Revenue Planning to cost elements

Hi,
I am Working on Project system object.
When i am trying  planned revenue is added on the project, I need to find if there is a way to assign the revenue amount on the lowest WBS to a cost element. This is required for revenue amounts to appear in costing reports. CJ42 is used to add planned revenue manually.

hi anuradha,
Revenue Planning
Use
Revenue planning can be necessary when you perform results analysis on a sales order item and use a results analysis method that uses the planned revenues to calculate the results analysis data.
Features
The net value (revenue) for sales-order-related production is determined in pricing in Sales and Distribution (SD). Pricing depends on specific conditions which you maintain in Sales and Distribution.
A particular customer orders a particular quantity of a product on a particular day. The variable factors – customer, product, quantity ordered, date – determine the final price for the customer.
The system uses the conditions you specified to calculate the gross price at which the customer is invoiced; any discounts applying to the customer, for example; and other values such as freight charges and tax.
Pricing is controlled by a pricing procedure which is selected through the sales document type. Price elements such as prices, surcharges and discounts, freight costs and taxes are saved in Sales and Distribution as condition types. The pricing procedure determines which condition types are used and the sequence in which they are calculated in the sales order.
Condition Types
The standard system contains the following condition types that can be used in connection with unit costing, product costing, and preliminary order costing in assembly processing:
Condition Types for Pricing
Condition Type
Meaning
EK01
Cost of goods manufactured (CGM)
EK02
CGM (statistical)
EK03
Fixed CGM (statistical)
Condition type EK01 is mainly used for cost-plus contracts in which the sales price depends on the expected costs.
Condition type EK02 is mainly used when the sales price is a market price and the expected costs are only used for informational purposes.
Condition type EK03 offers the capability of transferring the fixed costs of a cost estimate into the conditions.
The costs are transferred from the cost component view Cost of goods sold into the condition type.
The above-mentioned condition types must be of category Q. Whether a condition type of category Q is only used in pricing as a statistical value or for price calculation is controlled in the pricing procedure.
The condition type is created in Customizing for Sales.
The condition type can be selected as follows:
Through the sales document type
Condition types EK01 and EK02 are specified in the CndTypLineItems field in the sales document type.
Through the requirements class
This enables you to define different condition types for different sales document items of a sales document.
Condition types EK01 or EK02 are specified in the CndTypLineItems field in the requirements class.
Condition type EK03 is specified in the CondTypLinItFix field. You can only use condition type EK03 in conjunction with the requirements class.
Planned Revenues
Revenue elements from the SD pricing procedure that are not statistical are updated as planned revenue on the sales order item that carries costs and revenues, and can be viewed in the Product Cost Controlling Information System. Sales deductions can also be assigned to revenue elements through account determination, and updated on the CO object for the sales order item.
The condition type is selected through the sales document type.
Condition type EK01 is selected for sales document type TA (standard order). This means that the value from the cost estimate goes directly into pricing. A surcharge is calculated from this value and the net value for the sales order item is calculated.
Condition type EK02 is selected for sales document type TA (standard order). Pricing is carried out on the basis of condition type PR00. To maintain this price, choose Logistics ® Sales/distribution ® Sales ® Master data ® Prices ® Material prices and enter a material price. The material price is updated under condition type PR00, while the values from the cost estimate are updated under condition type EK02 and can be used for informational purposes.
Actual Revenue in Product Cost by Sales Order
Use
In Product Cost by Sales Order, actual revenues are updated to the sales order item that carries costs and revenues at the time of invoicing.
Integration
You can view the actual revenues in comparison with the planned revenues and costs in the Product Cost Controlling Information System at any time.
You can settle the costs and revenues that are updated to the sales order item to a profitability segment in Profitability Analysis (CO-PA) during period-end closing for Product Cost by Sales Order. When you perform results analysis, the results analysis data are settled to CO-PA.
The processing in Product Cost by Sales Order therefore differs from the processing in Product Cost by Order or Product Cost by Period (make-to-stock production and with a valuated sales order stock without a sales order item that carries costs and revenues).
If you perform this type of product cost controlling (such as in addition to Product Cost by Sales Order), then in Product Cost by Order or Product Cost by Period the revenues from invoicing are transferred to CO-PA.
If you are using the cost-of-sales accounting in Financial Accounting (FI) and are using a valuated sales order stock, you do not need to perform results analysis in order to transfer the cost of sales to FI. The cost of sales is transferred to Financial Accounting at the point of the goods issue posting.
Prerequisites
To ensure that the revenues are displayed on the sales order item, you must create revenue accounts and possibly sales deduction accounts as primary cost elements of cost element type 11 (revenues) or 12 (sales deductions). Make the necessary settings in Customizing under Controlling ® Overhead Cost Controlling ® Cost and Revenue Element Accounting ® Master data ® Cost Elements.
To be able to settle the costs to Profitability Analysis, you must make the necessary settings in Customizing for Profitability Analysis. Make the necessary settings in Customizing under Controlling ® Profitability Analysis.
Features
Billing
Billing invoices the customer for the goods and services delivered for a sales order.
In Sales and Distribution, you create an invoice (billing document) on the basis of a reference document. In order-related billing, the reference document is the standard order or the delivery document with delivery-related billing.
The data such as prices and quantities are transferred from the previous documents into the billing documents. The price can be calculated in the following ways:
Using pricing on the basis of conditions (such as material or customer)
On the basis of the incurred costs if you want to use resource-related billing
When you enter a billing document, the system proposes a billing type depending on the reference document.
The billing type determines the following:
Which pricing procedure is used for account determination for Financial Accounting
Whether the invoices are passed immediately to Financial Accounting
Account assignment is controlled by the following parameters:
The chart of accounts
The sales organization
The account assignment group of the customer (in the Account group field in the Invoicing screen of the customer master record)
The account assignment group of the material (in the Account assignment group field in the Sales 2 view of the material master record)
The account key in the pricing procedure
thanks
karthik
<REMOVED BY MODERATOR>
Edited by: Alvaro Tejada Galindo on Apr 15, 2008 3:10 PM

Similar Messages

  • Table or Function module to get Internal order planning and Cost element pl

    Dear All,
    Table or Function module to get Internal order planning and Cost element planning.
    Internal order planning from T-code KO13.
    Thanks in advance.
    Regards,
    Ravi
    Edited by: Ravi Chandra on Sep 13, 2011 8:08 AM

    BPEJ, BPEG, BPEP

  • Copy Detailed planning for cost elements in CJ9BS

    hi PS gurus,
    What is the purpose of selecting this option (Copy Detailed planning for cost elements)? What does it do?
    Many ThanKs
    MM

    Hi,
    In case you have done detailed planning for your project you can specify whether you want to copy the detailed planning data using this check box.Planning done using cost elements is called detailed planning in PS. CJR2 is the transaction to do that. For more details you can hit F1 on the field and check.
    Regards,
    Gokul

  • Planning at cost element group level

    Is it possible to plan values  at cost element group level instead of at cost element level in CCA?
    Thanks

    Hello,
    Yes it is possible. In t-code-KP06 Cost Center/Activity Input planning, we can select input values in the combination of individual Cost Center-wise OR Cost Center Group-wise and  individual Cost Element-wise OR Cost Element-wise. Here if you give Cost Element Group as your input value, you can plan cost for each Cost Element.
    Regards
    appalas

  • Planning on Cost Element group

    Hi Guys,
    I have a PLAN Query with costelement in the rows and i am extracting costelement group hierarchy from R/3 and using the hierarchy on the costement in the rows.
    Now i have a requirement users want to enter the PLAN data at the costelement Group level but NOT at the costelement level BUT the problem is COSTELEMENT GROUP is a TEXT Node.
    How do i handle this situation.
    Shashi

    Hi Shashi,
    Create 2 Char - 1) Cost Element Group & 2) Cost Elements.  Using External Hierarchy button in the char IO maintenance, select Cost Element Char as an external Hierarchy in the Cost Element Group char.   And then create a separate Hierarchy on the main basic char Cost Element Group.
    Before you build the hierarchy maintain master data for both char..
    Hope this helps.
    Jason

  • COST Element Based Planning

    Hello All,
    We are trying to plan cost of WBS Element based on cost elements.
    what we are trying to do -
    > CJ40, we want to plan on cost element level so on clicking the button "primary costs" (or via the menu: "Extras -> detailed planning -> Primary costs") we end up in an error message saying -
    Group INT-2 does not contain any entries
    Message no. K8004
    Diagnosis
    Group INT-2 does not contain any single values. You cannot use it in planning.
    System Response
    The SAP System rejects the planning layout and your entry.
    Procedure
    Use either a different group or enter values for group INT-2.
    CONFIGURATION for Planning Profile (T Code - OPSB) for the planning profile used in WBS Element Primary cost element group assigned is INT-2.
    Question2
    - Does cost element planning influenced by the cost element group assigned in the planning profile.
    - How to solve this error.
    Points assured.
    Warm Regards,
    Jatinder Bansal

    this is because in planning profile (Txn OPSB) you have INT-2 as cost element group and there are no cost elements assigned as pointed out by Venkat
    use transaction CJR2 instead of CJ40 and then plan for any cost element group or cost element that you already have

  • Plan Cost Element With Formula

    Dear Expert  ,
    Hope this message finds all fine  .
    my client need to plan cost element for specific cost center automatic depand on the result for other cost element
    example
    suppose we planned cost element 10000001 with value 100000
    we need to plan the cost element 1000002 as the following ( cost element 10000001 * 10 % )
    Regards

    Hi Sam
    This is not possible within the system
    You need to calculate it outside sap and then upload in sap
    Br. Ajay M

  • Change cost element category from 1 to 11

    Dear all,
    We created by mistake revenues accounts with cost element category 1 instead of 11.
    We created a sales document (contract) with account assignment to a WBSE. The revenues were appearing as negative planned cost so we realized the mistake.
    Now we have deleted the item in the sales document, we have created a new revenue account with the correct cost element category 11 and we have added to the account determination (VKOA).
    Now the revenue appears in the new cost element. Nonetheless we still see the revenue value as a negative planned cost. 
    If we create a new project and a new sales document everything is correct. But we want to mend the first one. Any idea of how?
    Best regards

    Fantastic !
    Thank you very much

  • Budgeting -Internal order - monthly -cost element wise

    Hi!
    Got a problem! Want budget for single internal order - cost element wise. We created one employee as internal order. For this internal order, want budget for Telephone exp Rs. 500 /- per month, Travelling Rs.1000/- per month.
    I checked in budgeting and came to know that we can budget for one internal order for one year not month wise. Another thing is we cannot budget cost element wise.
    Is there any solution for this requirement. Pls. let me know.
    I appreciate your efforts and thanks in advance.
    - SRK

    As you righly mentioned budgeting is not possible cost element wise/period.
    If you want for planning/reporting purpose alone (and not for availability control) you can create a seperate plan version and use cost planning with cost element and period wise.
    Regards
    Sreenivas

  • How & Where can we do Revenue Cost Element Planning

    HI,
    We need to do planning for Revenue cost elements. How & Where can we do Revenue Cost Element Planning.
    Generally we will do excel planning upload for Cost Elements in KP06. But where can we do Excel plannin for Revenue Cost Elements in the system?
    Kindly provie me the transaction code and some inputs on how can i proceed.
    It would be a great help if any one can respond on this.
    Thanks
    Kishore

    Hi Kishore,
    We can plan Sales Revenue through T-code KEPM-Edit Planning Data or through T-code KE13N by Uploading CO-PA-Sales Plan in Quantity and Revenue terms. Here we have to set  different Plan Layouts for Quantities and Revenues. After successfully uploading the data file,  we have to transfer the Sales Plan data to SOP in T-code-KE1E.  Then We can check the values by Co Code, Plant, Product-wise and Customer  in T-code KE25-Display Plan line items.
    Regards
    appalas

  • Unable to update revenue plan values in Easy Cost Planning

    Hi,
    Business maintains planned costs and revenues on WBS element using Easy Cost Planning tool. But for one of the WBS element system is not allowing to update/add planned revenue line items.User is able to update the planned costs for this WBS element.
    The Legend in Easy Cost Planning screen is Non-Changeable Cost Estimate.
    The status of WBS is REL,ACPT(Order Accepted),NSCH(Not Scheduled - Forecast Dates),RESA(Result Analysis Carried out).
    We have checked all the business process and all the revenue planning is allowed.
    Please guide us on how to resolve this issue.

    This is resolved...Select the WBS and click on CLOSE icon to reset the cost estimate. This allows to plan revenues again.

  • Error while uploading cost element planning data into KP06 transaction

    Hi,
    I am facing the below error while uploading the Cost Element Planning excel file in KP06 transaction code. Please help me in fix this issue.
    We are trying to enter a budget upload using Transaction code: KP06. We get the following message errors  when we do this. It seems revenue accounts cannot be entered using cost centers. Question, how should these accounts be added? Kindly help me how to add Revenue cost elements to this planning?
    Error accured when generating data for the planning processor
    Messange no.K9400
    Revenue element 451000 can not be planned on cost center 9720
    Thanks
    Kishore

    The cost element which have  category 01 only can be planned in the Kp06.
    Regards
    Ranjan

  • Cost Element missing in FAGLFLEXT for some PCA Plan records

    Hi Gurus,
    We have uploaded a PCA plan and can see the same in GP12NA. I see the planned values (GLPL) in FAGLFLEXT from SE16 under the correct accounts for 0L ledger for the correct company code and the fiscal year. I noticed a difference in the data
    1) For the revenue elements (11 and 12 Categories) the 'cost element' field is not getting populated in FAGLFLEXT. ('Account' is populated.) Is it expected?
    2) We have a Z library report that was built on FAGLFLEXT. The report uses the cost element groups to pull in the data and hence the 'Actual Values' are pulled in the report but the 'Plan Values' are missing. (Because of point1)
    Any pointers on how to fix this?Could you please suggest the places i would need to look to fix this?
    (I've checked that the plan vesion is activated for 2011)
    (The report has version Z2 as one of its parameters.)
    Regards,
    Erp.Warrior

    Thanks a lot for your replies.
    Waman: I've looked up the Note 983835 - NewGL planning: Cost element field (COST_ELEM) initial.
    This note talks about the Cost element not getting populated during planning. My question / confusion is in my case, the cost element is getting populated for some of them and not getting populated only for cost elem category 11 and 12.
    Is this note intended for this issue?
    Ajay: I've tried re-planning and still found the same issue. Thanks for your inputs. I'll analyse about the Note that waman has referred to and then may be go to SAP as suggested by you.
    Please let me know if any of you have any other suggestions as well.
    Thanks
    erp.warrior

  • Report Writer Issue - Revenue Cost Element - After Upgrade.

    Hello ,
       After upgrade some of the report writers are not pulling up all the plan data.
       I found out that the revenue cost elements (cost element category - 11) are not being pulled by
       report writer in ECC 6.00, where it used to pull them in 4.6C. These postings were done to
       our budget version using KP06.
       These revenue cost elements postings are not stored in COSP. I dont have any idea in which tables
       they are stored.
       Does anyone have any clue about this.
    Thanks,
    Sandeep

    Its a report writer report developed here..(not standard one)
    The cost center is a revenue cost center. So when we post our revenues we post it to this revenue cost center.
    The issue is in 4.6C env it used to pull this data, but in 6.00 it is not pulling.....
    Thx,
    Sandeep

  • Planning on WBS elements without cost elements

    Hi all,
    we are trying to implement the planning solution where users will be able to plan on individual WBS elements monthly but without providing a breakdown on cost elements. Standard SAP planning profiles allow to post plan values on WBS elements in annual view without cost elements. But when you want a monthly view the system you need to click on primary cost elements planning first.
    Is there any way to plan monthly but at cost object (WBS) level only?
    Many thanks,
    Roman

    Hi Eli,
    thanks for your response. We will be using budget functionality for budget purposes but at the same time we will need to use planning on different versions. I believe there are no versions for budget.
    One of the idea to minimize cost element planning is to introduce like a planning cost element to use with all planning postings and then include this into the same cost element group with the rest of cost elements for plan/actuals comparison reports.
    If you have something in your mind I would appreciate your input.
    Thank you,
    Roman

Maybe you are looking for

  • Home Hub Ethernet Connections

    Have had the BT home hub 1 for years with 3 PCs connected via Ethernet & USB connections (wireless is useless as house is 170 yrs old with 15 inch thick walls that have defeated all wireless attempts). Now that I have vision there are not enough conn

  • Using predefined data objects classes.

    I am always trying to be a better, more efficient Flex developer and I was looking at a project by Christophe Coenraets where he created collaberative forms using Flex/BlazeDS. I saw in his application that he was using multidirectional binding to a

  • Can I call a Skype to Go USA number from my Skype ...

    Hi There,     I'm travelling to Europe (France & Spain) from India. Since Skype hasn't started the Skype to Go in India, I was thinking of going for a Skype to Go number in the USA, which my family will call from their existing Skype credit (through

  • Address book scrolling corrupts list

    whenever i scroll through my addresses with my trackpad, mouse or tablet, the addresses blur and become unreadable. clicking on the address column snaps it back into focus, but further scrolling corrupts it again. if i switch from "view card & column

  • Error msg "unable to load" from Office2HD

    Converted pdf to DOC. Went to open within my Office2HD word processor. Get error msg "Load failed an error occurred while opening document". Original pdf document resident on my Google drive. How to open and subsequent edit?