What is target qty in process /production orders?
Hi Experts,
I am doing a report that needs to display the quantity and costs (target / planned / actual) of each component in the process /production orders. Through tcode COR3 --> given a process order# --> Goto -- > Costs, I can see total target qty / total planned qty / total actual qty for each component. But I can only find planned qty and actual qty from tables COSS, COSP, RESB. Where to get target qty ?
Can anybody explain to me what is exactly the target qty? Any tables to get target qty? Or any FM to get target qty?
Thanks a lot.
Yu
Dear,
Definition: target costs
Product Cost Controlling (CO-PC)
The costs expected to be incurred when a specific quantity is produced.
In Cost Object Controlling, the target costs are calculated on the basis
of the planned values of a service unit (such as the planned cost of a
production order) and the control quantities (such as the yield
delivered to stock).
Target costs can be used for purposes such as:
o To determine variances
o To valuate work in process
Total Target Costs
Total value of the target costs.
Calculated with the following formula:
Total target costs = Target cost debit + Target cost credit.
Use
Target costs are the planned costs adjusted to the actual operating
rate.
The target debit on a manufacturing order is the sum of the
activity-independent planned debit of the order and the
activity-dependent planned debit of the order multiplied by the actual
quantity of the order.
The target credit of a manufacturing order results from the goods
receipt postings to stock. The delivered actual quantity is valuated
with the planned price according to the price control.
The total value of the target costs is the sum of the target debit and
the target credit.
The target costs are calculated during variance calculation and updated
to the database.
The target costs cannot be shown until you have performed variance
calculation for this target cost version. The target credit for the
calculation of the total variances and production variances cannot be
calculated until an actual quantity for an order exists after a goods
receipt posting.
For the calculation of variances, the target costs are compared with the
control costs.
Dependencies
The calculation of target costs depends on the selected target cost
version.
Similar Messages
-
Excess Qty confirmation than Production order qty
Hi
SAP Experts
Is it possible to confirm excess qty of yield in co11n against Production order qty.
pl. guide me the steps required.
with Best Regards
YogeshYes,
If you do not waht to conform excess qty than the production order qty, then the following are the options
- as our friend told in Work scheduling view the under/over delivery tolerance should be zero and unlimited delivery tick should not be active
- In production order the under/over delivery tolerance should be zero and unlimited delivery tick should not be active.
- In OPK4 fior the combintaion of plant and order type the following confirmation parameters are to be maintained
Under delivery - X error if qty below under delivery tolarance
Over delivery - X error if qty above over delivery tolarance.
With this settings you can avoid what you wanted. -
Target cost for a Production order
Hi
How to get Target Cost for a production order?
Thanks
NagaWell Naga, Right now Im on HR implementation , but I programmed same kind of requirement two years before , but I got planned cost and actual cost .
I also notice cost analysis" the cost is not exact , it wont read the value from KP26 of that particular month .
Here I am talking about 4.5b system.
You can find the sales order ref on production order, and your production order is made up of your different kind of material like scarp, raw, semi-finished etc
Here are the steps I followed .
1- I read the material which you can see in material component on production order in Co03.
After that I take the qty and also multiply by the cost at which machine is posted .
I have that programs, as I need to find out . Ill post you later .
But you have to read the tables afko,afpo,afru,caufv,cost ..etc
Do you see information structure I refer you , If i am not wrong this CO3 ( cost analysis ) report use report painter ( Tr.Gr51,Gr52 ) . you can also see by going in to said transaction which information structure its populating . Thisll also help you.
Hope thisll give you idea!!
<b>P.S award the points.!!! DOn`t forget :)!!!!</b>
Good luck
Thanks
Saquib Khan
"Knowledge comes but wisdom lingers!!"
"Some are wise and some are otherwise" -
Transfer to PA the target costs of a production order
Hi everyone,
How can I transfer to PA the target costs of a production order?
Thanks
Cátia PereiraHi
1. Check your settings in KE4U - Strategy 001 must be assigned to PV=01 and Rec Type F
Tick the "Mat Cstng" indicator and assign COPA Qty Field ABSMG
2. Assign costing key to Mat Type in KE4J or KEPC
3. assign Cost Comp Str to VF in KE4R
4. Assign Value Fields to your variance categories in PA Transfer Structure....
Tick "Variances to Costing Bsed COPA" in your settlement profile
Br, Ajay M -
Change in Sales order deleted all process production order
Dear All,
We have Make to order scenario for our export sales. When we have receive order we make production with reference of sales order with help of t-code MD50 then convert plan order into production order.
IF sales department do changes in sales order it'll delete all processing production orders So, we have to do revoke all production orders manually.
2 query is that, Is there any way to run MRP (Make-to-order) on all line items of sales order ?
Please provide solution.
Thanks,
Farrukh khanDear Farrukh,
There is not tcode to run sales order for all line items, but if you run MD02 it will plan all sales order & line items also. You can run MD02.
Regards
Abhijit Gautam -
How to analyse actual cost for each operation in Process/Production Order?
Hi all,
IN SAP, I know that we can analyze plan cost for Operation in Process Order/ Production Order.
However, I can not analyze Actual cost for Operation .
I know the object when I good issue material is ORDER, not OPERATION.
But, as requirement of users, they want to analyze actual cost for each Operation.
CAn SAP do this analyze?
If Yes, What should I do in SAP to have this reports?
THanks in advance,
Emily NguyenHi Emily,
as I see from one other message that you're using material ledger. Then your expectation is apparently to also see the actual costs of materials in your production order by operation.
This is not supported. Actual material costs are handed up in material ledger multi-level settlement from one material to the next, bypassing the production orders.
That means the production order will always contain the material costs valuated at plan price, not at actual price.
For activity prices that might be better, when you revalue the orders at actual activity prices with CON2. But even there I am not sure that it will always be assigned correctly to the operations.
There is currently an enhancement in development, the operation level costing. But that will affect more the planned cost side not the actuals. Might be interesting to learn more about your requirements and the use case behind.
best regards,
Udo -
How to control Inspeciton generation from Process/ Production Order
Hi SAP Gurus,
In our business place earlier we used to have Process order.The specific Process order type wouldn't generate any Lot.But once we switch to production order , we are getting inspection lot for New Production Order type.
The need is that for specific production order (which is not for main production), the system shouldn't generate 03, 04 type of inspection lot with many real process / production inspection tests.
For this purpose we tried to limit the inspection type for Production order using Order type dependent parameter.
In that we assign new inspection type (other than 03 or 04 inspection types ). The new inspection type is attached with new Usage.And New usage has got its own Group counter with limited test.
So Group counter created with new usage. New usage used in new inspection type. And new inspection type tied with production order. With this we were able to limit for not having inspection lot of 03 inspection type for this production order.
But system generate the 04 type of inspection lot , though production order has got new inspection type attached with it.
Also the new setup 04 type of inspection lots in created mode.
How to make sure that system only generate the new inspection type inspection lots.
Advance Thanks for all the detail help steps.Hi
If you want to restrict quality inspection based on production order type, Its possible. Use exit QAAT0001. Take help from ABAPer, dont forget to set E_NO_INSPECTION based on the order type field there. VERY IMPORTANT: Put E_TQ32 = I_TQ32 in the program, otherwise you will get error "Post stock in QM only"
SDG -
Exit or Badi in the mass processing production order
Hi all,
i'm searching for a user-exit or badi when i save an order. I've found the badi workorder_update~at_save and the user exit EXIT_SAPLCOZV_001 but neither of them works when i use the mass processing function via transaction coid.
Anyone knows if exists a badi or user-exit for the mass processing of orders?
Regards,COID is a Report , what u are doing in COID.
Regards
Prabhu -
Process/Production Order WIP Reverse on Month starting date with postiing d
Hi Experts,
Is it possible to reverse the WIP of Production/Process Order at month starting date eg. 01/07/09. Posting date & Document date should be: 01/070/09.
In my current project production is batch management system. Some of the batches start at month ending days (Eg. 29/06/09) for we calculated WIP at dated: 30/06/09.
My Client wants to reverse that WIP next day, month starting hours Eg. 01/07/09 but while reversing the WIP system is posting the WIP reversing doc. posting date is 31/07/09.
Same batch which started production on 29/06/06 is closed at 03/07/09 as well as goods received same date. FG Stock A/c updated in accounting books.
At the same day If I print my trail balance system showing the Stock value double (WIP stock as well as FG stock)
First Month
Eg. Process Order WIP at 30/06/09 : 50000/-INR
Second Month
WIP Reversal Posting date:31/07/09 by system : 50000/-INR
FG Stock received at 03/07/09 : 50000/-INR
If I Print Trail Balance on 03/07/09 system shows : 1, 00, 000/-INR (based on Posting date)
Which is wrong..
Please tell me the way for Change the Posting date of WIP reverse document. OSS guys are replying as consulting issue.
I am waiting for your valuable reply.
Thanks & regards
BhagiradhaIn KO88, CO88 Select Menu bar Extras-> Posting date
Enter Posting and execute
Thanks for Rajesh (SAP Labs)
Thnaks & Regards
Bhagiradh -
Target quantity calculation in Production order.
Hi Freinds,
Target quantity of the components to be issued is calculated from the ratio from BOM of header material.
If there is component scrap for the components mentioned in BOM then the Target quantity calcultion also considers this and increases the quantity by the Scrap percentage mentioned.
Target quantity gets updated at the time of goods issue during confirmation
Problem is only for orders of one material, the target quantity calculated of components is not considering scrap inspite of maintaining the scrap for components in BOM.
Can anybody help in this matter, what could be the missing setting ?
Thanks in Advance
ShaileshHi Shailesh,
Please check whether the BOM where u maintained the scrap is being copied to the order. To my knowledge there is no other settings required to consider component scrap.
I think the BOM which is copied to the order might be of different alternative BOM where you have not maintained the scrap for that particular component.
Please check and revert.
Regards
Suri -
Report for material with sloc,qty available, and production order
hi friends, i need advice on getting this report for material with qty and specific sloc with the corresponding Prodn order numbers. in mb51 i could get all these details except the prodn order no. could you advice me please?
to make sure you know how to do this.
In the material document list, hit "Ctrl+F8" on your keyboard.
A window will pop up. Click on the button position and look for "order" in the list of available fields. That should do it.
Rgds. -
BAPI to get matrial /qty/ bin from production order
hii All,
which is the BAPI name to get the Bin/Material/Qty from production orderHI,
try using BAPI_PO_GET_DETAIL(S)
REWARD IF USEFUL
vivekanand -
Update of material movements through MB1A/MB1C in Process/Production Orders
Dear PP Guru,
Can any one help me regarding below issue:
When ever material movement is executed through inventory t-code like MB1A or MB1C, even if order number is used as referance, movement data is not updated neither in component withdrawal data of order not in COOISPI.
Is there any notes need to be applied?
Thanks and regards,Dear,
Check the material type in OMS2 whether the valuation area(plant) is having the value updation or not.
If you don't have the value updation for the valuation area it will ask for the details of account assignment.
Check Material doc display in MB03.
Check in OMJJ for your mvt type whether the value and qty update is ticked or not...check it in Account grouping tab.
check to MKPF and MSEG table is update the table also.
Regards,
R.Brahmankar -
Hi,
what is the table/fld for
Production order/work order qty and scheduling agreement qty?
I tried in CO03 but not getting
Can anyone help me....Hi,
For production order quantity..
AFKO-GAMNG "order header quantity
AFPO-PSMNG "Order item quantity
For scheduling agreement
EKPO-KTMNG "Target quantity (item)
EKET-MENGE "scheduled quantity (for each item & each schedule line)
null -
Withdrawal Qty exceed requirement Qty in production order
Hi: guys
In our system, withdrawal Qty can exceed requirement Qty for a production order, even we use planned GI. That means when we use MIGO/MB1A to process GI to reference production order, we can manually change withdrawal Qty. Even this Qty has exceed requirement Qty of production order, system also not give me any message.
Anybody can tell me how to customize settings to limit this function, such as give me a message (error or warning), and ensure withdrawal Qty can not exceed requirement Qty.
thank you.
HenryHenry,
I got what excatly the problem is in your case, the guy who executed has done it very cleverly.
What must have happenned, is that in the change mode of the order, the component quantity was increased and then Issued. Latter on in the change mode of the order again the quantity was reduced.
I think this is the excat case what you are having now in the system, the only clue left out for us is to check whether the manual change was perfomed or not. In the components overview scroll to the right side of the screen till you reach column with heading "ChngeProc.", here if the field value is "1" - then it is obvious that there was a manual change in qty for the component.
The possible resolution to prevent in future is to Make the dynamic message "CN" - 752 as Error in the prodcution order change program. You need to work with your ABAP person for this.
Hope I was able to get to the right problem and possible resolution.
Regards,
Prasobh
Maybe you are looking for
-
IPod with display color had an unknown error
HI guys. Like I said.This is my iPod: http://img22.imageshack.us/img22/1987/img0085va.jpg and then.just this afternoon, it display an unknown error: http://img221.imageshack.us/img221/5381/img0084h.jpg sorry for low-quality image.it had a picture I t
-
Dynamic Filename for Reciever File Adapter
Hi All, Can anyone answer to some of my quesries which are as follows a) . Currently Iu2019m working on an IDOC-to-File scenario in which I need to create zip file on file server by using a payload value. I search sdn and found a bean that can
-
Cannot sync my iphone from itunes with app got from apple store
Hello everyone, I wonder if someone can help me... I dwonloaded a free app from the apple store. My computer is authorized to do thisbut it keep on saying that it's not authorized and in order to transfer the app to the iphone I have to authorize it.
-
Hi there, I've been trying to deploy one of my AIR apps on the BlackBerry Tablet (PlayBook) Simulator and and have run into a problem packaging the .bar file using the command line. I started this off by reading the article at: http://www.adobe.com/
-
Popup on iPhone 60 minutes to reset code
Hi there, I just got a message on my iphone (without doing anything) to change my "code" in 60 minutes. Attached a screenshot (in german). The translation: "Code request, you have to change your code in 60 minutes or less". Anyone has an idea what's