To delete Profit Centre plan.

Hi
The user requires to delete the exising Profit centre plan and enter fresh (we use 7KEX to upload plan). Is there any other option than entering zero values to overwrite the exising values to delete the exising data?
Thanks & Regards
Nadini

Hi,
With transaction 0KE1 by leaving 'blank' the field 'profit center' all
profit centers are considered for the deletetion. You can reset all
your planning data without selecting one by one.
I hope this information helps you to solve this issue.
Best Regards,
Abhisek

Similar Messages

  • Delete Profit Centre Plan data

    Hi
    One company seems to have uploaded the same plan (via 7KEX) several times.
    Is it possible to delete or reverse this plan upload data?
    Thanks & Regards
    NW

    Everytime you uploaded,did it overwrite or added on to the existing values?

  • Profit centre planning

    hi friends
    can you guide me in the steps needed to build a profit centre planning in SEM-BPS. I need to create a model,so could someone guide me through it.
    regards
    kris

    Hi Kris,
    please check the delivered SEM planning applications. You can use these data models as a starting point.
    Regards,
    Marc
    SAP NetWeaver RIG

  • Transport of deleted profit centre

    Hi,
    I have a problem with transporting deleted Profit centre. Note 110030 states the procedure of the deletion/transport : 
    "First create the corresponding transport request.
    Then delete the profit center in question in the source system.
    Then release the transport request."
    A problem is that I have deleted the profit centre in the source system before the transport request was created, so any transport request I create afterwards does not reflect this change in the target system.
    My question is; do you know any other possible way to transport this change, and if not - what could possible consequences be if the profit centre is deleted in the target system manually as well, and not trasported to it.
    Thanks so much in advance
    Ana

    Hi,
    Don't worry; manual deletion will have the same results as transporting it from DEV.
    Regards,
    Eli

  • Deleting Profit Centres and removing them from Profit Centre Groups

    Hi,
    I have recently deleted some 3000+ unused profit centres from our system.  However the problem I'm having is that these existed in a number of profit centre groups and the values are still
    displaying with the text "no valid master record".
    Is there a quick way to remove these from the profit centre groups as I don't relish the prospect of removing them all manually.  The standard hierarchy is not a problem they have autoatically been removed from there.
    thanks in advance.
    Paul.

    Hi,
    The deletion of the profit centres has been completed and wasn't a problem. 
    It's the removal of the values of these profit centres from various profit centre groups that is causing a problem. They still appear in the groups even though the underlying master data no longer exists.
    Paul.

  • Cost Centre Plan data not updating FAGLFLEXT

    Dear Experts,
    In our production environment, our cost centre plan is not updating FAGLFLEXT table. Profit centre plan using GP12N is fine.
    We are using the New GL and have FIN-CCA and FIN-PCA scenario activated.
    Integrated planning is ticked in the planning versions for both Controlling and New GL Plan versions.
    Controlling plan version and New GL plan version have the same name.
    In table Controlling table COSP, I can see the plan data on business transaction type RKP1.
    I expect to see it in FAGLFLEXT with RKP1 but I see no plan values at all.
    In fact, in the previous 3 environments, we have not had this problem and cost centre plan and actual has updated FAGLFLEXT. Only in Production...
    Any suggestions? Help if you can! Thanks alot,
    Deb

    Dear Ravi,
    I don't think this is the problem.
    It seems that:
    - the CC plan was created -> it updated CO tables e.g. COSP -> no update to FAGLFLEXT
    - the CC plan was deleted -> it updated CO tables with negative value -> updated FALFLEXT with negative value
    -the CC plan was update again -> it updated CO table -> updated FAGLFLEXT and balance with negative value is zero
    - the CC plan was deleted again -> it updated CO tabe with negative value -> FAGLFLEXT  is in minus value!
    It seems like somewhere between first and second steps, the scenario FIN-CCA was not behaving like it was active!
    Have you come across this before?
    Thanks!
    Debora

  • Problem while running the Profit center Plan/Actual Report in Background

    Hi
    While executing the T.Code s_alr_87009722 (Profit Centre plan/Actual Comparision Report) on fourground it is giving all the profit centers/groups in the particular profit center group. But when i run the same report in back ground mode it is picking only the last profit center in that group. Please help me regarding the same.
    Regards
    Surya

    hi prakash ramu,
    even it is not working. it is directly talking me to spool request..
    i think it is not possible, while ur running the report in background.,
    any how if possible could u pls send me the code...
    thanks
    ramu

  • Profit Centre Hierarchy Change and Profit Centre Budget

    Hello Friends
    For better view of Profit Centre Reports we are planing to change the Profit Centre Hierarchy.
    I wanted to know that, are there some Specific Points which we have to take care of, before changing the Hierarchy?
    Will some other settings get affected in System after changing the Hierarchy?
    Also i want to know the TCode for entering Profit Centre Budget in System.
    regards
    prashant

    Hi,
    Profit centre planning (there is no budget for profit centres) is entered via 7KE1 transaction. If you change your hierarchy you should think of the effect on your reporting and allocation processes. That is if you use certain group in your cost allocation cylce and now you change it, it might have an effect on costs distribution.
    Regards,
    Eli

  • Deleting the profit centre

    hi,
    I have a problem when deleting a profit center as follows :
    1.when deleting from Tools in config we got the message
    " profit centre scenario is active in general ledger".
    2.when  deleting from application menu:
                (a)The "Set to inactive " function is grayed out.
                (b)when you mark the profit center for deletion we got the message
                  "profit center scenario is active in general ledger".
    this happens in all clients.
    please help as we are going live shortly.
    your help is highly appreciated
    waiting eagerly for the response.

    Hi,
    Try with T.code KCH5N.
    Regards
    Mani

  • Activity elements planned values not showing in profit centres and cc.

    Hi,
    i'm currently working on a project involving Co and PS. I'm in charge of the CO module and i've got a problem with planned values on activity elements and in PS. Planned values are calculated on activty elements and so are actual and they show in real time in profit centres and cost centres but not their planned counterpart values. i've absolutely nothing on profit and cost centres reports. Integrated planning is activated in PS and so is project in versions.
    i've asked the PS "Expert" and he said it comes from the "plan cost calculation" tab in cj20n, which obviously isn't the cause.
    Doesn't it come from the project profile or status profile customizing? (opsa or ok02)?
    Can the problem come from CO?
    any help appreciated
    regards
    xavier

    Hi Sreenivas,
    thanks for your help and sorry for my late answer.
    what is the difference between FAGL_CO_PLAN and transaction 1ke0.
    when i log on transaction 1ke0, i can see all my planned values.
    wouldn't the issue be resolved by launching t-code faglgcle "fi-gl activate update of plan line items" ?
    regards
    xavier

  • Validate the posting date for profit centre documents actual/plan

    Hi,
    I have an requiremnt where we want system to validate the posting date for profit centre documents actual/plan, Functionality should be same as system check  posting period for FI documents maintained in OB52 and controlling cost centre documents posting period maintained in OKP1.
    For creating Profit centre document activity types are available in Tcode 0KEO.
    I have come across Exits EXIT_SAPLPC08_001 and  EXIT_SAPLPC08_002. But i am notsure whether we can use these and implement these.
    PLease suggest what can be done to achieve this.
    Regards,

    Hi,
    U can use subsititution and specify that the profit center could be your head office or the store as per your req...
    I think thats the only option we have..
    Cheers
    Raghu

  • Profit centre deletion

    Dear gurus,
    I am trying to delete the profit centre having no postings SAP throwing an error New General Ledger Accounting is active...How can I delete it ???
    Regards,
    Pradeep Kumar M.

    Hi:
    For OSS notes, go to:
    service.sap.com/notes
    (here you can search by note number or by any search term).
    You need to have OSS Id to login and access notes. If you dont have OSS login, please ask your basis administrator to generate for you at service market place.
    Hope it helps.
    Thanks.
    Rahul

  • Deletion of Profit Centre

    Isn't it possible to delete a profit centre ?  While I am trying to delete a profit centre (after removing the segment also), system is saying that "profit centre scenarion is active" (or) " the facility is not available to the profit centre object".  I have not posted any data to the Profit Centre which is to be deleted.

    Hi,
    If you are activated profit center accounting in FI, we can't delete the profit center, Because profit center accounting is used as scenrio update in New GL.
    but the we can lock the profit center for postings in the master data.
    Regards
    Srinu

  • Automatic plan figures updates at Profit Centre level.

    Hi,
    I would like to know whether do we have any scenario like Automatic Plan figures updates at Profit Centre Accounting level when we do Cost Centre planning.  The Profit Centre should be picked up by the system automatically from the Cost Centre master. 
    Of course, here the Cost Centre to Profit Centre relationship is 1:1. 
    If anybody come across the above required scenario, please let me know how to achieve it.
    Thanks for your inputs well in advance.
    Note: I know we can copy the Cost Centre plan figures to Profit Centre level by using copy function.
    Regards.
    Chandra

    Hi
    In version maintenance, you need to tick integrated planning....
    In PCA, create the doc types for planning and maintain no ranges...
    Also, if you are on New GL and you want to use New GL planning, you need to do settings in new GL menu for the same... assign version to ledger, fiscal year , etc
    last month there were couple of threads on it .. Refer this link for new GL planning settings
    Re: Buget Upload, Planned values-KP06
    Regards
    Ajay M

  • Doubts on clearing line items in profit centre and deleting the profit cent

    hello All
    We are using ecc 5.0 and new g/l, document splitting is activated. We are not using classic profit centre accounting.
    We have two accounts which has values for profit centre 1010219.
    1. 228100 which is assigned in cross company code clearing account
    2. 228200 which is assigned in cross business unit ( as a part of zero balance account) in documen splitting.
    now i want to clear all he entries for this profit centre and transfer them to another profit centre 1010403.
    I am unable to do so as everytime I try to pass cross profit centre entry, Account 228200 gets a balacing line item( as a part of zero balance). this way my profit centre trail balance will never become zero.
    can some body help me with this,,,,
    1. in classic profi centre we could use t-code ke90 just to pass a document entry in PCA, this is not possible in new g/l... is there alternative.....
    please  help....
    thanks
    sanjeev

    Hi,
    You can try Profit Center Distribution(both sender and receiver gets original account numbers) or Assessment(Assessment cost element shall be a bring in between) to transfer values from multi profit centers to one single profit center or multi profit centers. The cycle can be run on a periodical basis.
    Trust this answers to your query!