Test Package in Test Management tab of Change Document

Hi Expert,
When we test on CHARM, we realized that the test package in test management tab can only be
attach before the developer change the status to "Pass normal change to
test". Is this standard or can we do any configuration to allow the
test package be attach during "Test for Preliminary Input" status?
Thanks
Best Regards
Remy

Hi,
I manage to solve this issue as below,
Go to SPRO
>SAP Solution Manager Implementation Guide
>SAP Solution Manager
>Capabilities (Optional)
>Change Control Management
>Standard Configuration
>Change Request Management Framework
>Adjust UI objects by User Status
Thanks
Best Regards
Remy

Similar Messages

  • Regenerating test packages in Solution Manager 4.0 after blueprint changes.

    Hello,
    This is the scenario.
    A test plan and test package (1 process = 1 test package) have been created.
    The blueprint has changed and a new step has been added to the process (the process that has already been assigned into a test package.
    How do you get that new task/step into the test package??
    Current situation:
    I've managed to regenerate the test plan with the new task listed under the process. However when I go into change test package the new process is NOT there. Why is that? Can I had a new step to a package or not?
    Regards
    Dan

    You must go down to the transaction leveland click and then regenerate it will then be eligible in the package for regeneration.

  • How to assign test cases to test package and test catlog?

    how to assign test cases(stwb_tc) to test package(stwb_2) and test catlog(stwb_1)?

    Hi
         goto to transaction stwb_1 enter the text and you will a get a screen now
    goto to Menu
    EDIT->Nodes->insert->As subnode
    on the selecting you will get the option to add a test case (stwb_tc) or  a test caltalogue.
    Please reward if useful..

  • Solution Manager Tab Name Change - is it possible

    Hi
    I am new to Slolution manager config. and would like to know if I can change the Tab name of the Solution manager where you have Tabls like Gen.Documentation, Proj. Documentation, Administartion etc.
    If we can change the names, then please let me know the cofig. steps.
    Thanks,
    Atul

    Hi Valdecir
    Thanks for the quick response.
    We are ready to maintain it but could you please let me know the proess / config to change the tab name.
    Thanks,
    Atul.
    Hi Atul,
    It is a matter of translation. As it is standard text if you change them, you will need to maintain the change log as they can revert on the next suppor package or upgrade.
    Regards,
    Valdecir

  • How to select test cases efficiently for a test package?

    Dear experts,
    I would like to ask you if you have found a way administer how to assign test cases to test packages and test packages to testers. For regression tests this assignment remains relatively stable (often the key users).
    Do you know a way to administer this within the solution manager - or do you recommend the old excel table.

    Hello Ragu!
    Thank you for your answer! My question was regarding the organisational side, I didn't get this clear.
    I know how to generate a test package and how to assign a tester to a test package but where do I get the information which test packages I need and which tester to assign to which package.
    Maybe a good option is to assign the tester as a team member on the process step level. Thus the assignments can be listed with SOLAR_EVAL using "Assignments / Test Cases" with option "Display Team Members". This list would help to generate the test packages. The selection of the test cases for the test package has do be done manually because there seems to be no filter for team members.
    Regards,
    Martin

  • Test Package - Assignment to different tester

    hi to everybody,
    I'm using STWB_2 and STWB_WORK during test in an implementation project. I have created a test case with different process steps. Some of these steps are to be executed by a key user, other by another key user. How can I assign the different tester inside the test package. I would like to show this information when the testers display the package. Any idea????
    Thanks a lot
    lelio

    Hi Lelio,
    Ok. So, you have already considered the Package creation at Transaction Code Level.
    One suggestion is, to let the first tester finish his/her transaction, have a test step called 'Create a message', let him/her create a message alerting the next tester to commence the next step. All such messages are with respect to a given 'Test' within a Test package - at Test document/ Transaction level, so they'll have the right 'context' when someone opens the message.
    I know this isn't a great solution, but using a standard functionality for a different use.
    Best regards,
    Srini-
    Hi Lelio,
    I was going through [this|https://websmp107.sap-ag.de/~sapidb/011000358700000193922008E] presentation today - from SolMan Enterprise Edition and it seems like your query is answered by this version of SolMan. Please go to slides 8 to 11 of 25.
    There is also a [SAP Tutor |https://websmp107.sap-ag.de/~sapidb/011000358700000183912008E.sim]file which explains how the new functionality works. It's great to see this - and I wish this was part of normal SolMan pack itself !
    Of course, this would come at some extra cost. Perhaps, a case for you to consider at a later stage, or if your project/support organisation can spare that rightaway
    Warm regards,
    Srini
    Edited by: Srinivasan Radhakrishnan on May 26, 2008 3:08 PM

  • How to change the sequence number in the test packages?

    Hello,
    I need to change the sequence number in the test packages. Currently I use "move test case." However you can only move one item at a time.
    There is another option to make this change?
    Best regards,
    Elisabete

    Hi Elisabete,
    Sorry, I've to acknowledge the reply from Fabricius.
    That's poor in release 7.0. A former version provided a solution where it was possible to move a testcase even over pages at once.  May be SAP changed this functionality because of other problems caused by the former solution.
    Therefore I am looking for a business blueprint structure meeting the logical and operational process for little need of changes in sequences.  And I create E2E-scenarios / E2E-processes as an additional structure in a project to have an easier approach in the Test Workbench.  An other option is to divide test packages into smaller ones.
    I hope we can look foreward to a better and more comfortable solution in release 7.1.
    Best regards,
    Adelbert

  • Test Package Sequences in Solution Manager Test Management

    Hello,
    Is it possible to have a sequence in a test package with only one test case but 2 or more testers?
    I have individual test cases which will be tested by several testers e.g. tester1 completes first half, tester2 second half using results obtained from tester1. I do not want to split it into 2 separate test cases.
    Is there any way of creating virtual copies of a test case in a test package so I can assign a sequence or any other possible solution?
    Thank you.

    Hi,
    As far as I know the only solution for this would be to split it in two test cases, so you can assign the two testers in sequence.
    You can assign the same test case for multiple testers but you can't split half of it for each tester.
    Kind regards,
    Fabricius

  • Unable to invoke Sequence in the test package management

    Hi Experts,
    Today when i am working on creating test packages suddenly after selecting the node i am unable to do Sequence for the test package i tired by clciking the sequence buttton and also i tried from menu goto-->sequence. new window is not opened and also no error mesaage is also displayed.
    can any one suggest please.
    Regards,
    Naveen Gunda

    Please check in transaction SICF, if service: /default_host/sap/bc/webdynpro/sap/agstwb_ce is activated. Please expand for this the tree via "/default_host/sap/bc/webdynpro/sap/" and activate then the node "agstwb_ce".
    After activation of node "agstwb_ce" select "test service" from context menu of this node.
    What happens then?
    Other approach:
    Try to execute function module "CALL_BROWSER" in SE37 with url www.sap.com.
    Typically a popup from SAPGUI comes up for security questions, to allow access to this url.
    Does it bring the popup and after you choose allow, does the browser start?
    Regards,
    Christoph

  • Transport of Test Plan / Test Packages

    Dear all,
    We intend to transport a test plan with all test packages from the development Solution Manager to the productive Solution Manager because in the productive Solution Manager no configuration is allowed.
    We are using the Solution Manager functionality to execute manual testing in the following way:
    On SOLAR02 the project 'FOUNDATION' is stored. The project 'FOUNDATION' has been migrated from a outstanding sandbox Solution Manager system to all three Solution Manager Systems: DEV, TEST and PROD. Test scripts have been uploaded on the 'test cases' tab of the respective business process branch.
    In the development Solution Manager SMD a test plan has been generated using the uploaded test scripts mentioned above.
    On the quality assurance Solution Manager the same project 'FOUNDATION' is stored and the same test scripts are uploaded on the same branches.
    When the test plan is transported (using the recommended STWB_2 transport functionality) from the development SM to the quality assurance SM there are two issues.
    1. The transported test plan cannot be edited / regenerated anymore. An error message "The specified structure does not exist" is displayed. Message number is SOLAR056.
    2. The transported packages can be assigned to users but no notes can be added to the test cases. The error message is: "Unable to find template". Message number is SOFFICEINTEGRATION231.
    It seems that the transported test plan cannot retrieve the underlying project structure, even it is identical to the project structure of the development SM.
    This problem is urgent to us, as the test phase is starting next week.
    Thank you very much for your support.
    Best Regards,
    Marc Reinhardt

    Hello Marc,
    We have experienced similar problems. A transport of the test plan and copies of the test plans have resulted in us loosing status values and test notes. 
    I was informed it had to do with the fact the information is stored in the GUI. How I don't know, I am not a technical person.
    I was wondering if you may have encountered the similar problems I have had above and found ways around it.
    You can reach me at [email protected] as well.

  • Test packages cant be created in locked system

    I am using project management part of solution manager, & because the info structures are sap objects, I have to transport any change to a test package. I cannot create them in the production system as it is locked to changes. Other sap objects lets you tick the current settings box in sobj & then sap treats it like master data (which in reality this is !!)
    Has any found a way around this, I think it is crazy to have to transport test packages

    Rajesh,
    Answer is very simple. I did get same kind of problem. It is very simple answer depending on your R3 version.
    Use password all capital letters. Don't include any small letter at all. unlock your user id and change password to capital letter. BW doesn't like small and capital letter mix. this bug is fixed in ECC 6.0
    <removed_by_moderator>
    *Do not ask for points
    Read the "Rules of Engagement"
    Regards
    RK
    Edited by: Juan Reyes on May 21, 2009 9:30 AM

  • Project - Change Management Tab missing

    Hi Guys
    After renaming a test Solution Manager, which is a copy from an existing System, Change Management Tab is not visible in the a Project Attributes.
    Before the SID renaming, the tab was visible, but after chaning the name to SMT, it no longer appear.
    When accessing  SOLAR_PROJECT_ADMIN transaction, under System Landscape, there are only three tabs instead of four
    Some logical relation is missing? Any idea where can I verify why?
    Thanks!
    Copied and Renamed system (SMT) with SOLMAN_ADMIN, client 200
    Original System (SSM), user SOLMAN_ADMIN on Client 200

    Hi,
    as you copied the system, probably there is a missing entry which defines the client in which ChaRM will be active. Check in SPRO below "Change Management->Basic Configuration" the IMG activity "Activate Integration with Change Request Management->Activate Change Request Management and Set-up client". It must have your client 200 specified.
    Regards,
    Raquel

  • Date assignement is absent in test packages.

    Hi All,
    I have created one project and related to that defined scenarios for the same.
    Later when i created the test plan i got the scenarios with test cases.....and also  with actual and plan dates which are coming from solar02 transaction.
    When we generate the test plan and later create test packages dates are not appearing.
    Please help and points will be rewarded.

    Hello Prakhar,
    the SAP Solution Manager - Test Workbench integration works as follows:
    The assignments that you make on the <i>Administration</i> tab in transaction SOLAR02 are also visible in the Test Workbench STWB_2 transaction on the very same <i>Administration</i> tab. This holds true when generating test plans; when selecting the contents for a test package there is now way to seperately see planned/actual dates for there is no <i>Administration</i> tab available on this leve.
    So if you have experienced this behaviour, the functionality works as it has been implemented.
    The dates that you maintain in SOLAR01 and SOLAR02 indicate the planned and actual processing time for your scenarios, processes and processes steps. So this information may contain all the efforts for building up the appropriate process structure, assigning documentation, doing the configuration and creating and assigning test cases and so forth - depending on your project scope.
    In the Test Workbench (STWB_2) your see all this <i>Administration</i> information as display only, including for example respective key word assignments. You can now go ahead and size and generate your test plan based on those structure filter criteria (status, project team members, keywords).
    So to sum up: The <i>Administration</i> information gets displayed on the test plan level and can be used to appropriately generate your test plans. It is not, however, seperately displayed for test packages (test package level), which resemble a view on your test packages.
    I hope this clarifies what you were looking for.
    Best regards,
    Doreen Baseler

  • Can't create Test package

    Hello, After updating up to 22 version new problem has apeared in Test management. I can't create test package in newly created Test Plan. There are disabled buttons like a "create package" and "change package" on the "Test package management" screan. I try to make it with SAP_ALL authorisations.

    Try using this authorization SAP_SOL_PROJ_ADMIN_ALL
    some authorizsations are not included in the SAP_ALL
    hope it helps.

  • ECATT Test Package-urgent

    While running test configuration through Test Package, I cant find the option for choosing variants at execution time for which test configuration will be executed.what can be done in this case........
    thanx for ur concern......

    hi,
    pls go through
    I have Separated that two fields by TAB.
    While i am executing transaction it is taking material from my text file but not taking gross weight and therefore no changes made.
    So i dont understand where is the problem?
    I want to check it is taking gross weight from file or not but i dont know how to
    check..
    So please can u help me?
    i am sending u my code....
    abap.
    DATA : TOT TYPE I VALUE 0,
    FILE TYPE STRING.
    DATA : BEGIN OF I_MARA OCCURS 0,
    V_MATNR LIKE RMMG1-MATNR, " Material Number
    v_brgew like mara-brgew, " Gross Weight
    end of i_mara.
    CALL FUNCTION 'F4_FILENAME'
    EXPORTING
    PROGRAM_NAME = SYST-CPROG
    DYNPRO_NUMBER = SYST-DYNNR
    FIELD_NAME = 'FILE'
    IMPORTING
    FILE_NAME = FILE_V-PATH.
    FILE = FILE_V-PATH.
    CALL FUNCTION 'GUI_UPLOAD'
    EXPORTING
    FILENAME = FILE
    HAS_FIELD_SEPARATOR = 'X'
    TABLES
    DATA_TAB = I_MARA.
    DESCRIBE TABLE I_MARA LINES TOT.
    COUNT = TOT.
    CLEAR I_MARA.
    ENDABAP.
    DO (COUNT).
    ABAP.
    DATA : V_READINDX TYPE I,
    FILE TYPE STRING,
    INDX TYPE I VALUE 0.
    DATA : BEGIN OF I_MARA OCCURS 0,
    V_MATNR LIKE RMMG1-MATNR, " Material Number
    v_brgew like mara-brgew, " Gross Weight
    end of i_mara.
    DATA : WA LIKE I_MARA.
    FILE = FILE_V-PATH.
    CALL FUNCTION 'GUI_UPLOAD'
    EXPORTING
    FILENAME = FILE
    HAS_FIELD_SEPARATOR = 'X'
    TABLES
    DATA_TAB = I_MARA.
    V_READINDX = INT_LOC.
    READ TABLE I_MARA INDEX V_READINDX INTO WA.
    V_MATNR = WA-V_MATNR. " Material Number
    V_BRGEW = WA-V_BRGEW.
    ENDABAP.
    TCD ( MM02 , MM02_1 ).
    INT_LOC = INT_LOC + 1.
    ENDDO.
    2..... can see from your code, you have defined the FILE field inside ABAP....ENDABAP,, but after ENDABAP ... this FILE contents are not available.
    Define FILE as a V parameter,,, I think you will get the file path.
    pls reward if it helpful
    thanks
    vana

Maybe you are looking for

  • Logical standby in noarchive mode

    Hello, does anybody know if it is possible to run a logical standby (10gR2) in noarchivelog mode? For my understanding it should be possible, why not... But I can't find a piece of documentation which prove this. Thanks in advance, Boris...

  • Pets Game - No Buy "PADLOCK"

    many pets players are happy with their owners and/or situation and banner up as "no buy" pets to avoid being taken out of these situations... the reasons are various but usually because good friends wish to stay together... there is currently no meth

  • A Beginners Guide to creating Photoshop HTML Extensions with Jquery-UI.

    Like alot of you here, I've been struggling to learn how to create these new HTML extensions.    I thought I'd take the time to make a tutorial of what I've discovered.  I've posted it here:  adobescripting.com/MAIN_wp/creating-photoshop-html5-extens

  • Error 1335 When Installing Compact RIO Module Software 2.1.4 From Hard Drive

    I'm having issues with the installation of the CompactRIO Module Software 2.1.4. Initially, problems were occurring when trying to communicate with the device, as it was denying access to it from the Development PC. Various things were tried such as

  • Webi Page View Not Displaying Page Size Correctly.

    Hi Everone, I have an issue with one report where the page size sttings do not translate when viewed in HTML Page View. Figure one is the report as seen in the editor - as you can see the page is displayed correctly - A4 Portrait: And, when the repor