Scheduling agreement,(GR value is wrong)

I have one scheduling agreement, the price is 1.31 INR from 10.10.2007 and i made GR for this three times, it shows correct quantity and value in Purchase order history, in 18.10.2007 the one GR is showing me wrong value, per material isit, showing me 0.02 INR why?(we are putting the quantity is correct)
for the vendor and material Inforecord is existed in that, also 1.31 per item is there, and validity of inforecord is up to 9999 year.
what must be the reason,
i have checked any body changed the value are not, but they have updated that from30.10.2007 they made value 1.32 Inr per material
what are reason?
sapman

Hi,
It looks like system has posted GR with difference in price i.e.1.32minus 1.31 i.e.0.02 , Please check was there any reversal of this GR?or any scales maintained in inforecord for quantity? is the accounting document also posted with same price?If accounting doc is posted correctly then it might be an po history updation problem just check
BR
Diwakar

Similar Messages

  • Change in Scheduling agreement condition value

    Hi Friends
    i have a scheduling agreement with a CVD condition maintained as 10%. the SA is not yet closed and the CVD value has to be changed to 8%. i cant update the value as it is not coming from condition record. cant delete the material line item also. please suggest any alternatives.
    thanks in advance

    Have you created SA with info record?
    can you able to maintain the CVD at info record level with effect from say 26.06.2009 as 8%
    keeping other conditions unchanged
    this is just a thought

  • Scheduling Agreement JIT / Forecast calculating wrong

    Hello experts,
    I´m with a problem with JIT / Forecast.
    The forecast are calculating wrong values. For example:
    Cumulative quantity calculated: 584
    JIT schedule:
    DATE             TIME         Order Quantity       Cml. released quantity        Open Quantity
    06.01.2012     00:00     32          32                      
    10.01.2012     00:00     352          384                      
    13.01.2012     00:00     128          512                      
    17.01.2012     00:00     88          600              16
    Forecast schedule
    DATE             TIME         Order Quantity       Cml. released quantity        Open Quantity
    20.01.2012     00:00     112          112                      
    24.01.2012     00:00     224          336                      
    27.01.2012     00:00     128          464                      
    31.01.2012     00:00     200          664          
    The values of forecast are calculating by Cumulative quantity calculated that is 584 and I dont have any Open Quantity and in this case I need to have Open Quantity in Forecast.
    The forecast must not be calculated by the amount in transit
    Help me.
    Tks
    LFC

    Hi ashish
    Check the  planning delivery schedule tab and go to item data -> delivery schedule header and check wheather any proper information has been filled or not
    Regards
    Srinath

  • Wrong data in MCE1 & MCE3 reports for scheduling agreements

    Hi All,
    I have got problem while executing MCE1 & MCE3 reports.It shows wrong PO value and GR Qty. While executing , I am giving inputs as P.Org,Vendor and Period in T.Code MCE1. After executing ,I select Info Structure S011.But the output is not matching with Actual GR quantity and PO Value if you see Purchase Order History.The same case with report MCE3 report,where Info Structure S012 is being selected.
    I have checked in MC26 , where data field for period determination is set as Purchase Order date.
    So Can anybody assist me on this ...How to get the exact data (PO value,Invoice amount,Order qty)which should match with PO history??
    Further to this, Is there any Standard report to get the value of materials bought via consignment??
    Please let me know if there is any customization setting involved??
    Thanks in advance..
    Somu

    1> On what logic is the system picking that calculation schema?
    As per "Define Schema Determination" in spro Purchasing document should pick the Pricing Procedure .
    After creation of scheduling agreement have chacked your values in Scheduling agreement (Purchase ORG ,Schema grp in Vendor)
    2> What settings can I do to make it pick that calculation schema only which has been assigned with POrg Sch Gp and Ve Sch Gp?
    Check in Vendor mater is there any Plant specific Purcahsing data maintained.If it is plant specific Check purchasing data for that Plant.

  • Limit to the value of Goods receipt in a Scheduling agreement

    Hi All,
    Please let me know if there is any way to limit the goods receipt posting against a Scheduling Agreement to equal to or less than the total agreement value. Or else if the GR's has already been posted for some value, the system shuld check and allow a user to post furthur for the remainin value only.
    Also let me know if there is a way to check the remaining quantity in the scheduling agreement and allow MRP run to generate new schedule lines for that quantity only..

    Hello
    It is a special case that we have to analyze that order now.
    As I said, this material was not costed any time.  This production order was created for a Sales order.  when I go to the cost analysis from the production order, I find the plan costs.  But it is not from the costing run CK40n or CK11n.  I hope it is from the sales order cost estimate.
    But I am unable to understand how the goods receipt was posted as the material master does not have any price.  I find that the goods receipt was posted @ 489.88 per unit.
    I am unable to find out from where this 489.88 unit price was used by the system for GR posting.

  • Cumulative Qty Received by Customer wrongly updated in Scheduling Agreement

    Hi All,
    I face a strange issue in Schedule Agreement[Forecast Delivery Schedule].
    The exact scenario is as follows:
    1)On 17/09/09, I saw a CmlQtyReceived of '249'.
    2)On 19/09/09, this value got changed to '141'
    3)On 23/09/09, this value again got changed to '249'
    I was not able to identify the reason for the '141' Qty getting displayed on 19th. Even if I go to Analysis now, there is no Forecast Delivery Schedule with '141' Qty to support the display.
    Do let me know the issue in this.
    Needless to say points will be awarded for helpful replies.
    Regards,
    Raj Kumar Reddy.

    Hello;
    I researched about this issue and I would like to recommend you to check the FAQ note about the most critical problems with Scheduling Agreements, note 923104.                                                                               
    As stated in question 2 (or also 3), you can check and correct the cumulative quantityes using Report SDLIPL01. Regarding this report, please refer to note 923105.                                                                               
    In addition, I kindly ask you to please check notes 922638 and 922639 about more details regarding the cumulative quantities.                   
    Also, read the follow notes related to fiscal year changes:
          336670    Avoid the fiscal year change (introduction) 
          332971    Avoid the fiscal year change (coding)      
    Well, I hope those documentation can help you a lot.
    Regards
    Ruy Castro

  • Item Text value of scheduling agreement number (ME32L).

    Hi All,
    How I can get all changed values of item text for a scheduling agreement number in ME32L transaction. Actually when I am using function module ‘READ_TEXT’ it will give only last changed value of item text. But I want all changed values of  item text.
    Please reply ASAP. It’s very urgent.
    Thanks & Regards
    Rakesh

    Dear,
    Thanks for your reply.
    i checked the assigned schdule line catogry as L2 and it have the tick mark over the Req / Assmbly.
    anyother reason?
    Thanks

  • Scheduling Agreement pricing condition PB00 value

    Hi Experts.
    Within pricing schema I do have pricing condition PB00 that is manually put in by the user. I have created a routine in order to calculate the PB00 value based on some logics and assign it to PB00 within the pricing schema.
    So, if the custom logic are found, the price value should be change accordingly, if not the value put by the user will be kept.
    The problem is that, at end of my routine the price is correctly calculated (let's say the user writes 2 and my routine calculates a price of 3) and the price is correctly updated on the scheduling agreement line field NETPR. But if i go inside the item to see the conditions I still see PB00 with the not-changed value.
    Can anybody suggest? I am manipulating xkomv-kbetr and  konp-kbetr.

    Hi, Thanks for answering.
    They are set so. But i need in any case to change the value of PB00 accordingly to my routine.The problem is that, at end of my routine the price is correctly calculated. PB00 value is 2 and it correctly recalculated by my routine to 5. on the SA item I see hte net price equal to 5, but if I go in the details I see condition PB00 still equal to 2.
    Do you have any hints? thanks.

  • Schudling agreement with time dependent excise base value taking wrongly.

    Sub: in migo excise base amount is not changing as per the scheduling agreement type LP ( time dependent ).
    I have created the scheduling agreement type LP with time dependent.
    I have maintained the price value in two validated period i.e
    01/07/08 to 31/07/08 price is 100 rs.
    01/08/08 to 31/08/08 price is 200 rs.
    I have maintained the delivery schedule on
    15/07/08 of quantity  1 nos.
    When I am doing the goods receipts for the scheduling agreement on
    Document date I am giving  15/07/08.
    Posting date I am giving 15/07/08.
    I am giving the posting date in the excise  also 15/07/08.
    After item ok.
    When I will the excise base value it is taking 200 and also excise duty is also calculating on 200.
    When I will post the document
    The stock account and GR/IR account is taking 100 only
    And excise duty is posting  for rs: 200 only
    Why the excise base value is not changing as per the validity period.
    What setting I have to do the change the excise base value  as per  the  validity date maintained in the time dependent .
    regards
    jrp

    Hi
    I was wondering in J1ID there is validity from date only no to date, Pls tell where you have maintained excise base amount based on from to period.
    In J1ID if you maintain any new accesable value for the later date it will consider that.
    Rgds
    Srini

  • Set Default Values on Purchasing Scheduling Agreements

    Good day All.
    I need to ensure that the  Confirmation Control Key(EKPO-BSTAE) , Unlimited Over delivery indicator (EKPO-UEBTK), Creation Profile (EKPO-ABUEB) and Jit indicator (EKPO-FABKZ) is automatically updated with default values when a scheduling agreement is created for a specific purchasing organisation. Please advise if this is possible via config (SPRO). 
    Many thanks, Yumna
    Edited by: Yumna Abrahams on Aug 10, 2011 2:58 PM

    Hi,
    To set default values for screen painter parameters initialize the field names with default values in the PBO module....
    say u have the field name as f_field1....
    in the PBO of that screen initialize it....
    f_field1 = '100'  "here 100 is the default value.
    <b>reward points if useful.</b>
    regards,
    Vinod Samuel.

  • Freight value in PO and Scheduling agreement

    Hi,
    The freight value getting added with material cost when we do GR against PO, but not getting added with material cost when we do GR against Scheduling agreement.
    What is the reason, and how to correct it ? (we required it to get added with material cost)
    Regards,
    Sattuj

    Hi,
    Can you please tell me how you maintained freight condition in scheduling agrrements? Did you add them in supplementary pricing procedure... if yes could you do a MIRO for planned delivery costs ?
    i am using standard LPA doc type and it does not allow time-independant conditions.. so without removing the "time-d" tick on the doc type.. is there a way taht we can maintain other consiions other than price on scheduling agreement line items ?
    regards

  • How to create zero valued Schedule Agreement

    What is the config required for enabling the creation of zero valued Schedule Agreement?
    Thanks,
    Kiran

    Kiran Bhattiprolu wrote:
    What is the config required for enabling the creation of zero valued Schedule Agreement?
    >
    > Thanks,
    > Kiran
    Then you have to maintain info record for material and vendor in that inforecord you have to maintain value then  at the time of sheduling agreement sys will not ask the value it will be taken from info record automatically..
    Thanking you

  • Condition values and validity periods of a Scheduling agreement .

    Dear Friends,
    I have one querry .Where does (in  Database table) ,  the condition values and validity periods of a Scheduling agreement stored .
    Thanks and regards in advance.
    Vijay.
    Edited by: vij kot on Sep 9, 2008 12:09 PM

    Hi,
    Refer Tables
    KONH - Condition Header
    KONP - Condition Item
    KONV - Conditions (Transaction Data)

  • Wrong delivery date in Schedulling Agreement

    Dear All,
    We maintained scheduling agreements for our Customer's Materials.
    For all tomorrow's deliveries i.e of 05.07.2008 all scheduling agreements are showing today's date i.e 04.07.2008 in VL10e as delivery.
    Delivery Date : 05.07.2008
    Goods Issue Date : 04.07.2008
    Loading Date : 04.07.2008
    Material Availability Date : 04.07.2008
    Trans. Planning Date : 04.07.2008
    Interesting point is that no delivery is showing pending for 05.07.2008 in Vl10e. All the deliveries of 05.07.2008 are appearing in today's date.
    I checked factory & Sales calender of company. Saturday is working day
    Regards,
    Sagar Pande.
    Points will definitely awarded.

    Hi,
    If you have maintained Delivery Schedule for Scheduling Agreement as 20.05.2011 and Vendor has supplied materials on 15.05.2011 then you can not do GR on 15.05.2011 since Delivery schedule of Scheduling Agreement are firm and have control over dates.
    You need to revise the delivery schedule in ME38 to 15.05.2011 and then do GR.

  • Change Schedule Lines values for Each Item for a Scheduling Agreement ?

    Hii
        I want to change the Schedule Line Schedule Qty for Each Line item for a
    Scheduling Agreement .
    I cannot use BAPI_PO_CHANGE as this is for PO only and gives error for
    a scheduling agreement.
    I am on 4.6c so i SAP does not have BAPI_AGREEMENT_MAINTAIN .
    Please help me out on using a BAPI or FM to do this.
    Regards
    Gaurav

    Hi,
    isn't the Schedule Line a special case of SALES order  that might be changed with a BAPI_SALESORDER_MAINTAIN.... If ther is no BAPI for this in your system, you might create new contracts with reference to existing ones using BAPI_CONTRACT_CREATEFROMDATA.
    Regards,
    Clemens