Hi All,
         I have a requirement in which i have to add alternate material to the BOM, I am using the transaction MRTRS_START  for transformation of General recipe to Master recipe.
I have implemented the BADI BOM_UPDATE and used the method CHANGE_BEFORE_UPDATE to add my code to add alternate material to the DELTA_STPOB table.
Problem is,it is reflecting in C202/C203 but change number is not updated for the same and operation number  is also missing for the added material.
Then i came across a class CL_RMXM_ROM_MR_MAT_ASSIGN and several other similar classes. I am not able to figure out how to proceed?
  Thanks in advance.
Alok Patel

If you want it to be last for sure, why don't give it a number like 999? Or 777, so you will be able to add more later?

Similar Messages

  • Alternate material in BOM

    Can we use any material as a alternate material in BOM

    Check this good explanation from Rich... U can easily understand the concept
    A Bill of Material is used to know how to build a product. For example, say your product is a bicycle. What are the components of the bicycle. Well, we have a frame, seat, wheels, handle bars, brakes, etc. These components make up the bill of material. In SAP, you create a BOM using transaction CS01, to change is CS02, to display is CS03. Alternative BOMs, are versions of BOMs tied to the same parent material.
    codeParent Materail - Bicycle
    Component Materials - Frame
    Wheels
    Seat
    Handle Bars
    Brakes[/code]
    In simple words... Alternate BOM means for the same material group we can have have multiple alternatives 1 and 2 with the same BOM.
    goog example would be....
    Let the FERT be a car.
    The BOM of a car will have various components. Suppose if we want to use
    a different type of siren in some models then here we can create a 2 bom(alternate) & add siren along with the other components.
    Hence depending upon the model ordered we can choose the BOM.
    For a normal car, BOM 1 &
    for a car along with siren BOM 2.

  • Cs11 not Display Alternate Material Qty

    Dear Experts
    Whenever we r Putting Alternate Material in BOM and Set it Prioty And define the Qty as similar with other one and after that
    whenever we r checking Display in Cs11 Then System will Not Show Us the Alternate Material Qty And Also The Qty of Number 1 Material whose alternate is Define. both material R Blank Qty .
    What would be there.
    Rgds
    Pankaj Agarwal

    Dear Pankaj,
    Whenever you are checking the BOM display using T code CS11for a product which has alternative item group,then after
    executing the report,click on the change layout(control+F8) and select the fields like component quantity and not
    comp.Qty,and also usage probability and alternative item group,because if you have only the field comp.Qty,then in case if you
    have given the usage prob as zero means then it wont get displayed in the report.
    So select the change layout and select for the field Component quantity and check the same.
    Regards
    Mangalraj.S

  • How can I add alternate component in same BOM

    Hi Experts,
    One of my requirement like this , in same alternative BOM I want to add alternative components with existing components.So please advise how to do.
    With Regards
    Aravind

    Hi,
    This is discussed before in SCN. Please go through below links for your query,
    Alternative component in BOM
    alternative materials in PP
    Alternate Item in BOM
    Re: PR( purchase requ) for Alternative material in BOM
    Regards,
    Narresh

  • How to do backflush of alternate material in a bom?

    Hi,
       My user wants to do choose alternate material at the time of backflushing  according to material availability..
    currently we are maintaining as following priority - 1
                                                               strategy - 2
                                                                probability - for first material (100)
                                                                 rest of material as  blank.
    any body please guide me what should be the right procedure to achieve this.
    Already iu have searched found a thread Can we define alternate material in a BOM  try to apply our expert suggestion but it is not working.
    Kindly anybody help me to solve the issue.
    Thanks & Regards
    Sandeep Kumar Praharaj

    Hi Ramagiri,
      I have gone through your document but my user wants he should select the component according to his requirement.
    for that purpose i have opened the planned order in md12
    select the first component make the usage probability to 0.
    select the second component change the usage probability to 100
    after that requirement has been transfer from first alternate component to second alternate component.
    But after when i am trying to do the backflushing through MFBF second alternate component is not showing in overview screen it is still showing the first component.
    can u please help me why it is happening & explain how to achieve this point as you mentioned
    Thanks& Regards
    Sandeep Kumar Praharaj

  • Lot size in BOM as well as for alternate material

    how can we define the Lot size and validity period for a BOM means we want to define that 1 to 100 qty are to be produced with alternate 1 and 101 to 1000 for alternate 2. How the same can be defined in the master BOM.
    There is one component in the BOM and there is a alternate material is also, Users want to define that while issuing the material , system allow to issue only say qty " 50" and then alternate material for next lot.
    Is there any possibility to define the BOM as per the above requirement.
    thanks
    harish

    Dear Harish,
    if u have alternative BOM's, then creat production versions
    1) creat BOM with two alternatives (say alt 1 1to 100 & alt 2 101 to 200)
    2) creat multiple Routings with two group counters
    3) creat production version in MM02 in MRP 4 view or work scheduling view
    4) in BOM slection in MRP 4 view maitain the prameter as 3 or 4
    Then MRP takes care of lot sizes difined in PV & BOM and creat procurment proposals
    Regards
    kumar
    Edited by: kumar kumar on Aug 3, 2009 8:02 AM

  • Can we define alternate material in a BOM

    Dear All,
    Can we define alternate material in a BOM,If yes,How???
    pl. guide....
    Tushar Aute

    Hi,
    In BOM , alternative items are assigned to alternative item group on the general data tab page.
    In the production order in the general data tab page.
    We can define the alternative item based on priority , strategy and usage probability.
    Priority:
    This defines the priority of the item within the alternative item group.
    This determines the priority of planned withdrawls of items.
    EX Two items are assigned to alternative item group
    item A Priority 1
    item B Priority 2
    The system reads the item A first.
    Strategy:
    use the strategy to determine how the planned withdrawl is controlled
    within the alternative item group.
    The strategy should be same for all alternative items within a alternative
    item group.
    If the value 2( 100% check) is defined for the strategy the first material in
    the defined priority sequence for which sufficient quantities are available
    are reserved.
    Usage Probability:
    MRP Plans these alternative material components according to probability
    of use.Material requirements for BOM Components are planned according
    to usage probability.
    The planned withdrawls for the production order are based on the reservation lists.These lists are based on the priority and strategy.
    Regards,
    nandha
    Edited by: S.Nandakumar on Feb 21, 2008 7:21 AM

  • Alternative material in BOM

    Dear SAP Friends,
    I have a BOM with 1 material & want to add 1 alternative material if previous one is not available in stock.
    pl tell how to create alternative material in BOM without creating alternative BOM.
    Regards,
    Chandra.

    Hi chandra
    Alternative items can be added to the BOM without alternate BOM.
    In change mode of BOM CS 02 go to BOM item details There you can see alternative items with item group
    There you can define you items with Priority,usage probability , Strategy,
    Alternate item will be selected during MRP run as per your usage probability
    Regards
    J . Saravan

  • Error message when trying to add item in change BOM goup

    Hi I went to transaction cs05,and trying to add item to specific material with BOM group,an error message popped up and saying assign the item to an alternative,what does it mean? How to solve?

    Hi,
    A finished material can have multiple alternative BOMS which can be stored in a common BOM group number. CS05 is used to change these multiple boms.
    When you add a new item in CS05, system will ask - to which alternative bom the new item should be assigned and that's how you are getting this message. For example, if in a bom group you have 3 differnet alternatvie boms for a FG material, when you add new item in CS05, you will see 3 checkbox at the right hand side of the screen. If you want to assign new item to all the three alternative BOMs , than select all the three check box and save.
    Regards,
    Ravi Thakkar.

  • Alternate Group in BOM

    Hi experts,
    I'm having the problem with Alternate group in BOM. I'm maintaining the the raw materials in BOM i.e A1,A2,A3,A4 like that number of materials is there.
    I'm grouping the materials with alternate group
    A1: Alt Grp-01, Priority-1, Strategy-2, Usage-100% 
    A2: Alt Grp-01, Priority-2, Strategy-2, Usage-0% 
    A3: Alt Grp-01, Priority-3, Strategy-2, Usage-0% 
    A4: Alt Grp-01, Priority-4, Strategy-2, Usage-0% 
    I given the qty for all raw materials is 100kg.
    While i'm converting planned order to Process order. The BOM materials is taking as
    A1 - 1000kg
    A2 - 0kg
    A3 - 0kg
    A4 - 0kg
    Why 1000kg taken and I don't need the materials A2, A3 and A4 in the process order. Is there any option to get drop-down list. May be its customizing.
    Naren

    Dear
    Why do not your go for Discontinued Material  concept in case if  you think that A2/A3/A4  should be be considered based on the stock avaliablity .
    In MRP4 view for material A1 , you can keep the Discontinued Material  , Effective Out Date , Discontinued Material Indicator as 1 so that when ever there is a stock  un-availablity , it  should be considered while planning and sub sequently in process order .
    When copiying BOM to Prococessd order , there is no operatunity to change the qty   because it happens automatically based on the order type dependent parametrs for process order (OPL8 ) but you can change the qty in process order change mode -compoenet over view .
    If you are maintaining production verion , you can implement BAdI MD_MODIFY_PRODVERS or MODIFY_PRODUCTION_VERSION based on  stock situation .
    Regards
    JH

  • Scrap Material In BOM

    Dear All,
    I want add a material as scrap in the BOM....
    what should be the material type used for scrap material......???
    which Item category should be used in the BOM...
    Please Suggest
    Regards,
    Pawan Shetty

    Dear Pawan,
    what is the scrap you are trying to add in the BOM?In case if you want the scrap % that is to be considered for the
    components at the time of planning means,then you can differentiate and mention as component scrap or operation scrap in the
    BOM--->item details.
    If it's also one of the output material along with the header material means,then you can create a separate material code for the
    one which you mean as scrap and maintain the same with item category as L and in terms of negative quantity in the BOM of
    header material(main product).
    Check and revert.
    Regards
    Mangalraj.S

  • When I sync my ipod to add new material, sometimes itunes will automatically rearrange the song order of my pre-existing albums by number of plays. Why does it do this? And is there a way to stop it?

    When I add an album to itunes and subsequently to my ipod, everything is arranged by track number of the album. Sometimes when I sync in order to add new material to my ipod, itunes for some reason automatically rearranges some of my pre-existing material by songs with the greatest number of plays to least (though sometimes it seems to be completely random). When I check itunes on my computer, everything still appears to be in order but the way it appears on the device often is in the previously mentioned disorder. Why does it do this? Is there any setting that I can adjust to make it stop because the only way I've found so far is to delete the rearranged material and re-import the cd and then re-sync. It might sound picky, but I prefer that my music be in order by track number as the artists themselves intended for various reasons the foremost being that I often listen to whole albums from start to finish and this glitch makes such problematic. I have found some settings in preferences that focus on how material is arranged but this seemed to be focused on the actual folders where the music is located on my hard drive and not the way it appears on the ipod. If anyone knows the reason it does this or has suggestions on fixing it, I would be greatly appreciative. Thanks.

    Did the original songs that do not appear on the car player play in the Music app on the iPod? Sometimes glitches happen and they do not. Also, If y ohave a 5G iPod/iOS 7, purchase songs  will show with an cloud icon by them if they are not downloaded if Shall All is turned on in Settings>iTunes and App Store

  • Multi level follow up material in BOM

    Dear All,
    Our client have a requirement for multi lvel follow up material in BOM.
    for example
    BOM for Finish Good made of A.
    if material A is depleted then used material B
    if material B is depleted then used material C
    if A and B have stock used A(higher priority)
    I tried to used follow up material in MRP4 and BOM but it can not be used for multi level like this case.
    Is there any solution for this?
    Best regards,
    Fred

    Hi anyway I tested the BOM master data like this
    F/G 1 Master Box
    |--- A 10 PCS  Alt Group Z1  Priority 1 Usage 100% Strategy 2 (100% Check)
    |--- B 10 PCS  Alt Group Z1  Priority 2 Usage 100% Strategy 2 (100% Check)
    |--- C 10 PCS  Alt Group Z1  Priority 3 Usage 100% Strategy 2 (100% Check)
    Stock A is depleted
    Stock B enough
    stock C enough
    Expected result F/G only used B 10 PCS
    Actual result is
    F/G 1 Master Box
    |-- A 10 PCS
    |-- B 10 PCS
    |-- C 10 PCS
    Do ou have ides how should the percentage in BOm is maintain?
    Best regards,
    Fred

  • Excise Value and Freight value should be add to material cost in the depot

    Hi,
    Can any one help me on my scenario?
    We have depot concept my client requirement is excise Value and Freight value should be add to material cost (inventories at depot) in the depot
    Thanks & Regards
    KMR

    Hi All,
       In Depot Sale. This are the Excise Duty Passed on to the Customer BED, AED ECS, SHECS, Other then that its added to the material cost. Define a Pricing procedure for value added to the material cost in both Procurement & Sales base your problem will be solved.
    Regards,
    Pherasath

  • MRP run for header material with bom usage-3

    Dear All,
    We have header material with bom usage-3.We maintain the stock at child components only ,not at header
    I have created the planned independent requirement for header material.I have created a sales order but sales order is not shown in md04.
    What can be the further setting  I am missing for mrp run of above scenario.
    with regards,
    pradeep

    Dear ,
    Couple of checks points for you :
    1.Check the material master Sales Org Veie-Item Categoery .As you have mentioned Item Categoery -TAQ which is not relevent for requirement planning throgh schedule line category -CT ( CT means there will not be any inventory or good movement and requirement will not be passed for MRP ) .Only CP -line item categoery does requirement passing through MRP and it will show u in MD04. So the summery is if you want to generate an MTO order for the same FG material , you should matian the Sales Line item categoery as MTO in sales Org View and it will pop up in VA01 whiel logging Sales Order .
    Generally , TAQ item categoery are used in Project Billing or Delivery .ok  and they will not be having any availabilit check so it KP ( no check ) .
    But for MTO order , you should have availablty chek 02/01 in MRP3 view and also MTO Sales Item categoery .
    Based on the above information logg an sales order , release credit chek in VKM3, SAVE and check in MD04.
    Create PIR in MD61 and Run MRP on the both cases .I have tested its working .but noit with TAQ item categoery ok
    2.Why do you need to create Sales Order for dependent Item-Y because it will be in X-BOM item  ? Make sure that Y- should have Sales Item categoery in material master -MM02-Sales Org View as NORM item .If you really want to create sale sorder for this item , it should TAN or NORM .
    3.Other PIR detail is fine .
    Try and revert back
    Regards
    JH