Report Painter - Amount consumed X Planned costs

Hello SAP consultants,
I am developing a report (with report painter) and I have not been able to create a column which bring the information resultant from the calculus: Amount consumed (os activities) X Planned costs (to that activities).
Could someone give me a tip?
Thank you.

Hi:
Do you have these two columns already defined in the report - Amount consumes and Planned costs?
If yes, the third column would be of type "Formula". And in that forumla column, you define the formula definition (first column * second column).
If not, then you need to first add these columns before you have formula on them. In report painter, you can't have a column with some logic in itself. The formula column would need to refer to the other existing columns in that report.
Hope it helps.
Thanks.
Rahul

Similar Messages

  • Report Painter: Cash Flow Actual/Plan Report on Profit Center

    I must create a Cash Flow report Actual/Plan/Variance Figures per Profit Center by using a report painter.
    It will be created in monthly basis format, and year-to-date format (two different formats).
    The format is in GL accounts instead of standard Cash In and Cash Out format.
    I need to extract the Plan figures. However, we don't have planning on PCA. We are only doing plan on cost center, either revenue or cost (revenue is created as cost element category costs/reducing tax).
    Should I extract it from the Cost Center Plan & add up all plan amounts of the cost centers that attached to the specific profit center? How can I do that?
    What do you suggest as the best solution? Please explain briefly and using what t-code, tables and fields to extract from.
    Thanks,
    -=Meila.S=-

    Hi John,
    Go to Menu - > Edit -> Variation
    You can set the order of the Selection Screen fields there.
    Hope this helps you
    Regards
    Andrew

  • CN41N and S_ALR_87013533 report not showing Production order planned cost

    Hi Experts,
    I am having issue to get total planned production order values in my CN41N or S_ALR_87013533 cost report. I am facing 2 issues :
    1. CN41N repoet does not show individual material cost planned in BOM.
    2. CN41N report and S_ALR87013533 report does not show total value but only picking fixed value.
    Example :
    1. CN41N report :
    Above screenshot shows no values in Project plan cost & Order cost column but it shows total cost as a lumpsum on top for project. I need to know how can i get material cost populated here for Project Valuated stock material?
    2. S_ALR_87013533
    This report shows Total Cost of BOM as 1 line under Material Procurement activity similar to CN41N report. Also Order value is picking from Fixed cost from planned order and total cost is added on top. How can i get Total cost picked from production order?
    Is there any Setting in PS config which allow me to pick the detail production order plan cost in both report under planned cost.
    Thanks in advance.
    Ashish

    Hi Ashish,
    I doubt whether Item level reporting  in S_ALR... (hierarchy report) is possible or not because I haven't seen item level cost in them only the lump-sum cost because they are summarized at cost object level itself. Navigation path are there which we use to go into details of cost.
    Please check the following links:
    https://scn.sap.com/thread/1743833
    (In the above thread,focus on  Mr. Mohamed Rafi comment.)
    http://scn.sap.com/thread/3530080
    http://scn.sap.com/thread/1311820
    Order cost plan in report CN41N
    Display of plan cost., CN41N | ABAP, SAP, benX AG, benXBrain,&…
    Just an additional pointer ,have a look on your costing variant and variation variant settings for material section.
    Regards
    Saurabh

  • Report painter- Amount in Document currecy instead of LC

    Hi,
       Am new to report painter. i created report painter in FDI4. this report is to display the due amount.
       when i click on table cell, which is amount field . Am chosen cell type as  'Select with Key figure' option .
       After then i try to select key figure for that cell (Popup:Element definition).
       In F4 selection there is only one Key figure which is Amount in LC.
       I need to display the field value as Amount in Document currency.
       How to bring Amount in Docment curreny in that F4. Is it possible.
      I didnt get any thread related to my requirement in SDN.
      pl help.

    Solved by myself..
    Two steps to be taken to bring Amount in Doc. currency as a key figure(F4 help).
    1. Added new field 'WRSHB' , data element for this field WRSHB_D (Used Append Structure) in RFRRD20 structure. FDI4 used this structure only.
    2. create new entries in TKAF table under application class Account receivable FBRD. field value WRSHB ,data element  value WRSHB_D, and others field value are as same as DMSHB record.
    After these steps, now u check in FDI4 tcode.  U can get Amt in doc. currency as key figure.

  • Report Painter Request - Cost Center and WBS Element

    Hi Everyone,
    Currently, my company settles all project related expenses through to a cost center by way of an internal settlement cost element (category 21).  The issue with this is that when the expense gets to the cost center, they lose all visability as to where the expense originated, such as salaries or travel expense (category 1 cost elements).  We can't switch the settlements to the originating cost element from wbs to cost center just because of the additional data/volume that will cause.  My thought was to create a report painter that can run by cost center but also show the wbs's that settle to that cost center and group the expenses by primary cost element (cat 1).  I'm assuming that there is a way to marry a cost center and wbs element by way of the wbs settlement rule but how would that be done for reporting purposes?  I've seen it done before by way of a nightly job that created sets based on the combination of cost center and wbs but I'm not sure how that was done.  Any advise and examples?
    Example:
    Cost Center:  IT
    WBS: A.0017.01.01 (settles to cost center IT)
    Postings made:
    1.  CC IT and CE 552000 "salaries"..............................$20,000
    2.  WBS A.0017.01.01 and CE 552000 "salaries"........... $5,000
    3.  Settlement of WBS to CC (expenses flow through to CC IT by way of CE 985000)
    I want to run CC IT and see that the account 552000 really shows $25,000 and can be broken down by cost object (CC and WBS by the amounts above)
    Thanks,
    Pete

    Hi Peter,
    I had a similar requirement and used report painter report group 1SHK-002 (in library 1VK).
    I took a copy of the standard and ameneded it slightly, I switched the explode so it occured on the cost center not cost element.
    The report runs so that direct costs on the cost center are shown at primary cost level. And values settled to the cost center are shown on the partner object. In your case i guess WBS Elements (Partner ObjType WBS).
    Now in my case I didnt need cost element breakdown on partner level, just on cost center so effectively I have(sorry for text alignment but I hope you get the idea):
    GL1   .............  100
    GL2   .............  250
    + Cost center1 total ....350
    GL3 .............   50
    GL4 ............. 100
    + Cost center2 total.... 150
    Primary Cost Total ..... 500
    X-YZ-1.200 .............   50
    X-YZ-1.400 ............. 100
    + WBS total ............. 150
    IO 1............. 100
    IO 2  ............. 100
    +IO total  ............. 200
    Partner Total............. 350
    Overall total .............  850.
    Its not exactly like your requirement but it might be a good report for you to work with to get what you need.
    Elaine

  • How to add "Cost Plan Version" and "Planned Cost" into CNE5 report?

    Hi,
    I would like to display Cost Plan Version(VERSN) and Planned Cost in the CNE5 report.
    How to retrieve Planned Cost that based on the Cost Plan Version ?
    Appreciate helps. Thanks.
    Regards,
    See Mun

    Plan versions:   A plan version is created in accounting and stores different cost plans for a project, such as an "optimistic" and a "pessimistic" plan.
    Now coming to plan version 0 is verson where actaul cost is updated in your organisation.
    Plan version 1 is used for the planning...
    How to see the  same in CJE5 is suggested by Virendra..
    However there is no filed name planned cost  in report but the name of the filed is Proj.cost sched.000
    with which you can achieve your result.
    path is run txn CJE5>give your Project no.> F8> in new screen> F5-->in new Window scroll down in the  right side for the Proj.cost sched.000 filed > with select take the same to left side>Enter--> values will displyed for this field in your report.
    similarly you can use the other fields as well... take help of F4, to know the meaning of fileds.
    Regards
    Nitin
    Edited by: Nitin  Patoliya on Jan 17, 2009 11:18 AM

  • How to add new Characteristic in Report painter?

    Hi All,
    My requirement is Create/Modify a Report in Report Painter/Writer which should generate cost information in Controlling Area Currency for all sites (domestic & international) associated to the Project. Earlier same Report is fecthing Object Currency Values for the given Project.
    When i  tried to add  "Controlling Area currency"  in place of "Object Currency" characteristic, then from the available characteristics of the FORM/Report,   i am unable to find the  "Controlling Area urrency".
    Please let me know  how to get this "Controlling Area currency" characteristic.
    Note: This Report is intially developed in Report painter  So no ABAP code is present , So People who knows Report painter/Report Writer concepts with Currency translations can helpme out.
    Please do the needful  as i am new to Report Painter please Give T-codes and any useful links regarding this Multiple Currency handling /Currency conversion concepts of Report Painter.

    I am designing the P&L report and I want to split my R&D expenses split down by Internal Orders. Since, I have not seen Internal order field in summary table of new GL..ie., FAGFLEXT  table.
    I want to know how this can be achieved in the same report in report painter.
    I am talking this issue from Report Painter point of view where each report is based on library , which is defined per summary table.(ie., Library can refer to only one table....finding it odd to believe there is no join in reporting tool).....
    Thanks and let me know if you want to know more on the issue I am facing.

  • GR55 Report Painter Issue

    Hi,
    I have an issue in report painter-GR55. Our report in report painter will show planed / actual cost, planed /actual quantity. Our material cost planing is done from cost activity of the project builder. Whereas in the report output , some material quantity is showing as planed quantity for which planed cost of the project is showing wrong. We are picking data from RWCOOM Table. Please advise on this.
    Thanks & Regards,
    Ranjan

    Not possible....SAP standard behaviour....

  • Report Painter Issue-GR55

    Hi,
    I have an issue in report painter-GR55. Our report in report painter will show planed / actual cost, planed /actual quantity. Our material cost planing is done from cost activity of the project builder. Whereas in the report output , some material quantity is showing as planed quantity for which planed cost of the project is showing wrong. We are picking data from RWCOOM Table. Please advise on this.
    Thanks & Regards,
    Ranjan

    Not possible....SAP standard behaviour....

  • Plan cost of Valuated Sales order

    Hello,
    I am using Valuated Sales order and wanted to see the Plan cost is sales order report KKBC_KUN.
    a) When i use a costing variant in the Requirement class with automatic marking, i am able to see the plan costs in the sales order report.
    b) However if i dont use and costing variant in the requirement class and instead use the valuation with standard price of Make to stock inventory (with out val.strategy is checked), my sales order report does not show the plan cost.
    I want to use option (b) and also see the plan cost in the sales order report. Is this acheivable.
    Regards
    Raghu

    Hi Raghu
    Valuation Indicator in Req Class and Costing fields in Req Class are independant things
    You can specify valuation field as A (No Separate Valuation) and still use the Costing fields to calculate sales order cost estimate.. This will remain for info sake only
    However, it does nt make sense to calculate SO Cost est if you dont use that in valuation
    br, Ajay M

  • Planned cost for Results Analysis

    Dear Friends,
    SAP reads line items from COSS and COSP to determine the planned cost for result analysis.  What line items does it consider while summing up the planned cost.  I wish to reconcile the planned cost as considered in result analysis.
    I am considering the line items from COSS and COSP where
    Value type = 1 or 11
    Beltyp = 1
    Version = 0
    Business Transaction ????
    What values should I put for business transation ?    Or is there a SAP standard report which matches with the planned cost value of result analysis.
    Standard report S_ALR**** does not always match with the planned cost value in result analysis.  These reports read values from RPSCO table which is a summary table.  
    Regards
    Jayesh.

    After releasing production order all primary and secondary costs get attached to the order.
    You can see planned cost in Tcode:CO02>>>>Goto>>>>>>>Costs>>>Analysis>>>under cost trend layput.
    Yogesh Thorat

  • Report Painter - Use SKF to calc act/plan unit costs in CCtr report

    Hi Report Painter Gurus,
    I am an end user working with our Report Painter consultant and I have asked for a Cost Centre report with columns for Actual Costs, Actual Unit costs, Plan costs, Plan Unit costs for Month and Cumulative. I have seen this report in my previous business so I know it can be done but consultant says it's impossible.
    The report I previously used had the SKF values at the bottom of the cost centre report and then the unit costs columns (both actual and plan) referenced these SKF cells in the formula which divided Cost by SKF.
    We have created the SKF using KK01 and posted dummy amounts in KB31N but consultant says he cannot reference the SKF values in the formlas.
    If you can spell it out to me (I have dabbled in Report Painter myself), then I am sure I can explain it to consultant.
    Any help gratefully appreciated!
    Cheers,
    Matthew.

    Matthew,
    I think it is quiet simple. When you add a column to the report painter report you can choose from the drop down menu for 'Basic Key figure' whether it is Costs, Activity quantity, Statistical quantities, etc.
    So if you have a column with Costs (X1) and one more column with quantities (X2), you can easily come up with another 'formula' column and use the equation (X1/X2).
    I think this should serve your purpose.
    Best regards,
    Vishal Thakur.
    Edited by: Vishal Thakur on Mar 2, 2010 11:08 AM

  • Report Painter Drilldown on Cost Element for Project Systems

    I am currently working on a report for Project Systems. I am trying to copy the functionality of the Internal Order summary (60I2-001) into report group 6P3. I was able to copy the whole layout and also the values of 6oI2-001 into a copy of 6PP4-001 but when I double click on "Balance" it is bringin up the ALV report that 6PP4-001 is using. I would like to call another report which looks like 6LS0-001 but contains Project System info made in report painter when I double click on Balance. Is this possible? Please let me know how.

    Hi Avinash,
    See my replies below.
    1 a & B: You are planning Qty on NWA and capturing costs - labor & Equipment on NWA elements.
    When  you are having elaborated to NWA-Element level, split your total work on each NWA-element and post labor cost. Thus you will have planned Vs actual costs at one place.
    coming to equipment cost - are you capturing using PO through GR?.
    2.a : Option1- create a separate WBS elements for materials and plan cost at WBS level. That value would be your total planned cost of material procurement as estimated. Under this WBS elements create NWAs and assign the materials. With this set up you can assign material and procure so that will have actual costs coming from GR.
    Option 2: Create a one General Cost activity and assign the total planned cost of material on this NWA.
    When you assign the material components, diligently you have to reduce the equivalent amount from the general costs activity. Also note that on component screen, you have to check box "Cost relevant" so that material cost will add to Cost NWA. Let the different materials  have their own valuation class and have default CEs accordingly. that would not be big issue.
    Please discuss with your MM team to get more information. Also my suggestion is to leave blank CE field in configuration.
    The option2 is very cumbersome and high risk but one have to be very cautious to reduce the value from Cost NWA in order to sustain the planned material costs whenever they added.
    3. I have answered the relevance of Cost relevance check box in above.
    Hope above makes sense.
    Thanks,
    Sudhakar

  • Issue with report (S_ALR_87013611) that is actual/plan line items for Cost

    Hi Gurus,
    I am having issue with the report (S_ALR_87013611) that is actual/plan line items for Cost Center.
    When i execute the report for a cost element  510200 the amount is 23,380.13, but when i drill down on it by double click on that amount the value in obj curr is 15468.91. Hence there is the differnce. When i futher drill down by double click on the amont of 15468.91 and i go to display group currency and take the total it is 23380.13 and display in local / doc currency the amount is 15468.91. I guess due to this there is difference. The cost center & the cost elements are the same i have checket it.
    My concerns is that the group curr is USD and obj curr / local curr is USD. So is group curr and doc curr is USD then when i click on dislay curr and select group curr why the amounts are changing.
    Kindly adivce

    Try to look if there is any filtering criteria applied in the report to which you drill-down.
    The difference can be also caused by the "value type" - some reports show actual and statistical costs together in one column while the others strictly show (are defined to show) only e.g. actual costs (type 04) and not the statistical costs (type 11)

  • Project System - Report Painter - Cost roll up issue

    Hi,
    We have an issue with the roll up of the costs in Report Painter report in Project Systems. The problem occurs only with those costs which have been settled to an internal order from a WBS element.
    We are using the same cost elements to settle to the Cost Center and Internal order and roll up of the costs work fine for those settled to cost center. But the roll up does not happen for the costs settled to an internal order. Would appreciate if someone can guide on how to fix this issue.
    Raj.

    Here are the values:
    Period/year     000.1900     Remainder 1900     PERIO     Period/year
    Value Type     4     Actual                                                 
    Value Type     10     Statistical Plan                                                 
    Object ind.     P     Project item                                                 
    Object ind.     1     Order plan values: appended, apportioned     9     Order values: not appended, deleted
    Debit type     1     Costs and credit-side payments                                                       
    Thanks for your help.
    Raj/

Maybe you are looking for

  • Global variable in interface IF_EX_ME_PROCESS_PO_CUST

    Hi experts, I have implemented BADI ME_PROCESS_PO_CUST. I have written my code in method PROCESS_ITEM. I want know how can I declare a global variable for that interface so that I can access that variable across different methods (PROCESS_HEADER) of

  • New toolbar created, FF4 Restarted then there's no new toolbar!

    I've been creating a toolbar to put my addons for web development and when FF4 is restarted, sometimes the toolbar were erased from the settings. I had to re-do the process again. Now everytime FF4 crashes, it forgot my toolbar.

  • Best practice for sudo

    Hi I am trying to install sap as a sudo user. What is the best practice to setup sudo ? I am getting this error when i install as sudo sapinst Output of /usr/sap/SPD/SYS/exe/run/brconnect -u / -c -o summary -f stats -o SAPIAL -t all -m +I -s P10 -f a

  • Hierarchical tree node problem

    Hi all -- Today's problem is (drum roll)............ My application uses a heirarichal tree where each tree node contains the name of a form within this system. The user can navigate from form to form by clicking the appropriatetly name tree node. Th

  • How to generate 8.192MHz clock on labview FPGA 7854R series card?

    Hi,    I am using NI PXI-7854R series card which has Xilinx Vertex 5 FPGA on it. I am trying to derive a clock of 8.192 MHz from the 40MHz on board clock of FPGA. But it ends up giving me only 8MHz clock. Is there any way of accessing the PLL which i