BAPI_PO_CREATE1 not triggering Release Strategy
Hi,
We are using the BAPI, BAPI_PO_CREATE1 to create Purchase Orders Programmatically. But this way the Release strategy is not being triggered and the PO is directly being sent instead of blocking for the Releases.
Whereas the appropriate release strategy is being triggered when the PO is created using ME21N using the same data that was used in the BAPI (Same Purchase Value, Purchase Group etc..).
Is there any Option in the BAPI to trigger the Release Strategy or any OSS Note or any customization requirement to resolve this issue.
Regards,
Rajeshwar Rao J
Hi,
I hope this issue was resolved...
Please help how it was released .
i am also getting the same problem (my system is upgraded from 4.7 to ecc6 in ecc6 only we have implemented Bapi to create PO)
Thanks
A. Prasad
Similar Messages
-
User exit for triggering release strategy
Hello Experts,
My requirement is when changes are made in purchase order (ME22N) then once again release strategy will have to get trigger.
is the user exits exists for this purpose,if yes, What is it?. I searched alot but not able to find right exits.Hello ,
I think you can achieve this via configuration .Basically you want the release strategy to get redetermined based on the changes in the item or if the price of these items increase a certain level .if you have the release startegy as changeble in the SPRO ticked it will automatically go for new release strategy if you have the value of release indicator set .This can be done SPRO->MM->Purchase order->Release procedure for purchase order->Define release procedure->Release indicator.
Set the appropriate value .
Remember you need to know what is that it retrigger that release strategy .
The link below deals with similar requirement ....
[http://sap.ittoolbox.com/groups/technical-functional/sap-log-mm/retrigger-release-strategy-for-purchase-requisition-with-any-change-1858101]
Thanks
Anjaneya .
Edited by: Anjaneya Bhardwaj on Aug 31, 2011 8:21 AM -
SAP Note PO release strategy based on net price
Hi
As we know this is standard sap as the PO release strategy can configure on PO net price not any other prices e.g. effective price etc.
can any body suggest me the related SAP NOTE for the same.
It's highly required for me to convince to the client.
Thanks in advance
JayeshCheck the below exit and include which can be used in your case to consider the effective price.
Exit: EXIT_SAPLEBND_002
Include: ZXM06U22
Ask you ABAPER to include Logic as per your case -
Why not correct release strategy is called outb
I have created two release strategy 1,2 for release group G1 as below, but when I create PR, only release strategy 1 is called out although the criteria belongs to release strategy 2. Please tell me whether is wrong, thanks.
Release group G1 Rel. Strategy 1 Buyer of NB
Purchase Requisition Document NB
Plant 9850
Total value of requisition for < 1000.00 CNY
Release group G1 Rel. Strategy 2 1st line manager
Purchase Requisition Document NB
Plant 9850
Total value of requisition for > 1000.00 - 10000.00 CNY
what I have created PR total value is 4000Charlie,
Thank you for your quick response, I have tried according to your instruction, but still release strategy 01 is called out. No other release strategy is called out, please tell me what should I do? thanks,
Edited by: King Qi on Sep 17, 2008 9:35 AM -
Purchase Requisition Release Strategy not triggeringusing Userexit M06B0001
Hi,
My client wants to trigger PR Approval based on the Department,based on User it will go to respective Line Manger.
For that I am using Userexit M06B0001, But when I am using this Characterictis it is not triggering Release Strategy.
If I am using other Characteristics like Plant it is triggering.
Can Anyone Help me on this.
Best Regards,
RajuHi Raju,
Did you checked for this Characteristic if it's attributes are correctly maintained. Also Reference to Table field is correctly mapped. I hope you must have done this correctly, but check it once again to confirm.
Prashant Rathore. -
Hi,
I have used the class PO_release.This class is having the characters as doc type,pur org,net value,pur grp.
I assigned this class to the release group.One strategy defined based on this group.
In CL20N i have maitained the values for the characters.
When i trigger the PO release is not working.Please be informed that PO createdbased on the values maitained in the CL20 N transaction.
Kindly let me know why release not triggered.If i miss any settings let me know.Hi,
I would say try this -
Remove all characteristics from class.
Then maintain only 1 characteristic in class and maintain characteristic value and match the value with the PO.
Try doing some dummy changes in PO and check whether system triggers release strategy.
If it is maintain values for other characteristics one by one and check the release.
Hope it works.
Thats how I manage such cases.
Regards,
Dipak -
Rel. strategy is not triggered while creation of PR with cost centr
Hi Gurus,
While creation of PR release strategy is not getting triggered with cost centre BCWSV870. But release strategy of PR triggered for cost centre BCWSV852 (In PR changed only cost centre as BCWSV852 instead of BCWSV870). Both cost centres are similar and the both cost centres are exist in characteristics value in CL20N for the same release strategy.
My question is why for one cost centre triggers release strategy triggers and for other cost centre release strategy is not triggered. Can you please tell how come this and rewarded for answer this.
With regards,
C. Sundar RajanHi,
In regard to problematic PR with cost center BCWSV870, was your PR maintained with only one line item? or multiple line items?. In additions, when defining cost center as part of the release strategy structure, did you enter all cost centers with leading zeros? Tak a further look into OSS Note 365604 for your further investigation.
Cheers,
HT -
UserExit required - Do not Create PO without Release Strategy
Hi
My requirement is Do not Create PO without Release Strategy.
When user try to save PO, it should not allow to save, if it does not have Release Strategy.
For this scenario, we require which UserExit.
If UserExit, can you guide me which userexit and the following steps.
For this scenario, which is the best way to control.
If you got anyother options other than userexit can also be advised.
Pls advise me.
With Regards
KameshHi Shailaja
Very thanks for your reply.
Some more doubts,
I think Release strategy data will be populated in I_EKKO table.
I can use fields from I_EKKO-FRGSX & FRGKE.
If these fields are initial (ie) PO without release strategy, I want to exit PO without saving - Creation.
So here can i put Error message if the fields are initial.
IF i put Error message then the PO screen will be block ? in that Error message.
Just want to confirm before testing something with the Exit code.
Is this the way to proceed.
Thanks in advance,
With Regards,
Kamesh -
Issue with PO Release strategy
Hi experts,
I have problem with Po release strategy in 5 to 10 purchase orders, i have created few purchase orders(2000 Po's) with same document type and company code ..etc and saved, then release strategy has been triggered.
For few purhcase orders release strategy has not been triggered.
If i take 1 po from that few purchase orders(Release strategy has not triggered) as reference and again if i create PO,new purchase order have getting created with release strategy.
Can some body tel how this ican be possible, hope this might be standard syatem behaviour.
Hope i should delete thos e purchase orders and i should create new PO's instead of of old PO's (Without release strategy).
Some experts can share their experiance in this regard.
And how i should proceed further with this issue.??
ThanksHi,
You issue in your system has 2000Nou2019s purchase orders with release strategy has been triggered but 5 to 10 purchase orders do have release strategy.
& when you are creating a new PO with reference to old purchase orders (which release strategy has not triggered) and on saving NEW PO created with triggering release strategy.
Cause for above:
PO which release strategy does not trigger because the purchase orders are created before setting release strategy for PO. Those PO triggered release strategy and all are created after setting release strategy for PO.
Action:
Its completely business call for business users to go for options:
Option-- >1# You can use same old PO which release strategy does not triggered, do GR and all other process
Option-- >2# You can create new PO with reference old PO which release strategy does not triggered and upon saving you will have new PO number with release strategy triggered, then release PO & do GR and other related process.
Regards,
Biju K -
PO Release Strategy - Only for Non MRP generated materials
Hello,
I have a requirement in which any material which was generated via MRP (via PR) should not go through a release strategy at the PO level, but a non MRP generated PR should...
Is this possible at all? I know its possible at the PR level, but not sure at the PO... Would this be a case where we would need to added a field to the CEKKO structure thats for MRP generated PRs ?
ThanksHi,
By business any PO created, should follow release procedure as PO a committed document which will further send to vendor.
If you are sure about your requirement, PO created from MRP PR should not follow release strategy, then no need to go for any User Exit.
Just create separate document type for PR (ZMNB) , create separate document type MRP PO( ZMNB) and link MRP PO document type ( ZMNB) with MRP PR document type( ZMNB) in flowing path:
SPRO>MM>Purchasing>Purchase Order>Define Document Types
Now select your ZMNB B Purchase Order Document type and click link purchase requisition document type in Dialog Structure, enter ZMNB Purchase Requisition Document type with a new entry & save.
As you created release characteristics of document type (CEKKO with BSART), then do not keep Value u201CMRP PO document type (ZMNB) u201Cin the release characteristics of document type and design your release strategies.
Now create your PO with MRP PO document type (ZMNB) and see no release strategy triggered.
Regards,
Biju K -
Purchase order release strategy with multiple characteristics
Hi All,
We have Purchase order release strategy based on the following characteristics:
Total Net Order Value
Purchasing Organization
Release strategy Type
a few other custom fields
We would like to have PO's with release strategy based on a particular Material Group [say X]. I have created a new Characteristic with respect to CEKKO-MATKL and added this characteristic to the same class.
I have created a new release code [HR] [we need a different person to sign off] and a new release strategy [TR] for which I have assigned the release code HR. In this release strategy, I have set it to get activated for a particular Material Group that does seem to work, but the remaining PO's are not getting triggered for other material groups. For other release strategies, I have left the material group field blank, because they need to be triggered for any material groups except X.
Could you please let me know if I am missing something or is there an alternate approach to this ?
Thank you,
SatishHi,
Obviously system will not trigger release strategy in ur case since in the classification data for other strategies u have left it blank excepting X for one strategy.
Since u have added a new characteristic Material group and assigned it to class then system expects an input for Material group for triggering release tab.If this is left blank then system by default will not trigger release strategy tab.
Solution:
First add all existing material groups in values tab of mat group characteristic then maintain the required set of material groups except X in other strategies in classification data.
Hope this is clear to you.
Regards,
Uzair -
Overall release of PR in Release Strategy
I have created item-wise release of PR using with Classification of Rel Str.
But when I am creating overall release of PR I am not getting the tab.
I made settings in Rel Gp screen (ticked te check box for overall rel) & also ticked the check box in the document type of PR.
Pl guide
regards
VSHi VS
Am confused. You wrote 'Have created item-wise release strategy' and also asking 'Overall release'.
If you have "made settings in Rel Gp screen (ticked te check box for overall rel) & also ticked the check box in the document type of PR", then you have configured Overall release.
If PR does not get release strategy tab at header, it could be due to incomplete release strategies. No release strategy might have been triggered for your PR data. Do you see release strategy tab at item level ?
Best regards
Ramki -
Service entry sheet Release strategy Error
Hi Guys
I have one scenario where Iam not able to post Service enrty sheet
We have release strategies A1,A2,A3,A4,A5
Some service entry sheets are there in the system with each release strategy
We have deleted A2,A3,A4,A5 and A1 remains there
While release the service entry sheets which are having Release strategies A2,A3,A4,A5
We are facing problems not able to release
please provide any solution to this error ,
It is not possible to restore previous release strategies A2,A3,A4,A5
We need to change release strtegy A2,A3,A4,A5 to A1 for existing service entry sheets
Please suggest solution.
Thanks in Advance
SAP MMHi,
You are created release strategies A1, A2, A3, A4 & A5 and now deleted A2, A3, A4, A5 but A1 remains there in the system.
You could have take precaution ieu2026u2026all SES should be released 1st and then deleted youu2019re release strategies A2, A3, A4 and A5.
For quick solution------ >As now deleted A2, A3, A4, A5 and you want to triggers A1 only for all already created service entry sheet(SES) , then just go to all created SES, do some changes( like change quantity and then retrieve the original quantity in SES) by editing SES and see how re- triggers release strategy A1.{ 1st do it for one SES(as SES number created, you will have same SES number after changes in SES) and try for all SES}
Regards,
Biju K -
Workflow not triggered for PR from MRP run
Hi,
I have PR Release strategy workflow configured, working well when i try to create PR manually, triggers workflow.
PR's created thorugh MRP run, triggers release strategy but not workflow.
I checked the event trace 'releasestepcreated' event not triggered through MRP run.
Please respond ASAP.
Your inputs will be highly appreciated.The response i got from SAP.
Please see note 67866 Purchase req. from materials planning -> no workflow
Thanks,
Indira -
Problem with purchase order release strategy
Hi Guru's
i am dealing with problem of service purchase order release strategy , when i making the service po , i am not giving any over fulfillment tolerance , after release & making Service entry sheet of PO , when i go to the change mode and change
over fulfillment tolerance say 90% , system allow me to make , and not applying release strategy again , so there can be a miss use of this Scenario , so is there any possibility that release strategy , will appear again when change the tolerance ,
0r any other idea from your side , to avoid this ,
your suggestions are really always helpful to me , please guide me for this also
Thanks & regards
NehaHi Neha,
A reset of the release strategy only takes place if
- the changeability of the release indicator is set to '4' in
case of a purchase requisition and '4' or '6' in case of
another purchasing document (purchase order, request for
quotation, contract, scheduling agreement),
- the document is still subject to the previous release
strategy,
- the new TOTAL NET ORDER VALUE is higher than the old one.
The total net order value is linked to CEKKO-GNETW for a purchase order,
CEBAN-GSWRT for a purchase requisition item-wise release and CEBAN-GFWRT
for a purchase requisition overall release.
If you have maintained a Tolerance for value changes during release
(V_161S-TLFAE), the release strategy is reset when the value of the
document is higher than the percentage you have specified and if the
document is still subject to the previous release strategy.
Review the SAP note 365604 and 493900 for more
information about Release strategy.
Regards,
Ashwini.
Maybe you are looking for
-
404 Error when loading IWeb page
Greetings once again! I have been using the IWeb program for setting up my business in nature photograhy and have passed out business cards that say web.mac.com/debo0063/iweb and people have been telling me they get 404 errors when they look up my si
-
I chose by mistake ''voice over'' and now I can't unlock my iPod
Yesterday while I was changing some settings I saw that Voice Over, I didn't know what it was so I chose it and then I couldn't choose anything else. After that iPod locked and now I can't unlock it . I can't choose and select anything. Can someone g
-
Implement Database Audit on Oracle applications DataBase
Hi , I have faced an issue . there are someone log in to the database and with sql statement through sqlplus he delete a record I need a plan to implement an audit for this issue and a security method to apply to prevent this issues and if it applica
-
GL account description different
Hi Guys, I have some postings that on the description field is not pick up the gl account description but the asset number. Does anyone know how can I solve it? Thanks
-
HT4539 I am being restricted from downloading items already purchased.
For a long time now, items which I have purchased will not down load automatically. Now I can not select SD versions. I have not been able to track prior purchases to redown load. It seems as though my ablility to download purchased items is being sy