Reconciling labor costs with GL

Hello,
I have an issue reconciling labor costs with GL.
The report "Generate Cost Accounting Events Report" shows the total amount for labor cost transactions as $10M
wheres after running the "PRC Create accounting" the journal posted in GL is only $9M.
How do i find out the discrepencey of $1M. Are there any reconciliation reports available to compare the transactions between GL and PA.
Note: There is no data in gl interface and there is no exceptions reported in distrubute labor costs ,and cost accounting event reports

Looks like there might be $1MN not accounted, check for expenditures labor and trying to do a export from expenditures inquiry screen for a date ranges and then compare with the report data
also looking for any exceptions, run the exceptions report detail request
Thanks
Krishna

Similar Messages

  • How to handle labor cost?

    Dear All,
    Scenario:
    I have a finished component ;an assembly of 3 items,how to handle the labor cost i am paying for assembling in SBO.
    could you all please write in detail .
    Thanks,
    Nandakumar

    Hi Nandakumar,
    you could have a look at this Expert Empowerment Session:
    PDF:
    [18.05.2007 -  Moving Average Price calculation - effects of Rounding|https://websmp203.sap-ag.de/~sapidb/011000358700000418832007E/KP_MAP_in_BOM.pdf]
    Recorded Webex
    [18.05.2007 -  Moving Average Price calculation - effects of Rounding|https://websmp203.sap-ag.de/~sapidb/011000358700000415572007E/CW20_FIN_moving.wrf]
    There is an example involving a BOM with integrated labout costs.
    & also this Wiki:
    [How to include labour cost in a BOM. |https://wiki.sdn.sap.com/wiki/display/B1/Howtoincludelabourcostina+BOM.]
    All the best,
    Kerstin

  • Material & Labor Cost separate in Report

    Hi Experts,
    i have some list of orders now i want to track the Material and labor cost separately.
    Is there any standard report for the same.
    Regards,
    Kavvya

    Normally cost analysis is done by order type wise, plant wise & palnner group wise with respect to technical object(FL/Equipment). If you club all order then you will not have any meaning ful analysis. As such one report for material consumption(goods movmt in order) is there -IW3M.
    You will have to develop customise report (use  table PMCO)
    Shakti

  • How to reconcile Projects module with GL module?

    Dear Experts / Dina,
    If someone of you can help me in understanding the (Oracle provided) / (workaround) / mothod or procedure to reconcile Projects costing module with General ledger module ?
    Does Oracle Provides seeded mothods for reconcilling projects with GL? or Customer needs to create custom reports? If yes then what is the principle of designing such report?
    Your help on this is really appreciated.
    Thanks

    Unfortunately there is no easy answer to this. Oracle unfortunately do not provide a report that does this. To reconcile correctly you have to do it both ways i.e check that all that is in OP is in GL, and then all that ia in GL (that is project related) is in OP. This is because project related costs can get into GL and not get into OP (e.g. through AP). I won't launch into a detailed explaination, but the starting point in OP is a table called PA_COST_DISTRIBUTION_LINES_ALL which hold the most granular cost information and accounting CCID that can be used for reconciliation. Revenue reconciliation involves other table(s) depending on how you recognise revenue in OP.
    There used to be a product called Complete Projects Reconciliation from a company called Projected Consulting (changed name to Project) that did this - have a look on Google. But they no longer offer this as a product (consulting solution now)
    Hope this helps

  • Labor COsts

    Hi all,
    In a make to stock  product costing scenario :
    1) How does the labor costs and material overhead costs reflected in FI side.?
    2) Do we need to run any specific steps for these secondary costs to reflect in FI ?
    We collect these costs using Activity types and then how does this flow in to FI.
    Thanks,
    Sai.

    Dear,
    WEmake cost elements/value categories for your requirements(like internal labour, external labour, overheads etc.) Also he will make activity type for ur requirement like: activity type : Labour hours.
    U can also try this with T-code Ka01, Ks02, Kp26, Kl01.
    The assign cost element to value categories...in SPRO.
    Also assign this activity type in ur work center(cost center tab).CR02
    And in order cost tab , u will see the labour cost.
    Then we calculate variance WIP and settlment .
    Regards,
    R.Brahmankar

  • Labor Cost - PM Order

    Hi PM Gurus,
    For my PM Orders Operations I use employees to report time. I just need to know where and how to set the automatic account posting for the labor costs. Please explain.
    Cheers
    Deee

    Hi Andrew/Kedar,
    There are two things we are talking here the labour cost posting happening to Order and the final settlement to G/L. Both things are totally different from FI and CO perspective.
    For labour posting to Order:
    1.Define a Cost Center  - KS01(which is assigned to Work center)
    2.Define a Activity type  - KL01
    3.Define a Cost Element - KA01. This CE is secondary CE of type 43 - Internal Activity Allocation. You assign this CE in Activity type defined above.(Usually you dont have one to one relationship between CCtr and CE, so you dont assign Cctr on Cost ement)
    4.Using KP26 you define the rates of Cost Ctr and Activiy type combination.
    5.Whenever time is confirmed, the rate is picked up from KP26 and cost is posted on Order. If you see the Cost element report, this cost will be reported against the CE of type 43, defined above.
    FI/CO postings
    When you confirmation the Cctr on Work Ctr gets credited and the Order gets debited with the cost.
    For settlement to Cctr from Order
    1.This is a CO settlement. We are transferring Order cost to an Cost center, which is CO posting or internal posting
    2.In this case we need a  secondary Cost Element of type 21 as a settlement cost element, which is defined in your allocation structure of settlement profile. The settlement cost element could also be debit cost element, in this case you dont need to specify settlement CE.
    3.When you do the settlement the Order gets credited and the Settlement Cctr gets debited with that cost.
    Kedar - For your question
    1.If Settlement Cctr and Work Cctr Cost ctr are same
    In this case , since the source and trget Cctr are same, the Ccts gets credited initially and Order is debited. When you settle from Order to CCtr again the Order is credited and Cctr is debited. So the same is CCtr is credited first and then debited.
    2.If Settlement Cctr and Work Ctr are different
    In this case, the source CCtr (Work ctr Cost Ctr) is credited and Order debited with labour cost. During settlement Order is credited and Settlement Cctr is debited.
    Hope this clears your doubt.
    Thanks
    Sarang

  • Hide Labor Cost

    Hi, I hope somebody can point me to the solution:  in 7.4 with the old GUI enabled, how can I hide the hourly labor costs?  Goes without saying, it's thoroughly unprofessional for individual hourly rates to be visible to team members (it's a violation of standard HR policy, also).
    (Please don't point me to an old plugin, thanks.)
    This topic first appeared in the Spiceworks Community

    Thanks for reply. However, they are not using standard cost. They are using Moving average cost for every items, but it's not calculated by warehouse. See my first posting for the setting we made.
    I tried: in the authorization setting -> inventory -> price list -> "price in the price list: %s, will be up" configured as "no authorization". It works (item cost displayed as *** in the item master) but SAP inventory reports e.g. inventory status report cannot be run after configuring this.
    Understand it can be masked off using SDK Add-on. Any idea of doing it without running additional add-on?

  • Copy standard cost with Cost Component from another material

    Hi,
    I need to copy standard cost from another material not only total price but also details of cost component split. I try to used transaction CKUC with procedure of "explode material cost estimate" but the reference material use "mixed costing" and isystem stop explosion.
    There is another procedure in order to make this copy? I can not use special procurement because are different codes (material A / Plant XXX copy froma material B /Plant XXX).
    Thanks for your support.
    Mic

    Hi Chandra,
    thanks for your suggestion, it works but only if I explode a level ... material "B" contains two mix codes  that also contain their mixes. So system shows this message "Mixed cost estimate explosion in level 2 for material xxx" and "Mixed cost estimate exists: maximum of 2 explosion level (s) possible".
    So Is not possible to copy and esploded a standard cost with multi level mix?
    Thanks
    Michela

  • Raw Material Costing with Overhead, Product Cost Planning

    Hi,
    I have an issue applying overhead to purchased raw materials. We need to apply this overhead for only a certain materials. So, I have defined a overhead key/overhead Group, and assigned the group in the material master of the raw material. The overhead is 2% freight on raw material costs.
    In the std.costing variant, I have assigned the costing sheet under Overhead on material components tab of the corresponding valuation variant. I have also included the Freight OH in the cost component structure.
    However, when I run the costing with CK11N for the raw material, it is showing only the raw material cost, not the overhead.
    What could be the problem?
    I appreciate your help.
    Thanks,
    Ram

    Is the overhead rate a percentage type or quantity based?
    Have you maintained both actual and plan rates (1 & 2) under define % based OH rates or Qty based OH rates accordingly?
    Does the validity date (in define OH rates )cover the date of costing?
    Is the Costing sheet assigned to the valuation variant at plant level?
    Is the OH base in the costing sheet includes the cost element of the raw material?

  • How can I enter "Flate rates for travel costs" with more than 2 decimals?

    Hi expert,
    I want to enter flat rates for travel costs in table T706F.
    I have a figure with more than 2 decimals (0,066), but I cannot save it, because only 2 decimals are allowed for EUR.
    I don't want to change the decimals for this currency.
    I found OSS note 446116 which is release independent. It is a note of 30.10.2001.
    It suggests to create a new currency e.g. EUR3 and enter translation ratio's and exchange rates.
    This seems pretty drastic.
    Do you know if there is another way to handle this issue?
    Thank you.
    Kind regards,
    Linda Verding

    Hello Christian,
    I have checked it with consultants from SAP Brussels.
    They confirm that OSS note 446116 can be used to create flat rates for travel costs with more than 2 decimals.
    I will create a new currency (EUR3) with the description "for travel expenses only".
    Kind regards,
    Linda Verding

  • Settling Labor costs

    Hi Experts,
    How do you settle any labor costs. I have created a secondary cost element and tied it an activity type. In the work order I enter 2 hours of this activity. Can I settle these costs from a secondary cost element to a primary one?
    Thanks

    HI,
    once it is secondary cost you cannot bring it back to primary cost.
    Best regards, Christian

  • Shipment cost with diff. service agent

    HI,
    I want to calculate shipment cost for a customer. The customer is based at location D. I am transporting  materia; from locationA. From A to B my shipment type is Truck and service agent isX . From B to C my shipment type is Train and service agent is Y. From C to D my shipment type is Bus and service agent is Z.
    service agent  X an Y  are  charging on the basis of KM and Z  the basis of material weigth.
    I want to create  and calulate a shipment document / shipment cost document one each for a service agent.Also, want to combine cost of shipment and the same should get refelect in customer invoice.
    Also, let me know how should i go for automatic leg determination in shipment and about tax in shipment document?

    Hi,
    In bulk transportation and distribution you can assign partners at the following levels:
    Shipment header
    Vehicle
    Shipment stage
    You can assign multiple partners at each of these levels. The shipment costing process uses the partner assignments to calculate and settle costs with service providers (partners).
    Activities
    Partner functions and partner procedures are defined in Customizing for Sales and Distribution by choosing Basic Functions - Partner determination - Define and assign partner determination procedures. You can freely define partner functions, however, the following partner procedures must be used:
    OTR
    Shipment header
    OTS1
    Shipment stage
    OTS2
    Shipment transfer point
    OTS3
    Shipment border
    OTS4
    Shipment vehicle
    Partner Assigned at Shipment Header Level
    Partners used for the entire shipment are assigned at the Shipment Header level. You assign partners to shipments from the Shipment Header screen by choosing Goto - Partner header.
    Partner Assigned at Vehicle Level
    You can assign partners to vehicles within a shipment. For example, the partner could be a carrier responsible for the vehicle. A different partner can be assigned to each vehicle in the shipment. You assign partners to vehicles in the Vehicle Overview screen by choosing Goto(2) - Vehicle partner.
    Alternatively, you can assign carriers to vehicles in the vehicle master data record so that the carrier is automatically proposed for the vehicle in a shipment. This partner is used for all the stages of the vehicle route, if no partner was defined in Customizing for the route or stages.
    Partner Assigned at Stage Level
    You can assign a different partner to each stage in a shipment. The stage type (leg, transfer point, and border crossing point) determines the partner procedure. For example, partner assignment at stage level could be used to represent a customs agent at a border crossing. You can assign partners to stages from the Document Stage Assignment screen by choosing Goto - Maintain stages - Goto(2) - Partner stages.
    If you assign a partner to a route or stage in Customizing, the partner is automatically proposed for the corresponding stages of the route. If the partner is changed in the Vehicle Overview screen, then all partners which are not from Customizing are replaced with the one that was entered in the Vehicle Overview screen. You can assign partners to stages in Customizing for IS-Oil Downstream by choosing TD - TD Master Data - Route Definition - Define routes and stages.
    regards,
    Siddharth.

  • Benefits: Health plans show costs with bi-weekly rates in Enrollment screen

    Hello,
    I have created 2 new health plans.  During testing, I noticed when trying to enroll employees via the Enrollment screen, the plan options show costs with bi-weekly rates rather than monthly rates.  For these health plans, I had set the cost variants and costs rules to "Monthly."  Is there another setting somewhere that I am missing?  Please advise- thanks

    The benefit payment model assignment is configured in view V_T74HE (note VARGU is getting from feature MODDE). You can check this payment model through view V_T549W to see what period parameter it's set to (PERMO). It's probably currently set to 'bi-weekly' instead of 'Monthly' in your system.
    Rgds.

  • Importing landed costs with DTW

    hi all,
    I use SAP B1 8.81 PL04, exesite there a way to transfer the landed costs with DTW?
    thanks

    Hi,
    It may not be available in your PL. The latest DTW has the Landed costs folder with 3 templates OIPF, IPF1 & IPF2
    Thanks,
    Gordon

  • DBM labor cost in the pricing

    Dear Friends,
       We plan to use DBM Time Management . When the technician clocks in time, the labor cost hits the internal order correctly. But, the same cost doesn't hit my labor cost condition type in the pricing.  Due to this, my profit center in the billing is wrong.
    What am I missing here? Couldnt find any documentation regarding this
    Appreciate your help
    Best regards,
    Shafi

    Hi
    if you want to have your profit margin on the SD order 100% accurate this is the only way but this will have a big impact on performance. As normally labor rates don´t differ so much I would recommend to create a condition type where you maintain the average labor rate. This gives you a profit margin as well but not as accurate.
    In CO PA you get the right figures but normally you don´t do this order level
    regards
    Stephan

Maybe you are looking for

  • Default tax code in PO from Condition record :::::::

    Hello experts If a condition record for a plant vendor material combination  is maintained for a particular tax code , is it possible to default the tax code maintained in PO from the condition record?? Pls give ur valuable inputs Regards Anis

  • Different user or different database

    Hello everyone, we have oracle 10g server on win2008 64bit os, now we run one project and its data on the server. After a months a new big project will be run on the same server . So we must answer this important question? We can run new project data

  • HT3258 After downloading Mac OS X I can no long download photos from Safari to iPhoto.  How do I fix this problem?

    I downloaded Mac OS X Mountain Lion and now I can't download photos from Safari to iPhoto.

  • Scxi 1001/1102/1303

    I am having trouble getting accurate thermocouple readings from my 1001/1102/1303 components.  I have 10 channels hooked up to the device.  All values are not accurate and are negative (in the -300 to -400 range.)  Further, when I unplug one thermoco

  • Idle time Closed Connection