Acual Cost of Prodcution

Hi ,
This is regarding Actual cost calculation.
I have three material X - RAW MATERIAL, Y-SEMIFINISH MATERIAL, Z-FINISH MATERIAL.
X=Stand. price Rs.10
Processing cost Rs.10
Y= Stand. price Rs.25
Processing cost Rs.10
When i produce Y , Cost will be = 10 (X) + 10(processcost)= 20 RS.
So actual Price during prodcution is 20 , but it taking 25 (Standerd price of Y) in next step for production of Z (25+10=35 Rs.)
So its coming wrong picture...it should take 20 Rs. What i have to do for getting actual cost after prodcution.
Whre i can see this comparision ???
Please Suggest
Regards
DHIRAJ

Hi,
Please check with below report
KKBC_ORD
Check with individual cost element for proceesing cost & raw material Cost.
Maybe ur Actual production cost will be  higher than the Planend cost
Regards
Pradeep

Similar Messages

  • Actual Cost of Prodcution

    Hi ,
    This is regarding Actual cost calculation.
    I have three material X - RAW MATERIAL, Y-SEMIFINISH MATERIAL, Z-FINISH MATERIAL.
    X=Stand. price Rs.10
    Processing cost Rs.10
    Y= Stand. price Rs.25
    Processing cost Rs.10
    When i produce Y , Cost will be = 10 (X) + 10(processcost)= 20 RS.
    So actual Price during prodcution is 20 , but it taking 25 (Standerd price of Y) in next step for production of Z (25+10=35 Rs.)
    So its coming wrong picture...it should take 20 Rs. What i have to do for getting actual cost after prodcution.
    Whre i can see this comparision ???
    Please Suggest
    Regards
    DHIRAJ

    Hi,
    Please refer the below steps.
    1. Creation of Production Order with account assignment as WBSE
    2.Production Order Confirmation on completion of manufacturing of material
    3. Settlement of Production Order to respetive materials / WBSE based on business requirments.
    Hope this will help you.
    Regards,
    Rakesh Pradhan

  • Target Vs Acual Cost Comparison for multiple process orders

    Dear SAPians,
    I want to take a report for target vs actual cost for all process orders and product cost collectors created in a particular period. I have checked the standard report KKBC_ORD that serve my purpose but for a single order. I want the same report for multiple process orders and product cost collectors.
    Is there any standard report or should I create a report painter report. I have tried to create a report painter report based on library 7KO, but target cost was not showing for selected order.
    Kindly suggest.
    Shirazi

    Target Costs are available in library 601 for internal orders (and can be used for process/production orders).
    Regards,
    Adrian

  • Is Operation wise costing feasible in Maintenance Order?

    Hi Gurus,
              I have a requirement of enhancement so that the acual cost can be populated operationwise.
              Is this feasible in R/3.
              If yes what are the difeerent points I have to take care.
    With best regards,
    Narendra Dere

    Hi,
    Costing is on the basis of activitiy type which yuou carry out for maintenance
    And these activities are nothing but your operations
    so carry costing for activty it means you calculated cost of operation.
    Kapil

  • Material ledger- pipeline materials actual costing

    Dear all,
    I am having problem with pipeline materials not being included in multilevel actual BOM in Material ledger actual costing. My client need information about actual quantity of pipeline material (natural gas) being consumed in multilevel production. I am not sure if pipeline materials are subject to actual costing/material ledger. Actual cost component is showing the amount of costs of natural gas, but in multilevel BOM, pipeline materials are not included. Am I right about this?
    thanks in advance,
    Duu0161ko

    Hi Rafal,
    there is a functionality built into acual costing to cover this:
    [WIP Revaluation  |http://help.sap.com/saphelp_erp60_sp/helpdata/en/9e/9e7a74681f1d4f9ba6f5d64aba4a44/frameset.htm]
    best regards,
                   Udo

  • Actual Costing/Material Ledger (CO-PC-ACT) - Actual costing

    Hello,
    I have same problem with actual costing in material Ledger.
    When I perform the actual costing a price differences that belongs to materials (orders) which at the end of the period are WIP, remain not split and don not book them on Accruals and defer.acct(material ledger) (OBYC - Transaction LKW).
    Moreover,  in the following month, system does not taking into account the value.
    Does anybody had similar problem or  knew how tu handle it?
    Thanks in advance,
    Rafal

    Hi Rafal,
    there is a functionality built into acual costing to cover this:
    [WIP Revaluation  |http://help.sap.com/saphelp_erp60_sp/helpdata/en/9e/9e7a74681f1d4f9ba6f5d64aba4a44/frameset.htm]
    best regards,
                   Udo

  • How do I add family members to my plan?

    I have an existing Verizon Wireless account. I'd like to add my girlfriend and my son to my plan.  Can't seem to find info on how to add them, or what the acual cost will be per month.   And the "live chat" button seems like it is perpetually unable to function.  Getting frustrated.

    Search for Assumption of Liability. That's what you want to do to add them if they are already Verizon Wireless customers. If they are on another carrier, then you would be adding the appropriate number of lines to your account and porting the existing numbers in.

  • Production Order GR with Planned Price

    Dear All,
    We are using following steps for production order=
    1) Create BOM, for Semifinished material with Price control = "S"
    2) Create Roting, with all Keys PP01, PP02 and PP03 with Material allocation to respective steps
    3) Standard Cost Estimation using CK11N and CK24
    4) Create Production order using CO10 with Material and WBS Element.
    5) Material issue against Reservation. But the material may be changed after releasing prodction order first time. And Actual issue for the BOM material may be more or less in qty.
    6) Final confirmation with completion of last phase confirmation of production order.
    7) Production Order TECO
    8) Prodction Order Settlement using KO88
    Now my problem is while I am doing final confirmation the GR done is with Planned price (Based on BOM) + Subcontracting charges which it is set with production order while releasing it for the first time.
    Kindly tell me is the system behaviour is correct or wrong?
    We are expecting that GR should happen with the actual material issue price + Subcontracting charges only.
    Please reply.
    Thanks & Regards,
    Vishal Kadia

    Vishal,
    This is for your information.
    If you have production order of 1 EA- Starnadar Price =10 rs
    Raw material cost=5
    Activity Cost=2
    Overhead Cost=2
    So COM=9 rs
    Suppose after production order creation plan cost is 9 rs, hence after confirmation there is no varience (plan vs actual) so actual cost is also the same 9 rs.
    Now as you said if system will go for GR against actual cost, that will post in cost of good mfg account at the time of GR.
    As per std SAP after GR also you can issue the material to that order, hence if you will go for more goods issue of new material against that order (unplanned issue) of rs 5 for the same order then the actual cost will again change (recalculated), but for that oredr material is allready GR with actual cost, then you will not able settle the cost of newwly issued material on that order.
    So whatever the plan and acual cost GR will be done against std price maintioned in material master ( 10 rs)
    This is my understanding.
    Hopes that will clear your dought.
    Tara

  • Error in CO88 - Very Urgent

    When we run CO88 - Actual Settlement, I have the following error occurs -
    "Order 1101396: Split delta (207,260.00 in currency 10) according to standard
    price
    Message no. MLCCS 015 "
    Can some one help me, very urgent

    Hi,
    this error is related to material ledger actual costing. it seems that some acual cost component split cannot be created in the proper way. Normally I would recommend to open up a message to SAP support on component CO-PC-ACT to let the experts investigate into that. Since you state that it is very urgent you may try to help yourself by the program MLCCS_KO88_TREATMENT. The usage is described in
    <a href="https://service.sap.com/sap/support/notes/632752">note 632752</a>
    I would assume that the error vanishes if you declare in that program that you want to use a split according to the standard price.
    best regards,
                         Udo

  • Project at component level

    Dear All,
    Can we get the actual cost of project at component level from
    PS Report.
    Regards,
    Nitish

    Hi,
    Acual Cost can be capture upto WBS/network  levels only.It is not possible to to get it at component level.As cost Object shuld be Unique Number with reference to which purchase or production docs are created.U can strucure ur project with activities n WBS so that u can capture major component cost.
    But as in System ur not posting actual cost against Components u can't get such report.
    Rgds

  • Cost of Production BOM in Prodcution Order

    Hello Experts,
    Here is scenario that i need help :
    Assume that we have a Production BOM with two components with a price of $10 in the pirce list :
    Parent Item: A0001 ( Price of A0001 is $10)
    Components  : A0002,A0003   ( Price of A0002 is $0 and Price of A0003 is $10)
    When we create a prodcution order for A0001 with a quantity 1000 and close , i noticed that in the summary tab of Prodcution Order and noticed that Actual component cost : $10,000 and Actual cost : $0 and Total Variance : $10,000.
    Due to this there is variance in Prodcution Clearing Account. Could you please help me a right approach on how to enter correct cost for Production BOM.
    Any help will be appreicated.
    Thanks,
    Praneeth

    Resolved

  • Make to order and make to stock scenarios in prodcut costing

    Dear Co Experts,
    I am new to product costing, in product costing there are two way to estimate the cost of the product by using make to stock and make to order.
    Kindly tell me the scenario of make to order and make to stock
    In make to order scenario what are the minimum configuration steps are required in controlling, PP, MM, and SD.
    In make to stock scenario what are the minimum configuration steps are required in controlling, PP, MM, and SD.
    How we will defend the costing variant in make to order scenario
    I really appreciate for your early response
    pls tell me end to end cycle for both the scenarios
    Warm Regards
    Venkataswamy

    Hi
    In Cost Planning in Product Costing,We configure Cost variant
    Costing variant is a A tool that contains all control parameters for costing, including
    parameters that control how cost estimates are executed and the material
    prices or activity prices that are used to valuate the costing items.
    In Cost Object Controlling  category a)by order b)by period c) sale order
    a) BY Order,We create Co Production Order which will be used in Make To Order Production.
    b) By Period,We create Product Cost Collector which will be used in Make To Stock or Repetitive Manufacturing
    c) By Sale Order,We create sale order with linked to Co production order,We can use Make To Order Scenario.
    Re: Repitative manufacturing
    www.sap-topjobs.com/SpecialPP/samplepc.doc -
    Regards
    Edited by: Dublin on Oct 19, 2009 10:02 AM

  • Actual Cost of finished goods in MIGO

    Hi,
    The value of Finished material in FI Document generated in MIGO takes the (Goods Receipt Quantity) X (Planned/Moving average Price from material master), Where as it should take the Total Actual Price calculated after Order Confirmation Based on Actual Material Purchase Price & Actual Activity Posting Value.
    For example:
    Present scenario
    Material-> MIGO QTY>Moving Avg Price -->MIGO FI Document Value
    Finished> 1000  EA> Rs. 10/ EA--
    >Rs. 10,000=00
    Required Scenario:
    MIGO FI Document value= (Purchase Value of Raw Material)+ ((Activity Posted while Confirmation)X(Activity price))
    Thanks.

    Hi,
    What u said is right Mr Kapil.. See when u do GR From Production Order System Calculate Moving Price or Planned Price from
    material Matser .
    As per ur Reuirement u told it should calculate (Raw Material Price + activity+OVHD).
    it is possible only when order quantity is less , suppose say your order qty is 150 mt per day and your Plant capacity is 500mt
    per day production will be done in a half day, sale can be done on same day after Production with the formula what u told.
    If suppose say , Your order is 2000 ton of Oil , it will take u to complete 4 days for your Total production as you told, GR should
    be done on (Raw Material Price + activity+OVHD) formula, you dont know exact activity price for 2000 ton until u finish your total
    production, at the same time until u do GR sales cannot be done. So in SAP Gr is intially done on Moving Average Or Planned
    (Standard Price) , After totla Prodcution GR is Compared with Actual Cost(Raw Material Price + activity+OVHD)= :"Variance".
    Plus are MInus is Reduced or added to Finished Goods Account or PP account during Settlement.
    If any wrong Pls Correct me Experts,
    Pavan

  • Issue in Mixed cost..

    I have issue in Mixed cost..
    Scenerio: just for example
    BOM 1
    Material A - HALB Rs 14
    Material B - HALB + Activity cost Rs 2 -> Rs 12
    Material C - HALB + Activity Cost Rs 2 -> Rs 10
    Material D - ROH procured -> Rs 10
    A can be procured directly from supplier as Rs 16.
    I want to weighted average cost for Material A while releasing cost estimate & same should be update in material master accounting view
    I Activate Mixed cost in spro. & maintain ck94 & ck91n. as prodcution version 1 as 50% procurement as 50%
    But Weighted price not update in Material A. Only RS 14 is updated.
    KIndly provide soultion for my issue. KIndly explain step by step..
    With Regards
    Swetha

    Hi,
    Maintain Vendor info record for Material Master  and in costing variant  select  tab Material from vendor info record.
    Regards,
    Sreekanth

  • Actual cost are not updating in prodcutcost collectors ( KKF6N) - Variances

    Hi SAP's
    We are facing the problem with the Variance calculation for product cost collectors.
    The issue is When we are calulating the Variances for prodcut cost collectors the actual costs are not ( For few materials of BOM) updating.
    Because of these the variances are showing high.....If I settele this variances to COPA, my copa report is will be going wrong.....
    Please help me to comeout of this problem.
    Thanks in Advance
    PrasadReddyS
    FICO Consulatnt

    Hi Anand
    Please add the budget profile at Plant maintenance order level no need to add any substitution rule
    budget should also be control at order level
    Thanks
    trinath 