SUB CONTRACTING PO FOR MATERIAL HAVING ALTERNATE BOM

Hi,
we are having following scenario for subcontracting process.
FIN1 material can be produced either from RAW1 or RAW2.
In PO for FIN1, in BOM assignment , BOM for FIN1 with RAW2 as sub component  is  assigned. But when thay want to make FIN1 from RAW1, system allows to issue RAW1 to subcontractor as it is maintained as subcomponent in alternate BOM of FIN1(not in PO) but while doing GR it gives message of " DEFICIT OF STOCK W. VENDOR UNR. 10 EA : RAW2 1000 O"
I thot that this msg is arrising as component RAW2 is not provided to vendor ( as it is maintained in PO a subcomponent for FIN1). So what I did , I added another item as FIN1 in same PO with sub component as RAW1, and then carried out the process, so it worked. But this makes confussion to user as there are severel items in PO, and to judge against which item he will hav to make GR.
So my question is, is there any setting or scenario in SAP to solve this issue?
Regards

1. You will definitely create two subcontracting info records for two raw materials say RAW1 and RAW2.
2. There will be two seperate production versions for these two materials.
3. Update respective production versions in respective subcontracting info-records.
4. This will help to upload the alternate BOM even you changed the material from PO
Amol

Similar Messages

  • Sub-contracting purchase for by-products

    Hi
    I am doing Sub-Contracting PO for By- Products. I have maintianed in BOM , the by-product material code in "-ive" qty.
    Consider Material A - Main Product
                   Material B - By_Product
                  Material C - Raw Material
    When i do GRN, Material A triggers 101 movement Tpe, Material B triggers 545-0 Moveent Type and Material C triggers 543-0 Movement Type.
    But When i check the stock of material, Material B is lying as Vendor Stock.
    Kindly let me know whether this transaction and movement type updation is correct.
    Else let me know the steps.
    I need to Receive Material A and Material B in my Stock.
    Thanks & Regards
    T.Madhesh Kumar

    HI
    Thanks for u r reply. But i need to receive the material A and material B same time during Goods receipt itself. Is there any possibilities that i can receive both the material in Un-restricted stock during goods receipt.
    Thanks & Regards
    T.Madhesh Kumar

  • Component Allocation LSMW not working for materials having alternative BOMs

    Hi Experts,
    I have a requirement in Component allocation LSMW.
    Component Allocation LSMW was created using a material which do not have an alternative BOM and the LSMW NOT working for materials having alternative BOMs. Currently iam using Batch Input Recording method in LSMW.Can any one suggest me is it possible by recording method in Lsmw. Because in transaction CA02 when we click the CompAlloc button in application tool bar we get a pop up screen with alternative BOM's, we have to choose any of them. If we choose any of the alternatie BOM in the pop up screen then it will be fixed always, but depending upon my flat file value of alternate BOM i need to pick the value. It is not static.
    Can any one suggest me is there any BAPI for this requirement.
    Your hel will be greatly appreciated.
    Thanks & Regards,
    Venkat.

    Use BDC instead of LSMW, that will solve your problem.

  • Sub-contract PO for FERT item

    Hi,
    We have a finished product (FERT) which is assembled In-house using several items.
    The same finished product is also assembled at vendor's place.
    At present we are going through service PO (MB21N) since we are not able to make a sub-contract PO for a FERT item. In this scenario  how shoud we set the master data (MRP2 Procurement views). Is there any way we can do this?
    Please suggest, its urgent.
    regards
    Shivkumar Kanti.

    Hi
    In Material Master, MRP View 2....for that FERT Product maintain Special Procurement Key: 30....
    so when ever you run MRP.....automatically for that FERT product, Sub contracting PR with Item category " L" will be created....you can Convert this     SC-PR   in to SC-PO  with Item category  "L"
    If you already maintained BOM    for that FERT Product...the components will be automatically exploded in SC-PO, Item Details,Material Data....
    These Component you can send it to SC-Vendor useing T.Code: ME2O.....by 541Movent type...
    After completion of the Assembling, you can get back the FERT product from SC-Vendor in MIGO, useing 101Movement type....that time the components you have provided to vendors  are automatically consumed in   543 O--  movement type....
    If there is any over consumption or under consumption of your components at SC-Vendor....SAP Best practice provides you the option of Subsequent Adjustment....
    Reward if useful
    Regards
    S.Baskaran

  • Refurb sub contract PO one material two line items

    Hi we have the following scenario:
    We have a sub contract (item category L) for a rotable spare.  We create a service PO for the MATERIAL.  When the invoice comes in there are two line items as we charged for materials used to repair the item at one tax rate, and the service to replair the item at another rate.
    How do we goods reciept / SES this to ensure that we only get stock of one coming back in from the vendor but capture two lines in the invoice to ensure that the invoice doesn't block?  So we can't create a two line item PO as the goods reciept would book two into stock.
    Any suggestions?
    Thanks hope this makes sence.
    Other things that might help:
    Single item recursive BOM
    Goods issued to vendor via ME20
    Legal requirement to have two lines as we are paying two rates of tax

    Tracey Durkin wrote:Hi,
      So we can't create a two line item PO as the goods reciept would book two into stock.
    >
    When you have one PO line item for Recursive BOM , and one for service, this will not book two in to stock
    One will be material into stock and other will be service payments, not stock as no material is involved in service
    So you can do recursive BOM for same item , at this item you can capture material used by vendor
    And at the second line with item category "D" you do service entry both can have different tax codes
    Thanks
    Diwakar

  • Deleting and Adding components in a Sub contracting PO, for every line item

    Hi,
    I have requirement where in I need to change the Item category from Blank to 'L' for a given Line item, and for this Line Item I need to go to the Delivery Schedule lines and delete the existing Components and add new components to every Delivery Schedule line. This is going to be a LSMW object with a custom program.
    I tried for recording ME22N, but couldn't do this as ME22N  is not BDC friendly, and in ME22 the Item category field is Display only. I also tried with Function modules/BAPIs but nothing seems to be working out.
    Can anybody help me get a solution to this requirement. Would appreciate a quick response as its a priority requirement for me.
    Thanks in Advance,
    Saleem.
    Ph : +91-9845627631

    1. You will definitely create two subcontracting info records for two raw materials say RAW1 and RAW2.
    2. There will be two seperate production versions for these two materials.
    3. Update respective production versions in respective subcontracting info-records.
    4. This will help to upload the alternate BOM even you changed the material from PO
    Amol

  • Service Contract Determination for material product

    Hello,
    I am trying to implement service contract determination for a complaint and I observe that the service contract gets determined at the complaint item level only when I add a service type product at the item level and not when I add a product of material type. Is this a system limitation that a service contract can be determined only for a service product or am I missing some configuration? Has anyone else faced a similiar issue?
    Thanks,
    Divya.

    hi divya
    the contract get determined even after adding product of type material
    1.create a srv contract (sc)
    2.add product of type material
    3. release the contract and save it (note the no.)
    4.create a trnx complaint(crmc) maintain the setting fr contract determinition(F)
    5.put the product in trnx and ur contract will get determined
    see if it suffice ur requirement
    "reward points if u find useful"

  • T code for material having sales view maintained

    i want list of material having sales view maintained.

    >
    guptasansat wrote:
    > i want list of material having sales view maintained.
    You can try MM03, then in search criteria, you can use Sales material by description, input sales organization, and do search, it should bring up materials with sales organization maintained in sales view.
    Edited by: Afshad Irani on May 29, 2010 3:05 PM

  • Split Valuation For Material Having No Open PO & Stock

    Hi Experts,
    Will somebody throw light on split valuation where there is no any open PR, PO & Stock for that material but system does not allow to make material split valuated.
    System shows error meassge giving old PO nos list.
    (Logically all these POS whole business transcations/cycle is  completed )
    I want split valaution to be done to the material whose stock is nil also there is no any open PR,PO for that plant in the system.
    But I dont prefer to delete line items of the old PO for doing the split valuation.
    Please suggest solution
    Thanks in advance.
    Ramesh
    Edited by: RameshChandra  Soni on May 17, 2008 11:46 AM

    Hi,
    You can find severaé threads about this on this forum.
    Some hints:
    1. In MM02 try to set the split valuation > Save > SAP will give error message > Push the appearing 'Display errors' button > SAP will say what hinders you from being able to set the split valuation.
    2. As I remember stock has to be zero in current and previous period. (You can set your stock to zero in the previous period using MB1A201posting date in the past; after having set split valuation you can reset your stock level via MB1A+202).
    3. IMPORTANT: you have to archive all existing batch records.
    4. etc
    BR
    Csaba

  • Standard cost with material with alternate BOM and Routing

    I have a set up where the same material can be manufactured in 2 different production lines and each production line has two different BOMs and Routings. If I want to have a blended standard cost for the material what are our options?
    We do not want to do split valuation.
    thanks a lot

    Hi
    You can different PCC (Product cost collector) for both lines of the same product (Product cost by period).
    You can define a production process within a product cost collector for each line of production with a combination of BOM and Routing. TCode KKF6n. It would generate a order number for each production process.
    You can use each order within the PCC for each production line to capture the costs for seperate lines.
    Regards,
    Suraj

  • Sub contract migo for excise item

    Hi
    I have prepared the following documents
    1.     Subcontract Purchase order (x is parent item and y is child item)
    2.     Subcontract challan (for child item y)
    In our case supplier added some materials for producing X for that they charged ED
    I prepared migo referring Subcontract challan and subsequently I captured Excise internal Number through J1IEX (referring Migo Number & Enter the Invoice Number)
    While posting Part 2. System displayed the message Part1 is not updated.
    Kindly suggest your valuable feedback.
    Note: Otherwise tell the process of how to handle of subcontract item with excise invoice.
    Regards
    Pons

    Hi,
    Subcontracting Process
    Subcontracting without Payment of Duty
    - Creation of Subcontracting PO (ME21N)
    - Transfer Posting of Components to Subcontractor (Mvmt Type - 541) (MB1B/ME2O/MIGO)
    - Creation of Subcontracting Challan w.r.t. Transfer Posting Doc (J1IF01)
    - Goods Receipt w.r.t. Subcontracting PO and Refer Subcontracting Challan at the time of GR (MIGO) {GR with 101 and autoconsumption of components with 543 movement}
    - Reconciliation of Subcontracting Challan (J1IFQ)
    - Completion of Subcontracting Challan (J1IF13)
    - Generation of Annexure IV (J1IFR)
    Subcontracting under Full Payment of Duty
    - Creation of Subcontracting PO (ME21N)
    - Transfer Posting of Components to Subcontractor (MB1B/ME2O/MIGO)
    - Creation of Excise Invoice w.r.t. Transfer Posting Document (J1IS)
    - Capture Excise Invoice at the time of GR of Finished Goods w.r.t. Subcontracting PO (MIGO)
    - Post Excise Invoice (J1IEX)
    Master Data
    - MM01- Material Masters for Components and FG
    - XK01 - Vendor Master (Subcontractor)
    - CS01 - BOM for FG
    - ME11 - Purchase Inforecord for Subcontracting
    Note: - Excise Transactions need to be performed only if it is applicable.
    Hi,
    Refer link;
    [Subcontracting Process w/o Payment of Excise Duty|http://help.sap.com/bestpractices/BBLibrary/Documentation/J85_BPP_V2_EN_IN.doc]
    Subcontracting Process
    Subcontracting without Payment of Duty
    - Creation of Subcontracting PO (ME21N)
    - Transfer Posting of Components to Subcontractor (Mvmt Type - 541) (MB1B/ME2O/MIGO)
    - Creation of Subcontracting Challan w.r.t. Transfer Posting Doc (J1IF01)
    - Goods Receipt w.r.t. Subcontracting PO and Refer Subcontracting Challan at the time of GR (MIGO) {GR with 101 and autoconsumption of components with 543 movement}
    - Reconciliation of Subcontracting Challan (J1IFQ)
    - Completion of Subcontracting Challan (J1IF13)
    - Generation of Annexure IV (J1IFR)
    Master Data
    - MM01- Material Masters for Components and FG
    - XK01 - Vendor Master (Subcontractor)
    - CS01 - BOM for FG
    - ME11 - Purchase Inforecord for Subcontracting
    Configuration: -
    - SPRO > Logistics - General > Tax on Goods Movements > India > Business Transactions > Subcontracting > Subcontracting Attributes
    Here maintain following;
    Excise Group         XX
    Excise TT            57FC
    Subtransaction Type  01
    Subtran Type Text   57FC CHALLAN
    Subc. Period        180
    Rate-subcontracting
    Mvt Grp Issues      0001
    Mvt Grp Receipt     0002
    Filter Non exise
    EI Items            10
    No. range no.       01
    ***. Val. /Exc Inv
    Subcon Output Type  J1IF
    - SPRO > Logistics - General > Tax on Goods Movements > India > Business Transactions > Subcontracting > Maintain Movement Type Groups
    Here maintain following
    MVT. Grp. MvT S
    0001      101 O
    0001      541 O
    0002      542
    0002      542 O
    0002      543 O
    - J1I9 - maintain No range for object "J_1I57FC" for series group

  • Error message in PR for material having stock above reorder point

    Hi Experts,
                      We want the error message while creating Purchase Requisition (ME51N) for a material which is having stock (MMBE)  above Reorder point ( MRP1 View of material master-MM03) .Is there any user exit available for this requirement.
        MAXIMUM STOCK LEVEL
         With reference to this thread i checked the user exit   MEREQ001 . But this exit will contain include ZXM02U01 Which is showing error message - program names ZX..are reserved for includes of exit function groups .I want to open this include if i want to write the code for the above req.
    Regards,
    RAHUL S

    Hi Rahul,
    you can ignore the message "program names ZX..are reserved ..." - because you are in such a reserved function module. Just create the include, active your coding and activate the exit (transaction CMOD) -> then you have an active implementation of an user-exit.
    BR,
    Christian

  • Report For Sub Contract Material

    Dear Experts,
    Is there any standard report for finding the details of the subcontract.
    I tried through ME2O, MBLB where I am not getting the report I wanted.
    I want to take a montly report for all the subcontract work given to the vendor. (The work is completed )
    Please help. Thanks

    Thanks,
    In ME2L I am able to get the details, but the problem is;
    I want to get a report which will give me the full details of the Sub COntract PO.
    Example. I created a Sub COntract PO for Fineshed Material A. For makng Material A I need to supply Material B, Material C to the Sub Contract Vendor.
    I want to know by the end of the month
    1) The Subcontract PO
    2) Final Material (Material A)
    3) Raw materials Supplied to vendor (Material B & Material C)
    4) Status of the order
    5) Material A given back to me
    6) remaining Material (Material A)
    Please help.

  • Partial Production & Partial Sub contracting for halb material

    Hi,
    we have fert 1000 with halb 2000 and roh 3000. It's MTO Process and for fert i have selected collective indicator 2 and MRP Run with MD50. If halb 2000 stock is available it will be show as stock in md04 screen and if stock is not available we run mrp md03 for halb to genereate planned order. My client wants here to check the capacity availability to produce that halb..if it is available for say qty 1 then partially production order will be created and rest another qty say 1 more will be given to sub contract. In material master i have taken X as procurement type. when i am converting the planned order to purchase requsition i entered the item category as L with out any account assignment. I am not able to take goods receipt for sub contracted material because system is throwing error as account requires and assignment to co object. I also tried using account ssignment M but if do so the received sub contract material is shown against the sales order number stock..so again from there i need to trasfer to unrestriced for using to the header fert production order. I want the halb production order cost and subcontract cost to be accounted to sales order.
    Some one Please help me. Answers will be rewarded.
    John

    Hi,
    I believe your solution may be:
    1) make settings that while you release the production order system checks the capacity availability, if there then release the order otherwise do not release the order.
    2) I think you can go for production version option too where you can either go for external subcontracting or inhouse production.
    3) I think you have project systems there. So the cost will definately go to the project if the requirement is against a WBS elememnt for the project & the settings in FICO module have done by your Fi person.

  • Single BOM across multiple plants in sub-contracting

    We have a single purchasing organisation managing sub-contracting for around 17 plants. This organisaiton purchases sub-contracted items for all the plants.
    The problem we are facing is having to maintain the same BOM for all the 17 plants.
    The central purchasing org is going to create the PO with multiple lines - requesting delivery from the vendor to the different plants.
    How can we avoid having to create the same BOM in every plant?
    Regards,
    Praveen.

    hi 
    u can  avoid  by choosing  the  recurrcive  allowed  for  BOM  can  avoid it
    kishore  reddy

Maybe you are looking for

  • Date error while scheduling infopackage

    Hello Friends I am facing a pecular problem. Some time back we had taken a backup from production to quality system. I have loaded the data with the option "initialization without data transfer". It is successful. After that we are loading deltas and

  • My phone screen is lagging, my phone screen is lagging

    my screen is not true to the touch anymore. I find my self typing text messages or emails and I have to stop to let the phone catch up to my typing. Sliding throuh pictures or switching screens is the same I swype and then have to wait a second or tw

  • Trouble connecting Ipod touch to home stereo.

    Hello, I have an Ipod Touch 3rd gen.  I currently use it mostly in my car and I use a simple aux 3.5 mm jack from the itouch to my aux input on my car stereo to listen to music.  Works great.  Now, I have been trying to get my ipod to connect to eith

  • Duplicate columns created in Document Libraries

    Hi, We are having issues with duplicate columns being created in document libraries after copying/moving documents between libraries (SharePoint 2013): Unable to find any users with similar issues on forum Thanks in advance K

  • Aperture appends (Number) to computer name in the import pane

    I keep seeing a weird issue on two separate Macs after upgrading to Yosemite/Aperture 3.6. When I open the Import pane, Aperture keeps adding a ( + Number + ) to my computer name, i.e.: MacBook Pro (6) iMac (3) Has anyone else seen this issue and fou