What is target qty in process /production orders?

Hi Experts,
I am doing a report that needs to display the quantity and costs (target / planned / actual) of each component in the process /production orders. Through tcode COR3 --> given a process order# --> Goto -- > Costs, I can see total target qty / total planned qty / total actual qty for each component. But I can only find planned qty and actual qty from tables COSS, COSP, RESB.  Where to get target qty ?
Can anybody explain to me what is exactly the target qty? Any tables to get target qty? Or any FM to get target qty?
Thanks a lot.
Yu

Dear,
Definition: target costs                                                                               
Product Cost Controlling (CO-PC)                                                                               
The costs expected to be incurred when a specific quantity is produced.                                                                               
In Cost Object Controlling, the target costs are calculated on the basis 
    of the planned values of a service unit (such as the planned cost of a   
    production order) and the control quantities (such as the yield          
    delivered to stock).                                                                               
Target costs can be used for purposes such as:                                                                               
o   To determine variances                                                                               
o   To valuate work in process                                                                               
Total Target Costs                                                                               
Total value of the target costs.                                                                               
Calculated with the following formula:                                                                               
Total target costs = Target cost debit + Target cost credit.                                                                               
Use                                                                               
Target costs are the planned costs adjusted to the actual operating    
    rate.                                                                               
The target debit on a manufacturing order is the sum of the            
    activity-independent planned debit of the order and the                
    activity-dependent planned debit of the order multiplied by the actual 
    quantity of the order.                                                                               
The target credit of a manufacturing order results from the goods      
    receipt postings to stock. The delivered actual quantity is valuated   
    with the planned price according to the price control.                                                                               
The total value of the target costs is the sum of the target debit and  
    the target credit.                                                                               
The target costs are calculated during variance calculation and updated 
    to the database.                                                                               
The target costs cannot be shown until you have performed variance      
    calculation for this target cost version. The target credit for the     
    calculation of the total variances and production variances cannot be   
    calculated until an actual quantity for an order exists after a goods   
    receipt posting.                                                                               
For the calculation of variances, the target costs are compared with the
    control costs.                                                                               
Dependencies                                                                               
The calculation of target costs depends on the selected target cost     
    version.

Similar Messages

  • Excess Qty confirmation than Production order qty

    Hi
    SAP Experts
    Is it possible to confirm excess qty of yield in co11n against Production order qty.
    pl. guide me the steps required.
    with Best Regards
    Yogesh

    Yes,
    If you do not waht to conform excess qty than the production order qty, then the following are the options
    - as our friend told in Work scheduling view the under/over delivery tolerance should be zero and unlimited delivery tick should not be active
    - In production order the under/over delivery tolerance should be zero and unlimited delivery tick should not be active.
    - In OPK4 fior the combintaion of plant and order type the following confirmation parameters are to be maintained
    Under delivery - X error if qty below under delivery tolarance
    Over delivery - X error if qty above over delivery tolarance.
    With this settings you can avoid what you wanted.

  • Target cost for a Production order

    Hi
       How to get Target Cost for a production order?
    Thanks
    Naga

    Well Naga, Right now I’m on HR implementation , but I programmed same kind of requirement two years before , but I got planned cost and actual cost .
    I also notice “cost analysis" the cost is not exact , it wont read the value from KP26 of that particular month .
    Here I am talking about 4.5b system.
    You can find the sales order ref on production order, and your production order is made up of your different kind of material like scarp, raw, semi-finished etc
    Here are the steps I followed .
    1- I read the material which you can see in material component on production order in Co03.
    After that I take the qty and also multiply by the cost at which machine is posted .
    I have that programs, as I need to find out . I’ll post you later .
    But you have to read the tables afko,afpo,afru,caufv,cost ..etc
    Do you see information structure I refer you , If i am not wrong this CO3 ( cost analysis ) report use report painter ( Tr.Gr51,Gr52 ) . you can also see by going in to said transaction which information structure its populating . This’ll also help you.
    Hope this’ll give you idea!!
    <b>P.S award the points.!!! DOn`t forget :)!!!!</b>
    Good luck
    Thanks
    Saquib Khan
    "Knowledge comes but wisdom lingers!!"
    "Some are wise and some are otherwise"

  • Transfer to PA the target costs of a production order

    Hi everyone,
    How can I transfer to PA the target costs of a production order?
    Thanks
    Cátia Pereira

    Hi
    1. Check your settings in KE4U - Strategy 001 must be assigned to PV=01 and Rec Type F
    Tick the "Mat Cstng" indicator and assign COPA Qty Field ABSMG
    2. Assign costing key to Mat Type in KE4J or KEPC
    3. assign Cost Comp Str to VF in KE4R
    4. Assign Value Fields to your variance categories in PA Transfer Structure....
    Tick "Variances to Costing Bsed COPA" in your settlement profile
    Br, Ajay M

  • Change in Sales order deleted all process production order

    Dear All,
    We have Make to order scenario for our export sales. When we have receive order we make production with reference of sales order with help of t-code MD50 then convert plan order into production order.
    IF sales department do changes in sales order it'll delete all processing production orders So, we have to do revoke all production orders manually.
    2 query is that, Is there any way to run MRP (Make-to-order) on all line items of sales order ?
    Please provide solution.
    Thanks,
    Farrukh khan

    Dear Farrukh,
    There is not tcode to run sales order for all line items, but if you run MD02 it will plan all sales order & line items also. You can run MD02.
    Regards
    Abhijit Gautam

  • How to analyse actual cost for each operation in Process/Production Order?

    Hi all,
    IN SAP, I know that we can analyze plan cost for Operation in Process Order/ Production Order.
    However, I can not analyze Actual cost for Operation .
    I know the object when I good issue material is ORDER, not OPERATION.
    But, as requirement of users, they want to analyze actual cost for each Operation.
    CAn SAP do this analyze?
    If Yes, What should I do in SAP to have this reports?
    THanks in advance,
    Emily Nguyen

    Hi Emily,
    as I see from one other message that you're using material ledger. Then your expectation is apparently to also see the actual costs of materials in your production order by operation.
    This is not supported. Actual material costs are handed up in material ledger multi-level settlement from one material to the next, bypassing the production orders.
    That means the production order will always contain the material costs valuated at plan price, not at actual price.
    For activity prices that might be better, when you revalue the orders at actual activity prices with CON2. But even there I am not sure that it will always be assigned correctly to the operations.
    There is currently an enhancement in development, the operation level costing. But that will affect more the planned cost side not the actuals. Might be interesting to learn more about your requirements and the use case behind.
    best regards,
                      Udo

  • How to control Inspeciton generation from Process/ Production Order

    Hi SAP Gurus,
    In our business place earlier we used to have Process order.The specific Process order type wouldn't generate any Lot.But once we switch to production order , we are getting inspection lot for New Production Order type.
    The need is that for specific production order (which is not for main production), the system shouldn't generate 03, 04 type of inspection lot with many real process / production inspection tests.
    For this purpose we  tried to limit the inspection type for Production order using Order type dependent parameter.
    In that we assign new inspection type (other than 03 or 04 inspection types ). The new inspection type is attached with new Usage.And New usage has got its own Group counter with limited test.
    So Group counter created with new usage. New usage used in new inspection type. And new inspection type tied with production order. With this we were able to limit for not having inspection lot of 03 inspection type for this production order.
    But system generate the 04 type of inspection lot , though production order has got new inspection type attached with it.
    Also the new setup 04 type of inspection lots in created mode.
    How to make sure that system only generate the new inspection type inspection lots.
    Advance Thanks for all the detail help steps.

    Hi
    If you want to restrict quality inspection based on production order type, Its possible. Use exit QAAT0001. Take help from ABAPer, dont forget to set E_NO_INSPECTION based on the order type field there. VERY IMPORTANT: Put  E_TQ32 = I_TQ32 in the program, otherwise you will get error "Post stock in QM only"
    SDG

  • Exit or Badi in the mass processing production order

    Hi all,
    i'm searching for a user-exit or badi when i save an order. I've found the badi workorder_update~at_save and the user exit EXIT_SAPLCOZV_001 but neither of them works when i use the mass processing function via transaction coid.
    Anyone knows if exists a badi or user-exit for the mass processing of orders?
    Regards,

    COID is a Report , what u are doing in COID.
    Regards
    Prabhu

  • Process/Production Order WIP Reverse on Month starting date with postiing d

    Hi Experts,
    Is it possible to reverse the WIP of Production/Process Order at month starting date eg. 01/07/09. Posting date & Document date should be: 01/070/09.
    In my current project production is batch management system. Some of the batches start at month ending days (Eg. 29/06/09) for we calculated WIP at dated: 30/06/09.
    My Client wants to reverse that WIP next day, month starting hours Eg. 01/07/09 but while reversing the WIP system is posting the WIP reversing doc. posting date is 31/07/09.
    Same batch which started production on 29/06/06 is closed at 03/07/09 as well as goods received same date. FG Stock A/c updated in accounting books.
    At the same day If I print my trail balance system showing the Stock value double (WIP stock as well as FG stock)
    First Month
    Eg. Process Order WIP at 30/06/09                              : 50000/-INR
    Second Month
          WIP Reversal Posting date:31/07/09 by system     : 50000/-INR
          FG Stock received at 03/07/09                               : 50000/-INR
    If I Print Trail Balance on 03/07/09 system shows        : 1, 00, 000/-INR (based on Posting date)
    Which is wrong..
    Please tell me the way for Change the Posting date of WIP reverse document. OSS guys are replying as consulting issue. 
    I am waiting for your valuable reply.
    Thanks & regards
    Bhagiradha

    In KO88, CO88 Select Menu bar Extras-> Posting date
    Enter Posting and execute
    Thanks for Rajesh (SAP Labs)
    Thnaks & Regards
    Bhagiradh

  • Target quantity calculation in Production order.

    Hi Freinds,
    Target quantity of the components to be issued is calculated from the ratio from BOM of header material.
    If there is component scrap for the components mentioned in BOM then the Target quantity calcultion also considers this and increases the quantity by the Scrap percentage mentioned.
    Target quantity gets updated at the time of goods issue during confirmation
    Problem is only for orders of one material, the target quantity calculated of components is not considering scrap inspite of maintaining the scrap for components in BOM.
    Can anybody help in this matter, what could be the missing setting ?
    Thanks in Advance
    Shailesh

    Hi Shailesh,
    Please check whether the BOM where u maintained the scrap is being copied to the order. To my knowledge there is no other settings required to consider component scrap.
    I think the BOM which is copied to the order might be of different alternative BOM where you have not maintained the scrap for that particular component.
    Please check and revert.
    Regards
    Suri

  • Report for material with sloc,qty available, and production order

    hi friends, i need advice on getting this report for material with qty and specific sloc with the corresponding Prodn order numbers. in mb51 i could get all these details except the prodn order no. could you advice me please?

    to make sure you know how to do this.
    In the material document list, hit "Ctrl+F8" on your keyboard.
    A window will pop up. Click on the button position and look for "order" in the list of available fields. That should do it.
    Rgds.

  • BAPI to get matrial /qty/ bin from production order

    hii All,
    which is the BAPI name to get the  Bin/Material/Qty from production order

    HI,
    try using BAPI_PO_GET_DETAIL(S)
    REWARD IF USEFUL
    vivekanand

  • Update of material movements through MB1A/MB1C in Process/Production Orders

    Dear PP Guru,
    Can any one help me regarding below issue:
    When ever material movement is executed through inventory t-code like MB1A or MB1C, even if order number is used as referance, movement data is not updated neither in component withdrawal data of order not in COOISPI.
    Is there any notes need to be applied?
    Thanks and regards,

    Dear,
    Check the material type in OMS2 whether the valuation area(plant) is having the value updation or not.
    If you don't have the value updation for the valuation area it will ask for the details of account assignment.
    Check  Material doc display in MB03.
    Check in OMJJ for your mvt type whether the value and qty update is ticked or not...check it in Account grouping tab.
    check to MKPF and MSEG table is update the table also.
    Regards,
    R.Brahmankar

  • Production order qty fld

    Hi,
    what is the table/fld for
    Production order/work order qty and scheduling agreement qty?
    I tried in CO03 but not getting
    Can anyone help me....

    Hi,
    For production order quantity..
    AFKO-GAMNG "order header quantity
    AFPO-PSMNG "Order item quantity
    For scheduling agreement
    EKPO-KTMNG "Target quantity (item)
    EKET-MENGE "scheduled quantity (for each item & each schedule line)
    null

  • Withdrawal Qty exceed requirement Qty in production order

    Hi: guys
    In our system, withdrawal Qty can exceed requirement Qty for a production order, even we use planned GI. That means when we use MIGO/MB1A to process GI to reference production order, we can manually change withdrawal Qty. Even this Qty has exceed requirement Qty of production order, system also not give me any message.
    Anybody can tell me how to customize settings to limit this function, such as give me a message (error or warning), and ensure withdrawal Qty can not exceed requirement Qty.
    thank you.
    Henry

    Henry,
    I got what excatly the problem is in your case, the guy who executed has done it very cleverly.
    What must have happenned, is that in the change mode of the order, the component quantity was increased and then Issued. Latter on in the change mode of the order again the quantity was reduced.
    I think this is the excat case what you are having now in the system, the only clue left out for us is to check whether the manual change was perfomed or not. In the components overview scroll to the right side of the screen till you reach column with heading "ChngeProc.", here if the field value is "1" - then it is obvious that there was a manual change in qty for the component.
    The possible resolution to prevent in future is to Make the dynamic message "CN" - 752 as Error in the prodcution order change program. You need to work with your ABAP person for this.
    Hope I was able to get to the right problem and possible resolution.
    Regards,
    Prasobh

Maybe you are looking for

  • IPod with display color had an unknown error

    HI guys. Like I said.This is my iPod: http://img22.imageshack.us/img22/1987/img0085va.jpg and then.just this afternoon, it display an unknown error: http://img221.imageshack.us/img221/5381/img0084h.jpg sorry for low-quality image.it had a picture I t

  • Dynamic Filename for Reciever File Adapter

    Hi All, Can anyone answer to some of my quesries which are as follows a) . Currently Iu2019m working on an IDOC-to-File scenario in which I need to create zip file on file server by using a payload value.  I      search sdn and found a bean that can

  • Cannot sync my iphone from itunes with app got from apple store

    Hello everyone, I wonder if someone can help me... I dwonloaded a free app from the apple store. My computer is authorized to do thisbut it keep on saying that it's not authorized and in order to transfer the app to the iphone I have to authorize it.

  • Packaging a .bar file for the BlackBerry Tablet (Playbook) Simulator Using Command Line.

    Hi there, I've been trying to deploy one of my AIR apps on the BlackBerry Tablet (PlayBook) Simulator and and have run into a problem packaging the .bar file using the command line.  I started this off by reading the article at: http://www.adobe.com/

  • Popup on iPhone 60 minutes to reset code

    Hi there, I just got a message on my iphone (without doing anything) to change my "code" in 60 minutes. Attached a screenshot (in german). The translation: "Code request, you have to change your code in 60 minutes or less". Anyone has an idea what's