2LIS_03_UM setup

Dear Gurus,
I have already setup the tables for 2LIS_03_BX and 2LIS_03_BF, uploaded them in the cube 0IC_C03 and compressed suitably.
For filling the setup table for 2LIS_03_UM, when I execute OLIZBW, company code is mandatory. As I have 6 companies, I gave * for company code but no records get picked up.
If I decide to do 2LIS_03_UM setup 6 times for 6 companies, do I have to make the table MC03UM0SETUP blank 6 times? Do I have to do INITupload in the cube 6 times and then DELTA also 6 times?
If I do "deletion of setup data" (Tx LBWG) 6 times, will it have any side effect on the 2LIS_03_BX and 2LIS_03_BF which have already been setup and uploaded in the cube.
Kindly advise.
Regards
Lalit Kumar Jain

Iam filling the setup tables for 2LIS_03_UM for one company code. And when iam checking the setup tables after that ,iam not able to find any rows in it.
I checked RSA3 also. No data...Please suggest what to do.
I have already loaded 2LIS_03_BX and 2LIS_03_BF into cube and compressed them as per the setting required.Now iam trying to load 2LIS_03_UM also..

Similar Messages

  • 2LIS_03_UM setup required field

    Hi, Guru, I am facing a very strange issue here. When I am in R3 trying to fill the setup table for 2LIS_03_UM, it requires that a value in company code to be provided. We have more than 100 company codes, I really don't want to run setup table by company code 100 times. Here is the error msg if I don't provide a value for the company code. I tried with '*' and hope that it will include all values but that didn't work.
    Fill in all required entry fields
    Message no. 00055
    Diagnosis
    You have attempted to update data or start an action. However, not all required information was specified.
    System Response
    The system could not execute the action.
    Procedure
    Enter all required information. Fields in which you must enter data are prefilled with a checkmark or question mark ("?") by the system. If the current screen contains tabs, check all tabs to make sure you have filled in all required fields. Then restart the action.
    Thanks in advance
    Chimei

    No, the company code is a single value selection. I can put ranges for document number, fiscal year or posting date but not company code.
    I am not able to post a screen shot but here is the basic layout of the screen. you can see that there is no "to" for the company code below and it is required which is the issue I think. The other fields are all optional.
    Archiving Run
    Company Code
    Accounting Document                                to
    Fiscal Year                                        to
    Posting Date                                       to
    Name of Run
    Termination Date                05/06/2011
    Termination Time                16:36:47
    Chimei

  • 2lis_03_um setup tables issue

    Hi experts,
    we have taken downtime to fill the setup tables for inventory.
    MCNB - 2lis_03_bx
    OLI1BW - 2lis_03_bf
    OLIZBW - 2lis_03_um
    we have the company codes 1100,1200,1300,2000,2800 at the moment in ECC.
    but we will have more company codes coming up in next 2 months.
    here my doubt is if we fill the setup tables for the above company codes for material revaluation (OLIZBW), do we need to take downtime again to fill for the upcoming company codes??
    OR if u know the upcoming company codes then we can fill the setup tables for those company codes also, even there is no data once the new company codes starts the deltas will be coming into BW, instead of taking downtime again and fill the setup tables for the new company codes?
    Please clarify these issues.
    Regards
    venuscm

    Filling setup table wouldn't be required for the upcoming company codes..
    Since delta captures new and changed records, the new records for the upcoming company codes will be captured in the delta loads, hence there is no need to fill up setup tables again for the upcoming company codes.
    The only thing you have to do this either dont give any selection for company code during initialization or include the upcoming company codes also in the selection if required during initialization.
    --- Thanks...

  • 2lis_03_um setup table

    Dear all
    I am currently working on stock, for that data sources BX, Bf are successfully loaded into the cube 0IC_C03 . but i now am trying ti fill the setup tables for UM data source  it is throwing error "fill in all required  fields".
    I have given "name of run, termination date and time, and selected rerun check box". Please some one help me if i miss anything?
    Pl confirm is it mandatory to give "document data restriction " like company code, year ....?
    Thanks
    Bhaskar

    Hi Bhaskar,
    For any screen where you see below (yellow)highlighted tick mark then it is a mandatory field on the SAP screen and you have to provide a input criteria.
    So in case of UM datasource you have to provide company code for setup tables.
    Thanks
    Amit

  • Fill 2lis_03_bx and 2lis_03_um extractor

    hey all
    what is the tcode to fill 2lis_03_bx and 2lis_03_um extractors ?
    thanks
    Laura.

    for 2lis_03_bx
    Setup Tcode is MCNB
    For 2lis_03_um
    Setup is Tcode is 0lizbw or mcbnerp
    Thanks
    Vj

  • Error when running setup table for 2LIS_03_UM

    Hi experts,
    When running the setup table for 2LIS_03_UM, we got the error message "Plant FP01 does not exist." Any suggestions on how we can fix this?
    Thanks,
    Donna

    check if this plant has been maintained in source system or not. If not, ask the concerned team to maintain it.
    Another way may be to allow error records which should ignore errornous records and rest should be filled in setup table.
    Regards,
    Gaurav

  • Why the duration for performing setup(2LIS_03_UM) is too long?

    Hello Expert,
    I am loading the 03 setup table now.
    For the 2LIS_03_BF, the duration is about 40 minutes and the data record in MC03BF0SETUP is about 15000.
    However, for the 2LIS_03_UM, it has run for about 1.5 hours and the data record in MC03UM0SETUP is only 580. Now the thread is still running.
    Do anyone know why?
    BTW, I have run the setup for UM twice yesterday. Because the permitted time for the user is used up, the operation was terminated.
    Thanks
    F-B-I

    Hi......
    Dont' delete entries of Delta Queue.
    When you do the next delta, the previous to previous request's delta records meant for repeatition are automatically deleted i.e confirmed.
    The delta entries are stored in delta q inspite of deltas being pulled in Bw, just in case if delta repeatition is needed.
    Also when you carry out a repeatition request for delta in Bw for the same delta(in case of failures etc), these get pulled in BW.
    Also don't delete queue in SMQ1......Deleting entries in the queue (be it outbound or inbound) is not a good idea. This will either lead to data loss or data inconsistency.
    As per my knowledge ..........I don't think we need to delete it...
    Regards,
    Debjani........

  • Problems with filling of Setup table for 2LIS_03_UM

    I am not able to fill up this table. I mean its not getting filled thorugh TCode OLIZBW.
    Setup table for 2LIS_03_BF is getting filled up though.
    Can anyone foresee what can be the reason.
    Thanks PB

    Nope I am not. But the problem I have posted in my last note that i was getting -ve stock values which was resolved when i loaded the data with infosource 2LIS_03_UM in development. when I am testing it in QA I am not getting dat in this extractor.
    I had a chat with MM Functional Consultant , he said I probably wont get this data.
    Now I am not sure how will I be able to resolve the problem.
    Regards
    PB

  • 2LIS_03_UM - FULL LOAD VIA SETUP TABLE NOT EQUAL TO DELTA

    Hello,
    I try to load stock data with 2LIS_03_UM.
    When I extract data using setup table and full load I don't get the same records as I get with delta load. Although the key figures values are the same, the documents numbers are different. Most documents from delta load are ML (material ledger) documents while documents from full load (via setup table) are mainly FI documents.
    What can be the reason? How can I fix it?
    Thank you,
    Hadar

    Hi,
    Delta load extracts data from Delta Queue based on your update mode selected in LBWE.
    Full Load or Init load extracts data from Setup tables, here if you are extracting data from setup tables ? did you fill the setup tables now or not after deleting the existing data of the setup tables?
    are you getting same values when compare to R/3 and BW data for some document numbers?

  • Filling setup tables for 2lis_03_um

    hi
    i am trying to fill setup tables for um. its nott allowing me, i gave name of run and date and time .
    its asking Archiving Run  . i am trying to give or f4 its not allowing me?
    please let me know

    Hi Suneel........
    Check this thread by Roberto Negro......
    Archive run.
    Hope this helps.....
    Regards,
    Debjani.....

  • G/L Account is Blank in 2LIS_03_UM

    Dear ALL,
    Good Morning,
    Datasource 2LIS_03_UM is not populating the G/L Account (SAKTO). Even when I fill the setup table, the field SAKTO is blank.
    Could anyone suggest me from which table this field will be populated because we have requirement to get the G/L Account from BSEG table against the document no.
    Is there any way to get the data other than the datasource enhancement.
    Thanks in advance.
    Regards,
    Abhishek Jain

    Hi,
    Make use of table - "T030" where you can get the GL accounts based on Valuation class.
    From UM datasource, you would be getting Material & Valuation class..
    In material master, Valuation class is maintained for each material. Valuation class & GL account combination is maintained in "T030".
    By this you can link up the GL accounts with revaluation data at BW side as well.
    Hope it helps.
    -- KRPK

  • Setup tables Inventory Management

    Hi,
    I want to fill setup table for BX via tcode MCNB (in R/3).
    Can I start with the setup table for BF using tcode OLI1BW parallel or I have to wait till the job RMCBINIT_BW (tcode MCNB)
    is finished!
    Same question for UM: Can I start the setup table for UM (tcode OLIZBW) parallel with the job RMCBNEUA (tcode OLI1BW)
    or I have to wait till the job RMCBNEUA is finished!
    Is there any possibilty to enter more company codes for the setup table for UM (tcode OLIZBW) as we have 120 company codes
    Or I have to plan the job for each company code separtely.
    Moreover I will load data (first opening balance, movement, revalaution) into BW when the setup tables are filled on R/3 side.
    Is it ok?
    Thanks for the answer.

    Hello Moha,
    Yes, Venkat, is right.
    This is the order
    2LIS_03_BX3 Material stock (Parallel)
    2LIS_03_BF Material movements (Parallel or with UM)
    2LIS_03_UM Revaluations
    Please see this Inventory Document
    [How to Handle Inventory Management Scenarios in BW (NW2004)|https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/f83be790-0201-0010-4fb0-98bd7c01e328]
    [Non-Cumulative Values / Stock Handling|https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/93ed1695-0501-0010-b7a9-d4cc4ef26d31]
    Thanks
    Chandran

  • 2LIS_03_UM Datasource Material  belonging to Stock Category 'E' Issue.

    Hi,
    We wanted to use 2LIS_03_UM Datasource  for Sales order Stock Valuation as we want these valuations in Daily level at sales order item level .  But we are having a problem in Extracting  Materials with Stock Category(BSTTYP) 'E'.  I have selected fileds  LBWE MBLNR, KDAUF, KDPOS from LBWE pool and brought them to the Extractor .  After filling the setup table in OLIZBW with the Company code and posting date. In RSA 3 i am getting data for the company code and posting date. But the Fields BSTAUS and BSTTYP with values 'V" or null.   I just came across in one of the forums we have to do some config in
    include LMCB1F20 (routine STA_VERAENDERUNG).
    And joins on tables MSEG, T156C, T156M
    cosidering fields ->
    BUSTM, ZUSTD, CNT02, LBBSA, SOBKZ
    Can i have some more details on how to do this in R/3.
    Thanks

    Hi Arun,
    Valuated Stock with unrestricted use is a Non - Cumulative key figure and you dont have to add this field to this data source or for that matter to any data source. You can simply include this info object directly in the Inventory Cube and write the Update routine accordingly.
    Before writing the routine you must ask your finctional guys to provide you with the classification of the material movements. I mean are there any Z Movements for this key figure? What are the process keys for this? etc...
    This will help you in writing the routine for this key figure.
    Hope it helps...

  • 2lis_03_bf and 2lis_03_um Reinitialization precautions?

    hi experts,
    My client is Using 0IC_C03 Inventory Cube since December 2009. they have generated Opening balance at that time and initialized the 2lis_03_bf and 2lis_03_um data sources and doing deltas.
    but the problem is that they have deleted the Init requests from the Target cube and they wanted to analyze the data from Day 1 which is December 2009. so client wanted to delete the complete data from cube and reinitialization has to be done.
    My questions are
    1          is do i need to Generate the Opening Balance again for 2lis_03_bx??? or not required? if required what are the Selection Criteria i have give while filling setup tables in MCNB TCODE.
    2          2lis_03_bf reinitialization Steps like i will extract the Initialize with Data transfer, what are the steps i need to perform after DTP Extraction into 0IC_C03 cube? tell me exactly how to take care of Marker Update.
    3         2lis_03_UM reinitialization Steps like i will extract the Initialize with Data transfer, what are the steps i need to perform after DTP Extraction into 0IC_C03 cube?
    please give ur inputs..
    regards
    venuscm

    Hi Sachin,
    Thanks for very useful information regarding Initialization.
    2lis_03_bx -  ECC SIDE - Do we need to select the Transfer Structure (2lis_03_bx) as well in MCNB and which Radio Buttons i have to select (only valuated stocks, All Stocks (Including non_valut), and what about Zero stock to be transferred do i need to select ?), and what about Time of termination how much i have to give??
    for example -  i am filling up setup tables on 01-10-2010 at 10.00.00 how much time i have to give at Time of Termination??
    BW SIDE - Client has generated the Opening Balance, but when i look at the PSA Data it shows that no Data, but requests are
    there.
    Just now i tried in Quality System - There are 30596 records in RSA3, and after DTP extraction in the Cube there are about 50000 records and there are routines in the Transformations?? will it any problem??
    2lis_03_bf - ECC Side - How Much Time can i give if i am filling up setup tables on 01-10-2010 at 10.00.00 how much time i have to give at Time of Termination?? AND can i fill the setup tables paralally (MCNB,OLI1BW,OLIZBW) ???
    BW SIDE - Once i have extracted the Data by initialization with data transfer and DTP to 0IC_C03 Cube, for next Delta Requests do i need to select the check Box (NO MARKER UPDATE)??
    2lis_03_um ECC SIDE - regarding 2lis_03_um do we need to ask the Client for Company codes??? I think we cannot give range.How Much Time can i give if i am filling up setup tables on 01-10-2010 at 10.00.00 how much time i have to give at Time of Termination??
    BW SIDE - Once i have extracted the Data by initialization with data transfer and DTP to 0IC_C03 Cube, for next Delta Requests do i need to select the check Box (NO MARKER UPDATE)??
    Please specify clearly.
    regards
    venuscm
    Edited by: venugopal vadlamudi on Sep 30, 2010 10:15 AM

  • 2lis_03_um can not be filled

    Hi, gurus here.
    I am filling the setup table of 2lis_03_um in AIME ECC PRD. I've finished the filling job of 2LIS_03_BF and it's OK.
    But the filling job of 2lis_03_um can not be started, I checked it in SM50, nothing happened.
    The info of status is either "Background job was sheduled for program RMCBNERP" or "DataSource 2LIS_03_UM contains data still to be transferred", the results are same, nothing happened.
    I've checked in SM13, no error data in it.
    No delta queue in RSA7.
    What's wrong?

    Hi
    Have you deleted the setup tables before you start filling it.
    Have you used tcode OLIZBW to fill the setup tables?
    check out the below ones
    How to fill up set up tables for 2lis_03_UM and BF?
    http://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/906b837a-0d54-2c10-08b8-bde70337547e?QuickLink=index&overridelayout=true
    Regards,
    Venkatesh

Maybe you are looking for

  • Can an editor and I work on the same project, at the same time in PPCC?

    I'm trying to figure out if two people can edit a project in live time... I'm currently struggling with the 20gb cloud limit for my projects and I think I'm just going to bring an in house editor into the mix.  Can he and I edit the same project from

  • Additions/Changes I would like to see in V2 of Edge Animate

    A way to "center" text under the Position and Size panel. A way to properly format text. I can't make a bulleted list properly, no way to indent an extra line. Folders! I want to be able to orginize my timeline area (like Flash did). The ablility to

  • How to Upload a file in a Batch Mode ?

    Hi, I want to upload a Comma separated value File via RFC to a BW system. The scenario is the following: From a Portal server i call the BAPI using JC0/JCA. The problem is that GUI_UPLOAD does not support a BATCH job. At least i get a error when call

  • Does 785GM-E51 DVI support dual link?

    I am considering buying the 785GM-E51 motherboard which comes with a DVI port (as well as HDMI and VGA of course). Will the DVI support dual link?  If so, what is the maximum resolution I could have on the two monitors (say, at 60 Hz with high colour

  • How to handle Error Handling In Mediator.

    Hi guys, Accually my reqirement is need to handle Error exception in Mediator. I am new for Meditor. we read source file through Mediator and route the data to Database Table in betwen need to handle Error Handling...What type of Fault handling we ca