Availability Control problem

Hello Friends,
WBS actual postings moved over defined budget tolerance value.Availability
control type is 1, CJ03 shows the status AVAC (Availability Control Active).
In configuration for availability control it is specified if total value reach 90% of budget value then throw an  error and if it surpases 110% of budget value  throw error message
When i checked the 'Change documents in Status management' for the WBS element ISBD or insufficient budgeting status changed lot of time from 'Active' to 'Inactive' as shown.
ISBD Insufficient budgeting"
Inactive  08/01/2006 11:29:36 PDUFRE            Create Purchase Order           
Active     07/28/2006 02:56:14 RKNA    
Inactive  05/18/2006 08:30:24 JGUIDRY            Change budget operative
Active    05/12/2006 14:57:28 PDUFRENE        Create Purchase Order           
Inactive 05/12/2006 11:14:53 RHYMEL             Change Purchase Requisition     
Active   05/12/2006 10:18:41 SFOLSE             Create Purchase Requisition     
Inactive 01/18/2006 15:41:04 PPALA                Create Purchase Order           
Active   01/18/2006 15:41:04 PPALAHAN         Create Purchase Order           
ISBD or insufficient budger is shown if as per the availability control restriction actual or committment surpasses proposed tolerance limit.
Is it possible to surpass this error and post to WBS.? Does this depends on any user status, because when i tried simulation is quality system ,system popped up error showing value exceeded available limit.
Please give your suggestion, i heard this is a serious SOX violation.
Rahul

Hi
ISBD error message will come the moment when the budget is almost exhausted. You could have done Cost planning and Budgeting for the WBS element. If you are utilising most of the amount of budget within the short period, system will throw this error as in the background, system divides the amount budgetted for individual months period and system forecasts the expense for the balance period based on the actuals incurred for the WBS element till that period. This happens because of the Availability Control being active.
Regards,
K Lakshmanan

Similar Messages

  • Problem in activating the Funds Management BCS and Availability Control

    Hi experts.
    After running the program RGLIUGEN to generate the required includes in program SAPLGLIU, the generated programs come with syntax errors. When I manually correct the errors ,the program post the budgets and budget releases but does not update values for availability control to the effect that whenever one tries to post any amount against the budget, we get the following error  :
    Overall budget exceeded by 100.00 USD (FM PB Availability Control) for document item 00001
    All suggestions will be appreciated

    The following tolerance limits regarding payroll entries are currently configured in the system. Once the 90% level of the budget is exceeded, the system will generate one notice. After the 100% is reached, the system will repeat the notice every time an entry occurs.
    90%      Warning message – Internal mail (only once)
    100%    Warning message – Internal mail (repeatedly)

  • How to hide or supress availability control screen in VA01

    Hi,
    I want to hide Availability Control Screen in VA01. Can you please help me how can i supress that screen.
    Regards
    Malik

    Hi Nabheet ,
    disabling the Button wont solve the problem , System automatically do availability check based on the stock and scheduled delivery date , if no sufficient stock then system will  propose new schedule line dates....
    so disabling the Button wont stop doing all these checks........it needs to be done thru config/E Spot which will skip all these validations...
    regards
    Prabhu

  • User Account Control Problems with Premier Elements 7 32 bit in 64 Bit Windows 7

    I found User Account Control Problems in other forums but didn't see much in Premiere Elements, so I hope this helps others who may be having problems with 32 bit programs in a 64 bit computor. When I first got my 64 bit I didn't have problems.
    Back in February I bought a Quad Core Desktop with Windows 7 64 bit. Haven't been on the forum for 7 months since I wrote in regarding importing video with the Pyro AV Link (Premiere Elements Tips and Tricks). I was having problems importing video which started after March 28 sometime, as that was the last time I didn't have a problem importing VHS. Took me a few months off and on to find out what worked.
    I started uninstalling Windows updates and any programs I had installed back to that point in time. Checked after uninstalling each item. The capture screen would come up on a delayed basis but clicking on capture did nothing. Although no driver is required for IE1394 (so they say) I read where some people using the Legacy driver had fixed some problems, so I switched to the Legacy. Seemed to work great (for a few minutes).
    I had even uninstalled and reinstalled PE7 but no difference. Finally I noticed a shield in the PE7 Desktop icon. Thats weird. Never had that before. Just decided to show up after I had done all of the stuff I mentioned. Turns out at some point in time since I've had the computor Windows 7 decided to flag my 32 bit program as misusing the 64 bit system. User Account Control. I never bothered too much with UAC and just clicked on the yes box wen it popped up asking if I wanted this or that to take control of my computor. I tried using the minimum setting for safety reasons, and then finally turned User Account Control off. Bingo! PE7 capture works again and still working.
    While I am not recommending that people arbitrarily turn UAC off, this appeared to be my problem. I would recommed that they try turning it off before uninstallin a bunch of stuff. Having a restore point may or may not have been a fix for me. I think one of the Windows Updates caused the problem but I am not going to uninstall any more stuff at this point, I have not been back on the internet or installed any more updates in my desktop. I am going to use my laptop for internet and used the desktop for video.
    I am guessing this could be a problem for any 64 bit systems trying to use 32 bit programs. IE: XP,Vista,Windows 7 64 bit. In Vista there is also Data Execution Prevention (DEP) which you can turn on or off, supposedly to prevent misuse of memory (as I understand it), but Win7 either doesn't have it or I haven't found where it's located.
    Maybe this has been covered in the forum somewhere and I missed reading it. Hope I am not too confusing. Anyway, whatever feedback you guys have would be great.  

    John,
        Thanks for your answer, and I did check out the link you suggested. However, I have Windows 7 Home Premium as most people have I think, and the XP program was not available. I started with Vista and now have Win 7. I never could navigate around in XP anyway so am content to just leave User Account Control off.
        Interesting side note to turning UAC off is that my desktop seemed to be using more of the CPUs, where half of them were "Parked" as I wrote in also about 7 months ago when I 1st got my desktop. I am pleased to say that video processing seems to go quicker with UAC off. Have to observe things some more to confirm.
        I just thought if others were having problems after installing Windows Updates and leaving UAC off worked then they could possibly pinpoint a problem.

  • Availability control on statistical WBS element

    Hi everybody,
    The issue deals with <i><b>availability control on statistical WBS element</b></i>.
    <u>Part 1</u> : I released 25000 as budget (CJ32) for a <b>statistical WBS element</b>.
    Availability control is active for this WBS element.
    We made a good receipt (MIGO) for 20000 on an AUC (asset under
    construction) - so we get the value as statistical value on the WBS
    element -, then invoice verification (MIRO) and finally the asset
    transfer (ABUMN) from asset under construction to fixed asset.
    On this statistical WBS element we get +20000 (MIRO) and -20000 (ABUMN).
    The problem is that the amount that is used for the availability check
    is 0, instead of 20000 as you can check !!!
    We set a budget on the statistical WBS element in order to have the
    availability check ... and this is not working as the system in the described case shows 25000 as available but for me we should have only 5000 (= 25000 - 20000).
    <u>Part 2</u> : This is working perfectly (I get the expected value for available) when we use a <b>"real" WBS element</b>, put an expense on it, then run the period end closing tranction CJ88 in order to transfer the cost on an AUC, and finally run CJ88 again in order to transfer from AUC to fixed asset.
    Did anybody already encountered this problem with statistical WBS element ? How did you solve this (we would like to keep our statistical WBS element) ?
    Thanks in advance for your help.
    Benjamin

    Hi Benjamin,
    Pl go through the link below :
    http://help.sap.com/saphelp_47x200/helpdata/en/3e/a98337dd34ca76e10000009b38f8cf/frameset.htm
    I have not faced this but as far as I remeber for AUC Statistical assignments have some limitations.
    Any specicfic reason for keeping the WBS Statistical? Are you able to see "0" zero on this WBS in CN41.
    Regards,
    Sudhanshu
    PS: Assign points as a way to say thanks.
    Cheers,
    Sudhanshu

  • Availability control is not able to  activate in ko22

    Hi frds,
    my problem is i am going to creat availability control to order in 2012 i gave amount after order oerview also i gave amount but if we r not activate the budget control. because that is display mode.
    in ops9 we had given activat type 1.that budget profile maintain in order type also.but i am not able to activate the availability control. can u please suggest me how to activate.
    Actually my requirement is department wise budget control.when we are purchase any asset through po the amount will be reduced from that department. can u tell me suggestion this one also this is  correct way r funds management implementation is the correct way.
    Thanks,

    Hi,
    The Availability control will activate automatically when you enter budget in the order.

  • Fund Managment - Availability Control

    Hi! all experts,
    I have come across the following Fund Management problem :
    If there is NO budget data for a commitment item in this financial
    year, Purchase Order can be saved against that commitment item even
    thou Fund Checking has turned on. There is NO ERROR MESSAGE. That's is
    WRONG.
    Once entered budget data of $1.0 via FR04 to that commitment item, on
    saving the Purchase Order, system will display an error message :
    Availability Control : Item 001 B2010 / 163000 payment budget exceeded.
    How can this problem be fixed so that SAP will display an error message if there is NO BUDGET for a commitment item.
    THANKS IN ADVANCE.

    Hi! Sridhar,
    For temporary fix, I have created a $1.0 budget for each commitment item.
    Do you have any idea what's ran wrong? In last Financial Year, we don't have that problem.

  • Payment Budget Exceeded - Availibility Control

    We are trying to save a Purchase Order which is using a commitment Item, and get a error "Payment Budget Exceeded"and above this error it says Availability Control".
    but when we check the budget allocation against this commitment we find enough amount available.
    how do we get around this problem?
    Lalchand.R

    Hi suresh,
    I solved it myself.
    Ref: Note 573556 - If availability control works correctly?
    in this note he mentions :
    If you think the available budget amount is not correct, please run report RFFMAV01 (RFFMAV01X) or RFFMAV02 (RFFMAV02X) to check
    If the 'Assigned budget' is same as the 'Commitments/actuals', if not, you must run report BPINDX03 first to correct it.
    IN report RFFMAV02X the assigned budget and commitments/Actuals were not matching, I ran this BPINDX03 and all was done.
    Basically it recontructs the AVC.
    Lalchand.R

  • Controlling- Problem with Assigned

    Hi
    I have the following problem:
    I implemet the budget control through customizing.
    I start to creat internal orders and i settlement the original budget.
    Then i continued working as normal creating PO, invoices etc, all against the internal order.
    When i go to KO22 to see the original budget and the assigned, in some orders, the assigned is upper than the budget (its wrong becuase i implement the Bugdget controlling for internal orders). And in some cases the commitments plas the actual postings is upper than the assigned (its is wrog becuase the assigned is form by the commitments and actual postings).
    I dont know why it happend.
    Please if someone have a similar problem or know about this issue, please help me.
    Thanks in advance for your help
    Enzo

    Commitments and actual postings can exceed budget if tolearnce limt for 100% of usage is set up at warning / information i.e. it will allow to post additional costs /create PO against the order with information / warning message to the user.
    Check the tolearnce limit in customizing and it should be level '3' (error message) against 100% usage.
    Assigned value should be equal to actual & commitments. You can 'Set up Availability Control again' (KO31) to reconstruct the database for the orders with error.
    Regards,

  • Delivery Proposal is DISABLED in Standard Order Availability Control

    Hi Experts,
    Please help me solve my issue, I almost checked everything under SPRO>SD>BF-->Availability Check, but still cannot resolve my issue.
    Following are the symptoms of the issue that I'm encountering:
    Material cannot be confirmed (even though there are stocks)
    Complete Delivery, Delivery proposal & One time delivery are disabled in Availability Control Screen
    Here are some of the relevant configs which I checked:
    OVZJ entry for sales area is C (Delivery proposal)
    Checking group maintained in Material Master
    Any ideas please? ANy help would be much appreciated!

    1) Check the reservations for the material in MD04. The available quantity might have been confirmed for earlier sale orders and hence reserved for those sale orders.
    There are 11,000 cases in unrestricted stock. No reservations for the material.
    2) Check the inhouse production time in MRP2 view of the material master. It should be filled with production lead time.
    Done
    3) In OVZ9, the checkbox "check w/o RLT" is unchecked.
    This is our current setup
    Net, issue is still there.

  • Warning Messages related to Reconstruct Availability Control for Project

    Hi Gurus,
    In Transaction IM52 - Change Original Budget for Investment Management Program, after changing the Budget Values of Investment Management Position and when we check the transaction for error, we get Warning Messages, the warning message is as follows:
    You Must reconstruct the availability control for Project P.000XXX.
    We tried to reconstruct the Availability Control in Transaction CJBN and again checked for errors in IM52, then also we get Warning Messages.
    As these are only Warning Messages we can ignore and save the modified budget values for the Investment Management Program.  But we want to know whey these Warning Messages are keep on cropping up inspite of reconstructing the Availability Control for Project.
    You inputs on this will help us immensly.
    Thanks,
    KRN

    hi KRN!
    I am also facing the same issue.
    Even if i am having enough budget, while making a PO, the system says " Budget exceeded".
    i could processs the PO, after performing CJBW (deactivate), CJEN (refresh) and then performing CJBV ( activate availabilty control) for that project.
    This is repeating everytime i make a PO. is there any permanent solution?
    Even after performing all the above, if i check in IM52, and check for budgets (perform from menu), the error is " You Must reconstruct the availability control for Project P.000XXX"

  • Exempted cost element not working for budget availability control

    Hi,
    I have configure the exempted cost element in our sandbox client. In the SAP IMG menu Project System -> Costs ->Budget-> Specify exempted cost element I maintain the following entry.
    COAr      cost element        Origin Group
    0200         433010                     *
    Then in the material master of a material I maintain the origin group in costing 1 view as 001. Then I do a material issue against the network of a WBS in MB1A tr code mvt type 281 and post the cost to the cost element 433010. As per the exempted cost element logic this should not affect the budget availability since the cost element 433010 is define as an exempted cost element. But the system shows actual incurrence for this transaction and reduce that must amount from the budget. I check this is the S_ALR_87013558 report. To re-ensure I do the Project Info database rebuilt in CJEN tr code then activate the availability control in CJBN but this is of no use. The S_ALR_87013558 still shows the budget available as total budget minus the cost incurred in the cost element 433010 in the above transaction.
    Please let me know if anybody has configured the exempted cost element in their client and have resolve this issue.
    Thanks and regards'
    Preetam

    Hi,
    This is a std SAP Functionality and system should exempt the costs for the cost element maintained in the Configuration for that Controlling Area.
    Muzamil

  • Control problem

    I create a swf by Flash locally which point to a flv in a
    remote flash media server, FLVplayback component included, it work
    fine locally. Uploaded to FMS3, played without the control problem,
    such as Play/Pause, seek bar.
    Is it something I need to configure in FMS, or in Flash.
    Please advice.
    Thanks!

    Between version 1.0 and 2.0 the API in the JBCL controls has
    changed. We are actually moving away from JBCL completely (please
    do send feedback if you have a comment on that) to a Swing and
    Infobus standard based library of visual JavaBeans.
    You will still be able to use the JBCL controls in JDeveloper
    2.0. The best thing to do is to take your 1.x based application
    AND the 1.x based JBCL.ZIP file into your new environment. This
    way you will be able to continue to use these apps and
    components. Taking the 1.x JBCL.ZIP file will make sure you have
    the same version of the JBCL library that you were used to in
    version 1.x.
    Hope this help,
    -Roel.
    Hans Duijn (guest) wrote:
    : Hi,
    : I developed an applet in v1 that worked fine. I tried to
    rebuild
    : the applet in v2 but some problems occured. One, The
    : ChoiceControl populated with the method
    : 'ChoiceControl1.setItems' but in v2, this does not work till a
    : explicitly called 'queryDataset.open'. Is the way to do it or
    do
    : I have to use special properties for the
    dataset...and...second,
    : I'm using an listControl that, in response to a selected item
    in
    : the ChoiceControl, changes frequently. No new list appears till
    : I update the applet the hard way (hide it and bring it to
    front)
    : or click the mouse on the hidden items. 'listControl.repaint()'
    : has no result. Am I doing something wrong? It worked in v1...
    : and third...when can we expect the final version 2?
    : Thanx.
    null

  • Project Availability Control

    Hi,
    I would like to confirm if availability control / check happens only at actual posting level or also during commitments and other trigger points?  Please also advise where to set the proj availability control for different trigger points.
    Vivian

    SAP as provided different business transaction groups to control budget at different levels (PR,PO, FI Postings etc).
    Please refer Note :628978
    Glimpse of the note:
    Business transactions are assigned to a business transaction group in the availability control. You can define tolerance limits for each budget profile for the availability control actions in the various business transaction groups. It is not clear which business transactions belong to the individual business transaction groups of the active availability control.
    Business transaction group 00 (Purchase requisition)
    Business transaction group 01 (Purchase order)
    Business transaction group 03 (Goods movement)
    Business transaction group 04 (Financial accounting document)
    etc.
    Venkat

  • Budgeting & Availability Control

    Hi Gurus
    We had activated Internal Order Budgeting & Availability Control check & had used it to procure Fixed Assets. The internal order is created (t-code KO01) & budget value is assigned (t-code KO22). The internal order is assigned to an asset (t-code AS01). This asset is used for procurement in MM module - purchase order (t-code ME21N), goods receipt (t-code MIGO) & subsequently invoice verification (t-code MIRO).
    We have a unique situation. Some of our colleagues have created the order, assigned the order to the asset & completed the procurement cycle without assigning the budget. Now we would like to assign the budget to the internal orders we had missed & would like to check the availabilty control for all the transactions we had carried out. Is there a way to meet our requirement. What are the alternatives available to us?
    Thanks,

    Hi,
    I suggest you collecting the data on these orders (KOB1/KOB2), sum up the amounts and check what budget these orders required. There is no retroactive availability check possible. You can switch it on, but it will be active only for future postings.
    Regards,
    Eli

Maybe you are looking for

  • Resolution/Sidebars From Motion to FCP

    Hey guys, Absolute noobie here, so please bear with me; I am following the tutorials on the apple FCS DVD and am onto the Motion section, i have done the whole 'send to montion' on the "Blue Horizon" bit and I've just done command save and popped bac

  • Column not allowed here

    HI, I have a function and i want t odo like this: create or replace function func( dbl varchar2,tr varchar2) return number is d2 timestamp :=sysdate; trc varchar2(4): dblnk varchar2(255); begin trc:=tr; dbllnk:=dbl; execute immediate 'insert into t@'

  • What's a good forge game for the iPad?

    I was wondering if there was a game for the iPad kind of like Gary's Mod or the forge on Halo Reach.

  • Photoshop Touch and iPad

    When I paid for a year of Creative Cloud, I was under the impression that all the programs and apps listed were included.  However, when I tried to put PhotoShop Touch on my iPad, I was sent to the Apple Store to pay $9.99.  Is this not included in w

  • Choice of a new superdrive ?

    hello i need to replace ( or add one ) my superdrive that doesn't want to burn DVD-R anymore ( DVD-RW is ok ) Connecting is IDE in macpro 3.1 ( early 2008 ) . my question is : would you have a reference of a DVD superdirve that would fit/work in ? (