Tolerance Key BR in subsequent credit

Hi All,
Invoice has been posted for qty 0.022 kg for amount 210 USD.
Now user wants to subsequent credit,for 135 USD as he has to recover the amount from the supplier.
While posting subsequent credit, system raising an error message...TOLERANCE KEY BR HAS TO BE MAINTAINED....
we have checked the Tolerance key is not maintain for that Company code.
My question is for subsequent debit QTY is not mandatory, then why system is asking for Br key ,which is purely relate with qty.
Thanks....
Abhishek B

Hi All,
Any body help me on this issue.
Thanks..

Similar Messages

  • Subsequent credit/debit is this the way?

    Dear all,
    I am a bit confuse what kind of posting (i.e. subsequent credit/debit) is require in MIRO.
    scenario:
    Our vendor will give us discount and normally will combine the discount amount in the vendor invoice.
    Example:
    PO  with RM100
    Invoice will show          $100
                               disc    ($20)
                               total  :  $80
    Finance will pay $80.
    My question is in MM side do I need to post any in MIRO (subsequent credit/memo)? if I post $80, then, the invoice still open?
    Thnaks.
    tuffy

    Hi Kris
    If I will to choose your method, this is what I did in MIRO but still got some issue.
    1 - Put in the PO as the reference and hits enter key, the Balance field value (on top of MIRO) shown $150. And the one line item shown $150
    2 - Put in  the discount $20 on the discount field (i.e. cash discount field right?) in the payment tab.
    3 - Change the line item amount field to $100
    4 - tick the tax checkbox, and put in the value of $100 in the header Amount field (ie. above tax amount field)
    hit simulate and post?
    is that correct?
    but this RM100 is MIRO and PO is RM150, will this cause problem? or my step is wrong.
    thanks
    tuff

  • Maintain tolerance limits in the Tolerance key

    Hi,
    Could any one help me how to maintain these Tolerance limits in the Tolerance key. This is an error I receive  while creating a PO.
    Best Regards,
    Sridhar.k

    What is the Error Mesaage no you are getting??
    Solution is as Follows
    Set Tolerance Limits for Price Variance
    In this step, you define the tolerance limits for price variances.
    When processing a purchase order, the system checks whether the effective price of a PO item shows variances compared with the valuation price stored in the material master record. In addition, it checks whether the specified cash discount value is admissible.
    Variances are allowed within the framework of tolerance limits. If a variance exceeds a tolerance limit, the system issues a warning or error message.
    In the SAP System, the types of variance are represented by the tolerance keys. For each tolerance key, you can define percentage and value-dependent upper and lower limits per company code.
    Standard settings
    The standard SAP System supplied contains the following tolerance keys:
    PE Price variance, Purchasing
    Tolerance limit for system message no. 207. This message appears if the specified effective price exceeds the predefined tolerances when compared with the material price.
    SE Maximum cash discount deduction, Purchasing
    Tolerance limit for system message no. 231. This is a warning message, which appears when the specified cash discount percentage exceeds the predefined tolerances.
    Note
    You can specify whether the system message appears as a warning or error message using the menu options <b>Environment -> Define Attributes of System Messages.</b>
    Activities
    Maintain the tolerance limits for each tolerance key per company code
    Regards
    Biswajit

  • Subsequent Credit - Unplanned Delivery Charges

    Hello,
    We have a return purchase order (ERS based) say for e.g.100 EA with a total value of $500. We complete creating the delivery, picking and goods receipt (Mvt type 161). Since this is an ERS based PO, we execute MRRL to create the credit memo and complete the cycle. The credit memo is created successfully and the entire cycle is completed. So far so good.
    Now, we need to collect an additional freight charge (unplanned) of $50, from the vendor and hence we are trying to post a subsequent credit. Now while posting the subsequent credit we make sure of the following:
    1. We only provide the quantity as 100 on the subsequent credit line item. No dollar value is given.
    2. From the right most drop down box on the subsequent credit line item, we select the "Goods/Service items" option.
    3. On the basic data tab on header, we input 50 in the "Amount" field.
    4. On the details tab on the header, we input 50 in the "Unpl. Del. Csts" field.
    Now when we try to simulate. The simulation shows that the vendor account gets debited by $50, and the GR/IR account gets credited by $50. However, as per our understanding the GR/IR account should not be pulled in at all, as there are no open items left for this particular PO on the GR/IR account. The open items have been settled by the credit memo created earlier. Should it not credit the price difference/stock account in case if there is not stock coverage or in case there is, respectively?, instead of the GR/IR account?
    The system keeps pulling in GR/IR account to credit. Any explanation on this would be highly appreciated. I have checked the account determination and it is configured correctly.
    A second issue is that the system does not allow us to post the subsequent credit, and it keeps giving the error message " Unplanned delivery costs will lead to negative value" . I also fail to understand why is it trying to subtract the value of unplanned delivery costs from the line items instead of adding?
    This used to work before in the systen, not sure what broke it. But any help on how to resolve this issue would be highly appreciated.
    Thank you all.

    You can do this in two ways
    1) You can post the amount in "unplanned delivery cost" field of MIRO.  For doing this u need to assign GL account in OBYC
    or
    2) You can activate GL account tab for MIRO and then post the amount against a GL account in this tab.  This tab will come at item-level once it is activated
    hope this resolves ur problem

  • MIRO subsequent Credit Memo

    Hello Everyone,
    When I am posting a subsequent credit memo through MIRO for a Purchase Order with account  assignment category Asset,
    I am getting the following error message
    "Balance for transaction type group 10 negative for the area 01
    Diagnosis
    With the transaction entered, the balance for the transactions in group 10 in area 01 will be negative in this fiscal year. However, the balance of transaction type group 10, according to its definition, must be positive in each fiscal year.
    System Response
    The system rejects this posting.
    Procedure
    Check the transaction type, the amount and the fiscal year in your posting. If you want to post a credit memo to an acquisition from the previous year, then use a transaction type for a retirement. If necessary, you can change balance rules after talking with your SAP consultant".
    Can you please let me how to change the Transaction type in MIRO or how to go abt this issue.
    Thanks in Advance
    Vaman A

    Hi,
    Good evening and greetings,
    The solution for your problem is as below
    For this posting change the +/- sign allowed for the transaction type group to '*'.
    First you must activate the maintenance of the table in the ABAP dictionary for table TABWG (transaction SE11).
    You should then call transaction SE16. Enter table TABWG and select the affected transaction type group. Set the value '*' in field VZJSA.
    Once you have made the posting, you should decide whether you want to set the /- sign check again (VZJSA = ''), or whether a negative balance should continue to be allowed for this transaction type group.
    Alternatively, you can also change the proposed transaction type for the invoice receipt of affiliated companies. To do this, go to IMG Asset Accounting -> Transactions -> Determine transaction type for internal transactions.
    Instead of transaction type 152, enter transaction type 151 there under 'Acquisition from invoice receipt (affiliated)'.
    Check whether transaction type 151 in your system corresponds to the transaction type 151 described in note 327088.
    This is as per SAP OSS Note 139899 - AA629 when posting MR01/MRHR/MIRO invoice receipt
    Please reward points if found useful
    Thanking you
    With kindest regards
    Ramesh Padmanabhan

  • Subsequent Credit Memo

    I have a requirement to post a subsequent credit memo that have been send by some vendors in order to make correction to the prices that they have charged in a previous invoice.
    I need therefore to post a subsequent credit memo for a purchase order that have already been invoiced. The PO contains a great number of items and the subsequent credit memo that is received from the vendor contains only one value. How can the system determine and split this value to the items of the PO?
    Do I have to do something in the customizing??

    Hi,
    as you know when you post a subsequent credit if the price in the invoice is too high.th total quantity invoiced for the purchase order item remain same,total valu invoice is reduced
    as you got invoice from vendor for small amount,now you want to split this amount amoung all item
    i dont think there is any customization for same
    you have to reduce it maunally as per item
    Regards
    Kailas ugale

  • Reg Error: Message No FF 747 in MIRO Subsequent Credit.

    Hello
    While posting a subsequent credit in miro system is giving error message.
    message is The tax amount must not be greater than tax base amount.
    it is like credit memo for high priced amount in invoice.
    could you please put some light on this.
    thanks in advance.
    Gerhard

    Hi
    In tax code give 0% tax so that it will not caliculate any tax on that. Hope this will help you.
    Regards
    Muralidhar
    To say thanks reward points

  • PR tolerance key

    Dear All
    Where can I assign the PR tolerance Keys to the Document types, pl explain how the system will give error message in PO if price is exceeds than PR tolerance Price. what are all the configuration settings required
    Regards
    Ramesh B

    Hi
    In standard SAP it may not be activated. You need to use public sector management. You can see it in below customization.
    spro>public sector management->Functions for US federal government->integration->Materials management------> document to document tolerence.
    Here you can assign PR document type and tolerance.
    Regards
    Antony

  • Tolerance keys in Invoice Verification

    I have a question regarding tolerance limits:
    In the logistical invoice verification there are several tolerance keys. The explanation in SAP help is so difficult for someone to understand
    Can somebody explain me how these work in the system? Not the standard help text please, but more a practical example.

    To be honest the SAP config. help text is OK.  Create a calculation for yourself based on the help text and then experiment with an example in your sandbox system.
    As a minimum use the 'principle' key PP and probably also AN, AP, BD, DQ.

  • Maintain tolerance key

    Dear MM experts,where can i maintain tolerance key,e.g add new key

    Hi,
    From IMG>Quality Management>Quality Planning>Basic Data>Inspection Characteristic, Inspection Methond-->Define Tolerance Keys.
    Hope it's helpful to you!
    Good day
    Tao

  • Maintain Tolerance limits for  tolerance key B1

    Hi,
    When We tried to reverse a 'reversal' document using MBST  but the system does not let me a throws up the following message no. M8125...
    "maintaintolerance limits for tolerance key B1 (CoCode 5000)".
    I checked configuration in OMc0, we have  lower limit  10 % anf Higher limit 10% and  BOTH 'check  limit'.
    Still I donot where is the problem?
    Can somebody throw smoe light on this issue? Please....

    Any Help?

  • Maintain tolerance limits for tolerance key PE (CoCode S001)

    Dear all
    im getting error when i creating PO
    Maintain tolerance limits for tolerance key PE (CoCode S001)
    Please help me
    Regards
    venu gopal

    Hi
    You need to maintain the Tolerance key
    PE Price variance, Purchasing
    Tolerance limit for system message no. 207. This message appears if the specified effective price exceeds the predefined tolerances when compared with the material price.
    Maintain the tolearnce key in
    SPRO-> IMG-> Materials Management-> Purchasing-> Purchase Order-> Set Tolerance Limits for Price Variance
    If you want the sytem to propmt for a warning or Error message you can configure the same in
    SPRO-> IMG-> Materials Management-> Purchasing-> Environment Data-> Define Attributes of System Messages

  • Maintain tolerance limits for tolerance key PE

    Hi,
    How can I correct the error below?
    "Maintain tolerance limits for tolerance key PE"
    Thanks

    REFER BELOW SDN POST
    Re: TOLERANCE KEY ERROR DURING MIGO
    MAINTAIN TOLERANCE LIMITS FOR TOLERANCE KEY PE ACCOUNT ASSIGNMENT  -
    >  Please follow this link --> SPRO -> MM-> Purchasing --> Purchase Order --> Set Tolerance limits for price variance --> Here you have to set for Tolerance keys PE and SE. Just copy them from std co. code.
    Message was edited by:
            SHESAGIRI.G

  • Credit memo and Subsequent Credit/Debit Scenarios

    Hi All,
    I have to present all the invoicing scenarios to the client. These also include credit memo and subsequent credit/debit.
    Can someone please give me some examples of these. What is the meaning,how to handle,how do these arise.I will have to run these for them on screen.Please can you help me out with these.
    Regards,
    V S

    Hello,
    Subsequent Debit and Credits
    After an Invoice is successfully posted and the transaction is completed, Vendor approaches with additional amount invoice or correction in Invoice.You would like to post this additional invoice with reference to the original PO and item. Subsequent Debit / Credit functionality allows you to capture this difference without canceling original invoice.
    Please check this link
    http://help.sap.com/erp2005_ehp_03/helpdata/EN/a8/b99890452b11d189430000e829fbbd/frameset.htm
    Regards,
    Shailesh

  • Credit memo and subsequent credit

    Can anybody tell what is the difference between a Credit memo and subsequent credit memo.
    I am finding the impact of both on the PO as same.

    Hi,
    The difference betwen them is that a credit memo quantity and amount are
    affected but in subsequent credit only the amount is affected nor quantity.
    For example.
    You have in your po history.
    GR    amount  quantity
    x        10          10
    IR (normal invoice)
    x       10           10
    Credit memo
    x      5              5
    Now you have invoice 5 amount 5 quantity
    if you made a subsequent for per example
    amount 5
    in your po history you have pending
    0 amount an 5 quantity
    This quantity you must regularize with transaction MR11
    Transaction mr11 only regularize quantities but not amounts,so for this is used
    subsequent credit/debit.
    I hope my explanation helps you now to understand the differences.
    Best regards.
    Antonio.

Maybe you are looking for

  • Can't print from Desktop

    I bought an HP ENVY 7645 and can print from all my devices (phones, tablets) but it does not print from the desktop.  When I try to activate it from the desktop, the message is "Adding printer to your HP Connected Account failed".  Please help.

  • D2kwutil running with Forms6i under Windows XP

    Hi I'm trying to run D2kwutil.pll version 6.0.6.0 with Forms6i 6.0.8.8.0 under Windows XP and it's not working when I try to call WIN_API_FILE package. I tryed to run the demo form (WAPIDEMO) that I downloaded with the PLL but they don't run either -

  • Create PDF = Scan = AppCrash

    I have a new PC with Windows Vista 64 bit. 4G Ram. I have installed my printer scanner (Samsung SCX-4200) and updated Acrobat Pro 9.0 I have configured the presets Each time I try to create a PDf from the scanner, Acrobat immediately stops working an

  • What the heck is Automator?

    In LAYMANS terms, please, what exactly does Automator do?

  • Need help with dates  please-urgent

    Hi folks, please help me with this if you can. I run a weekly job, and need to have my java code create and use 2 dates to capture data for the whole week. begin_date mm/dd/yyyy (String) to be 7 days prior to current date end_date mm/dd/yyyy (String)