Wrong Schedule line getting created

Hi Friends,
When I am creating an order system is creating the schedule for the next day and not for the same day. I have material in stock, in my sales order the lead time is ZERO but still system is creating schedule for the next day.
Can someone please tell what could be the problem and the possible solution.
Regards,
Wasim

Hello Wasim,
- In TCode MM02, Check Scheduling in MRP2 Tab of Material master (if MRP is active.)
- In Tcode OVZ9 - AvC control, for your Availability check maintain (eg. 02) in material & Checking Rule:A-SD order.
Whether Check availability without replenishment lead time is unchecked, as this Indicates whether, during the availability check, the system checks the replenishment lead time. So, Items for which the delivery date falls within the replenishment lead time, but for which there is no inventory, are confirmed for delivery after the replenishment lead time. In the case of items for which the delivery date falls after the end of the replenishment lead time, the system assumes that everything can be confirmed.
Thanks & Regards
JP

Similar Messages

  • Schedule line getting created for material whose stocks are maintained

    Hi Friends,
    I am having an unusual problem of schedule line getting created for material whose stocks are there in the system. I have created an SO for some material, and all the material is having sufficient qty in the system but still the system is generating schedule line.
    Can someone please advice what could be the problem and the solution to it.
    Regards,
    Wasim.

    Hello Wasim,
    - In TCode MM02, Check Scheduling in MRP2 Tab of Material master (if MRP is active.)
    - In Tcode OVZ9 - AvC control, for your Availability check maintain (eg. 02) in material & Checking Rule:A-SD order.
    Whether Check availability without replenishment lead time is unchecked, as this Indicates whether, during the availability check, the system checks the replenishment lead time. So, Items for which the delivery date falls within the replenishment lead time, but for which there is no inventory, are confirmed for delivery after the replenishment lead time. In the case of items for which the delivery date falls after the end of the replenishment lead time, the system assumes that everything can be confirmed.
    Thanks & Regards
    JP

  • Schedule lines getting created even when material is there in stock

    Hi Friends,
    I have configured a normal material and have sufficient stock also, but when I am creating a sakes order the system is generating schedule line for the material even when I have stocks.
    Can someone please advice what could be the problem and the possible solution.
    Regards,
    Wasim.

    Dear wasimuddin.sayed,
    When you are creating sales order definitely system will create the schedule line for Confirm delivery date and delivery QTY.
    that is the functionality of schedule line.
    now if you don't have stock at plant level on the same date then as per availability configuration system will confirm the another schedule line on which confirm delivery date and  qty will be available.
    if not satisfy the answer request you to elaborate the question in detail.
    Best Regards
    Hanumant

  • Schedule line getting created even when material is in stock

    Hi Friends,
    I have configured a normal material and have sufficient stock also, but when I am creating a sales order the system is generating schedule line for the material even when I have stocks.
    Can someone please advice what could be the problem and the possible solution.
    Regards,
    Wasim.

    Dear wasimuddin.sayed,
    When you are creating sales order definitely system will create the schedule line for Confirm delivery date and delivery QTY.
    that is the functionality of schedule line.
    now if you don't have stock at plant level on the same date then as per availability configuration system will confirm the another schedule line on which confirm delivery date and  qty will be available.
    if not satisfy the answer request you to elaborate the question in detail.
    Best Regards
    Hanumant

  • Schedule Lines not created from MRP

    Hi !!
    I have a finished product ""111-2523-64"" and in its BOM i have a semifinished product ""111-2523-64-010"" produced(Inhouse)& three raw materials .
    For the Raw Materials I have made the scheduling agreement & source list with indicator ("2"" create schedule lines automatically""
    Problem -: Now when I run the MRP using T-Code MD02 the system is planning the finished & semifinished product 
    *but no schedule lines are created for the raw materials.*
    Please Guide , Itz very urgent.
    Regards
    Rahul Bhardwaj
    9909986406

    Dear Rahul,
    When u r running MRP maintain '3' for Delivery Schedules Field under MRP Control Parameters ( T Code MD02). Sheduling Agreement should be valid. If there is sufficient stock on hand compared with the requirement then system will not create any Schedule Lines. In material master of raw Materials on MRP2 view Procurement Type should be Maintained as 'F'. If u have maintained 'E' or 'X' then MRP run will not create schedule lines.
    Regards
    Sunil Kumar

  • Schedule Lines getting combined in a sales order

    Can some body tell me that is this a standard functionality of SAP that old schedule lines for which deliveries are created on previous weeks roll upto single schedule lines after certain time. I have a sales order for which different number of quantities got confirmed at different time and got delivered at various time in a span of 4 months but there is only one schedule line for them. Can someone help me in explaining this behaviour.

    Hi Nithin,
    When the the delivery is created for the full quantity of the schedule line,  these schedule line is now irrelevent in the sales order The delivery now holds the requirement. As the delivery quantitiy is not fixed to any schedule line, the confirmed qty and
    delivered qty gets moved to the requested schedule line during rescheduling. This is standard behaviour.
    This behaviou can be changed by using modificaton note 833272. This notes changes the standard behaviour so that the fully referenced schedule lines are scheduled according to the rules defined in Customizing.
    Also , Please review note 547508 point 2 for information.
    Thanks
    Amber

  • Schedule line getting confirmed when Ordered Quanity is greater than stock.

    Hi Sap Gurus,
    We have an issue in one of the sales scenario.
    In one of the sales orders the ordered quanity is purposely maintained greater than the stock at respective storage location(batch managed).
    In this case the schedule line should not get confirmed and it should not allow delivery document creation.
    But in the sales order the schedule lines are geeting confirmed and even the delivery document is getting created with picking request completion.
    Could you please help to understand :
    1.  why the schedule lines are getting confirmed when ordered quantity > Inventory?
    2. How do I stop delivery document creaton in this scenario?
    Looking for a quick response.
    Thanks in advance,
    Bhaskar

    Hello Bhaskar,
    Is Availability Check in your system considering Replenishment Lead time, if yes, then this is possible.
    Check this IMG Link:
    IMG - Sales and Distribution - Basic Functions - Availability Check and Transfer of Requirements - Availability Check with ATP Logic or Against Planning - Carry Out Control For Availability Check
    Here check the RLT settings.
    Also check settings under In/Outward Movements, where things like include Purchase Order can lead to confirmation of stock in Sales Order, despite physical inventory being present.
    Hope this helps,
    Thanks,
    Jignesh Mehta

  • JIT schedule lines not created automatically

    Hello All,
    I'm not able to get the JIT schedule lines automatically for some of the scheduling agreements. I'm familiar with the SA process and schedule lines, but never came across JIT and SA release. Can anybody help me to provide possible reasons of not getting the JIT schedule lines created for SA.
    Thanks,
    Amit

    Hi,
    Check following points -
    1) Scheduling agreement is released.
    2) In Source list of the material, the Scheduling Agreement & the relevant line item is mentioned. In the MRP area the option '2 - Scheduling Agreement delivery schedule generated automatically.
    3) If required quota arrangement is also maintained.
    Regards,
    Prashant

  • Automatic schedule lines not creating after MD03

    HI Gurus,
    When I am running MD03 system is creating Pur. Requisitions instead of Schedule lines
    I am running with
    NETCH
    2
    3
    1
    1
    1
    29102011
    Data maintained
    1.Material master /vendor master Auto po ticked (MRP type VB ROP 500 ,Safety stock 600, current stock 200)
    2.Sch. Agreement created with LP (validity period, Qty ok)
    3.Pur. Info rec maintained for vendor material for the plant.
    4.Source list maintained with Vendor,scheduling agreement no ,item no, MRP indicator 2 Fixed vendor ticked
    Now after Running MD03
    Pur. Req created for 400 qty
    but when I click on Procurement proposal manually I can select Del. Schedule and create
    but system is asking Agreement no. item,qty etc (I already maintained Source list system is asking again )
    Then why not system creating automatically..
    Please help..
    Thanks in advance

    Thanks  Jürgen,
    It was a problem of Date ,validity period of the SA.
    which I sort out any way thank you. for your input

  • Schedule lines are creating problem in PO-storage location in SAP

    Hello Everyone,
    We are using SRM 5.0 ECS.
    We create the PO in SRM and send it to R/3 backbend system. When we maintain the schedule line in PO(SRM side),the backbend system is not maintaining the correct storage location from purchase req. And when we do not maintain the schedule line in PO(SRM side), the backbend system maintain the correct storage location from purchase req.
    So here what can be the reason for this problem?
    Regards,
    Khushbu.

    Please I need help on this.

  • Order schedule lines not created using BAPI_SALESORDER_CREATEFROMDAT2

    Hi experts,
      I am creating sales order using BAPI_SALESORDER_CREATEFROMDAT2. I want to update the Order quantity in VBAP-KWMENG.I got the information from SDN when including the Schedule line in BAPI 'BAPI_SALESORDER_CREATEFROMDAT2  '.
      I tried by using Update flag = 'I'.I am not able to update, what are the values to be passed and how to update the field.
    Is there any other way..Please suggest me..
    Thanks&Regards,
    Karthik.

    Hi, In the BAPI if you look at the tables parameter you will find ORDER_ITEMS_IN and ORDER_ITEMS_INX as well as ORDER_SCHEDULES_IN and ORDER_SCHEDULES_INX. To update KWMENG you will have to pass that value to ORDER_ITEMS_IN-TARGET_QTY and update the same in the table ORDER_ITEMS_INX (ORDER_ITEMS_INX-TARGET_QTY) with 'X'.
    For updating schedule line go for ORDER_SCHEDULES_IN-SCHED_LINE and update X for the same in ORDER_SCHEDULES_INX.
    Try looking into the following code, I am filling in both the Item data as well as the Schedule line data.
      loop at t_mdata into fs_mdata.
        fs_item-itm_number  = fs_mdata-posnr.
        fs_itemx-itm_number = c_flag.
        fs_item-material    = fs_mdata-matnr.
        fs_itemx-material   = c_flag.
        fs_item-target_qty  = fs_mdata-kwmeng.
        fs_itemx-target_qty = c_flag.
        fs_item-item_categ  = fs_mdata-pstyv.
        fs_itemx-item_categ = c_flag.
        fs_itemx-updateflag = c_flag.
          APPEND fs_item TO t_item.
          APPEND fs_itemx TO t_itemx.
        fs_sline-ITM_NUMBER  = fs_mdata-posnr.
        fs_slinex-ITM_NUMBER = c_flag.
        fs_sline-SCHED_LINE  = c_sline.
        fs_slinex-SCHED_LINE = c_flag.
        fs_sline-REQ_QTY     = fs_mdata-kwmeng.
        fs_slinex-REQ_QTY    = c_flag.
          APPEND fs_sline TO t_sline.
          APPEND fs_slinex TO t_slinex.
      endloop.                             " Loop t_mdata
    c_flag contains 'X'.
    fs_item is of structure ORDER_ITEMS_IN.
    fs_sline is of structure ORDER_SCHEDULES_IN.

  • Sales Order Schedule Lines getting updated

    Hi,
    In my system when I am changing the delivery date of  'AB' confirmation in the Purchase order Item level confirmations, the corresponding  Sales Order' schedule line is also getting updated with the delivery date.
    So, my question is is this a standard SAP functionality or this fuctionality has been implemented through BADI, Exits etc.
    Regards,
    Rachit

    Rachit,
    This is standard SAP behavior. In 3rd party sale process, the changes done to PO (qty, dates) are updated automatically in the sales order.
    TW

  • Converting contract to sales order does not auto create schedule lines

    Hi
    When I convert quotation to sales order, then schedule lines get auto created.
    But when I convert contract to sales order, then schedule lines don't be auto created. Instead, a confirmation screen for proposal delivery date pops up for every line item in the sales order.
    Is there any suggestion how can I solve my problem ?
    Thanks..

    Hi,
    In standard SD module, system checks availability for each line item, gives you popup screen of confirmation.
    If you don't want availability or popuscreen of confirmation,then
    Go to VOV6 >>> Select schedule line which you are using in sales order for line item >>> Remove tick mark of availability check.
    Else
    Remove availability check rule from material master >>> Under tab Sales : ganral/plant
    kapil

  • Donot want to fix the schedule lines at an Early date even P.O is the creat

    Hi ,
      If a material is sourced via a Scheduling Agreement, then MRP automatically creates schedule lines for this to meet MRP requirements.
    However, if a separate PO is raised for the same material (irrespective of the supplier) at a date after one or more of the scheduling agreement schedule lines, MRP creates a message to reschedule in the PO in front of the schedule lines even if this is known to not be possible. the result is that the schedule lines for standard supply are not put in early enough.
       And We don't  want to fix the schedule lines in a t an early date to over come this.Is there any settings for the same.

    Hello,
    If you want to control MRP messages for rescheduling you can make settings in tcode : OMDW either at plant level or MRP group level.
    You can introduce Tolerance value forward & Tolerance value for displacemt in No. of days here.
    If system finds requiremnts within the tolerance no of days it will not create MRP Exception messages. This way you can avoid unwanted messages.
    Thanks,
    Ram

  • MRP not creating some schedule lines

    Hello Gurus,
    I hava peculiar issue for a Material.which has got dependent requirement from a header materila.
    For some reason they want to run MD03 for this partnumber "ABC" . Materila is x type. It has got Valid SA, Valid SOurcelist,Valid QA.It has rounding value of 60, MRP type PD and EX .Not plannig teimw fence RLT is zero, GR time is 1 days .
    In MD)4 below u can observe SChedule line is created except for feb 2nd, 03rd,o6, 7th.
    QUESTION-1 :In below MD04 report no schedule lines were created for Dep req of feb 2nd, 03rd,o6, 7th.
    Question 2:- even when STock is minus 6717 , the schedule line generated is for just 1400 etc
    MD04 for "ABC" in Plant
    02/01/2012     SafeSt     Safety stock               480.000-     47.000-
    10/17/2011     OI-SL     0451404013/00030          6.000              41.000-
    01/25/2012     DepReq     28299890               4.000-             45.000-
    01/31/2012     DepReq     28299889               512.000-     557.000-
    02/01/2012     ShipNt     0197672394/0550397074          540.000      17.000-
    02/01/2012     DepReq     28299889               600.000-     617.000-
    02/02/2012     ShipNt     0197676022/0550397074          900.000      283.000
    02/02/2012     DepReq     28299889               300.000-     17.000-
    02/03/2012     DepReq     28299889               3,300.000-     3,317.000-
    02/06/2012     DepReq     28299889               1,400.000-     4,717.000-
    02/07/2012     DepReq     28299889               1,400.000-     6,117.000-
    02/08/2012     SchLne     0550397074/00010          1,320.000      4,797.000-
    02/08/2012     DepReq     28299889               1,400.000-     6,197.000-
    02/09/2012     SchLne     0550397074/00010          1,380.000      4,817.000-
    02/09/2012     DepReq     28299889               1,400.000-     6,217.000-
    02/10/2012     SchLne     0550397074/00010          1,380.000      4,837.000-
    02/10/2012     DepReq     28299889               1,400.000-     6,237.000-
    02/13/2012     SchLne     0550397074/00010          1,740.000      4,497.000-
    GURUS PLEASE ADVICE
    Edited by: HKR on Feb 1, 2012 4:43 PM

    Hello
    Please check if there is any rescheduling exception messages near the fixed planning elements.
    Notes 71877 and 25388 provides more details about the rescheduling check during the MRP run.
    BR
    Caetano
    Edited by: Caetano Almeida on Feb 1, 2012 12:33 PM