RPM financial planning - units

Hello PPM experts,
We use financial planning for our portfolio items. Currently all amounts are shown in the currency defined on the item with 2 digits after the decimal. This is far too detailled.
Our project controllers would like to get the amounts in thousands of the chosen currency Meaning that instead of having the amount 168 000,00, the column should display 168.
Does anybody know how this is done?

hi,
In order to remove the decimals, you can change the 'User Settings' in 'Services' Tab on left panel in Portfolio management.
For displaying the data in thousands, I guess you would have to do so enhancement to the code only.
Regards,
Dolly

Similar Messages

  • Capacity and financial planning view in PPM 4.5

    HI,
    I am working on PPM 4.5 and would like to have some enhancements done in capacity planning and financial planning.
    Can someone suggest what are the webdynpro components to look out for ?
    Is it /RPM/UI_DASHBOARD ?
    regards
    abhishek

    Hi Amit,
    I'm using PPM 5.0. I have a requirement to Enhance the Financial Planning View. Where in I need to add an additional field(as a column).
    But I'm stuck up in the technical how go.!(.
    Do you have any idea on this enhancement? like, custom includes, BADI's etc..(I have got a BADI now /RPM/EX_FIN_PLAN, same you have mentioned in above post).
    Amit, kindly help in this regard.
    @Experts,
    Hi experts please look into this requirement & give your points.
    Rgrds,
    Santhosh

  • Financial Planning

    Hi experts,
    I am working on a new Financial Planning application, and I need to know when the financial planning will beging its values on /rpm/fin_plan.  If you know about some information about it and functions modules that i can review, pls tell me. 
    Thnx,

    Please send me your mail and i'm going to send you some useful documentation.
    if the documentation is useful please assign good points
    [email protected]

  • Planning Units issues in Hyperion Planning 11.1.2

    Hi, experts.
    I'm new in HP, so needed some help with misunderstanding of how PU&proccess management normally works.
    More detailed I interested at the area of Validation rules.
    I have to give an example of few problems I met during my try to implement this functionality.
    Firstly, it's a newest version of EPM 11.1.2 installed and supported by the vendor's professionals
    I have Planning app deployed in EPMA with 14 dims. I didn't drop any standard planning dimensions, all are present
    There is the only PU hierarchy to test how approvals works. It has 3 entities and 12 elements of additional dimension - functional group. Hence, there are 36 level zero members in PU hierarchy.
    Form1 consists of 36 rows according to PUH, columns are Period (17) and one custom dim for the target, plan values, it's diff etc. Validation rule VR1 on Form1 check negative values of target minus plan (I plan expences) VR1 has "No Promote" flag. Then I start 2 level0 planning units (entity1-FuncGroup1 and entity1-FuncGroup2). I try to promote these PU1&PU2. It's Ok only if negative exists I get an data error links drilling down into my form1. So user can see the error and all happy.
    Problem actually with form2 that has Region Dim in page. Entity,Functional Group,Account in rows and Plan value,Year,Period in columns. It also has VR2 for testing plan values greater than 1000 with No Promote option. Another VR3 checks values greater than 100 to add new approver, reviewer (no matter) to the approvals process management.
    Both VR2 and VR3 don't work accurately. They fired only for the first member in page (Region), hence any data validation for other regions except first skipped. In addition VR3 when triggered for Region1 always circles (between new and previous approver). It meens there is no way to finish this proccess using the promote option. Anyway you can approve PU, but all steps after current Aprover will be skipped in promotional path.
    Maybe I can't work with Proccess managment in the right way? So could anybody give me an idea what's wrong. I've spent much time googling any issues like me have
    Many thanks in advance,
    Vladimir

    Hi, Theresia
    Yes you're absolutely right, I created VR from the manage form's menu. So I use standard HP 11.1.2 functionality. I've seen it in new features while read Oracle documentation. Also with testing of approvals in Proccess managment I use distinct colours for negatives and diff values (greater 1000 and 100 in my example). Colours work fine, but i can't say it about aprovals :). And all these examples of using planning form VR's i've taken from oracle administrators&user guiide and from presentations of EPM 11.1.2
    In addition I've started work with Hyperion products 2-3 month ago. Hence I have to read a lot of information because my previous experience was OLTP, RDBMS not OLAP.
    As a first step i wanna know all standard possibilities of product i use. And also best practice and some often used technics. Many thanks for your idea with Smart list and BR i'll try it (though i use EMPA and Calc Manager rules). I know that soon I have to use Java API's, so I might read and learn Java to write the simplest code first. But for me it's too much info i have to load into my brain in such short period :)
    As a resume, my opinion it's a bug of new features EPM 11.1.2. But maybe I'm wrong cause none has said the same
    Anyway thanks, Theresia, for your help. If you know or will some new additional info i'll say you thanks again
    Best regards,
    Vladimir

  • Error While Opening dataform after creating Planning Unit Hierarchy

    Hi All,
    I created a Planning Application through classic wizard. Then i created a planning unit hierarchy, after which I am getting the following error: (when i try to open a dataform, from some user other than admin/owner)
    *"Security and/or filtering has resulted in a required dimension not being represented on this data form"*
    I know that this error occurs when some dimension members are represented on dataform but are not assigned with security rights. But thats not the problem in my case. Because I assign security rights to all members of all dimension just for the sake of testing. I later on identifed that this error occurs due to dimensions present in POV i.e. I need to select a single member of each POV dimensions, then in such case this error disappears.
    Now my question is that why i need to select a single member from each POV dimension? I general i leave POV dimensions as it is, while creating dataform
    Right now i aad a dummy member at the top of each dimension, e.g Account_UnSpecified, Entity_UnSpecified and so on . . . and then i select this member from each of POV dimension.

    Hi,
    You can try creating new Root folder and new workspace for your NWDS.
    1.  Create a new folder with name ' <userID>_NWDS_NEW_ROOT ' in your machine
    2. Create a new folder with name ' <userID>_NWDS_NEW_WORKSPACE ' in your machine
    3. Open NWDS (and logon to DTR)
    4. Remove all configurations from your Development Configuration perspective (except 'Local Development')
    5. Go to Window --> Preferences --> Java Development Infra --> Development Configurations
    6. Change 'Root Folder' to the folder created in step-1
    7. Close NWDS
    8. Create ' Run_NWDS.bat ' file in your NWDS installation folder which has 'SapIde.exe' file
    (it will be generally in --> C:\Program Files\SAP\IDE\IDE70\eclipse)
    9. Type following in .bat file -->
    SapIde.exe -data "<complete path to folder created in step-2>"
    10. Now double click on this .bat file to open NWDS
    Now logon to DTR, import configuration, create project from 'inactive DCs' and you should be able to create project and see it in respective perspective.
    Regards,
    Amey

  • What is better to use- Financial Plan Vs. Budget

    Hi,
    We are on 12.1.3 and using Project Costing & Billing.
    Now the requirement is to capture expenditure estimates at lowest task level and later compare it with actuals.
    I'm having few doubts, pls help throwing some light on these:
    1. How do we decide which one to use between budgets or financial plans.
    2. Is it possible to load either budgets or FP through excel.
    3. How can we compare estimated expenditure with actuals at a lowest task level.
    Pls help me on these doubts.
    P.S. We are not using GL Budgets, PA resource lists etc. We are looking at this budgeting requirement at very basic level-  just entering estimates at task level and comparing with actuals.
    Thanks

    I would recommend financial plans, …. biggest advantage we found with them was the ability to enter your cost budget and revenue budget at the saem time, in the same screen, …..
    And yes, you can laod FP's from excel, don't think you can with budgets, you would have to use a tol like dataloader i would guess, ...
    Comparing actuals with the estimates ? just write a report, ....
    Regrads,
    Eric.

  • Can a Financial Plan Type be attached to more than one Project Template

    We are working on Project Accounting through Self Service pages. For doing the Cost Budget we have created a Financial Plan Type. We attached it to a Time & Material Project. But later when we tried attaching it one more template, a Turnkey Template, it does not give us the Cost Budget-Financial Plan type in the drop down box.
    Hence, wanted to know whether we can attach a Financial Plan Type to more than one Project Template??? If yes, then why didnt we get the option in the drop down box?
    Chirag..

    Since you are not using Company code as the branch, and are using Profit centre as the branch, I dont think its right for you to set a default profit centre for any GL account in the Chart of Account for that company.
    all the SAP user in the company will be using the same company code to post, and thus, will be using exactly the same inventory account, if you set a default profit centre there, no point rite? You will need to implement a procedure to ask all the user to manually assign the profit centre during posting. Just like how we normally ask user to specify the company code before posting.
    The authorisation should be set by profit centre as well. hope this helps. Thanks.

  • User In Planning unit Hierarchy unable to see data form in editable mode

    hi all,
    we are facing a problem in planning unit hierarchy in Hyperion planning, where we have 4 users, Hierarchy is define as
    hierarchy: budget approved
    version: approved
    Entity: Finance
    Senario:Budget
    haroon asghar ( owner)
    adeel javid (Reviewer)
    Naeem asghar (Reviewer)
    Imtiaz (Reviewer)
    Issue is that,after start the budget activity (promotional path) by Admin, the data form editable to Owner haroon asghar
    but after completing his work by haroon,when he promote the planning unit ,the next user in Hierarchy "Adeel javid" unable to see data form in respective planning unit in uneditable data form not only for this user but all rest of the users as well,while i think data form should only uneditable(grayed) for user Haroon Asghar who promote the planning unit.
    we have checked all security rights to the users those are "Write access" but still Adeel javid is unable to enter data,so the budget activity is stop due to this problem.
    when i remove the planning unit then i log in with all user one by one and see all data form required version,scenario and entity were editable to all users mention above
    we want to run budget activity with the above planning unit hierarchy.
    plz any one provide the proposed solution of the said issue
    we are using Product Version     11.1.2.0.00
    Regards
    Anwar

    Reviewers will not be able to write data to the intersection. Reviewers can only review the data and follow-up with a Reject, Promote, Sign off, Delegate, Originate or Freeze.
    Please refer Article ID 1226783.1 in MOS.
    HTH-
    Jasmine.

  • Financial Plan in Multiple Currency

    Hello,
    In the HTML screens I want to create Budget Lines using Multiple Currencies. This means create a line in USD for a certain Task and for the same Task create also an Euro line. I've checked the Multiple Currency option at the Financial and Workplan also added each Currency to the Work - and Financial Plan. Still I'm not able to enter Budgte Lines in other than the functional currency USD. Can someone help me out on this one or send information how this functionality has to be ste up in Release 12?

    First you need to do setup for the Multiple Currencies under "Plan Settings" Tab of Planning Options. Check "Plan Amounts in Multiple Currencies" check box and in the "Currency" Tab select the different currencies like EURO and give the rate.
    Now go to your Budget Lines and add 1 budget line using your default USD currency. Now select that Budget Line which you have created using your Default Project Currency and also select "Add Currency: EURO" from the Drop Down List of "Select Planning Elements" and press GO button. This will create another Budget Line using EURO Currency. Now enter the Quantity & Cost and see the difference of Cost Calculation.
    I hope it's clear for you.
    Regards,
    Khan.

  • Report Painter - Use SKF to calc act/plan unit costs in CCtr report

    Hi Report Painter Gurus,
    I am an end user working with our Report Painter consultant and I have asked for a Cost Centre report with columns for Actual Costs, Actual Unit costs, Plan costs, Plan Unit costs for Month and Cumulative. I have seen this report in my previous business so I know it can be done but consultant says it's impossible.
    The report I previously used had the SKF values at the bottom of the cost centre report and then the unit costs columns (both actual and plan) referenced these SKF cells in the formula which divided Cost by SKF.
    We have created the SKF using KK01 and posted dummy amounts in KB31N but consultant says he cannot reference the SKF values in the formlas.
    If you can spell it out to me (I have dabbled in Report Painter myself), then I am sure I can explain it to consultant.
    Any help gratefully appreciated!
    Cheers,
    Matthew.

    Matthew,
    I think it is quiet simple. When you add a column to the report painter report you can choose from the drop down menu for 'Basic Key figure' whether it is Costs, Activity quantity, Statistical quantities, etc.
    So if you have a column with Costs (X1) and one more column with quantities (X2), you can easily come up with another 'formula' column and use the equation (X1/X2).
    I think this should serve your purpose.
    Best regards,
    Vishal Thakur.
    Edited by: Vishal Thakur on Mar 2, 2010 11:08 AM

  • Approvals Process:  Cannot promote a Planning Unit

    Hi, Am new to the Approvals process in Planning 11.1.2.2
    Have set up a Planning unit and assigned owner and reviewers to entities. Approvals template is set to "Bottom Up". Have also assigned a version and scenario to the Planning Unit H. When the Planning Unit is Started , the current owner changes to the user assigned as the owner and all is good. However when the owner attemptes to promote the planning unit to the next reviewer the promotion action fails with the message "Change status cannot change ownership to the new owner due to insufficient access". For my testing, have assigned the owner and all reviewers "Approvals Administrator" access to the planning application.
    Any ideas as to what access the error message is talking about ?
    Thanks !

    Dear,
    -Please check with the Provision that you have given to the USER,
    -Use file based export and checke wheater you missed any user to mention that hierarchy.
    -IN the approval hierarchy check  every node weather you have given the user there or not, chances are that even if you miss one member you will get
    this error.
    -We faced the same issue and we got resolved it by checking the Provision of the User and following the above steps
    Thanks
    Bejagam Naveen

  • Workflow Planning Unit Ownership - Begin the budget review process

    As an Admin, is there a way to assign multiple planning units with an import option or something like that? Right now the only option I see is to go in one-by-one and start the fcst cycle and then assign the ownership to the person who is entering the budget information. I have 150 Entity members to assign for one forecast cycle and was wondering if there was a "smarter" way to do this.

    Hi!
    We are referring to the same example of wf for which you answered some time ago. But we need to extend the process to the whole entity dimension. Thus we have this situation.
    our entity dimension: --> http://postimage.org/image/d3utdauzn/
    Our wf process:
    free format wf. (since the entity hierarchy does not follow a linear path: bottom-up or top-down)
    1.ENTITY 1 inserts data and submits them to a reviewer.
    2.the reviewer approves or rejects data.
    3.then the process should be sent to ENTITY 2,3,4 (lower levels of ENTITY 1) to start to modify/adjust data that ENTITY 1 has imputed and distributed to their levels trough a rule.
    the problem is at the 3rd point. How could ENTITY 1 or the REVIEWER pass the process to ENTITY 2,3, and 4 at the same time? I see that I cannot make a group of users owner of one PU, and then limit their level trough the provisioning. The only solution that I have found for this is to send an e mail to ENTITY 2,3,4 and then let them start to input their data (the drawback in this case is that they can always modify data in cells for which they have the write provisioning , and not only when the reviewer has approved data.
    moreover in the case the reviewer approves data sent by ENTITY1 he becomes the new owner of the PU, that is the only way trough which ENTITY 1 cannot modified them after the approvation)).
    Thank you very much.
    Edited by: user648334 on Jun 6, 2012 2:51 AM

  • When to prefer Financial Plan Vs Form base budgets? Adv and Dis-advantage?

    Hello Experts,
    Can any one explain me the difference between Oracle projects financial plan vs oracle projects form based budgets?
    What is advantages of each of them and when to provide preference over each other?
    is it possible to use both of them simltaneously?
    Does forecasting functionality available in both of them?
    Need insight on this
    Thanks
    will Really appreciate ur response.
    Thanks

    Hi
    Form based budgets are the only supported budgets for Budgetary Control and integration of project budget with GL budget.
    If you are not using those functions, there is no advantage for the form based budget.
    With financial plan you can load budgets using Web ADI.
    You can use more robust resource lists.
    You can use multi currency amounts
    You can generate budgets and forecasts based on various sources like workplans, actuals, commitments and any customized logic using client extension.
    You can report on financial plans using the HTML project performance reporting.
    You can rollup budgets and forecasts amounts on a program.
    Summarizations are done immediately and you don't need to run a batch process.
    Dina

  • Hiding few columns in Financial Planning screen for Portfolio Management

    Hi,
    Is it possible to hide few columns in the Financial Planning tab page for Portfolio Management.
    Please suggest how, if it is possible.
    Regards,
    Nishit

    Hi Nishit,
    What fields are you thinking about hidding?  the buckets are determined via your own configuration.
    Thank you,
    Michelle

  • Planning Unit Hierarchy - multiple owners per Entity

    Hi there everyone
    I have the following scenario and hope you can help me out with a few ideas:
    I have a planning unit hierachy set up. It works well except for one thing - the fact that you can assign only one owner per entity member. The business essentially has multiple owners for most entities. Ownership is determined by which accounts the user is responsible for. An example:
    User 1 is an owner for Entity A, but only for accounts 111-444.
    User 2 is an owner for Entity A, but only for accounts 555-777
    User 3 is an owner for Entity A, but only for accounts 888-999
    As far as I can see in the Edit Planning Unit Hierarchy screen, I am able to assign User 1 as an Owner for Entity A on the Assign Owners tab and I can specify accounts 111-444 in the Primary and Subhierachy Selection tab. Since I can only assign one owner, how can I now provide for User 2 and User 3 requirement?
    I'm using version 11.1.2.1. Any workarounds or suggestions would be highly appreciated!
    Thanks
    Juanita

    I had a similar business case in my previous project. There was no direct solution to this. But we had to stick to a workaround ( not a very nice and comfortable solution, but we were under critical timelines).
    User 1 is an owner for Entity A, but only for accounts 111-444.
    User 2 is an owner for Entity A, but only for accounts 555-777
    User 3 is an owner for Entity A, but only for accounts 888-999
    make a secondary hierachy with different entities i.e. User1_EntityA,User2_EntityA
    Entity A
    User1_EntityA
    User2_EntityA
    and then you can assign different users to all these entities. One major drawback with this is, if we have 100 entities with 10 users .. that will make 1000 more members.. anyhow we did it that ways.. if you get a better solution you can post it.
    Thank You
    Sandeep Kumar Upadhyay

Maybe you are looking for

  • Workflow in Project server 2013 online not going particular stage after Approval

    Hi All, i have created workflow using sharepoint designer 2013 for project server 2013 online. and i have also set the approver after the first stage. when i create a project using this workflow, project is created successfully and the approval task

  • Special Characters Not Displaying at Logon Screen

    Hello, my daughter set her password on her iPad using special characters and has been able log in  by holding down a certain letter on the keyboard and choosing a latin character.  This is no longer working as the popup menu doesn't appear when holdi

  • Need some help with Keynote export

    I want to create an swf file from Keynote that will be used in a looped Powerpoint slideshow. It will be no longer than 1 minute long. I create the file and export as a .mov. Then I used Visualhub to convert to an .swf. People have had lots of issues

  • Input Tax Reversal in AB08

    Hi I Created the Lease Master in ASO1 and then i did the Acquisition of this Lease. then i made the payment to this Lease assets vendor. Now, due to reason i want to reverse the Asset( AB08).But i dont want to reverse the input tax entry. So how can

  • Developer Support Tools for OS X

    What are the recommended tools roughly equivalent to Rational Purify Plus suite in OS X? (Purify, Code Coverage, Quantify) I know of Shark, gcov and the common stuff that is either FOSS or ships with XCode... are there others? [commercial or otherwis