Setting up subcontract PO

I am looking for guidance to be able to set up subcontract PO- Is there detailed documentation available in SAP?
Do I need to set up articles with BOM to be able to set up subcontract PO?
What config requirements do I need to consider?
Need help.
Thanks
Raj

Hi,
Refer following link;
Subcontracting Process
Subcontracting Process
Subcontracting without Payment of Duty
- Creation of Subcontracting PO (ME21N)
To create a subcontract order, proceed as follows:
   1. Enter the material you want to order and the item category for subcontracting (L) in the order item.
      Press Enter to display the screen for component processing.
   2. Enter the components that the vendor requires to manufacture the ordered material (end product). Note the following:
         1. You do not need to enter the date required for the components. This date is proposed by the system when you press Enter. It is calculated as follows:
                      o Delivery date of the item minus planned delivery time
         2. If you do not want the quantity of the components to be changed if the order quantity of the end product is altered, set the indicator Fixed quantity.
         3. If you want to assign a particular batch of the component to the vendor for the manufacture of the ordered material, enter the desired batch.
         4. You can determine whether the components are available on the date required by selecting Component List
            ® Component Availability. If you entered a bill of material as the material in the subcontract order, the components are created automatically.
   3. If you want to determine the components in the bill of material at a later date (for example, if the bill of material is subsequently changed), choose Item ® Goto ® Components ® New BOM explosion. The existing components are deleted and redetermined in the bill of material.
   4. Save the purchase order.
When you print the purchase order, the components are printed per order item.
- Transfer Posting of Components to Subcontractor (Mvmt Type - 541) (MB1B/ME2O/MIGO)
1. From the Inventory Management menu, choose Goods movement ® Transfer posting.
2. Enter the issuing plant and storage location. Choose Movement type ® Transfer posting ® Stck w. subcontract. ® From unrestricted. Enter the vendor and then choose Transfer posting ® Create with reference ® To purchase order.
A dialog box appears in which you can enter up to 4 purchase orders.
3. Choose Continue.
The collective entry screen appears. The vendor and the components contained in the purchase orders entered are automatically proposed by the system.
4. Edit and adopt (copy) the desired items.
5. Post the document.
- Creation of Subcontracting Challan w.r.t. Transfer Posting Doc (J1IF01)
- Goods Receipt w.r.t. Subcontracting PO and Refer Subcontracting Challan at the time of GR (MIGO) {GR with 101 and auto consumption of components with 543 movement}
When the vendor delivers the ordered material (the end product), you post a goods receipt for the subcontract order in the same way as for a standard purchase order. The system determines the components for each order item and creates a goods issue item for each component. As a result, the material document consists of the following items:
Goods receipt items for the materials supplied by the vendor
Goods issue items for the components
After you have copied an order item, you can change the quantities in the goods issue items.
Valuation: - The goods receipt is valuated at the subcontract price plus the value of the components consumed.
Note: - If by-products are planned in the purchase order as components with negative quantities, receipt of the by-products is automatically posted to the stock of material provided to vendor at goods receipt.
- Reconciliation of Subcontracting Challan (J1IFQ)
- Completion of Subcontracting Challan (J1IF13)
- Generation of Annexure IV (J1IFR)
- LIV for Subcontracting PO (MIRO)
Subcontracting under Full Payment of Duty
- Creation of Subcontracting PO (ME21N)
- Transfer Posting of Components to Subcontractor (MB1B/ME2O/MIGO)
- Creation of Excise Invoice w.r.t. Transfer Posting Document (J1IS)
- Capture Excise Invoice at the time of GR of Finished Goods w.r.t. Subcontracting PO (MIGO)
- Post Excise Invoice (J1IEX)
- LIV for Subcontracting PO (MIRO)
Master Data
- MM01- Material Masters for Components and FG
- XK01 - Vendor Master (Subcontractor)
- CS01 - BOM for FG
- ME11 - Purchase Inforecord for Subcontracting
Note: - Excise Transactions need to be performed only if it is applicable.

Similar Messages

  • Subcontracting with full payment of excise duty

    Hello friends,
    Can u plz give the complete configuration details for setting up Subcontracting with full payment of excise duty, Cenvat, Edcess.
    Purushotham

    Hi,
    Process Flow for Sub contracting with Excise duty
    1)The purchasing clerk creates a subcontract order for the subcontractor’s srvices.
    2)The warehouseman creates a transfer posting for the materials that you want to send to the subcontractor.
    3)The excise clerk creates an outgoing excise invoice for the materials.
    4)You send the materials to the subcontractor, together with the excise invoice.
    5)The subcontractor processes the materials and returns them to you, together with another excise invoice.
    6)The excise clerk captures the subcontractor’s excise invoice, using the purchase order as the reference document.
    7)The warehouseman enters the goods receipt.
    8)The excise supervisor posts excise invoice.
    The accounts payable clerk posts the subcontractor’s invoice.
    For this one only u require Account dtermination for ETT for OTHER in Logistic general-Tax on goods movement-India-Account determianation.
    Raghu

  • SUBCONTRACTING SCENERIO ISSUE

    HI,
    TO ALL EXPERTS,
                              This is Manish.I am here with one subcontracting scenerio issue which as follw explain -
    1)I have a material which is set for subcontracting.It have its own bom which includes raw material.
    2)Suppose price of that semifin. Material is10 /- & ration with raw matrl. Is 3:2 I.e
    3 kg of raw = 2kg finish & remain 1kg. is scrap.
    3)So I made a BOM in which I maintained 3 kg raw & 1kg scrap (in minus I.e -1 kg.)
    4)now I made P.O of semifin. Material in Kg. for jobwork to for XYZ vendor (I.e raw material will issue in kg & also return material I.e semif. Material is also in kg.)suppose raw I sending to vendor is of 200 kg. Means semifin. Will of 133.33kg & remain 66.67 kg. Will scrap.
    5)It means if I will send 200 kg raw then it will returns as 133.33kg of semifinsh.
    6)Then I made transfer posting to vendor by mb1b in which I send 200 kg of raw & create a challan.
    7)Note : the material both at while sending & receiving it weighted on weighing bridge,as it contains small diff. In weight.(because even u purchase the ms plate12 mm for a weight of 706kg. Standard,U will never get as exact as 706 kg.,there will some diff. in weight may it will be more or less)
    8)Then I got the material from vendor after some days as semifin. Material with bill.
    9)But as I told earlier u will never get exact material as expect. i.e if send 200kg u will never get 133.33 kg semifin. There will be some difference of 5-10kg.
    10) Suppose I received semifin. @ 125 kg instead of 133.33 kg as mentioned in bill.
    11) So when I will take G.R it will deficit by 8.33 kg.
    12)Now if I reconcile the challan it will give status as u201Cassignedu201D I.e partial reconcile means it shows there will 8.33kg. Of material still at vendor side,whereas practically it is completely delivered by vendor to us.
    13)The scrap generated in material will at vendor, he will sale it & we will include the rate of it in the material price.
    So finally as with reference with above scenario, is there is any chance to correct the system?
    As I know if u want to make it complete u will have to take separate GR. of scrap &/or to to take GR of semi matrl. As complete receive even if there is diff in weight.
    So is there any tolerances or process so we can put & make challan as complete reconcile?
    Please suggest appropriate solution.
    Thanks in advance,
    Manish.

    Dear,
    At the time of MIGO
    ur refering the s/c challan right ?
    at that time u r giving receiving qty say X for that consumption of raw material is Y which is as per BOM ok.
    now u find that instead of Y consumption is somthing (Y+1KG)
    fine
    now what u have to do ,
    for consumption line item in GR (which posts the 543 movt type) overwright the amount from Y to (Y+1KG).
    hope this will help u to understand the scanario.
    regards,
    Sujit

  • Subcontract process PO via delivery via shipment

    Hi,
    Can anyone let me know; issue the material to Subcontract Vendor PO through delivery via shipment?
    Present Scenario is,
    Create the subcontracting PO (PO with Item Category L)
    Issue the material with reference PO through MB1B transport positing using Mov.type 541.
    Goods receipt with reference PO by subcontractor MIGO-Good Receipt and using Mov.type-101
    MIRO to account for vendor's invoice for payment
    Create New separate PO for Transportation of difference Vendor
    Do the service entry through ML81N
    MIRO to account for Transporter vendor's invoice for payment
    Is it possible to Sub contract PO through issue the material via Delivery via shipment?
    Please advice.
    Regards,
    Devendra

    It is possible to provide the component to the vendor for existing purchase order through a delivery and shipment.
    See below SAP documentation: http://help.sap.com/erp2005_ehp_07/helpdata/en/4d/2b906243ad11d189410000e829fbbd/content.htm
    From the SC Stock Monitoring for Vendor list, you can also create a delivery via Shipping. The advantage of this procedure is that you have shipping documents and delivery notes for the shipment of the materials to be provided to the subcontractor
    To create a delivery, the following data has to be maintained in the system:
    the plant must be assigned a sales organization, a distribution channel, and a division. You can define this in Customizing for Purchasing, in the step Set Up Stock Transport Order.
    A delivery type has to be defined for the plant from which the items are to be delivered. You can define this in Customizing for Purchasing, in the step Set Up Subcontract Order.
    If you want to reference a reservation when you create a delivery, you also have to set the Predecessor necessary indicator to L (Provision to subcontractor necessary) when defining the delivery type. This means that the requirements generated by the reservations can be correctly offset against the deliveries created. You can define this in Customizing for Shipping, in the step Define Delivery Types.
    The vendor for the stock with subcontractor must be entered as the customer in the organizational units in the delivering plant, such as sales organization, distribution channel, and division.
    The material to be provided has to be entered for the organizational units in the delivering plant, such as sales organization, distribution channel, and division.
    The combination of shipping condition (from the subcontractor’s customer master record), loading group (from the material master record for the components to be provided), and the plant have to be assigned to a shipping point. You can define this in Customizing for Shipping, in the step Assign Shipping Points.
    To create a delivery, choose Edit → Create delivery. A dialog box appears, in which you can enter the data required to post the delivery. The system posts the delivery in the background and, after posting, it informs you in a dialog box how many items were posted.

  • Shipping point for OBD in ME2O for subcontracting PO

    Hi all,
    While creating delivery for subcontracting PO in ME2O ,getting error message " Essential transfer parameters are missing ".
    And for this shipping point it not there,not able to maintain it manually also since it is gray.
    Please advice what is the conditions for automatically picking the shipping point in ME2O - outbound delivery and even after maintainance what may be the reason for not picking automatically in OBD.
    Note :In my case shipping point assigned to plant and shipping condition maintained for that.
    Thanks
    Regards,
    Dhina.

    Hi
      Have u maintained delivery type LB for plant , IN SPRO-PO-SET UP Subcontract Order
    Thanks
    Saurava

  • Individual purchase order with subcontracting material

    Hi all,
    I've implemented a individual purchase order in a sale order by means of 'TAB' category item. The material has been set as 'subcontracting'.
    When I create the sale order, a purchase requisition is automatically created with M imputation and special stock 'E'.
    Once I create, the purchase order with reference to purchase requisition, I set 'L' category item. Then I save the purchase order.
    In order to simplify the flowchart, the vendor has enough stock to manufacture the required material.
    Then, Tx. MIGO, stock input with reference to purchase order.
    For the FERT material --> movement 101 E + is set.
    For the component --> movement 121 E - is set.
    How can I obtain 121 'O' - movement for components in order to decrease SC vendor stock?
    Thank you very much in advance for your support.
    Best regards,
    Alberto Ramos.

    Dear Charlie,
    Thank you very much for your response. As you comment, I made a mistake with the number of movement. Certainly the movement for raw material consumption is 543.
    I have executed the flowchart you describe. In your case, an independent subcontracting purchase order is done. This flowchart works correctly (with the results you comment. Actually the raw consumption are related to mov. 543 O -).
    The problem is when purchse order is related to a sales order. That is:
    1. Sale order TA with only one position material A. Category item 'TAB'.
    2. Material master for material A --> MRP 2 view --> Special procurement field: 30 - Subcontracting
    3. An automatic purchase requisition is created (thanks to 'TAB' category item, schedule line, ...)
    4. Tx. ME21N --> I create a purchase order with reference purchase requisition:
        4.1. Account assignment category field is set to 'M' from sales order / purchse requisition
        4.2. I manually set Item category field to 'L' for indicating subcontracting (I don't force this to be 'L' from sales order / purchase requisition because I need to use the same flowchart for subcontracting and not subcontracting materials)
    5. Tx. MIGO
        5.1. For Fert material the system executes mov. 101 E +  (as in your description)
        5.2. For raw materials the system exectures mov. 543 E - ( instead of 543 O -). I would like to obtain the reduction of subcontracting stock, because this material is in my center but povided to SC manufacturer.
    Should I do a 'Subsequent adjustment' by means of Tx. MIGO the movement are:
      - FERT material 121 E - (depending on adjustment)
      - Raw materials 543 E - (again 'E' instead of 'O' which is the result I would like to obtain).
    I will very much appreciate your comments.
    Thank you again,

  • Delivery for Subcontracting Orders - SC

    Hi,
    I have create a subcontracting PO.
    I would like to ask which should be the proper way of creating the outbound delivery?
    I've seen that in a ME2O there is a button to make the post Good Issue and another to create the delivery, but as the transaction is called "Stock Monitor for Vendor" I believe it must be another place to create the delivery.
    Nevertheless, when I try to create the delivery I'm getting the message: "Essential transfer parameters are missing in record:  000001"
    Thanks

    Hi,
    To create a delivery (against Subcontracting PO), the following data has to be maintained in the system:
    1. The plant must be assigned a sales organization, a distribution channel, and a division. You can define this in Customizing for Purchasing, in the step Set Up Stock Transport Order.
    2. A delivery type has to be defined for the plant from which the items are to be delivered. You can define this in Customizing for Purchasing, in the step Set Up Subcontract Order.
    3. If you want to reference a reservation when you create a delivery, you also have to set the Predecessor necessary indicator to L (Provision to subcontractor necessary) when defining the delivery type. This means that the requirements generated by the reservations can be correctly offset against the deliveries created. You can define this in Customizing for Shipping, in the step Define Delivery Types.
    4. The vendor for the stock with subcontractor must be entered as the customer in the organizational units in the delivering plant, such as sales organization, distribution channel, and division.
    5. The material to be provided has to be entered for the organizational units in the delivering plant, such as sales organization, distribution channel, and division.
    6. The combination of shipping condition (from the subcontractoru2019s customer master record), loading group (from the material master record for the components to be provided), and the plant have to be assigned to a shipping point. You can define this in Customizing for Shipping, in the step Assign Shipping Points.
    To create a delivery (in ME2O), choose Edit ® Create delivery. A dialog box appears, in which you can enter the data required to post the delivery. The system posts the delivery in the background and, after posting, it informs you in a dialog box how many items were posted.

  • Error: subcontracting challan - J1IF01 / J1IF

    Dear SAP Gurus,
    While creating subcontracting challan through tcode: (J1IF01), i am getting following error.
    "Error Msg: 8I802: Please specify the number of line items for the challans". for which I have maintained the following setting in subcontracting attributes
    "57FC-57FC CHALLAN-180-0001-0002-999-01-Assessable value Table First then Excise Invoice-J1IF"
    Also I tried the Solution suggested in the forum, using Tcode: J1IF - its giving following error msg as
    *"Error Msg: 8I402:Excise modvat accounts not defined for 57FC transaction and excise group". *
    But I have defined the modVAT account for the combination of excise group, ETT-57FC and G/l Account in path Specify G/L a/c for excise transaction
    Kindly suggest the solution.....
    Regards,
    Prashanth Pai

    Hi
    57CM     57F CHALLAN COMPLETION
    57FC     57F CHALLAN CAPTURE/CHANGE
    57NR     57F NON RECEIPT
    ARE1     EXPORT PROCESSING UNDER ARE1
    ARE3     DEEMED EXPORTS UNDER ARE3
    CAGI     CAPITAL GOODS ISSUES
    CAPE     CAPITAL GOODS
    CEIV     CANCELLATION OF EXCISE INVOICE
    DIEX     DIFFERENTIAL EXCISE THROUGH JV
    DLFC     GOODS REMOVAL THROUGH SALES
    EWPO     EXCISE INVOICE WITHOUT PO
    GRPO     EXCISE INVOICE FOR GOODS RECEIPT/PO
    MRDY     REVERSAL WITHOUT REFERENCE
    MRRD     REVERSAL INCASE OF COMSUMPTION OTHER THAN PRODUCTI
    MRWO     CENVAT REVERSALS FOR WRITE OFF
    OTHR     EXCISE INVOICE FOR OTHER MOVEMENTS
    TR6C     PLA ACCOUNT ADJUSTMENT THROUGH
    UTLZ     FORTNIGHTLY PAYMENTS
    Also maintain the accounts against the subtransaction types.What I see in your case is that you have not maintained the subtransaction type 01 against your suncontracting attributes
    Regards
    Sandeep

  • Subcontracting days limit 180 days

    Dear all ,
    where we can see the setting for Subcontracting Challan material expiry is for 180 Days in Spro ?
    Pl guide

    Hi,
    IMG =>Log general=>Tax on goods movement=>India=>Business transactions=>Subcontracting=>Subcontracting attibutes.
    In here for each excise groups you can maintain the subcontrecting challan periods (180 days), along with other required details.
    BR

  • Subcontracting in MTO scenario.

    Hi,
    We have an MTO sales order against which we are raising a subcontracting PO. At the time of goods receipt, movement type 101 'E' and 543 'O' has triggered. 3 controlling entries have taken place:-
    1. Cost for Goods issue to subcontractor is debited to PSG. (543 'O')
    2. Credit for goods receipt from subcontractor is credited to SDI.  (101 'E')
    3. Service charge for subcontractor is debited to SDI.
    The above entry has happened only once and is leading to excess credit on the sales order.
    When we replicated the case in test environment, we found that all the costs have gone to PSG (as per OKB9). The movement types are the same as before.
    We replicated a case where we triggered 543 'E' instead of 'O' and the costs are still going to PSG for all the entries. This was done by changing the 'individual/collective' indicator in material master. I believe this is the recommended SAP setting for subcontracting in MTO scenario as per following link.
    Subcontracting for Sales Order Stock and Project Stock - Managing Special Stocks (MM-IM) - SAP Library
    Can anyone explain when does system overrule OKB9 and take sales order as cost object?
    What can be the probable reason that system is behaving differently for only one occassion?
    Is there any other indicator in material master that I should look for?
    Can I look at OMJJ for possible causes?
    I know this has been asked several times on the forums before but I have not been able to explain above situation. So thanks in advance.

    OKB9 is only functional in the case where a "cost object" has not been assigned to a P&L transactions. That's why it is called "Default Account assignment". In the Case of your MTO, the sales order is really considered as the cost object and hence would take precedence over other default...once a cost object is determined, any further assignment of a cost collecting object becomes statistical depending on the type of cost objects. Basically cost objects have precedencies: I believe Sales order, internal orders, Cost center, etc in that order. Meaning, when 2 are assigned, the one in the lower order become statistical. In any of these cases, OKB9 takes a back seat. OKB9 only comes to play when the internally generated accounting entries will result in no cost object assignment, then SAP looks to see if you have a reference maintained in OKB9.
    Basically, for your MTO, the sales order (an maybe the cost center, etc assigned the to sales order) becomes the cost holder. OKB9 will not feature.
    OMJJ will help you simulate the goods movement and see how the accounts are derived/cost assigned. If OKB9 features, you will also see it referenced. But I don't think it will, unless your goods movement results in an accounting entries that internally does not reference the sales order, then OKB9 kicks in.

  • Subcontracting between intercompany plants

    Dear Experts,
    Can anybody tells me the configuration required for subcontracting between plants belogs to different company.
    Suppose A Plant sents material for job work to B Plant which, belongs to different company. We have created a vendor code for plant B and send the material thru subcontracting cycle. Now problem coming with Plant B. How Plant B prepares the invoice and stock reduces from Plant B.
    Needs Config setting. Full Points will be given for helping answers.
    Thanks
    GR

    Friend
    Two solution can be thought of as two solutions
    solution 1
    Sucontracting company does not want to track inventory and caputre subcontracting costs incured then follow the following
    Maintian vendor master linking to customer master ( subcontrancting comapny vendor and customer)
    Vendor for expensing subcontracting charges, customer master if you want to follow SD delivery
    Detail configuration is as mentioned below
    1. SPRO -Materials Management -Purchasing -Purchase Order - Set up Subcontract Order
    In the grid enter Supply plant code from where Input materials to subcontractor have to be delivered) and the Delivery type "LB" which is SAP Standard Subcontract delivery type
    2. Shipping point definition
    Spro - Enterprise structure - Definition - Logistics executin - Define copy,delete, check shipping point
    3. You should have set the shipping point for that plant which is done in
    Spro -Enterprise structure - Assignment - logistics execution - Assign shipping point to plant
    Check the following setting are also done
    4. Shipping point determination
    SPRO-Logistics Execution - Shipping -Basic shipping functions -Shipping points and Goods receiving points determination - Assign shipping points
    5. Delivery type definition
    SPRO - Logistics Execution -Shipping- Deliveries - Define Delivery types
    Last but not the least
    6. Material master should have sales1, sales2 and sales/plant view extened with necessary data like loading group, transportation group etc
    7. Customer master should have been set for respective company code and sales organisation
    Solution 2
    Create Cross company STO. Create Production order in the Subcontracting company (its plant) and capture material consumption and caputre overhead costs. Create additional STO to send finished material back.
    ENJOY SAP
    Regards
    Edited by: Gopal SP on Apr 2, 2008 12:39 PM

  • Subcontracting ,Plants

    Hi all
    please give subcontracing process between two plant having excise registration & input & output material ia aslo exciable
    whta will be the configuration steps
    & what will be the steps
    thanks

    Hi Sachin,
    Maintain Vendor Master linking to Customer Master ( Subcontracting company vendor and customer)
    Vendor for expensing subcontracting charges, customer master if you want to follow SD delivery
    Detail configuration is as mentioned below
    1. SPRO -Materials Management -Purchasing -Purchase Order - Set up Subcontract Order
    In the grid enter Supply plant code from where Input materials to subcontractor have to be delivered) and the Delivery type "LB" which is SAP Standard Subcontract delivery type
    2. Shipping point definition
    Spro - Enterprise structure - Definition - Logistics execution - Define copy,delete, check shipping point
    3. You should have set the shipping point for that plant which is done in
    Spro -Enterprise structure - Assignment - logistics execution - Assign shipping point to plant
    Check the following setting are also done
    4. Shipping point determination
    SPRO-Logistics Execution - Shipping -Basic shipping functions -Shipping points and Goods receiving points determination - Assign shipping points
    5. Delivery type definition
    SPRO - Logistics Execution -Shipping- Deliveries - Define Delivery types
    6. Material master should have sales1, sales2 and sales/plant view extended with necessary data like             loading group, transportation group etc
    7. Customer master should have been set for respective company code and sales organization
    Solution 2
    Create Cross company STO. Create Production order in the Subcontracting company (its plant) and capture material consumption and caputre overhead costs. Create additional STO to send finished material back.
    Regards,
    Nani.

  • Error while creating delivery using ME2O

    Hi ,
    We are using ME2O to creat delivery for subcontracting . But I click on "Create delivery" button there is an error message coming.
    The error is as following:
    Global official numbering: Input parameter incomplete
    Message no. ICC_NUMBERING770
    If anyone has any solution for it could you please let me know.
    Thanks in advance.
    Sonali.

    Then make sure you have defined the LB in purchiasng for sub contract order
    Or Goto this document and check that you have did all the config
    External Subcontracting: Configuration Guide
    1     Purpose
    This configuration guide provides the information you need to set up the configuration of this building block manually.
    2     Preparation
    Before you start installing this building block, you must install prerequisite building blocks. For information on the prerequisite building blocks, see the Quick Guide for installing Chemicals (located on the DVD in BBLibraryDocumentationChem_Quick_Guide_EN_US.doc).
    3     Configuration
    3.1     Defining Shipping Data for Plant BP01
    Use
    The purpose of this activity is to maintain the shipping data for the supplying plant. (Shipping of the components)
    Here you maintain the customer number of the receiving plant. This customer number is used in SD shipping processing to identify the goods recipient (ship-to party) if provision has been made in Customizing for a stock transfer to be carried out with an SD delivery
    Procedure
    1.     Access the activity using one of the following navigation options:
    IMG Menu     Materials Management à Purchasing à Purchase Order à Set Up Stock Transport Order à Define Shipping Data for Plants
    Transaction Code     SPRO
    2.     On the Change View “Stock Transport Order”: Overview screen, select the production plant BP01 and choose Details.
    3.     On the Change View “Stock Transport Order”: Details screen, make the following entries:
    Field name     Description     User action and values     Comment
    Plant          BP01     
    Customer no. - plant               
    Sales organization          BP01     
    Distribution channel          03     Intercompany
    Division for intercompany billing          01     Product division 01
    Language key          EN     English
    4.     Save your settings.
    Result
    The shipping data for plant BP01 has been set.
    3.2     Defining Delivery Type for Subcontracting
    Use
    The purpose of this activity is to assign Delivery Type for Subcontracting. For the supply of the input materials to be provided to the vendor (subcontractor) with respect to subcontract purchase orders, you have the option of creating an SD delivery from the list of stocks for a subcontractor.
    In this step, you can specify a delivery type for the delivery of materials to be provided to the subcontractor.
    Procedure
    1.     Access the activity using one of the following navigation options:
    IMG Menu     Materials Management  Purchasing Purchase Order  Set Up Subcontract Order
    Transaction Code     SPRO
    2.     On the Change View “Subcontracting Data: Delivery Type f. Provision of Material” screen choose New Entries (F5) and make the following entries:
    Field name     Description     User action and values     Comment
    Supplying plant          BP01     
    Del. type f. subcon.          LB     SAP Standard
    3.     Save your settings.
    Result
    The delivery type LB has been assigned.
    3.3     Assigning checking rule
    Use
    The purpose of this activity is to assign the checking rule B = SD-Delivery to the MRP-Group 0000. This rule defines the checking procedure to be used for the availability check.
    Procedure
    1.     Access the activity using one of the following navigation options:
    IMG Menu     Production à Material Requirements Planning  à MRP Groups à Carry out overall maintenance of MRP-Groups
    Transaction Code     SPRO
    2.     On the MRP-Group View choose Plant BP01 and MRP-Group 0000.
    3.     On the View choose the Button: Check.rule dep.reqmt screen make the following entries:
    Field name     Description     User action and values     Comment
    Checking rule          B     
    4.     Save your entries.
    Result
    The checking rule B will be used for the availability check for the components during creating the LB-PO.
    3.4     Defining item category determination in deliveries
    Use
    The purpose of this activity is to maintain the item determination for the delivery type LB and the Item category group VERP. (VERB is used in material master CH-4120)
    Procedure
    1.     Access the activity using one of the following navigation options:
    IMG Menu     Logistic execution à Shipping à Deliveries à Define Item Category Determination in Deliveries
    Transaction Code     0184
    2     On the Change View “Delivery item category determination”: Overview screen copy the entry LB/NORM to LB/VERP. (The item category LBN will be found)
    3     Save your settings.
    Result
    For materials with item category groups VERP you can create a delivery.
    3.5     Assigning Picking Locations
    Use
    The purpose of this activity is to assign the picking locations to the combinations of shipping point and storage condition for every plant.
    Procedure
    1.     Access the activity using one of the following navigation options:
    IMG Menu     Logistics Execution à Shipping à Picking  à Determine Picking Location  à Assign Picking Locations
    Transaction Code     SPRO
    2.     On the Picking location determination screen, make the following entries:
    Field name     Description     User action and values     Comment
    ShPt     Shipping Point     BP01     Shipping point BP01
    Plnt     Plant     BP01     
    SC     Shipping Condition     01     
    Sloc     Storage Location     0001     
    3.     Maintain another entry with the following values:
    Field name     Description     User action and values     Comment
    ShPt     Shipping Point     BP01     Shipping point BP01
    Plnt     Plant     BP01     
    SC     Shipping Condition     02     
    Sloc     Storage Location     0002     
    5.     Save your settings.
    Result
    Storage locations have been assigned.
    3.6     Searching Strategy for DL
    Use
    The purpose of this activity is to allocate the search procedure SD0001 to the order type DL.
    Procedure
    1.     Access the activity using one of the following navigation options:
    IMG Menu     Logistic General  Batch Management  Batch Determination and Batch Check  Batch Search Procedure Allocation and Check Activation  Allocate SD-Search Procedure/Activate Check
    Transaction Code     SPRO
    2.     Copy any entry for Sales Org. BP01, Distr. Channel 03 and Division 01.
    3.     Change the Sales Doc.Type to DL and save your entry.
    4.     Choose Save.
    Result
    The search strategy SD0001 has been assigned to the sales DL.
    3.7     Activating Automatic Batch Determination for Delivery Item Categories
    Use
    The purpose of this activity is to allocate the automatic batch determination for appropriate delivery item categories.
    Procedure
    1.     Access the activity using one of the following navigation options:
    IMG Menu     Logistics – General  Batch Management  Batch Determination and Batch Check  Activate Automatic Batch Determination in SD
    Transaction Code     SPRO
    2.     On the Choose Activity screen select Activate Automatic Batch Determination for Delivery Item Cat and choose Choose.
    3.     On the Change View “Automatic Batch Determination for Delivery Item Category” screen, make the following entries:
    ItCa     Description     AutBatchDt
    LBN     "Mat. Provided" Item     X
    4.     Choose Save.
    Result
    The automatic batch determination for delivery item categories has been activated for appropriate item categories.
    4     Master Data
    The following activities describe the master data required for this Building Block. The steps do not describe the transactions in detail but list the relevant transaction and the corresponding master data file. For more details on using the individual transactions refer to the Online Help in the system.
    4.1     Creating Customer C-9000 for Subcontract Vendor (S-9000)
    Procedure
    1.     Access the activity using one of the following navigation options:
    SAP Menu     Logistics  Sales and Distribution  Master Data  Business Partner  Customer  Create  Complete
    Transaction Code     XD01
    2.     Refer to the following file for details of the master data required: SMB15_SD_CUSTOMER_O034_J30_Q15.txt.
    4.2     Creating Info Record CH-6120/S-9000
    Procedure
    1.     Access the activity using one of the following navigation options:
    SAP Menu     Logistics  Materials Management  Purchasing  Master Data  Info Record  Create
    Transaction Code     ME11
    2.     Refer to the following file for details of the master data required: SMB99_ME11_O250_J01_Q15.TXT.
    4.3     Creating Output Condition Record
    Procedure
    1.     Access the activity using one of the following navigation options:
    SAP Menu     Logistics  Sales and Distribution  Master Data  Output  Shipping  Create
    Transaction Code     VV21
    2.     Refer to the following file for details of the master data required: SMB99_VV21_O229_J01_Q15.TXT.
    4.4     Creating Quality Info Record
    Use
    The purpose of this activity is to create the quality Info records for subcontracting.
    Procedure
    1.     Access the activity using one of the following navigation options:
    SAP Menu     Logistics à Quality Management à Quality Planning àLogistics Master Data  à Quality Info Record: Procurement à Create
    Transaction Code     QI01
    2.     Refer to the following file for details of the master data required: SMB18_QI01_O002_Q41_Q15.TXT.
    Result
    The Q-Info record has been created.
    4.5     Change material (add or replace values on Plant data/stor1 - Plant data/stor2.)
    Use
    The purpose of this activity is to add the storage condition to the appropriate material.
    Procedure
    1.     Access the activity using one of the following navigation options:
    SAP Menu     Logistics à Materials Management  Material Master  Material  Change  Immediately
    Transaction Code     MM02
    2.     Refer to the following file for details of the master data required: SMB10_MM02_O011_P02_Q15.TXT.
    Result
    The storage condition has been added to the material master.

  • Sub-contracting P.O

    Hi All,
    We have created sub-contracting P.O and while doing ME2O- create delivery.  We are getting below error msg.
        Depending on the category of the delivery being created, the system needs the following transfer data:
        o   Outbound delivery
            -   Shipping point, Sales organization,Distribution channel
                 Division,Material number,Delivery quantity,Ship-to party
                  Base unit of measure
    Inbound delivery
    Base unit of measure,Conversion factors for converting base and sales units (not for creating/replicating an inbound delivery in a decentralized Warehouse Management system)
    Goods receiving point (shipping point) when a delivery is
        created in decentralized WM
    Outbound and inbound deliveries from goods movements
    Shipping point
          -   Sales organization,Distribution channel,Division,Material number,Delivery quantity,Ship-to party,Base unit of measure
      Plant and sales unit transfer data is always mandatory.
    Please Anybody can tell me what configuration we have to do.
    Thanks and Regards
    Chandru

    You have to set up the shipping details just as you would do for a stock transport order with transfer posting happening through SD route. You have to set the delivery type for this document and the material should have sales/shipping data. Only then will the system be able to pick up the delivery type & thus create a delivery.
    This is given in detail in help.sap.com -
    From SC Stock Monitoring for Vendor as a Delivery via Shipping
    From the SC Stock Monitoring for Vendor list, you can also create a delivery via Shipping. The advantage of this procedure is that you have shipping documents and delivery notes for the shipment of the materials to be provided to the subcontractor (refer to  Goods Movements via Shipping)
    To create a delivery, the following data has to be maintained in the system:
    the plant must be assigned a sales organization, a distribution channel, and a division. You can define this in Customizing for Purchasing, in the step Set Up Stock Transport Order.
    A delivery type has to be defined for the plant from which the items are to be delivered. You can define this in Customizing for Purchasing, in the step Set Up Subcontract Order.
    If you want to reference a reservation when you create a delivery, you also have to set the Predecessor necessary indicator to L (Provision to subcontractor necessary) when defining the delivery type. This means that the requirements generated by the reservations can be correctly offset against the deliveries created. You can define this in Customizing for Shipping, in the step Define Delivery Types.
    The vendor for the stock with subcontractor must be entered as the customer in the organizational units in the delivering plant, such as sales organization, distribution channel, and division.
    The material to be provided has to be entered for the organizational units in the delivering plant, such as sales organization, distribution channel, and division.
    The combination of shipping condition (from the subcontractoru2019s customer master record), loading group (from the material master record for the components to be provided), and the plant have to be assigned to a shipping point. You can define this in Customizing for Shipping, in the step Assign Shipping Points.
    To create a delivery, choose Edit ® Create delivery. A dialog box appears, in which you can enter the data required to post the delivery. The system posts the delivery in the background and, after posting, it informs you in a dialog box how many items were posted.

  • Error in Delivery using ME2O : "essential transfer parameters are missing"

    Hi All
    We have a subcontracting PO for which when trying to create Delivery using ME2O we are getiing error "essential transfer parameters are missing in record 000001". I understand that this error is coming because shpping point is not ap[earing when click on create delivery tab.
    Any pointer in this regrd.
    Would like to inform that we have already connected the Vendor and Customer in respective master. Apart from that
    we have checked that shipping condition, loading group and plant is also set which determines the shipping point.
    Would appreciate usefule pointer as this is very urgent.
    Rgrds
    Yogesh

    Hi,
    Check following;
    OVX6 - Assign sales organization - distribution channel - plant
    SPRO > MM > Purchasing > Purchase Order > Set Up Subcontract Order > Here assign Delivery Type "LB" to Plant
    SPRO > MM > Purchasing > Purchase Order > Set Up Stock Transport Order > Define Shipping Data for Plants > Here assign the Customer Code of Plant and Sales Area to the Plant
    Note: - Customer Code of Plant is to be created in XD01.
    Check whether Material Master is extended to the Sales Area.
    OVL2 - Cross-check Shipping Point Determination

Maybe you are looking for

  • Can I connect a 4 TB USB drive to the airport extreme and use it as a network drive for Time Machine

    Can I connect a 4 TB USB drive to the airport extreme and use it as a network drive for Time Machine

  • Sender JDBC adapter can be Synchronous?

    Hi, can we use sender JDBC adapter as synchronous in JDBC-XI-RFC Scenario without BPM? thank you babu

  • Serious Leopard problems

    Since installing Leopard, I have at least 5 applications that will randomly quit (Safari, Firefox, Excel, Final Draft, iTunes) and weird other problems like freezing on quickbooks. Should I go back to Tiger? How would I even do that? Does anyone else

  • Phantom Frame Appears Between Two Clips

    I am new to FCP. When I play my video in the timeline, a phantom frame from another clip plays between two clips. I don't know if I accidentally placed one of the clips on top of it or something when I was moving clips, but I can't figure out how to

  • Work book transport problem

    Hi Experts, I have transported the work book to the production system and it went perfectly but my problem is now i have to place the work book under particular role but i am not able to find the work book under favourties or any where in analyzer bu