Hey Guys,
How do we transfer notification based on Work Center, Standard work manager does not updates main work center.
Requirement is to Transfer notification which are associated with work order when we transfer work order.
Please let us know how to transfer notification based on work center.
Thanks,
Madhur Kanungo

In Agentry you can trigger a Notification Change Transaction (Z_NotifTransfer) without a screen and update "WorkCenter" field on Notification Object. Please make sure you IsEdited = True and NeedsXmit = True along with the change to the Notification. This will update the notification object along with Work Order.
The other option is to extend the WO MDO Class and invoke BAPI_ALM_NOTIF_DATA_MODIFY  in the Transfer method.
thanks,
Chandra

Similar Messages

  • Email Sales order link from SAP Work Place

    Dear SAP Gurus,
    Well guys i have to mail the sales order link through the work place but its not working for the sales order. but its working for delivery order and billing document...so i want to know that why its not working?
    Regards,
    Mohsin

    Dear All,
    Can u please help me on this situation? I will be very thankful to u....
    Regards,
    Mohsin

  • PM work order tables in SAP

    Do anyone know which table in SAP contains the functional location and equipment info of an work order. I can find most of the info of an order in AUFK but missing the two fields mentioned above. Thanks

    Hello Robert,
    you can get the functional location from ILOA (first select field ILOAN form AFIH, then select the functional location from ILOA). Or use view CAUFV - as far as I remember, the functional location is part of CAUFV too.
    Best regards
    Stephan

  • Print out documents attached to a work order before Releasing a work order

    Team
    Requirement is given below. Need some advice.
    How to print out documents attached to a PM work order before the order is set to released status?
    Further the same documents have to be printed again after the order is released.
    Regards
    Sunil

    I think there is an OSS Note on this one - have a look there.
    There is a work-around where you do the following:
    - Enter IW32 and RELEASE the the order (but do not save)
    - Print out whatever you require
    - Exit the order without saving (therefore the RELEASE is not saved)
    Note: for one client we put a PRINT button on the Enhancement tab (user-exit IWO10018) for this purpose.
    Prometheus Group also provide a solution called Print Manager
    PeteA

  • Sending PM objects (work orders,notifications) to external address

    Hello,
    I have a question about sending PM object to external address type of recepient.
    When I select 'send object with note' and pick external address, I only get attached .txt file to be sent (with order number), not the actual order..Whereas the client is going to have virtually all services done by external vendors, who wouldn't have access to the system.. They aren't planning using Enterprise Portal
    Could anybody suggest how to accomplish that?
    Also, second portion of the question..
    Help says that the attachment of the object are not sent with it, ie. the recepient can only access them in attachment list in the object display.
    I was just wondering is there any enhancement that we can bypass it and enable it in email along with attached order
    Thanks in advance

    Thanks Peter,
    Actually, I couldnu2019t find that note..
    But I guess maybe I wasnu2019t clear enough, let me rephrase my question.
    So, they have a PM order PDF smart form and it doesnu2019t look a problem to mail that. Whereas,mailing the question is whether thereu2019s a way to send also attachments within that order which doesnu2019t look like being available by standard SAP. Again, I am not talking about attachments from whatever hard drive, which you can attach when sending via u2018send object with noteu2019), but enclosing whatever supportive docs with order.
    So, any ideas how to enable it?
    Thanks in advance

  • GRC 10 Work Inbox Notification or Universal Work List instead of SMTP

    Hi,
    I wanted to check with you all if there is a possibility to get SAP internal Work Inbox or UWL notification instead of outlook/SMTP notification.
    The scenarios this will be required for us are
    1. User ID details communication at the end of the request.
    2. Notification if access is approved/ rejected.
    3. Notification for Firefighter approved or rejected.
    4. BRM role approval notification
    Kindly let me know if we can pull the notification from Outlook/SMTP to internal SAP Mailbox.
    Regards,
    Prasad Chaudhari

    Hi Guru,
    If I am not wrong the items mentioned send notification to outlook/smtp and not work inbox. The work inbox will get request for approval and uar/sod review.
    Are you talking of some parameter/settings to change this behaviour?
    Thanks,
    Prasad Chaudhari

  • Creating new work order - error on %001

    Hi all,
    Creating a new work order from the SAP Work Manager 6.0 application should be a standard functionality,
    However, on the system of our client, this goes wrong.
    Upon creating a new work order, we get the error 'Enter a numerical operation number'.
    New objects get an ID that starts with 'LOCAL_xx:xx:xx', which is converted to %001.
    SAP should recognize this and convert this automatically to 0010, 0020, ...
    how come this does not happen?
    it works fine on our SAP system, our customer's system gives an error.
    Kind regards,
    Judith

    Have you done any enhancement to  standard  product "specifically create method of  Work  Order Class handler" . or the standard product functionality itself is not working ?
    I don't see any reason why it works in your system but not in customer system. Try to put break point in create method of Work order class handler and check what  values are passed  for operation  number before invoking Work  Order create BAPI. 
    Infact Work Manager product converts local numbers to incremental  sequential  numbers before invoking create BAPI for Work Order.
    BR,
    Manju - SAP CEG UX/Mobile

  • SAP Work Manager 6.0 - Creating notification on mobile device (customizing the default Start and End date)

    Dear all,
    When I create a notification in SAP Work Manager 6.0, the notification gets created in the back-end with Start Date equal to Current Date + 1 day and End Date equal to Current Date + 3 days.
    Can you advise where I can customize this behaviour, so that the Start Date is for example equal to the Current Date and End Date being 14 days in the future? Is this something that would need to be configured in Agentry Editor or within the ABAP stack?
    Many thanks for your support.
    Pavel
    Tags edited by: Michael Appleby

    Hi Jason,
    We went this route and identified the initial values, and tried to modify those.
    No impact though, as if those values are being overwritten elsewhere (whatever value we set, no change on the backend).
    Please see the attachments with screenshots of Agentry Editor.
    Many thanks.
    Pavel

  • Adding a new screen on SAP Work Manager 6.0

    Hi All;
    I'm working on customising the SAP Work Manager 6.0 application. One of the things that I have to do is add a new screen "Pool Management". I have been trying to achieve this via the Agentry Editor 3.7.2 with no luck. So the first thing that I did was to copy an existing screen, for example the TimesheetView screen set, hoping that there would be a duplicate screen similar to this, but this doesn't seem to be adding the duplicate screen when I test via the Agentry WPF client. Please kindly advise how I would go ahead with a requirement like this. Please see image below for the screen addition that I am working on. I would really appreciate your help in going about with this!
    Much appreciated!
    Sizo Ndlovu

    Sizo,
    Steve is correct.  Examine the main screenset.  Choose the platform, then copy an existing screen or add a new one.  Modify it as needed.  It will now display as a new tab on the client.
    Jason Latko - Senior Product Developer at SAP

  • Error while generating Work Order

    I have a problem while generating Work orders in SNC.
    I set the configuration as belows.
    <General setting for Work Order generation>
    1.Granularity -> Work Order per Purchase Order Item
    2.Create WOs with Report -> Check
    3.Publish Work Order Upon Creation and PO change -> check
    4.Send Work Order Information -> Upon Agreement and when a Phase Is Completed
    5.Send Production Progress Notification -> When a Phase Is Completed
    <Phase Structure>
    1.Comp. from SC Order -> Use SC Comp. as Input, Product and Co-Products as Output
    <Master Data Assignment>
    1.MD Used for WO -> Phase Structure
    2.Active -> Check
    When I use the program /SCA/WO_CREATE for generate Work Orders, Run time error occurs with below messages.
    Runtime Errors         OBJECTS_OBJREF_NOT_ASSIGNED
    Except.                CX_SY_REF_IS_INITIAL
    <Error analysis>
    The exception, which is assigned to class 'CX_SY_REF_IS_INITIAL', was not caught in
    procedure "GET_PIO_LCTYPE" "(METHOD)", nor was it propagated by a RAISING clause.
    Since the caller of the procedure could not have anticipated that the exception would occur, the current program is terminated.
    The reason for the exception is:
    You attempted to use a 'NULL' object reference (points to 'nothing')
    access a component (variable: "LS_NODEREF-R_NODE").
    An object reference must point to an object (an instance of a class)
    before it can be used to access components.
    Either the reference was never set or it was set to 'NULL' using the
    CLEAR statement.
    <Missing RAISING Clause in Interface>
    Program                                 /SCA/CL_WO_PHASE==============CP
    Include                                 /SCA/CL_WO_PHASE==============CM00V
    Row                                     1
    Module type                             (METHOD)
    Module Name                             GET_PIO_LCTYPE
    <Trigger Location of Exception>
    Program                                 /SCA/CL_WO_PHASE==============CP
    Include                                 /SCA/CL_WO_PHASE==============CM00V
    Row                                     45
    Module type                             (METHOD)
    Module Name                             GET_PIO_LCTYPE
    Please let me know what I have to do for this error.
    Thanks and Regards
    JT

    Hi JT
    Clearly the problem is with the method GET_PIO_LCTYPE of interface /SCA/CL_WO_PHASE
    Check whether note 1363834 should be implemented
    It could be because of some corrupted WO entries in database
    or some customizing entry it is expecting
    suggest you to debug the method and try to check what it is expecting
    Best Regards
    Vinod

  • So where we see the status of this work order request

    Hi All,
    I have submitted work order WO00034931 in SAP for a new vendor address but it seems my approver (Andre Vabre) never received it. In SAP, its status is “Submitted for Approval”.
    So where we see the status of this work order request
    Thanks,
    Kumar

    Hi
    You can make the price of a variant dependent on the characteristic values assigned (Pricing).You can use
    variant conditions to define surcharges and discounts for a variant
    Variant u2013Pricing steps
    Create condition record
    create a procedure where you enter the reference from the characteristic
    Assign the procedures to either the characteristic values
    configure the material in the sales order
    The net price for the material is displayed
    If a value that triggers a variant condition is selected when configuring a material in a sales order, the price of the material displayed under Net value is automatically increased or reduced.
    In addition, the Conditions pushbutton is displayed.
    On pressing this pushbutton,
    One can see which conditions have
    influenced the price.
    I tried to list you as much detail as possible. Hope that you will be able to resolve your issue
    Thanks

  • Work Order based Purchase Requisition

    Hello,
    We currently create purchase requisitions from work orders in our SAP system today. The issue we face is can we add additional lines to these purchase requisitions without updating the work order.
    We want to add the new line in the purchase requisition directly from transaction ME52N.

    Hi All,
       I have a situation in which i have to populate values for the fields in the 'custom data' tab in Purchase Requisition. But here I am not creating Purchase Requisition, instead when a Work Order(Plant Maintenance related) is created, Purchase Requisition automatically gets created. So, i want an exit which relates Work order with Purchase Requistion so that i could populate values to the fields in the 'Custom data' tab when i save the Work Order.

  • Why the "Work Orders" Menu Item is hided in 2005 Edtion?

    David:
      Thank you!
      The "Work Orders" menu item in 2004 edtion is must useful, But it be hided in 2005,Why ?
      and whether can I show it and use it?
      help me, please!
      thank you!

    Fu
    in the SAP help the following is written:
    Work Order Window
    Definition
    The Work Order Window, from earlier versions of SAPBusiness One, has been replaced by the Production Oder. However, if you had open Work Orders when upgrading, the old Work Orders can still be viewed.
    When a Production Order is open, click on the base document icon  on the toolbar to display the Work Order on which it is based.
    i recommend you to use F1 in your sbo client
    and search for "work orders"
    than select title "Work Order Window" and there is everything in Detail !
    regards
    David

  • Using a hierarchy but also showing work orders that are not in hierarchy

    good morning bi people,
    i have a requirement to show data from a hierarchy which includes Operation and Maintenance information. for example it has an account broken into labour/material/trucking and below this is the pm acivity type and secondary cost element (concatenated). this hierarchy is a manually created hierarchy that is uploaded to BW and is not in ECC. The users do not want to see the concatenated field at the end of the hierarchy, but instead, want to see the Work Orders that have the PM activity types.
    At the present time, we have the report using the hierarchy but we need the work orders to replace the pm activity type/secondary cost element concatenated field. the work order field is a free characteristic and when we drag in the work order in analyzer, it works correctly.
    1) is this possible to use the hierarchy and somehow map the work order field to the end of the hierarchy within crystal?
    2) do you have a suggestion to change the hierarchy, without being a manual nightmare?
    all conversations are welcome.
    Erik

    Good Day Ingo,
    i have created a word document with screen shots of the hierarchy from BW, a screen shot of the BEx showing the free characteristic of Maintenance Order and a screen shot of the crystal report with the PM Activity type concatenated to the Cost Element. Once again, we do not wish to see the concatenated field, but rather see the Maintenance orders that have a PM Activity type the same as the concatenated field. 
    here is the link.
    https://docs.google.com/viewer?a=v&pid=explorer&chrome=true&srcid=0B1j5hXTptfntYWI1MDUzNGEtY2MxNy00YmMzLWJjZjEtZDA4OGZiYmMyNzFh&hl=en&authkey=CKq4xcgJ
    thanks Ingo,
    Erik

  • Actual hours done against a work order for a Work Center by non-maintenance

    Hi All,
    I have below question with respect to work center.
    -If there is this actual work hours done on a work order by non- maintenance personnel for a certain work center and same is not reflecting under operation tab of work order, then where & how this hours (done by non- maintenance personnel) for a work order is maintained for that work center?.
    -In which database table these hours done by non- maintenance personnel for a work order is stored by work center wise.?
    Thanks

    Have a look at the document flow button in the order header.
    The confirmation data resides in table AFRU
    PeteA

Maybe you are looking for

  • Issue in change incidence via email.

    Hello All, I have configured a rule in SO50 to process an incoming email. I have maintained my sap user ID for testing purpose in the Receipent address column. In the rule I have also maintained the class which is used to change the status of the inc

  • Flash/Active X fix included in 8.02

    Hi there, First off, thanks Macromedia..... oops sorry, I mean Adobe..... still getting use to that =) Anyhow, thanks for creating an easy to apply fix for the Microsoft none security active x patch thing..!!! Is there a way of applying it to a whole

  • Back to back envelope adjustment

    Possible newbie question: If I have a single track with back-to-back audio clips (like broll SOT) how can I quickly adjust the volume of each clip using the volume envelope without adding 2 keyframes at each edit point? I was told that with ProTools

  • Language DA ENG (int)

    I was earlier told that I only had to chose language in preferences for apps in my CC to chance. That didn't do it. What can I do? I don't want the apps in Danish, I'm used to work in International ENG. Please help!

  • Aggreated Invoice Statistical posting

    Hi Experts, This question is related to Aggregated invoice posting in a deregulated scenario. People familiar with this scenario will know that, Individual invoices are first posted to end customer contract account and then aggregated posting is made