BOM Explosion not seen

Dear Experts,
My Equipment BOMs and FL BOMs are not seen in the structure view when gone through IH01 (All relevant check boxes ticked in)
Whereas, these are visible when I go through IL03 --> Structure.
May kindly share the knowledge to troubleshoot.
Regards
Jogeswara Rao

Dear Friends,
I have found the problem.
This is happening because the date value in the Valid From field of IH01 is 31.12.9999.
This I have set to Dynamic Date Calculation with Current Date Name of variable. (In the Variant Configuration)
Now the current date is defaulted in this field and the BOMs are appearing.
Regards
Jogeswara Rao

Similar Messages

  • MRP RUN- KIT BOM explosion not working

    We setup one layer BOM’s for our maintenance KITs as parent material and components as child material.  For  example KIT is TS10000-K1 and components are TS10001, TS10002 etc setup as next layer with in the BOM. Both KITS and components are defined as material types ERSA (Spare parts). These one layers BOMs are setup as production BOMs and expected to create purchase requisitions for KITS and components by exploding BOMs during MRP runs. We use purchase requisitions and convert them into POs to procure both KITS and components. We DO NOT USE Panned orders and Production orders. 
    The safety stocks / reorder point are considered as demand for KITS and components as we do not have any external demand for KITS and components.  
    MRP run is creating purchase requisitions automatically for both KITS and components as per safety stocks and reorder point defined in MRP Views of Material Master. This is working as expected.  
    The issue is: KIT BOM’s are not exploding to generate purchase requisitions for the dependent components of KIT BOM. Please suggest the way to resolve this issue. 
    Split valuation: Also we plan to use split valued KITS with both new and refurbished. So we need BOM explosion for split valued KITS
    also (after the 1st issue is resolved).   
    I verified the following items to make sure the required configuration and data setup is defined correctly.
    1) Planning file activated Plant - OMDU 
    2) Executed MRP run with Total Planning - MDBT and MD02 (single item, multiple levels)
    3) BOM explosion for MRP activated- OS23 
    4) MRP type in MRP1 view- PD and VB (I tried both separately but BOM is not exploding).
    5) Procurement type “F” (MRP 2 view) and lot size “EX”  
    6) Planning strategy in MRP 3 view (tested w/o planning strategy and with strategies 10 and 40. But BOM is not exploded)
    7) BOM status and usage (status is active and usage is for production-CS02 and OS20)  
    8) BOM Validity date (Valid) 
    9) BOM structure in CS12 (BOM is exploding in CS11) 
    10) Availability check  
    11) Selection of BON ID to have BOM usage indicator assign (OS31).
    12) No alternate BOMs or production versions or work scheduling view are used.
    Please review the above 2 issues and suggest any workable solution. Thanks in advance!
    NOTE: I extensively used MRP with multi-level BOM explosion in my earlier projects without any issue. However the above issue is a  bit strange  why one layer BOM is not exploded in this case. 
    Regards
    Srini  

    Hi
    Thanks for your response. I reviewed all SAP notes and none of them are applicable to my scenario.
    1808396 - BOM changes not considered by MRP: I have not changed BOMs.
    1781324 - MD11: Valid BOM alternative is not found. We do not have alternative BOMs.
    1791009 - No BOM explosion after changing production version: We am not using production versions.
    Our Material KITS are PM spare assemblies set up as BOMs and consists of individual spare parts as components. We are creating purchase requisitions and not planned orders. We are not using PP functionality/Production orders.
    MRP is generating purchase requisitions for KITS and components as per ROP and safety stocks. In other words it is working as expected.  The issue is BOMs which are parent assemblies are not exploding to the next lower level components.
    Please note that I am not getting any error messages when MRP is executed.
    Regards
    Srini.

  • BOM explosion not done because there is no free item number anymore

    Hello,
    I have a problem with BOM explosion when creating a sales order.
    All the following actions are done with VA01 :
    -  I enter a material (main item 10) with a rejection reason, so the BOM explosion is not done :OK.
    - Then  I add the same material (main item 20) without rejection code, so the BOM explosion is done, it means sub items 21, 22., ...,31,32 are determined:OK
    - Finally, I remove the rejection code on item 10, the problem is that there is no place anymore to do the BOM explosion because I have 12 sub items (10 +12 = 22 and it is not possible as I have already an item 20).
    I have a popup with message V1-142 (There are not enough item numbers free for a structure explosion).
    I know that it is possible to change the increment with VOV8, but my customer want to keep this one: 10 by 10 for main item and 1 by 1 for sub item.
    He told me that he think that there is a user exit in order to put the remaining sub items at the end of the sales order like this
    10 main item A
    11 sub item 1 (A)
    12 sub item 2 (A)
    19 sub item 9 (A)
    20 second main item (B)
    21 sub item 1 (B)
    22 sub item 2 (B)
    32 sub item 12 (B)
    33 sub item 10 (A)
    34 sub item 11 (A)
    35 sub item 12 (A)
    Maybe it's a strange idea, but could you please tell me what are the different possibilities to manage sub items when there is no place to put them :
    - put a higher increment in VOV8? Ok but my customer don't agree
    - other solutions?
    Thanks.

    Hello,
    Did you ever find a solution for this? The notes mentioned in the earlier post dont appear to be relevent for 6.0.
    I have a similar issue when dealing with Cross Sell items. When it tries to insert the additional items I get the V1142 message, then the items are copied at the end of the list but the higher level item reference is incorrect for the cross sell items.
    I do not want to change the increments but it appears to be the only option.
    Any ideas are appreciated.

  • BOM explosion not done for externally procured item.

    Hi Experts,
    We have done MRP run for finish goods which is creating planned orders for HALB material, but it is not further exploding the BOM of HALB material, so  we are not getting any planned order/pur requisition for ROH. Plz help me out asap.

    Hi,
    When you run MRP for an externally procured item say - HALB , proposals will be generated say-planned order for ext proc for that item and the BOM will not be exploded further.

  • BOM Explosion not happening in RFC call...

    Hi All,
    We are facing a strange issue in our project. We are using a RFC call for order creation. When we execute the FM through SE71 using a BOM material, the BOM gets exploded correctly. However, if the same material is passed through the RFC call, it is not getting exploded.
    The BAPI used for order creation is BAPI_SALESORDER_CREATEFROMDAT2.
    If any of you have encountered such an issue and know any resolution, please let me know at the earliest.
    Thanks in advance.

    Make sure that you are converting to the internal format when calling via RFC.  Meaning, that you need to have leading zeros for things like sales document numbers.  So if your sales documennt number is 12345, make sure that you are passing it to the RFC call, like 0000012345.
    Regards,
    Rich Heilman

  • VC - new characteristic does not show in PS BOM explosion / CU50

    Hello World,
    we added a new Characteristic to a class that is basis for a Material BOM explosion. In transaction CU50, the new characteristic can be configured by selecting its single values and the result shows up correctly in the BOM explosion. 
    Unfortunately, it is does not show up in the BOM explosion result of the SAP PS module @ Network Activity where the explosion is done concerning to our biz process. All other characteristics explode properly in the PS BOM explosion. I have no clue about the difference of the newly added characteristic is that makes it behave differently (only) in the PS system, not showing up in the result.
    In CU50 @ Menu Extras @ Result I found a trace of the difference, but cannot interpret it due to a lack of documentation of the resulting screen that is entitled "Configuration : Result". Here, in table "Detail List", only the faulty new characteristics show additional extra Dependency entries with a light green background that cannot be found with all other characteristics in the same table. These extra entries can be drilled down by double-click and produce a pop-up window that shows some status information and the dependencies source code.
    Question: what do the extra entries of dependencies say, why are they shown and why not at other characteristics?
    By understanding this difference I hope to find the reason why these characteristics are not exploded in the PS module (which is my primary question).
    Thank you for a helpful answer!
    Marcus

    Hi Jong - Moon cho,
    Please check following setting,
    1.Consider setting the Individual/Collective indicator to 2. (MRP 4 view)
    2.In order to get dependent requirements from the planning of configurable materials, components should not be configured with strategy group 70 or 59.
    Also refer the bellow link
    http://help.sap.com/saphelp_47x200/helpdata/en/cb/7f9b7043b711d189410000e829fbbd/frameset.htm
    Regards
    Girish

  • BOM explosion in subcontracting PR

    Hi...
    I have one issue of BOM explosion in subcontracting PR.
    I have created BOM, routing & PV. Production version maintained in info record.
    While creating manaul subcontracting PR , BOM is not exploded giving error message as "Not possible to determine any components".
    I have checked validity of BOM, PV found ok.
    Also Proc. type X & Spl. proc type 30 maintained.
    Any suggestion to the problem appreciated
    Regards
    Tushar

    Dear Tushar,
    Check this link
    [Sub contracting PO - BOM components are not seen;
    Regards
    Madhu

  • Report for Cost of Multiple products with Multilevel BOM explosion

    Hi,
    Our client has a requirement of a report showing standard cost estimate of multiple FG products, with multi-level BOM explosion.
    In short, the requirement is to get a CK13N report for multiple products.
    Has anyone come across such requirement? The requirements seems to be very normal.
    But, I have not seen any standard report for the same. If there is any, please suggest.
    or suggest a better solution for the same.
    Thanks in advance. Pts guaranteed.

    Hi,
    I totally agree with you that this is a totally vague requirement.
    However, let me share the reason for such client requirement.
    We have a customer, for which we produce certain parts for select models. Now, the arrangement with customer for pricing is based on the raw material and other production cost for all such parts. Based on the fluctuations in cost, the pricing would be finalised.. on a monthly or quarterly basis.
    For this purpose, the customer requires to know the raw materials used in each of the part.
    Individually it could have been managed. But the price change in terms of % is decided at global level and not for each part.
    Please suggest

  • Production Order, BOM explosion

    Hello Guru,
    I have a production order, which when view the Administration tab of it's creation was on 30.01.2009, but in the General Tab it start/finish date was 01.02.2009. And the confirmation was 02.02.2009. One of the component of the FG material for this order was subject for material substitution with change number effective on 01.02.2009. When i check the BOM list of the order it still display the old component A, but in its confirmation goods movement it already use component B the component A seen in the BOM list of the order was not been goods movement on the confirmation. How this happen? And also can you explain to me during creation, release,confirmation of order when is the time it really explode BOm for the Fg material?
    Thanks

    Thanks Vivek it is clear to me the since the confirmation was been establish effective of the bom change.
    But it is still not clear to me that the creation date of the order was 30.01.2009 and its start/finsih date in general tab is 01.02.2009, how was this happen?
    And please explain to me the process of BOM explosion, that will be registed in the Master Data tab of the order, when this was really exploded? in the creation, released,confirmed? since in the master data it tells that BOM explosion was on 01.02.2009.
    Could you help me interpret the status change done in the order,
    BASC batch change assignment complete  active 02.02.2009
    BCRQ order to be handle in batches active 30.01.2009
    BNAS batch not assigned inactive 02.02.2009, active 02.02.2009
    CNF confirmed active 03.02.2009
    CRTD created inactive 02.02.2009, active 30.01.2009
    DLV delivered active 03.02.2009
    EXPL external conv. of planned order active 30.01.2009
    EXTS change by external system active 30.01.2009
    GMPS goods movement posted active 02.02.2009
    MACM material commited active 02.02.2009
    MANC mat. availability not checked inactive 30.01.2009, active 30.01.2009
    MSPT material shortage inactive 02.02.2009, active 30.01.2009
    NTUP dates are not updated inactive 30.01.2009, active 30.01.2009
    PCNF partially confirmed inactive 03.02.2009, active 02.02.2009
    PDLV partially delivered inactive 03.02.2009, active 02.02.2009
    PRC pre-costed active 30.01.2009
    REL released inactive 03.02.2009, active 02.02.2009
    SETC settlement rule created active 30.01.2009
    TECO technically complete active 03.02.2009

  • BOM is not getting displayed in case of centralized planning plant.

    Dear All,
    there are 2 plants for which we have centralized planning. the users have created Equipment BOM for the two plants. but in case of the second plant for which the planning plant is different from the maintenance plant, the BOM is not getting displayed in the Maintenance Order (i.e. in the components tab).
    kindly through some light on it. whether i have to do some settings for it.
    Regards,
    Ritesh Kapoor

    Hi,
    Yes while using IH01, i have ticked the BOM explosion option, but when i am giving the plant there then only it is displaying the BOM of that equipment.
    Also when i am creating an order for the same equipment, then it does not displays the BOm & shows the message which i have written in my previous mail.
    Ritesh

  • BOM Explosion for Multiple Process Orders

    Hi,
    I hope someone can assist me with the following: Is there a report I can run or transaction I can do to have BOM explosion for multiple Process Orders? I would like to input process orders for a week and see the BOM details per PO.
    Thanks

    Dear Sukendar,
    1.For this requirement you have to go for a Z report and you can give the Functional Spec's to prepare
    this report to your ABAP consultant.Prepare the input format,logic of the program and the output format.
    In the logic part you can make use of this Functional Modules's CSAP_MAT_BOM_READ or 
    CSEP_MAT_BOM_READ  or CS_BOM_EXPLOSION   or CS_BOM_EXPL_MAT_V2 .
    2.Using CEWB helps you to identify all the material that's having the BOM,but here the report does not
    shows you the level by level by BOM for a FERT.
    Check and revert back.
    Regards
    Mangalraj.S

  • BOM is not exploding in Sales Order

    Hello,
    In Sales Order VA01, when i try to put my finished product it has an error message: ( Material 10001676 is not copied from the bill of material.)
    and the Diagnosis
    When the bill of material was exploded, it was established that no sales document item could be created for material 10001676.System Response
    The system ignores the material during bill of material explosion.Procedure
    Check if the BOM explosion can be used without material 10001676. If not, delete the main item which lead to the BOM explosion. You may be able to enter an item manually in which the material 10001676 in the BOM is replaced.
    How could i explode the FG material in the SAles order
    thanks

    Check whether you have created the BOM correctly or not.
    Create the BOM in t.code CS01.
    BOM usage "5" must be entered and specify your Plant.
    In the next screen,enter the components and their units/quantity and the BOM item category as "L" (stock material) and save it.
    Go to the material master of the BOM material, in the "Sales org 2" ,enter "Item category group" either LUMF or ERLA.
    If you want that the sub-items (Item category TAE) will be free and Main item(Item category TAQ) will be priced, then use Item category Group ERLA.
    If you want that, Main item(Item category TAP) will be free and sub-items(Item category TAN) will be priced, then use Item Category Group LUMF.
    Go to the Item category details (VOV7) for Item category TAQ and TAP, in field "Structure scope" ,enter value A or B as required from the drop down.
    Now, if you will create the order, the BOM will explode.

  • BOM Explosion needed on PO and/or Delivery for Stock Transfer PO Process

    Good afternoon,
      I have been researching the SDN and web for a solution to my problem to no avail so far. 
    The business problem I need to solve is the requirement for our STPO process to explode certain BOM's that are transfered from one company/plant to another company/plant in order to record batch/serial # component information by the delivering plant on the delivery and verification of the batch/serial # in the receiving plant during MIGO processing of the delivery.  This is needed by our Service Mgmt department in order to track servicable items within the Finished Good (medical devices industry).
    It appears on the SDN that a BOM can not be exploded on a non-Subcontracting PO (which would be ideal for us), but barring this problem, we are trying to have the BOM explode in the Delivery created from the STPO via the VL10B transaction.
    The STPO generates a Delivery doc with type NLCC and item category NLC.  I have maintained the material master for the BOM material to have an Item Category Group of ERLA, and I have modified Item Category Determination in configuration in Logistics Execution for deliveries to include ERLA, usage V, and NLC as default item category.  But, the deliveries generated from the STPO still do not explode, like what normally happens if the delilvery of the BOM was created from a standard Order.
    The components for the BOM need to be displayed on the Delivery (if not the STPO), so the cleark can record the Batch/Serial #'s for each component.  Then when the receiving plant posts the Goods Receipt for the delivery a user exit we have (based on movement type and material document code) builds a Service Mgmt table that is then processed to De-install the BOM and components from the former plant and install the BOM and components at the receiving plant (and then subsequently at the ultimate customer's location when a normal sale is made), generating a new Functional Location.
    Has anyone here had to do anything like this before?  Would any of you have any ideas on how this BOM explosion might work on the PO or Delivery?
    Thanks in advance.
    Scott.

    No responses to this question.
    Subject dropped.

  • BOM Explosion needed on Delivery for Intercompany Stock Transfer Order

    Good afternoon,
    I have been researching the SDN and web for a solution to my problem to no avail so far.
    The business problem I need to solve is the requirement for our STPO process to explode certain BOM's that are transfered from one company/plant to another company/plant in order to record batch/serial # component information by the delivering plant on the delivery and verification of the batch/serial # in the receiving plant during MIGO processing of the delivery. This is needed by our Service Mgmt department in order to track servicable items within the Finished Good (medical devices industry).
    It appears on the SDN that a BOM can not be exploded on a non-Subcontracting PO (which would be ideal for us), but barring this problem, we are trying to have the BOM explode in the Delivery created from the STPO via the VL10B transaction.
    The STPO generates a Delivery doc with type NLCC and item category NLC. I have maintained the material master for the BOM material to have an Item Category Group of ERLA, and I have modified Item Category Determination in configuration in Logistics Execution for deliveries to include ERLA, usage V, and NLC as default item category. But, the deliveries generated from the STPO still do not explode, like what normally happens if the delilvery of the BOM was created from a standard Order.
    The components for the BOM need to be displayed on the Delivery (if not the STPO), so the cleark can record the Batch/Serial #'s for each component. Then when the receiving plant posts the Goods Receipt for the delivery a user exit we have (based on movement type and material document code) builds a Service Mgmt table that is then processed to De-install the BOM and components from the former plant and install the BOM and components at the receiving plant (and then subsequently at the ultimate customer's location when a normal sale is made), generating a new Functional Location.
    Has anyone here had to do anything like this before? Would any of you have any ideas on how this BOM explosion might work on the PO or Delivery?
    Thanks in advance.
    Scott.

    No responses to this question.
    Subject dropped.

  • How to restrict BOM explosion in Quotation and Sales  Order

    Dear all,
    How can we restrict BOM main item explosion in Sales Order.
    this BOM main item is having special order items which have to generate purchase requisition (item category - BANC),
    with out exploding bom main item, can we generate a  purchase requisition for BOM subitems, can any body explain me that how can we do that.
    your suggestions will be highly appreciated.
    thank you
    Raghu Ram

    Hi Raghu Ram,
    The BOM explosion is controlled by item category.
    In the item category configuration screen, under "Bills of Material/ Configuration", you can see "Structure Scope" field.
    Select the one which is applicable to your case:-
    "blank" - Do not explode material structure
    A - Explode single-level BOM
    B - Explode multi-level BOM
    C - Configuration, no BOM explosion
    D - Configuration, poss. with BOM explosion
    E - Structure from Customer_Function (product selection)
    Hope this helps
    Regards,
    Nicole

Maybe you are looking for

  • Can I sync an iPod touch and an iPhone on one account?

    I have an iPod touch and my dad has an iPhone.  I have an iTunes account on my computer and he has his own account on his laptop.  He wants some music on his iPhone that is currently in my library.  Can I connect his iPhone to my iTunes account to pu

  • PC and MBP keyboard/mouse switch

    I got a MS natural keyboard as well as Logitech thumb-ball mouse that I use often with my PC. When I put the MBP on the desk, I'm constantly switching to the MS Natural KB and Logitech Mouse and thought if there's such KVM device that will handle onl

  • Big history table based on SCD2

    Ola, Has anyone of you ever experienced difficulties running millions of records through a SCD2 mapping? I created a couple of history tables and created mappings to fill them, based on SCD2-method. When I tested the mappings with a subset of data (1

  • Download SAP Netweaver Mobile 7.1

    Hi Friends, Where can I get SAP Netweaver Mobile 7.1? Is it available on Service Market Place? If yes from where i ccan download it? If no, then what is the procedure for getting DVD's from SAP? Pls help me. Its urgent. Thanks and warm regards Purnen

  • Dvd to website

    hello everybody i have made a project in encore with 9 movies, motion menu, chapters etc . i would like to put it in my website as is. is it posible? i exported it to flash and got a file with 4 files on it 1. sources 2. flash dvd .swf 3.authoredcont