My client has production process:
They want fix planned quantity for order 1000 lbs. End of the process they receiving fix quantity 950 lbs and remainig 50 lbs goes to Rework. and Every 2 month, they use all these collected  rework materials and run different kind of production process, and getting fert. (Note: so they want to use those rework materials again and make fert product)
So if i am wrong than correct me;
very first step create regular production order for 1000 qty. in detail.
I did co01 for 1000 qty. >> Migo GI >> Co15 Yield 950lbs, Rework 50lbs >> Migo GR.
I receieved 950 lbs in Migo GR, and i can see it under material stock overview MMBE. but i dont know from where can i receive those REWORK stock. and where can i see those rework material? Please Guide me.
If i am doing wrong scenario than please correct me and explain me correct solution for my requirement. and also let me know, where can i see Rework materials stock overview ( like MMBE) or if i can get report that is also helpful.
Thank you
NTP

Hi,
If your requirement is to keep track of Rework,
then you need to receive the scrap in 531 movement type against order. Since you don't the actual scrap for each order, at the end of the order or during order confirmation you can make a Rework entry with 531 movement type.
If it is rejected FG, then it should not be used for sales or other orders so one way is to create a new material as Rejected FG scrap (EX RFG001) and receive the material with 531 after the order.
So now you will have the stock of rejected FG under the code of RFG001, you can also use the rework Qty. The same can be possible for other materials also.
1. Create a Material for Rework (this material will be used to receive the rework materials of all FG), lets say RE001
Use: Since the valuation of rework material (i.e, the price of the material) is less than the Finished goods, so it is always best practice to create a material for rework. If in a order, you can receive the rework material as this code
2. During Confirmation in CO11N, enter the Rework material RE001 with -50, Mvmt type 531 and enter a storage location.
3.Recieve the Material and keep it in the stock.
4. In the next order if you want to ues the rework material in the order BOM, make any entry for RE001 with the required qty.
By doing this you can issue the rework material to the orders you need.
Please do a test cycle in your sand box and revert back.
Thanks,
JK
Thanks,
JK

Similar Messages

  • APO canuFF1F

    Dear gurus,
    Would you give your suggestion on our business scenario as following, can APO SNP and PP/DS feed such case?
    More than 15 work centers, 8 operations, last 3 operations is for product testing, others operation is for product assembly,  if the product fails to pass at test operation, it would  go back to any assembly operation or previous test operation depend on different fail reason.. both rework and normal product are sharing the same production line.  in production management, it is kind of make to stock( target stock + shipment plan), and the production need to balance rework stock as well.
    We would like to use SNP to get the mid-term planning(assembly level), which can be referred to MRP run (raw material level). and we need it as input to  short term planning (PP/SD) as well.
    Thanks for your comments! 
    Thanks&Best Regards

    BTW, The forecast is the trigger for SNP run.
    --Thanks.

  • Rework batch stock not propose at a time of delivery creation,

    Hi, Experts,
    I have face one issue at a time of delivery creation:
    Issue : All FG stock availbale in table MSKA , that all stock prapose in availibility run in SO but the same quantity not prapose in delivery document,
    For example : In table MSKA , Initially stock is 100 with 10 batch with 10 quantity fo each batch, Out ot 10 , 2 batch marked for rework, & that batch against consumption (261) also done, AFter consumption in MSKA stock available 80,
    But when we create delivery document , System propose only 60 quantity insted of 80, Actully FG stock availble 80 in table MSKA,
    In SO - Availibility run time system propose 80 quantity, Only delivery time propose 60 quantity,
    We are using MTO scenarion in my company,
    Pls revert me with solution, Any Std. configuration is missing for rework process,
    Request you to alos send me which STd.configuration require for rework process,
    Thanks a lot in advance,
    Regards:
    Happy,

    Resolved,

  • Stock posting for rework

    Hello All.
    After a usage decision has been made to rework all the items in an inpection lot where should I post the material for the rework to occur.
    I cannot post it as blocked because order connot backflush from blocked.
    Also connot post in unrestricted beacuse fifo will pick from any location and not necessarily the one I want.

    Thank you for your response,
    I mean to say the material will be usable after the rework.
    But after the usage decision is made to rework the items where do I post them to,
    so that the rework order created consumes the affected parts and not good stock.
    For example if there is one rework order and one standard order for the same item in the same work center,
    how do I we know to pick the faulty materials for the rework order and the good material for the standard order.
    Can an order be created in one storage location (say welding) to consume stock from another storage location such as quarantine?
    Does the material reamain as Q stock until after the rework? If this is the case can an order be created to consume the Q stock and after the rework is complete convert to unrestricted use stock?
    Regards,
    Chris

  • Rework for quantity in sales order stock

    Hi Gurus,
    The following is the scenario of my client.
    My client is a paint manufacturing Industry. T
    They Will create a sale order for 100 Gallons of paint.
    Will convert the sale order to process order and bring the stock to quality inspection (batch managed)
    After inspection quantity will be moved to sale order unrestricted use stock.(321 mvt type)
    Now i have to send  only 1 Gallon to the customer and based on the approval from customer, we will dispatch the remaining quantity.
    In case the customer rejects the sample, i want to carry out rework for the remaining batch (balance 99). Now the stock will be in sale order unrestricted use.
    How to carry out the rework for the unrestricted use quantities in sale order stock.
    Please let me know how to address this scenario
    Please give your views it will be helpful for me.
    Thanks and Regards
    Hari

    Hi,
    For mapping this requirement you have create a rework process order type and when ever you create rework process order for rest 99 you have to delete all component from component overview tab and add that stock of 99 pcs which is lying in sales order stock.
    Note :- This can only happen if this is not the dispatch location. If this is the dispatch location you also have to create a separate storage location before this sales order location.
    Regards
    Vivek

  • Scrap and rework qty stock

    Dear ALL,
    IN MY SCENARIO I AM DOING THE PRODUCTION CONFIRMATIONS IN CO11N USING MAIN OPERATION IN THE ROUTING.I AM USING AUTO GR FOR HEADER MATERIAL(101)MOVEMENT IN THE FINISHED GOODS LOCATION OF THE CONCERNED SHOP & GI FOR THE COMPONENTS AS PER BOM FROM THE RAW MATERIAL LOCATION OF THE SHOP.BUT I AM UNABLE TO SEE THE STOCKS OF THE SCRAP AS WELL AS THE REWORK QUANTITY OF THE HEADER ITEM.PLEASE HELP ME SO THAT I CAN UPDATE THE STOCK OF SCRAP & REWORK QTY.IN THE SYSTEM IN THE BLOCK LOCATION OF THE SHOP.
    THANKS IN ADVANCE
    R SEHGAL

    Hi Rakesh,
    There is no standard report for scrap quantity. We have to develop Z report with the help of tables like AUFK-AUFM and AFVV.
    The best way is get the details of scrap from table AFRU (field XMNGA) and download to excel with order type or with material/plant combination.
    If you are having rework orders for scrap then you can display this rework quantity from COOIS transaction.
    If helps reward points and close this thread.
    Regards
    TAJUDDIN
    Message was edited by:
            TAJUDDIN MOHAMMED

  • Rework batches stock not propose in delivery document & only propose in SO,

    Hi, Experts,
    I have face one issue at a time of delivery creation:
    Issue : All FG stock availbale in table MSKA , that all stock prapose in availibility run in SO but the same quantity not prapose in delivery document,
    For example : In table MSKA , Initially stock is 100 with 10 batch with 10 quantity fo each batch, Out ot 10 , 2 batch marked for rework, & that batch against consumption (261) also done, AFter consumption in MSKA stock available 80,
    But when we create delivery document , System propose only 60 quantity insted of 80, Actully FG  stock availble 80 in table MSKA,
    In SO - Availibility run time system propose 80 quantity, Only delivery time propose 60 quantity,
    We are using MTO scenarion in my company,
    Pls revert me with solution, Any Std. configuration is missing for rework process,
    Request you to alos send me which STd.configuration require for rework process,
    Thanks a lot in advance,
    Regards:
    Happy,

    Resolved,

  • Setup rework order defaults to Blocked Stock

    Hi,
    We need to setup like that when we create Rework Order for a particular plant it will defaults to "Blocked Stock"( as we see in the Goods Receopts tab of the Production order).
    Can anyone please help me how can we do the setting?
    Thanks

    Hi Moumita,
    For the Re-work scenario, you have to proceed as follows:
    1. First of all, create a order without material; Transaction: CO07.
    2. Go for initial stock posting to blocked stock using movement Type 565 in transaction MB1C.
    3. Then, do the GI and go for PARTIAL CONFIRMATION.
    4. Thereafter doing the GR, post the blocked stock to quality inspection stock using movement type 349.
    5. Then, do the RR and UD.
    6. Then, perform the costing with the help of your CO Consultant and finally, go for the issuing of Debit memo to the vendor.
    Hope it helps.
    Cheers,
    Kaushik

  • Creating a web service to consume price of a particular stock from ???

    hey,
    i'm new, donno much about web services in terms of writing it, but i do have some knowledge about wat it actually does...
    im here becuz i wanna create a web service to consume the price of a particular stock and then store the closing price along with the dates into a database
    now, im abit lost here.. how do i know where to get the information from? is it possible for me to write a web service to communicate with Yahoo! Finance or any other sites which allows consumption of information?

    If you are talking about simple XML transformation of the SOAP payload between the client calling your service and the final destination of the message you are routing, the ESB approach may be a better fit.
    If you have more complex transformation in mind, with major processing and rework of the message in the intermediary, you may be better of with using the POJO approach. Write your service and embed a callout to the other service in your implementation. If the two services share the same Java Model, you may even be able to re-use the same Java Bean.
    To get SOAP Element instead of Java bean, you just need to use the noDataBinding option with either genProxy and topDownAssemble (or assemble). See the WS-Guide [1] for details. Chapter 18 will give you all the details about the different WSA command line parameters.
    Hope this helps,
    -Eric
    [1] http://download-west.oracle.com/docs/cd/B31017_01/web.1013/b28974/toc.htm

  • Rework

    Dear Experts,
    Scenario,
    1.     For certain material there are 5 operation defined in routing.
    2.     Order quantity is of 100 PC. Settlings are maintained such that 2nd operation cannot be confirmed unless 1st is confirmed.
    3.     While confirming order through CO11N  for 1st operation the figures are, 70 PC yield and 30 PC as rework.
    4.     For second operation I can confirm maximum 70 PC, This is truly logical as 30 were put in rework.
    5.     I presume, 30 PC are lying somewhere in system and liable for goods receipt after rework.
    Queries,
    1.     What is the treatment for quantity put in rework for these 2 conditionsu2014 a) OK after rework  b) NOT OK after rework?
    2.     How PCs should be declared (in stock)after rework?
    Thanks in advance,
    Anand Rao

    Hi,
      For 30 PC declares as rework, for that you need to create rework order without material with sutaible routing with reference opration set & BOM by manual entry.
    That order should crate with reference parent order, so that we should able to book extra rework cost to parent order. For order settlemet sequence would be first child order & then parent order.
    At time of maintaining BOM for rework production order, you can maintain -ve quanity for scrap that we are unable rework.
    Please refer below link as well.
    rework order
    Rgd,
    Chetan

  • By product not getting posted to stock while confirming the order

    Hi PP gurus,
                      I am facing a problem. The scenario is : My client is running foundry for manufacturing castings. In case a) He gets pattern as a free issue material from the customer for manufacturing casting. In this case he charges only the rework charges from . In this what need to be done: My doubts are:
    1) What type of material should the pattern be made( free issue material or HALB) because for free issue material i cannot make a routing.
    2) How the above process of charging only the service fro customer be carried out.
    3) If i make the BOM of casting as Pattern as one line item & Used pattern as a by product whose value is negative. When i confirm the production order for casting only casting comes to stock , the by product doesnt come to stock.
    What should i do.
    I really need help for these queries. Whoever answers i will give him 10 points.I am at client site i need a quick solution to it.
    Regards
    Ashish Khurana

    Hi Ashish,
    When you confirm the prod order for the fert, the fert material will be posted the unrestricted use stock & to move the byproduct ie p003, you have to use the 531 movement.
    use migo, GR , enter the reservation no. (you can get the reservation no. form the prod order of the FERT). & then 531 mvnt,
    After this byproduct will be posted.
    Also ensure that "clear open reservations" indicator is not selected when you do confirmation of the prod order.
    Regards,
    SDs

  • Rework on sales return finished goods material

    Hi all,
    There is sales return finished good in stock.
    This FG is rejected by quality assurance due to some quality reasons.
    Now, rework to be done on this FG to make it as per quality standards,
    After rework the material code of FG will remain same and sales will dispatch this FG in the same code.
    How to show this rework process and what r the steps.

    Hi,
    This is handled via Rework Order type, I Feel PP would be the better forum to Get better details regarding your issue, its a normal process in production to do rework on materials once they are identified as not meeting the required specification.
    Regards
    Chandra Shekhar

  • How to deal with the rejected stock if it is rjected by QC

    Dear All,
    please let me know how to deal with the rejected  stock from Quality point of view.i.e., for incoming materails and Finished if returned from customer
    Regards,
    P.Vijaya

    hi
    if material is rejected for incoming material then you can create Notification for incoming material due to  you can return back material with print for that you have to record defects in result recording. in T-code QM02 if result is recorded with defects. or you can create with Qm01.against vendor
    if material is returned from costumer you can create inspection lot for that for that you have to maintained inspection type 06 in material master. you can result record for that you can create notification for that. or rework for this material as per quality check or can scrap
    if have any problem please come back
    regards
    Pravin

  • Sales Order/Delivery for particular customer From his Reserve stock?

    Dear Couleague,
    There is one scenario that faulty material from customer Co. get back by
    Return Order (RE), Then return Delivery --& post goods receipt, Of the sold material,
    Now co. (PP/QM) do rework Process (assemble, dismantle ...... whatever on the basis of return order) & make perfect material ok
    Now this stock PP/QM people put under RESERVE STOCK because it belongs to that particular customer
    Now I want to deliver that stock to that Particular customer,
    1) HOW CAN I DO?
    2) HOW CAN I PICK UP THAT ReserveMaterial while doing Sales Order/ delivery?
    Even though I maintain copy control from RE to OR & AvailabilityCheck?                                                                               
    Thanks
    Suresh

    Hi Suresh,
    As and when you get a return order for repair, then you do the PGR and place that stock into a different storage location and you get that repaired and when you are doing PGI then fetch the stock from the same storage where you have placed the stock when you did the PGR.
    If you are having serial number concept that will help you to give the same piece which you have collected from the customer to return the same piece.
    We have implemented the system in the same way in our previous implementation.
    Thanks,
    Mahesh.

  • How to handle this Rework Scenario.

    Hello friends,
    Following is the rework scenario that is in Pharma.
    My client produces finish product quantity extra than required. Suppose i have order of 1,00,000 tablets. Production order is created and production is completed. Suppose for this order 1000 tablets are produced extra than order quantity. This extra production is kept in production only. In such way, for each order, extra quantity of finish good  goes on increasing in production.
    Suppose now i have order of 10,000 tablets and in production i have 5000 tablets that are already produced. Now i use this 5000 tablets as rework material. I want that when i run MRP system should generate order of only 5000. I do production of  10000 qty. by using 5000 rework material and 5000 order quantity.
    How can i map this scenario in SAP?
    Thanks

    hi
    Pls. find here step by step procedure for Rework Order :
    REWORK HANDLING PROCEDURE
    There are two way one is manual and another is with trigger point (ref operation set)
    1.Create Rework order without material at CO07 with out material .
    2. Assign the settlement receiver as original production order at settlement rule.
    3. Assign the rework material & component if needed at rework order & assign the issue storage location (unrest- use storage location above).
    4. Do the confirmation for rework order & rework material will be issued from stock to order
    5. GR will not be done for rework order. To get stock for reworked material Do the GR for orginal order & settle the both order .
    Another method,
    1. Create a Reference op set in tcode CA11.
    Enter the plant, Description, usage and status
    for the ref op set
    2. Create a Standard trigger point in CO31.(Ex
    Production)
    Enter the Trigger Point usage /Group as FERT.
    3.Tick the Trigger Point Functions.
    4. Enable the indicator create order with Reference .
    5.Enter the system status as PCNF.
    6.The system will says standard trigger point exists from which you can
    select the created Trigger Point (EXx Production)and save.
    7. MD02/MD04.
    8. Convert the Planned Order into Production Order and Release the order.
    9 .Now confirm th ops.
    10. For the last op enter the yield and rework qty
    and set the status as PCNF.
    11. If the status of last op is PCNF then in the
    system a POP UP will appear as Activited by
    Trigger Point /Create order with reference/order
    number/sequence and op number which trigger point
    works and enter.
    12. Now a rework order will be created.
    13. In c003 enter the number which is next to the actual prodn order no.Rework order will be seen.
    Hope this helps.