Subcontracting POs -- planning components with MRP

Hi!
I would really appreciate getting your help to resolve the following issue.
Ex: We use subcontracting to get our vendor to produce Part X with components A, B and C that we supply (we may have the components in stock or we may need to buy them externally).  We use subcontracting BoMs.
When MRP runs, it creates a purchase req for Part X -- which is what we want.
But it doesn't create requisitions or reservations for components A, B and C.
MRP creates reqs or reserv. ONLY when I issue my purchase order for Part X.
How can I get MRP to issue requisitions or reservations for components A B and C while Part X is still at the requisition stage.
Thank you!

Hi
Have you selected dependent requirements in Material master (MRP view).
please check whether BOM explosion selected for MRP in IMG.
also please check
http://help.sap.com/saphelp_47x200/helpdata/en/f4/7d2a8f44af11d182b40000e829fbfe/content.htm
regards
Srinivas

Similar Messages

  • Problem when creating planned order with MRP run

    Hello,
    I create a material with a fix reorder point, MRP type VB. When I run MRP with MD03 on this material I have several problems :
    - planned order is created with an opening date in the past, so I have error 'Opening date in the past' in MD04. How can I generate a planned order with opening date not in the past
    - when changing manually opening date, after running again MD03, I have error 'No BOM selected'. Material is configurable, has a text BOM, a routing and a configuration profile. What is the problem? When modifying planned order, I have message :
    Material requires configuration
    Message no. 61259
    Diagnosis
    Orders and requirements for a configurable material must have characteristic values.
    Usually, you should create a variation for configurable materials managed in inventory management which has the default variant configuration.
    System Response
    MRP: Requirements without characteristic values for a material cannot be planned in MRP.
    Procedure
    Check requirements or orders.
    Create a configuration evaluation for the material in the material master record if necessary.
    Thanks in advance.

    Hi
    I am facing the problem. Could you please tell me if you have resolved the above problem? If yes, Could you please provide me as how you resolved? Thanks in advance.
    Thanks
    Nagesh.

  • Subcontracting - How to plan the components in MRP

    Hi Experts,
    We have the following  requirement to map the subcontracting scenario in SAP MM.
    1) Subcontracting PR has to be generated during MRP run for all the FERT materials ( Done )
    2) Auto convertion of PR into PO by scheduling the batch job ( Done )
    3) Goods issue with subcon delivery ( done )
    4) Pick list from subcon delivery ( possible)
    My question here is How to create the delivery schedule lines for components thru MRP and made available to the subcontractor in the required date.Client does not want to maintain the inventory for even 1 week.
    Example :
    FG required date 7.01.2009
    PO release date 30.12.2008
    Component level A Requirement date 29.12.2008 ( How we can control in MRP)
    Component Level B Requirment date 03.01.2009 ( How we can control in MRP)
    Appreciate your reply.
    Thanks / Karthik

    Hi
    Thanks for your reply.
    Let me brief about the process.
    Client wants to consign the components at subcontractor's place and will be considered as a separate plant.So the subcontractor will manage the component stock which is supplied by third party vendor directly to the subcontractors place. so there will not be any frieght cost issue.
    But the client requirement is not to spend more money on  component inventory so when the level 1 components are required the system should generate the delivery scedule with required dates.
    1) Component A is reqd to manufacture the HALB assemply at level 1
    2) Component B & HALB to manufacture the Finished Goods at level 2
    My requirement during MRP run
    1) PR for FG
    2) Delivery Scedule for Component A with reqd date
    3) Delivery scedule for component B with reqd date
    Can I make HALB as phantom BOM???
    or Suggest me how I can do other way round..
    Thanks / karthik

  • Subcontracting with MRP areas / Customer consigment

    Dear all,
    I'm currently looking for some information regarding subcontracting processes with MRP areas.
    On the first hand I need a general overview how subcontracting purchase orders would be handled with MRP areas. In addition I'm really interested in the replenishment of the subcontractor stocks. On the other hand some facts about the customizing would be fine.
    My second topic is consigment stocks at the customer. So I need similar information as for the MRP areas but regarding this customer consigment.
    It would be really great if someone has some literature recommendations or official documentations about these issue.
    Many thanks in advance!
    Regards
    Enrico

    Hi Enrico,
    Working with subcontracting and MRP area's gives you the option to plan the requirements for the subcontractor separately and you can then order the components separately. This functionality is used when working with scheduling agreements and direct deliveries to the subcontractor as there this is a requirement.
    A second instance where one would use and MRP area with sucontracting is that when a material is used both by the subcontractor and it's also used directly in the plant production. The requirements for the subcontractor can be separately planned using an MRP area.
    The following links may give you some more information regarding working with subcontracting and MRP area's
    [MRP area|http://help.sap.com/saphelp_470/helpdata/en/c4/106956ae8a11d1a6720000e83235d4/content.htm]
    [Planning for Components to be Provided in Subcontracting|http://help.sap.com/erp2005_ehp_04/helpdata/EN/c4/106956ae8a11d1a6720000e83235d4/frameset.htm]
    Edited by: Peter Pallen on Jun 5, 2011 7:19 PM

  • Subcontracting with MRP area

    Hi,
    we have a FERT material that  is in the MRP area by storage location.
    This material was produced internally. When we ran MRP the requirements and planed orders for FERT material and its components were showed in MRP area. It was ok
    Nowadays this FERT material was changed to subcontracted.
    We don't have a defined supplier for FERT material.
    When I run MRP the requirements and planed orders for FERT material are still in MRP area.
    When we run MRP for components, the requirements and planned orders go to MRP plant.
    This way if we have in MRP area documents placed to cover the requirements from FERT material, MRP will suggest to cancel them. In MRP plant the MRP will suggest to create another documents to cover. How can We avoid this problem?
    Thanks and best regards,
    Elaine

    Hi Elaine,
    If your FERT material is set to F , 30  then your MRP run in MRp Area will not create any dependent requirement.
    Assuming the setting is X in Material Master,
    Given an option please remove the MRP Area planning and the PIR related to that and shift PIR for you FERT material to Plant level in mD61,MD62. This should avoid Planned order getting created in MRP Ara and Plant.
    in my past experience unlesss you want to do Planning run with Scope as planning as Vendor th euse of MRP Area for planning for PIR leads to confusion for End users.
    Hope this helps.
    Thx
    MJ

  • Costing affect with MRP at planned order level and after production order

    Dear all,
    How the costing affect with MRP at planned order level and after production order completion?
    Edited by: Maulik on Jun 24, 2009 1:59 PM

    Dear Maulik,
    check Mr. Vinod's inputs abt costing
    1. Maintain following master data:
    MM01 Material Master with Costing and accounting view. Make sure all the cost Std, Moving avg etc is maintained along with valuation class in Accounting view 1. In costing tab pls make sure "with qty structure" and "Material Origin" are ticked.
    CS01 BOM with components marked with costing relevance in Status/Long Text Tab. Also check all the qty are correct.
    CR01 Work Center in Basic data tab maintain standard value key sau SAP1 and in costing tab maintain the workcenter, activity type and formulas (Usually standard formulas like for Machine Hours SAP006, Labour SAP007, Setup Activity SAP005 is used).
    KL01 Cretae activity types, in basic data tab maintain ATyp Category AS "1" and cost element (as provided by your FI Guy).
    KP26 Activity pricing, here with the combination of Activity type and the cost center you assign price to the activity.
    2. SPRO Activity
    Maintain Costing sheet IMGControllingProd cost controllingProd Cost PlanningBasic settingoverheadsdefine costing sheet.
    OKKN Define costing variant, you define costing type (In the costing type, you define the purpose of a material cost estimate by specifying, for example, which field in the material master record the costing results can be transferred to like std price, moving avg etc), Valuation Variant (defines how the prices are prioratized), date control and transfer structure.
    3. Costing Process Flow:
    1. CK11N CREATE COSTING RUN
    2. CK24 CREATE PRICE UPDATE (You Mark and release the prce to be updated)
    4. COSTING VARIANT WRT PP
    1. OPL1 DEFINE COSTING VARIANT WRT PP
    2. OKK4 or OPN2 DEFINE VALUATION VARIANT
    3. OKK1 or OPM1 DEFINE COSTING TYPE
    4. OPL8 ORDERTYPE DEPENDENT PARAMETER (assign the above creted costing type for both planned and actual)
    Hope this will throw some light on product costing.
    Regards
    kumar

  • Extending material with MRP (no planning file update)

    Hi,
    When you extend a material manually with the MRP-view , the planning file will be automatically updated after saving.
    Apparently this is not the case when doing mass change via LSMW. the planning file isn't updated.
    Can anybody confirm this ?
    Is it possible to make sure that the planning file is updated when executing the lsmw ?
    with regards
    Erik

    Hi Rupesh,
    Yes, but i would like to create receipts for the new requirments coming outside of the planning time fence (PTF). Let me explain with an example below:
    Product Structure: Header product (Currently in ECC MRP Type: P1) and 3 BOM Components (Currently in ECC MRP Type: P2)
    After CIF'ing all the materials to APO, we have the following dates in APO (giving just as an example)
    Today's Date: 1st Feb, 2015
    PP/DS PTF: 10th Feb, 2015 (10 Days)
    PP/DS Horizon: 10th Feb, 2016 (1 year from PTF)
    Scenario 1: If there is a new requirement coming on 5th Feb, 2015, i do not want the heuristic to plan/create new receipts (PReq's) even after the PTF. This is how currently it works with MRP Type 'P2' in ECC
    Scenario 2: If there is a new requirement coming after PTF (for e.g. on 20th Feb, 2015), I want the heuristic to plan for the new receipts based on the requirements date. This is currently working with this above settings, so i do not have to worry about this Scenario 2.
    Please let me know any other idea or work around for the Scenario 1 above. Basically all i want to see the heuristic is to ignore new requirements falling within PTF, but consider new requirements coming in after PTF.
    Thank you
    Regards
    PK

  • Notification on Receipt and Purchase documents getting fired on Production order having Items with planning method as MRP

    I have written a SP Notification to block adding of documents if block number is not provided. Notification is working fine on Purchase and Receipt documents. This notification also gets executed on Production Order where items included in Production order have planning method as MRP.
    Can anyone explain me the relationship between
    "MRP planned items"
    and
    "Purchase documents (Purchase Order; GRPO; Purchase Return; AP Invoice and Credit Memo) and Receipt of Production."
    Thanks & Regards
    Sonil Bhardwaj

    Hi Sonil,
    Can you post your SP , to look if there is any problem with SP ..
    Regards

  • Problem with scheduling planned orders in MRP

    There is a problem with scheduling planned orders in MRP. SFG is assigned to the BOM of FG. No inhouse production time maintained in the material master of SFG & FG. routing maintained for both . In OPU5 scheduling & capacity reuiremnts tickmarked for detailed scheduling. Scheduling level - via detaied scheduling. Scheduling type - backward. Adjust basic dates , adjust dep. req. to order start set. In MD02 , scheduling is via ' lead time scheduling'.
    My problem is the start date & time & finish date & time is same for planned orders of FG & SFG in the detailed scheduling tab of the planned orders. (Duration is same because of same capacity requirements on the same work centre. But how is the finish date same for both SFG & FG?)
    (Capacity requirements are being generated.)
    What could be the problem ?

    Dear,
    By scheduling the routing and maintain lot size dependent time in material is best practice and result of scheduling will be consistent.
    If you want SFG before FG you need to define lead time offset in BOM or need to maintain the floats before production.
    Hope clear to you.
    Regards,
    R.Brahmankar

  • Problem with MRP area

    Gurus,
    I had activated MRP area for exisitng client.
    The scenario is,
    Within a plant i have two MRP area. One is plant level (A) and the other one is storage location level (B)
    A finished good and its components belongs to both the MRP areas. (A and B) I created a Planned Independent Requirement for finished good at storage location MRP area (B) and run MRP via MD02 for MRP area B, i got a planned order at MRP area B. But the dependent requirements for the components are created at MRP area (A) plant level.
    My requirement is to get the dependent requirements at MRP area B for pegged requirements of MRP area B.
    Suggestion to this isue is highly appreciated.
    Thanks,
    Aravind

    Hi pravin,
    Thank you for the reply.
    Initially my client was not activated for MRP area. So when i activated MRP area, throughout my client for each of  the existing plants an MRP area is created by default. So, all the materials that belongs to the plant, by default belongs to the plant MRP area.(A)
    I created one more Storage location level MRP area (B) and assigned that to MRP 1 view of the finished good and all of its components. I also created a planned independent requirement for the finished good at MRP Area B. that is i can see the requirement in MD04 screen only with the MRP area B and not in MRP area A.
    Then i ran MRP for the finished thru MD02 for MRP Area B. I got a planned order in MD04 of MRP area B.
    As you are aware MD04 screen is specific for particular MRP area.
    This planned order is not displayed in MD04 screen of MRP Area A. But the dependent requirements for the components are not displayed in MD04 screen of B. But the dependent requirements are seen in MD04 Screen of MRP area A.
    As per my understanding the dependent requirements of components should be displayed in MD04 screen of B as my pegged requirements are from MRP area B.
    Kindly suggest and please let me know if any thing is not clear.
    Regards,
    Aravind

  • Purchase Order is generated after MRP for Material with MRP Type ND

    Hi Everyone,
    Material type := HAWA
    My material procurement type = F i.e. External Procurement.
    MRP Type = ND in Production server , and VB in Quality
    Lot Size = EX
    Material Status :- 15 Pre-release both for Quality and production server
    The Material is bulk material and bulk material indicator is set.
    Purchasing View is also maintained for the same.
    Planning Strat = Z5 Company specific
    Special procurement key:- Z7 Company specific
    I am running MD02 with following parameters.
    Create Pur Req =1, PR
    Create MRP List = 1, MRP List
    Delivery Schedule = 3, Schedule Lines
    Planning Mode = 2 Re- Explode BOM & Routing
    Scheduling = 1
    Issue:
    After MRP run, system is  generating PR, Though with MRP type ND purchase requisition should not be generated.
    Observation:- Looks like there is inconsistency of material date in Quality and production server.
    When I tried to run the planning , The Error message was generated"Material status is set to pre- release.
    After changing the material status to 20 (Active ) , when we run the MRP , The error message is generated "Material is not planned automatically "
    We havent been able to locate the root cause so far
    Please guide us
    Thanks in Advance,
    Ayaz
    Edited by: Ayaz Alam Khan on Feb 16, 2011 2:41 PM

    IF the material is ND, system won't Run MRP for the material
    Observation:- Looks like there is inconsistency of material date in Quality and production server.
    There is no link
    When I tried to run the planning , The Error message was generated"Material status is set to pre- release.After changing the material status to 20 (Active ) , when we run the MRP , The error message is generated "Material is not planned automatically "
    system will read the X plant  material status or plant specific material status first and then only system will read MRP type

  • Report for PO's/Pr's/Planned orders with exception code

    Hi all,
    Is there any report which lists out Purchase Orders/Purchase requisitions/Planned orders for a specific exception message number?
    For example when MRP is run some times the finish date for a planned order may be in past (exception message number 07). I would like to get a list of all the planned orders with exception message number 07. Similarly i would like to get PO's/PR's for a specific exception code.
    Any help is highly appreciated.
    Thanks,
    Avani.

    Hi Neetha,
    You can use the Collective access tab on the MD06 T-Code, don't enter a material number, only the plant number and MRP Controller number.  Then click on the tab marked Exception Groups, check box  number 7 and execute the report.  This will give you a list of all materials with exception group 7.  If you need it as a report. Once the report comes up you can click on MRP List on the tool bar at the top of the page and then click print.  This will format it so you can download it into excel by clicking on the Local File Button.  When the box comes up click on spreadsheet and save it to your hard drive as an excel spreadsheet.
    Hope this is of some help to you.
    Debbie

  • Creation of Purchase Requisition with MRP - MD02

    Hello,
    I have created a sales order using one material with MRP. When I run MRP-transaction MD02 for this material, a purchase requisition is created.
    What we want is to block the creation of the purchase requisition when the sales order has delivery block (code 02). I have been trying to use this enhancements; setting break-points in all function modules, but when running MD02 is does not stop there:
    MEREQ001      Customers' Own Data in Purchase Requisi
    LMDR2001      User exits restr. profiles of opt. pur.ord.-based load bldg
    LMDZU001      User exits in additional planning                         
    M61X0001      User exits PP-MRP materials planning                      
    M61X0002      User Exits PP-MRP Material Requirements Planning Evaluation
    Do you know a way to do this or also change data in the purchase requisition created with MD02?
    Thanks and regards.

    Dear ,
    Are you very particualr to process the Sales Order demand when there is a delivery block ?
    To restrict that  one you can do the following steps :
    1.Goto Sales Order -VA02-Select the line item -Double Click -Select the Schedule line  tab -Set Sechedule line item categoery as CN instead of CP.If it is CP then it will processed through MRP
    2.Change the pricining date and make credit block for sales Order and do not release though VKM3 so it will not be tearted through MRP run  to have PR geneartion
    Hope this is clear
    regards
    JH

  • Discontinued parts with MRP type VB

    We have scenario as below :
    1.       We have material A with stock 100, open PO 50.
    2.       The material A is now planned to be phased out by replacing it with a new material B
    3.       Material A had MRP type VB now we will change it to ND
    4.       Material B will have MRP type VB
    5.       So when we run MRP for materil B it should consider stock of material A & Open PO of Material A for calculation during the MRP run and the new requirement calculation should be
    Example :
    Material B is set up with RO point 100 and max stock of 150
    So when we run MRP for Material B even though stock for material B is zero it should not generate any new requirement as stock & open PO of material A exists.

    Hello
    Please take a look on the following note, which explains the general restrictions of the discontinuation process:
    43636 - Discontinued parts
    The note provides the following explanation regarding the MRP type:
    The material is planned using an MRP procedure, for example, MRP type PD.
    Therefore, since you are using MRP type VB, which uses a reorder point procedure, the discontinuation will not happen and your system is working as designed.
    BR
    Caetano

  • Problem With MRP

    Hi Friends,
    I am facing a problem with MRP. In my Implementation, my Client is a Automobile Gasket Manufacturer.
    One major product line is Gaskets which is high volume and low price
    We will use Make to stock  with streategy 40.
    Now the queries are as follows-
    1)       What should be the frequency of MRP Run for the plant (weekly , monthly of daily)
    2)       If  after one MRP Run- some Planned Orders and some Purchase Req are converted to Production Orders and Purchase Orders. My Prod Orders- 100 Pieces and PO is 1000 Kgs.
    Now subsequently , due to change in schedule,(PIR is maintained by Sales Department and it changes  often) lets say, my PIR is Changed from 100 to 10 Pieces ,
    How can a PPC  person come to know of this and inform the Buyer to foreclose the PO or amend the PO and as well change the Prod order also.
    Thanks in Advance
    Waiting for your Reply,
    Praveen

    Hi Praveen
    1) What should be the frequency of MRP Run for the plant (weekly , monthly of daily) : Daily Basis as your demand changes frequently.
    2) PPC will understand from MD04 screen where all the result of MRP as Stock Requirement List available.U cant change Production Order while running MRP as your demand changes from 100 to 10 pecies because Prodction Orders are firmed recipept.In that case you can change quantiy , do the availablity check and scheduled again  or set TECO so that it will not show up in the MD04 screen also.
    Any changes to demand and subsequent effect can be viewed through the exception messeges column in MD04/MD05
    Hope this will help you to figure it out.
    Regards
    Jia

Maybe you are looking for

  • Not all videos show up on Apple TV as do on computer

    My son posted a video on YouTube last night and I can find it in You Tube on my computer, but it does not show up in a search with Apple TV or my Internet-connected Panasonic tv. I don't have a YouTube account; I just go to the web site and search fo

  • Conditional for a text input box NOT being null? Sorry for asking so many questions!

    Okay, here's the situation. I'm creating a simulation of a form on which there are several text input boxes, 7 of which are mandatory fields. I know I can use a conditional to check whether the box has nothing in it by creating a null variable with n

  • MacBook to CRT TV... is it possible?

    Hi all, I have a 13" MacBook that I purchased in January 2010. I also have a very, very old CRT TV with an RCA port. I would like to hook up my laptop to the TV to watch YouTube videos and Netflix "watch instantly" videos on my TV screen. After some

  • How to bring the screen editable after errror message

    Hi All, I made a little validation in screen in me56 on a fixed vendor in item level. After which I issued an error message. I got the error message but the screen remains non-ediatble. I need to atleast open the field FIXED VENDOR for input for the

  • Muse site won't open keeps crashing-please help

    my site wont open.  I have been working from an external because I have had to work on it on two different computers.  today when I came home and tried to open my site on my laptop this is the error message I got as Muse crashed:  Adobe Muse encounte