Scheduling for planned order & production order
Hi,
I am not using fully routing.
I have given requirement.
08.2009--- 100 MT
09.2009--- 100 Mt
When I run MRP system always schedule FRom 01.08.2009 to 31.082009 .How to made settings.
I have maintained In house production date 30 days.Forward scheduling.System always calculates from the current date,If I given oder start in past is activated in customizing take as 01.08.2009 as order finish date.
Guide me
Regards
bhuvan
Hi bhuvan,
That is because of your requirement date.
Which are 08.2009 and 09.2009
08.2009 means your finish materials should be ready for delivery on 01.08.2009 similar way 09.2009 material should be ready for delivery on 01.09.2009.
System always schedules the orders to meet the requirment dates.you may find exception msg like rescheduling in(10) or Plan process according to schedule (30) along with those plan orders.
Regards,
Dhaval
Similar Messages
-
Collective scheduling for planned order
Dear Gurus,
i create the planned order using the bapi standard whit the production version , but when create the new planned order the version don't is read in the order, ( BOM + ROUTING ) OF THE version.
For read the production version you must reschedulling the planned order.
Are there the methods for read the production version at the creation of the panned order ,
or the strument for rescheduling collctive?
Thanks a lot
Daniele Pistilli
PP TEAMDear Gurus,
thanks for indication of the material master, but we don't always manage the versions of productions.
For the production order there are the routing without the production versions, but when i create whit the bapi or whit the transaction MD11 the new planned order manually i need setting the production version , but when i setting the version for the find the version ( bom+routing) i must re-scheduling the planned order.
Are there the BAPI or alternative soluction for re-scheduling the planned order collective, or for read directly the version present in the BAPI ?
Thanks a lot
Daniele Pistilli
PP TEAM -
When I choose leadtime scheduling in MRP RUN then system does forward scheduling always.
Then in planned order change mode when i do manually do scheduling then it does backward scheduling as per settings in OPU5.
How to get backward scheduling in MRP.??Dear,
MRP do the backwordscheduling but The system always determines the basic dates for planned orders using backward scheduling.
The system automatically switches to forward scheduling if the determined start date lies in the past.For this you have to maintain 2 settings.
1)In OPPQ - Plant parameters maintain the indicator for start date in the past allow. 2) In OPU3 for your plant & order type , maintain the no. of days for start date in the past.
Hope clear to you.
Regards,
R.Brahmankar -
Scheduling of planned order and Production order
Dear PP gurus,
I have run MRP , after running MRP, system has created planned order. These planned order dates are schedule by the system in 2015....I am not able to understand. how? . When i double click on
planned order order and try to convert it in production order those dates get copied into production order.
DO i need to change the dates thr? or keep the same dates which the system is giving>
I m going wrong somewhere. please tell me where and what is config for scheduling for planned order and production order?
Please tell me step by step procedure
Regards
Edited by: Aadi1981 on Apr 1, 2010 9:02 AMThanks for replying,
I have done the below setting for shceduling. Kindly check and let me know any setting needs ot be changed or incorect
FOr scheduling production order , i have configured below settings in OPU3
In OPU3 ,
Detail scheduling tab
Scheduling and Generate cap req tab is checked.
then
adjust scheduling , adjust dates tab, : adjust basic dates , adjust dep , reqt to operation date is selected
scheduling type is backward.,
Automatic scheduling tab is checked.
In OPU5
Scheduling of PLanned order
Scheduling and Generate cap req box is checked (selected)
Adjust scheduling
Sheduling level: via detail scheduling
adjust dates: adjust basc dates , adjust dep reqt , req to operation dates
For capacity scheduling ; always basic dates, dep reqts to operation dates
scheduling type ; backwards
apart from this do i need to do update ca96/ ca97?
best Regards
Edited by: Aadi1981 on Apr 3, 2010 7:42 AM -
MRP-Delivery Schedule for Sales order is not updating in Production order
Dear Experts,
I have created Sales order and maintained delivery scheduling, Then Run MRP through MD50,
We received Planned order then through this we have converted to Prodcution order.
When we observe the delivery schedule for sales order under assignment Tab in Produciton order which is showing zero instead showing line item of Delivery schedule.
I am able to see Sales order and Line item but i am not abel to get any delivery schedule line item.
Please suggest where settings are missing.
Thanks in advance
Regards
DonDear Experts,
Please provide me solution.
after Running MD50 transaction against Sales order.
If I maintained different Scheduling Line Item for First Line item of Sales order.
The Respective Scheduling Lines should update against Each Production order which has converted from Planned order.
Thanks in advance.
Regards
DON -
Disabling GATP for planned orders/production orders
Hi,
We have a scenario where we need to disable ATP check for production orders happening through GATP. That is, ATP check for production order materials should happen in SAP R/3. This is a problem because we have activated ATP check in integration models for sales orders and it is happening through GATP. Production Planning is happeninig in R/3 and we dont have either PP/DS or SNP in APO. ..only GATP.
any pointers on how the ATP check for planned orders/production orders can be blocked in GATP for the same materials which are active for sales order GATP check?
Thanks.hi Pawan /Prasun /vikas
Thanks for your helpful answers
@Pawan : Since we have recently gone live with production planning and its in the process of stabilizing we do not want to enable ATP check for production orders in GATP yet. Also since we are also using batch-determination with ATP check in production orders we still have to check how the system responds with the combination. Therefore,as of now, we dont intend to switch on ATP for production orders in GATP.
@ Prasun : I understand there would be a user exit (EXIT_SAPLATPC_001) which would help in doing GATP check based on order type/business event. However my concern is if the order does not belong to any of the order types will the system do a normal standard ATP check in APO or it will do a ATP check in R3 ? Our programmers are still looking how to tweak it but any pointers based on your experience will be helpful
Thanks -
REM scheduling in planned order
Hi,
I am using repetetive manufacturing. I have maintained Forward scheduling in transaction OPU5 and selected the selection ID 02 for rate routing for detailed and rate based scheduling.
Planned orders are created from MRP. When I check the planned order deatails, in the Det.Scheduling tab it shows scheduling type Forward and in the Production rates tab it shows backward scheduling. I have maintained Forward scheduling in OPU5. So the production rates tab shows different scheduling type. How?
can any one explain this.
thanks and regards
murugesanHI
Check the entry parameters for the planning table in OS80 .
check and revert
Regards
Anupam Sharma -
User exit/ badi needed for planned order create/change,collective ATP check
Dear All,
I'm looking for a user exit/ badi which can be used for planned orders at the stage of
mass collective availability check (COMAC tcode) update; or at some other relevant stages of mass update of planned orders.
I need after collective availability check to perform the following:
1) to copy date from "total comitment" field on header tab of planned order and paste it (replace old date) to order finish date on header screen
then
2) to start a scheduling.
Very appreciate your help.
Best Regards,
Andrey
Edited by: Andrey Kruglov on Apr 15, 2010 3:06 PM
Edited by: Andrey Kruglov on Apr 15, 2010 3:07 PMDear,
Use the BAPI : BAPI_PLANNEDORDER_CHANGE
Or use the function module MD_SET_ACTION_PLAF for Schedule planned order.
and the transaction MDAC Execute action for planned order
This function module includes the following actions:
Explode BOM
Explode BOM, check availability
Check availability, only explode BOM in the case of a requirement
Check availability, do not explode BOM
Reset availability
Change planned order data
Schedule planned order
Delete planned order
Assign the key for the respective action control to the materials in the material master (MRP 4 view).
Please refer this thread,
Re: MDVP for collective orders
Regards,
R.Brahmankar -
Creation of Reservation for planned order
Hi Team,
Is it possible to create reservation for planned orders after MRP run?
My opinion was the reservation can only be created with reference to production order after MRP. The reservation can not be created with reference to planne dorders after MRP run because planned orders are intermident document which will not exist in the system always. The planned order details will not be available in the system once it get converted into production order.
How the reservation will be processed which was created with reference to planned order after converting the planned order to production order?
Kindly need ur guidance.
Thanks
pskDear PSK,
In a typical discrete manufacturing setup production orders are the promised receipt for which reservations gets generated as
soon a production order is created.But only if the order is released goods movements can be posted against the reservation
details through MIGO/MB1A for 261 movement.
It's not required to create any reservation at the planned order level or which may not help you in any means to your business.
But however in a REM scenario MF60 is used to create stock transfer reservations for 311 movement where planned orders
are used for production backflush.To explain in detail even without any planned orders you can do a stock transfer reservation
for a production quantity.
Check and revert back.
Regards
Mangalraj.S -
How to connect MAPL and PLPO to derive work center for planned order
Hi,
Anybody know how to derive work center using MAPL and PLPO for planned order (PLAF). Is there any connecting table between MAPL and PLPO.
Please help asap.
Regards,
MitaliI guess u r trying to view the detail scheduling info (tab in MD13) for a planned order . In that case -
1. Go to PLAF and enter the planned order number. (PLAF-PLNUM) and get the ID of the capacity requirements record (PLAF-BEDID).
2. With this PLAF-BEDID go to KBED. pass the value here. KBED-BEDID. The KBED-ARBID values are your work center ID.
3. To get the work center texts ( the way is appears in the screen) - Pass this value to CRHD . CRHD-OBJTY = 'A' ( i.e Type work center) and CRHD-OBJID = KBED-ARBID.
Hope it solves ur prob.
Cheers
SKC -
Table For Planned Order Details From PP Module
In our organisation we are taking Plan Vs Acheivement from Production. So, intialy we taken Plan details from "PLAF" Table and Acheivement details from "S225" Table. But After running MRP at month end. Previous month plan get deleted and new order create.
how to get history data for Planned order.
Please help us.
Regards
NagaI don't think that there is any history in regard to planned orders. PLAF will get rebuilt according to your MRP parameters and I don't believe that the data is stored.
Regards,
Rich Heilman -
Hi Experts,
I have configured the ATP rule for Planned Orders. So I only want to check the component stock and Production Orders when running ATP check for the Parent Material.
In OPJJ, I only selected the following options.
Include Safety Stock : Ticked
Check without RLT : Ticked
Incl.production orders : X (Take all production Orders into account)
No other options or boxes have been selected
Also I have included the relevant Checking group in MRP 3 for the Parent Material (Checking Rule has been assigned to that Checking Group in Config) and also maintain the Plant Parameters for MRP (assign the checking rule to the plant)
So, For an example :
Parent : A
Components : B and C
Parent Material A has only 5 Planned Orders starting on same day 20.05.2014 each qty 5
Components B got stock 300
Components C got stock 1
When I ran ATP Check for the Parent material A using COHV, qty 1 has been allocated to all the planned orders as committed. Why is this happening ?
I also checked in CO09 for the Component Material C, and it says ATP Qty is only 1. I expected the system would allocate that stock 1 to one of the Orders but it seems to be not working as I expect.
Any explanations will be much appreciated and will not hesitate to avoid the points.
Kind regards,
IsharaHi DB49,
Appreciate your reply. Please see the following comments.
Right now I have been assuming that you have performed an availability check manually for one of the planned orders, and you got the same results (overconfirmation). Please confirm.
Yeah I have performed for one order and it gave me the same result. Also, when I perform for the 2nd Order, it allocates the quantity.
OK, basic things you should already have checked:
You have maintained the checking rule for planned orders (OPPQ or OPPR)
You have maintained the ATP group for the materials (OVZ2)
You have assigned the ATP group to the Material Master of the components (MM02)
You have maintained the scope of check according to the rules you mentioned earlier (OPPJ).
You have no planning strategy in the component material that would have invoked a special ATP.
I checked everything apart from point 2 (OVZ2). I have maintained that via MRP Group and that MRP Group has been linked to Master Data (MRP 3)
Really appreciate your support in this.
Kind regards,
Ishara -
How do I maintain storage location for Planned Orders in APO
Dear all,
Can you help us in maintaining storage location for planned orders in APO. The storage location from material master need to be updated in product master of APO and the same shall be automatically picked from product master during Supply Network Planning run.
Material master CIF is live.
We have got the following content error in CIF consistency check. How ever this is nt goging to harm any thing, but we would like to maintain in both R/3 and APO.
Error:
Plant and storage location in SAP APO: 2004
Plant and storage location in SAP R/3: 2004 FGPA
Thanks in advance
Ram Mohan Rao KolanupakaInstead of maintaining additional master data, i would rather use CCR user exits to switch off comparison of planned order at storage location level if the APO storage location is blank. This way you would not have to make changes to PPMs everytime a new scale out of the solution happens.
In SE18 check the user exit /SAPAPO/CIF_DELTA3 (interface RELEVANT_FOR_COMPARE_ORDHEAD)
If it is not possible to switch off this comparison then I guess changing master data is the next step. Do explore with a developer though about the first option. -
Where we enter raw material reservation qnty for planned order in monthwise
sir,
as per client requirement in every month raw material reservation quantity fixed for planned order in monthwise.
in sap Where we entere raw material reservation for planned order in month wise nov, dec, jan and whre its show.
is it possible after mrp run.can we check that raw material reserve stock in mmbe for planned order.
pl guide me step by stepDear Prakash,
1) in MMBE, you cannot see Reserved qty against plan order ( it is not a confirmed receipt )
2) the reserved qty which is shown in MMBE is against production order
3) only after converting plan order to production order ( Header material )
4) dependent requirements will convert into reservations
Regards
kumar -
Masss Scheduling of Planned Order
Hi
Is there is any transaction for Mass Scheduling of Planned orders preferabaly at plant level.?Dear Mayuresh,
In my understanding there is no T Code to schedule as set of planned orders
This will impact on the other reciepts and only during MRP rescheduling happens.
But also have a check the FM that Mr.Brahmankar has suggested.
Dear Rupesh,
Do u think even if you have an action plan and execute MDAC will it help to schedule the planned
orders?
Regards
Mangalraj.S
Maybe you are looking for
-
Values from a jsp page are null in Action Class
hi, i am working on an application...i have a jsp page with several inputs (type=text) and when a submit the form to to my action class all values received are null. Here is a part of code: the jsp file: letter.jsp <form target="_self" action="/
-
How can we know weather a report is running in background or foreground?
Is there any system variable to find it?
-
Quotes in a page level item not showing up as " when used in a hyper link
Hi all, In my app, I need to hyper link to a crystal report application with parameters from my page. I have a page level item that puts my parameter in quotes, but when the item is utilized in the hyperlink, the quotes come across as & q u o t ; (sp
-
Hi- I'm trying to use the latest Xercies/Xalan classes in OC4J 10.1.3 as described in the How-To swap XML Parsers document: http://www.oracle.com/technology/tech/java/oc4j/1013/how_to/how-to-swapxmlparser/doc/readme.html What I can see happening is t
-
Inserting records in a table after iterating through it
Hi, I have a table like this: Col 1 Col 2 1 rat 2 hen 1 dog 1 cat 3 lion My requirement is to process all the records with unique values in col 1, means I will be inserting these unique records in table A and if the record repeats like for values in