sales order. This BOM is used to produce the product.
    Assembly processing is a form of make-to-order production, in which the production order (assembly order) is created together with the sales order. In assembly processing the components for the product have, in general, already been produced. They only need to be assembled. The advantage of assembly processing is that an availability check is carried out for the components when you create the sales order. This increases the reliability with which dates can be confirmed
    considerably. Changes to the sales order are automatically also made in the production order and vice-versa.
    And also you can follow the below link to know more about REPITITIVE MANUFACTURING its a pdf document from help.sap.com
    http://help.sap.com/printdocu/core/print46c/en/data/pdf/PPREM/PPREM.pdf
    One More Example
    Repetive is usually a continuos flow, good example is making 5000 tv dinners you know how long it takes to make qty1 very little defects or fall out and you always have everything on hand to start the run, you may also make the same run 2-3 times per month so a cost collector is ok all cost go to top level.
    Discreet, You do have falls out reworks and move into production missing materials, long lead time its essential to know what and where it is at in production, cost may vary a little but each production order will be costed independantly for review.
    Best Regards
    Mir
    Edited by: mirosmank on Dec 28, 2010 11:25 AM
    Edited by: mirosmank on Dec 28, 2010 11:28 AM

Maybe you are looking for

  • How to debug module pool program

    Hi everybody, How to debug module pool program ,please send any material for module pool programming . Thanks & Regards, Siddivinesh.Jogu [email protected]

  • LMS 3.2: WISM not reachable

    Hey Pros. When I try to add WISM cards to the LMS they are not managable. Neither inventories nor configs can be collected. It's telling me "device not reachable". The community strings are correct and by trying "Management Station to Device" it says

  • The book is in the iBookstore, but...

    My compilation book of gardening articles and photographs was accepted by Apple and went live in the bookstore yesterday. After seven months of work, I was thrilled! Then I downloaded the sample chapter (the book has 164 pages, 53 chapters and as I s

  • Max number of pin changes

    I m new at bb playbook . Whenever I try to download any app, it gives msg that's have reached maximum number of pin changes for this account '.  Now how to resolve this problem,  kindly help immediately 

  • RequestDispatcher and stuff

              Hiyas,           I use a RequestDispatcher to chain up a couple of servlets which then           forward off to a jsp page.           I've also mapped the first servlet to "/index.html".           Now, when the request "index.html" I go thr