Settlement of planned deliv. costs not possible if GR-related data entered

Hi gurus,
        While doing T-code MRRL if i am entering the GR posting date and ticking the good + delivery check box an error message is trigerd 'Settlement of planned deliv. costs not possible if GR-related data entered'.PLZ reply the reson for this error.

I Have the same problem them I realise  that :
This message just appear if i am using doc. selection = 4 .
tks
Teresinha

Similar Messages

  • Not possible to determine shipping data for material  in PO(STO)

    I
    m doing STO for intra copmany code(plant to plant stock transfer),I have done all STO setting ,maintain material with plant and storage condition,loading groups , maintain customer with storage condition,created vendor with supplying plant.setting is done for supplying plant and receiving plant .
    Supplying and receiving plant combination with document type UB.delivery type NL and checking rule RP.Also maintain sales area for both plant.
    But when I m creating PO in ME21N below error is showing..
    *Not possible to determine shipping data for material ,kindly suggest if I have missed any setting...
    Regards,
    Vipin

    Hi Sharan,
    Thanks for your reply.
    problem got solved but in different way ,STO setting was wrong.
    I didn't maintain delivery document type(NL) on plant level  It was maintain at storage location that's why system couldn't determine shipping info for material.
    Please check the setting below.
    IMG> MM>Purchasing>Purchase order>STO>STO between storage location>set up storage location -dependent shipping point determination>define rule for determination of sipping point>
    here we have to set delivery document type(NL) to plant specific shipping point determination.

  • Not possible to determine shipping data for material in intra company STO

    Hi,
    just trying to set up a STO material movement between two plants belonging to same company code,sto customization is done,i have chosen raw material whose stock got maintained in both plants........when trying to post it gives an error message ....NOT POSSIBLE TO DETERMINE SHIPPING DATA FOR THE MATERIAL...COULD SOME ONE HELP ME...

    SPRO->Material Management->purchasing->scheduling Agreement->Setup Stock transport scheduling Agreement->Define shipping data for plants.
    Select the particular plant and click on details there also you have to maintain the same customer that you have maintained in J1ID.
    Then it will allow to create Stock transport order.
    I did the same thing it was working for me.
    Edited by: Vanitha Krishnamurthy on Jul 27, 2010 12:07 PM

  • TS1292 itunes says my itunes card "has not been properly activated" when i enter the code.  this is not the "invalid" message related to entering the code improperly.

    itunes says my itunes card "has not been properly activated" when i enter the code.  this is not the "invalid" message related to entering the code improperly.

    Are you able to go back to the store that you bought it from and ask them to activate it properly ? If not then you will need to try contacting iTunes Support (you will probably need to give them images of the front and back of the card, and possibly its receipt) : http://www.apple.com/support/itunes/contact/ - click on Contact iTunes Store Support on the right-hand side of the page, then iTunes Cards And Codes

  • Planned delivery cost not updating Through Invoic02 idoc

    Hi,
    We are using Inbound IDOC (INVOIC02) to create invoice. The enhancement that we are looking to do is to use the indicator Goods/Service items + planned delivery costs which is seen when we manually post invoices using MIRO. Can you please let us know of any inputs in this regard.
    For your information - the current functional module we are using to post invoices received through EDI is IDOC_INPUT_INVOIC_MRM and the message type is INVOIC. But this does not seem to help us in case of goods which has got a planned freight attached to it.
    Thanks
    Shasi

    Hi Experts ,
    Kaindly provide me your inputs ..
    Thanks
    Shasi

  • Is it possible to integrate relational data with OLAP cubes?

    I have a web application that accesses cubes created from AWM via the OLAP API. I need to integrate a column from a relational table in the front application and display the column along side cube data.
    Is there any way to achieve the functionality from the OLAP API?

    Can you explain how the relational data source relates to the OLAP data, is it a master-detail relationship? If this is the case then you could consider the following:
    1) Depending on how you are displaying the OLAP data. If you are using a non-BI Beans presentation bean then if the keys are consistent across both data sources it should be possible to create two separate queries and glue them together using the common keys within your data source module.
    2) Alternatively, you create a custom text measure within AWM and then use OLAP DML to extract the detail data and load it into a multi-line text variable that could be retrieved via OLAPI. This might not work if there is a large number of rows within the text variable to retrieve as formatting the results within your application might get complicated. The OLAP DML Help contains a lot of excellent examples that will help you create a program that uses SQL commands to load data.
    Hope this helps
    Keith Laker
    Oracle EMEA Consulting
    BI Blog: http://oraclebi.blogspot.com/
    DM Blog: http://oracledmt.blogspot.com/
    BI on Oracle: http://www.oracle.com/bi/
    BI on OTN: http://www.oracle.com/technology/products/bi/
    BI Samples: http://www.oracle.com/technology/products/bi/samples/

  • Change in  item category  and  settlement of  old sales order not possible

    Hi
    I   have to settle   sales orders  in VA88 and  transfer data to COPA.   I  want to do   directly  without  result  analysis. So, in the  item category, I  removed the result analysis key.   And  the  settlement  goes thru.
    My issue is that  there are  orders in  July 2010  which  have to be settled,  but  it  does not work since the  changes in  item category has  happened  this month in Aug 2010 and  the  July  sales order are also  invoiced.
    Pl  suggest a  solution  to  settle  the  July  sales order  to COPA.
    Thanks
    kamala

    Hi Kamala
    I see only one possibility... The old sales order consists of some GL accounts posted in it which is not mapped in the allocation structure...
    Alloc Str has 2 parts - i.e. One, it consists of a group of cost elements it has to handle and Two, it consists of the valid settlement receivers like PSG, CTR, etc
    You say, this alloc str works well with new sales orders.... The 2nd part of alloc structure (i.e. valid receivers) applies equally to all sales orders.. But what can really differentiate the 2 sales orders is the cost elements posted on it...
    I dont foresee any other posslbe reason
    Regards
    Ajay M

  • COPA - Planned Material Cost not appearing in KE30 report

    Hi all
      In COPA planning, I manually planned the Material cost (Material External Price) along with the Sales Quantity and Revenue for two company codes (one plant in each co code). But in KE30 report, I could see the material cost (MEP) values only for one company codeplant. What could be the issue?
      I even tried valuation in KEPM. Valuation step is calculating and populating the material cost in KEPM, but the values are not flowing to KE30 reports. And this happens to only one of the two company codes.
    Thanks
    Vamsi

    Hi Vamsi
    Please check table CE2XXXX, where XXXX = Op Concern.... Here, can you see the plan line items??
    If yes, then the issue is with your report definition in KE30... May be you are restricting values display in KE30 report by virtue of your selection parameters
    br, Ajay M

  • Planned material costs not seen in reports

    hi to all,
    i planned costs for a project using networks and activity elements and material components.  for the activity elements i placed the costs as a direct input and for material components, i input the required quantity and the material number. However, when i looked at the structure overview(CN41), the materials i placed have 0 cost. YET THE TOTATL AMOUNT in the network&activity INCLUDES the cost of the material (quantity multiplied by material price).
    Thanks in advance

    hi again..
    i checked both your suggestions but they have already been carried out earlier so the problem lies elswhere..(but at least i was able to eliminate some of the possible causes..).
    allow me to give an example of whats happening in my case..
    MY INPUTS:
    WBS 1
    NETWORK 1
      ACTIVITY 1
         Material Component 1     3 pcs  ( 1 $/pc)
         Material Component 2    10 pcs   (1 $/pc)
         Element 1(cost)             500 $
         Element 2(cost)             300 $
    OUTPUT REPORT:(CN41 - Project cost Sch 000)
    WBS 1                                  $ 813.0000
    NETWORK 1                        $ 813.0000
      ACTIVITY 1                          $ 813.0000
         Material Component 1           0.0000
         Material Component 2           0.0000
         Element 1(cost)                    500.0000
         Element 2(cost)                    300.0000
    So if you notice in the report the material is 0 but the total includes the material cost..
    thanks!

  • Error: "Not possible to determine shipping data for material" in STO

    Gurus,
    I have maintained the shipping point determination properly, still I get above error while creating ME21N.
    What could be the possible reason?
    Regards
    Trupti

    Hi,
    On top of the Shipping Determination configuration done, pls check the following: -
    1. Go to path IMG --> MM --> Purchasing --> Purchase Order --> Set up Stock Transport Order --> Define Shipping Data for Plant --> Assign a Customer no.-Plant for the respective Plant. This number is created in Sales Customer Master.
    2. Go to path IMG --> MM --> Purchasing --> Purchase Order --> Set up Stock Transport Order --> Assign Delivery Type and Checking Rule --> Make sure your PO Type is assigned to relevant Delivery Type.
    This should fix the problem.
    Thanks.
    Rgds.

  • Planned Delivery Costs Posting in MRRL

    Hello Experts,
    We have ERS active in our system for regular consumprion items. These are the items where the price settled is inclusive of packing anf forwarding charges. There is no issue of LIV for these invoices.
    But when in a Purchase order any other charges are loaded such as Packing, Forwarding etc. these charges fall under planned delivery costs in terms of LIV. And these charges are not captured at the time of LIV through ERS.
    Does anybody aware of any userexit or SAP note which will help me capturing these charges in ERS as well.
    Early response will be appreciated as I want to transfer all plant purchases' invpoice verification on ERS.
    Thnaks & Regards,
    Rahul Puranik.

    As per SAP Standard system, it is not possible to post the planned deliver cost thro' ERS or by MRRL.

  • Condition types related to planned delivery costs (Freight) from a PO.

    Hi Friends,
    I want to know which condition type is related to Freight in a purchase order.
    I have a PO which has different conditions like PBXX, FRB1, FRC1, etc. under the conditions tab. I want to get only freight related conditions through a bapi.
    SAP provides this functionality in MIRO/MIR7. When you enter a PO # and hit enter in MIR7, you will be displayed corresponding freight line items if you have selected "Goods/Service Items + planned deliver costs".
    Thank You,
    Hardik Shah.
    Edited by: Hardik Shah on Apr 2, 2010 5:49 PM

    There is no direct way to determine if a condition type is related to freight or not. Normally, the condition category for such condition types is "B-deilvery costs", but there can be others as well.
    I guess, you can hard code the condition types in your development, since the schema will not be changed frequently.
    Regards,
    Aroop

  • ERS for Return Items with Planned Delivery Costs also as credit

    Hi
    I have the requirement to process ERS-Returns (MRRL) where I need to have a credit memo for the product cost and the planned delivery costs incurred with the original order. ($15,000 for product and $1200 for delivery costs = Credit Memo for $16,200)  I have tested this extensively but in all situations the planned delivery costs creates an 'invoice' not a credit memo.  
    Has anybody encountered this requirement?  If so, were you able to resolve without implementing an enhancement?
    Thanks.

    For delivery costs you need to maintain the following customizing:
      > OLMR
        > Evaluated Receipt Settlement (ERS)
          > Specify Automatic Settlement of Planned Delivery Costs
    The flag controls whether to include or exclude planned delivery costs
    from automatic settlement.
    Regarding the planned delivery cost, it will not listed in
    transaction MRRL. This is the standard SAP design. Instead, please
    use transaction MRDC.

  • Problem with MIRO Transaction while posting Un planned Delivery cost

    Hi all,
    We have entered all the details including unplanned delivery cost in transaction MIRO. When we are trying to post the same by using post button directly with out simulation, system is asking for plant details.
    For first time we have entered wrong Plant details , system immediately asking again for plant details.
    Next time even if we entered correct plant details, the system is coming out from the screen MIRO and it is not posting the document.
    If you go through simulate button and it is working fine and it is giving Warning message, If we enter the wrong Plant details.
    My Client requirement is If we post the MIRO transaction including Un planned delivery cost with Post button. If we enter wrong plant details. System will through Error message, until we enter the correct plant details.
    Is there any way to do this. Pl help me in this regard.
    Regards,
    Ramesh

    In the MIRO T Code, U can see PO reference tab is there, Just below it there is Purchase order/scheduling agreement field is there . enter the purchase order number in blank field next to Purchase order/scheduling agreement and press enter. U can see it will  take the required data automatically.
    hope this helps
    regards

  • Planned Delivery Cost - MRDC

    Hi,
    I am trying to settle planned delivery cost maintained in PO through condition type - FRB1.
    Also maintained tcode details in table t169f.
    Did configuration in node - MM - LIV - ERS - maintained required details for the vendor
    I did GR against the PO.
    Now I am executing MRDC, nothing happens?
    Did I miss any step?
    Please revert.
    Regards,
    Dipak

    Hi
    check this
    add your freight vendor to configuration transaction: Materials Management > Logistics Invoice Verification > ERS > Specify Automatic Settlement for Planned Delivery Costs.
    Regards
    Kailas Ugale

Maybe you are looking for

  • SharePoint 2010: Scheduled Web Analytics Reports workflow is not sending ANY email

    Hello, I've a SharePoint 2010 Enterprise farm. I setup a Scheduled Web Analytics Reports workflow in a site collection with different web analytics reports options checked. So far I've not got ANY email. When I went to Site Workflows, I'm seeing that

  • Issue with archiving in file sender channel

    Hi Experts, We have configured a file to  ABAP proxy scenario in our production PI  7.0 system. the  file sender  communication  channel  is configured to perform " file content conversion"    and archive the  source file  after it is processed succe

  • Why can't I receive and download my app from Testflight/iTunes connect?

    This problem just started during the switch from Test Flight to iTunes connect last week. I've been receiving the email invite but when I go to download the app TestFlight says: "You aren't currently testing any apps. To accept an invitation, you mus

  • Can't use an IBM PS/2 UltraNav Travel Keyboard with Lenovo Dock?

    For my Lenovo Advanced Dock, I bought an IBM UltraNav Travel Keyboard with PS/2 connectors; I figured it might be better-buklt than the 31P9490 Lenovo version, which uses USB. I guess I hadn't thought it through, for the IBM keyboard requires two PS/

  • ABAP query transport issue

    Hi,    I have copied an abap query ZGA to ZGA_IND1 and changed the title to INDIA.  I gave transport number and released and transported to Quality. A transaction has been assigned to this Query   But when I execute this query from Quality machine us