BPC 10.0 NW - InfoAreas missing

Hej Gurus,
One of our users tried to make a copy of an environment and calling the copy "BPC". This copy failed after some time. After this failed copy, we keep getting the same error message everytime we try to copy an environment:
"Crete environment EnvironmentShell failure"
However, we are not trying to create an environment called Environment called EnvironmentShell but rather using the EnvironmentShell as the source of the copy. The same happens, if we try to copy from other sources, it fails giving the source environments name.
I have therefore been into RSA1 in BW to find the problem, and I am pretty sure, I have found it.
The normal structure in InfoProviders in RSA1 is
Business Planning and Consolidation - /CPMB/BPC
- Environment 1 - /CPMB/Env1
   - Cubes in Environment 1
   - InfoObjects in Environment 1
   - Multiproviders in Environment 1
- Environment 2 - /CPMB/Env2
   - Cubes in Environment 2
   - InfoObjects in Environment 2
   - Multiproviders in Environment 2
etc.
However, this structure no longer exist in our BW. The CPMB/BPC top note, and all InfoAreas have been deleted, and therefore all Cubes, InfoObjects and MultiProviders is in the "Unassigned Notes".
Is there anyway to recreate the structure in BW, so we are able to create new stuff?
Best Regards,
Mikkel Kristensen

Hi Mikkel,
You may try to drag and drop (just using your mouse) back to the /CPMB/BPC. Can you provide a screenshot? what does it look like in the unassigned node? Are all the cubes and infoobjects as a whole are in the /CPMB/Env2 in the unassigned nodes?
Also, you can check table UJA_APPL from SE16 and see if you can find the entries for the corresponding environment.
Best Regards,
Charlie

Similar Messages

  • SAP BPC NW 10 - Restore InfoArea /CPMB/ENVIRONMENTSHELL

    Hello Experts,
    We are facing a problem with Environmentshell and in order to try to resolve it I've followed note 1858372 - Failed to activate ENVIRONMENTSHELL - BPC 10NW .
    The problem is that now I don't have InfoArea /CPMB/ENVIRONMENTSHELL created and so I have all the infobjects under "not assigned" node.
    How can I have infoarea /CPMB/ENVIRONMENTSHELL created again? I have run program UJS_ACTIVATE_CONTENT with success but nothing happened.
    Can you help me?
    Thanks,
    Nadine

    Hello Jeff,
    Please see the mesage after executing the program:
    It means it worked ok, is that correct?
    Thanks,
    Nadine

  • BPC 7.0 drill down missing values

    Hi,
    in our reports when we drill down trought a dimension,
    we have missing rows.
    For exemple:
    LEVEL 1 - TOTAL 100
    LEVEL 2A - TOTAL 80
    LEVEL 2B - TOTAL 5
    we have LEVEL 2C missing with TOTAL 15
    the reason seems to be that there is another dimension named "2C" which has nothing to do with this hierarchy.
    If we only secodn level we have:
    LEVEL 2A - TOTAL 80
    LEVEL 2B - TOTAL 5
    MATERIAL_LEVEL 2C - TOTAL 15
    BPC is putting a prefix to "2C" because "2C" is also a customer...
    is it possible?

    Please create a customer message from the SAP Service Marketplace and report this potential bug with drill-down.  As mentioned when a dimension member is not unique BPC will prefix the member with dimension name and I suspect this is causing the issue when related to drill-down.
    Thanks
    [Jeffrey Holdeman|http://wiki.sdn.sap.com/wiki/display/profile/Jeffrey+Holdeman]
    SAP BusinessObjects
    Enterprise Performance Management
    Regional Implementation Group

  • Infoarea missing in query designer

    Hi All,
    We are using BI 7 analysis authourization, we had a request for one user to add one ods access, we have granted access to the user to ODS via RSA1. But issue is we are not able to see the infoarea and ods in query designer.
    Is we need any authourization to use the ods in BEX analyser or any other things need to be followed
    Regrads,
    Anbu

    Hi Anbu ,
    For query we need to assign some roles .Sometime even if we are able to see an infoarea in RSA1 but not able to see the query
    Check the role that query is having in RSA1->metadata repository
    In BEX analyzer you can check roles assigned to that user .This will tell you which infoarea are accessible to the user .
    You can also check in SU01 for roles of a specific user .
    Ask your BASIS to check which roles are needed to be assigned by comparing roles of user who can see those infoarea and who cannot .
    Hope this will help .
    Regards,
    Jaya Tiwari

  • BPC NW7 sp03 installation(packages missing)

    Hi
    WE are installing BPC7.0 NW sp03 as per installation guide. Successed in installing BPC admin client, office client.
    But at BPC excel interface, i observed few options are disabled.
    Eg: Under  eData menu item many sub menu items are disabled(16 out of 19) as well for appset(appshell) and application(planning), when i chose to run data manage pakage, a dailog box comes with company folder, but no package groups and packages are exising. Not only for appset(appshell) and application(planning), but also i tried with custom appset & app combination also, i'm not viewing any package group & packages, what might be problem?
    In backend(bw system), check system->status, for software component(CPMBPC), no support package is there? I know latest SP is sp08. Is datamager packages are not viewing, becoz of absence of support packages?
    could anyone  help for post installation activity?
    thanks,

    Any suggestions please..

  • Authentication error when creating EPM Add-in connection with SAP BO Enterprise connection type

    Hello, Experts,
    I have a problem with creation of EPM Add-in connection when SAP BusinessObjects Enterprise connection type is selected.
    An error message is "Error while communicating with the server. Framework message: Authorization failed."
    Here are the steps that were implemented and how this issue was reproduced:
    SAP BusinessObjects Planning and Consolidation 10.0 SP12 for Microsoft was installed and configured.
    Integration between SAP BPC and SAP BusinessObjects BI 4.1 SP02 was implemented. SAP BO users can successfully connect to SAP BPC system.
    EPM connector was successfully installed and deployed in SAP BusinessObjects BI server.
    BPC ODBO 2.0 SP04 64BIT was installed in SAP BusinessObjects server.
    EPM connection was successfully created in SAP BusinessObjects CMC.
    EPM Add-in and BPC ODBO 2.0 SP04 32BIT was installed in another computer (let's call it CLIENT) which has MS Office 2007 32BIT installed.
    From CLIENT computer we have launched Excel manually and successfully created BPC connection with Connection Type - Local.
    Then we have logged into BI Launch Pad and launched New / EPM document (Excel). Excel has started.
    In EPM Add-in we have pressed Logon.
    In connection window selected SAP BusinessObjects Enterprise connection type.
    An error "Error while communicating with the server. Framework message: Authorization failed." appears.
    Before this error appears we are not getting any window where we could select EPM connection (created in CMC) nor the possibility to enter username or password.
    Looking forward you valuable comments and suggestions.
    Thank you in advance.
    Donatas Budrys

    Dear, Roberto,
    Our user has Full Access to all BPC tasks and it is administrator in BI system.
    Also we can successfully connect with the same user using Connection type "Local".
    We had done some investigation and in the BPC SQL Server trace log we can catch the following message when an error occurs:
    ==============[System Error Tracing]==============
    [System  Name] : BPCXMLAService [Message Type] : ErrorMessage [Job Name]    : ValidateUser [DateTime]    : 04/23/2014 10:58:06 [UserId]      : [Exception]    DetailMsg  : {System.Exception: Invalid user    at SAP.BPC.Services.Webservice.XMLAService.XMLAService.ValidateUser()} ==============[System Error Tracing  End ]==============
    It is very interesting that after the EPM workbook is launched via BI Launch Pad till an error occurs we are NOT provided with possibility to enter any username and password. So the EPM add-in should use the same user which was logged into BI Launch Pad - in our case the user with administrative rights both in BI Launch Pad and BPC systems. Am I missing anything?
    Looking forward your feedback.
    Thank you in advance.
    Best regards,
    Donatas

  • LIVE REPORT ERROR

    Hi,
    I'm using BPC 7.0 SP 7 on single server SQL 2005.
    I try to create a new Live Report, but when I try to display selecting it from Live Report list I obtain this error:
    SYSTEM ERROR:
    The system encontered an error and cannot proceed.
    Please select the Back button and try again. If the problem persist contact your administrator.
    Job name :  http://sapbbi/OSoft/WebReport/WebReportView.aspx?ID=5
    Detail       :  Cannot load report template - return status="failed" -- SessionInfomation -- SessionStatussucceedSessionStatus -- SessionIDSessionID -- SessionTimeSessionTime -- SessionLastRequestTimeSessionLastRequestTime -- SessionInfomation -- resultFormato della stringa di input non corretto.resultreturn
    Anyone can help me?
    Thanks,
    Fabiola
    Edited by: Fabiola Vezza on Jul 13, 2011 4:01 PM

    Has the problem been solved?
    We are from this thread BPC 75 NW - Dimension files missed and have the same problems.
    Yet, previous post from Rizwan was helpful and with this we appeared to be able to run application pool (because it hasn't been working - now it's ok). But IIS doesn't - IIS throws two errors when BPC client try to download dimension from server:
    1) A process serving application pool 'ASP .NET 2.0' terminated unexpectedly. The process id was '2056'. The process exit code was '0xc0000374'
    2) A process serving application pool 'ASP .NET 2.0' suffered a fatal communication error with the Windows Process Activation Service. The process id was '3948'. The data field contains the error number.
    We would highly appreciate if author provide a bit information about the problem

  • SSAS Cube Connection with SAP BO IDT

    Hi Guyz,
    I have one requirement where i have to connect the SSAS cube with SAP BO along with cube security.I was able to connect the SSAS cube with the help of IDT using cube's Dll file , but i couldnot able to implement cube security in my SAP BO environment. The security incides the specific roles which are there in cube. My connection is not implementing the security which is there in cube.
    Kindly , provide any insights if anyone have on these.
    Thanks in Advance.
    Shweta

    Dear, Roberto,
    Our user has Full Access to all BPC tasks and it is administrator in BI system.
    Also we can successfully connect with the same user using Connection type "Local".
    We had done some investigation and in the BPC SQL Server trace log we can catch the following message when an error occurs:
    ==============[System Error Tracing]==============
    [System  Name] : BPCXMLAService [Message Type] : ErrorMessage [Job Name]    : ValidateUser [DateTime]    : 04/23/2014 10:58:06 [UserId]      : [Exception]    DetailMsg  : {System.Exception: Invalid user    at SAP.BPC.Services.Webservice.XMLAService.XMLAService.ValidateUser()} ==============[System Error Tracing  End ]==============
    It is very interesting that after the EPM workbook is launched via BI Launch Pad till an error occurs we are NOT provided with possibility to enter any username and password. So the EPM add-in should use the same user which was logged into BI Launch Pad - in our case the user with administrative rights both in BI Launch Pad and BPC systems. Am I missing anything?
    Looking forward your feedback.
    Thank you in advance.
    Best regards,
    Donatas

  • SAP BPC 7.5 NW SP15 - Dimension member descriptions are missing

    Hi Expert,
    We are using SAP BPC 7.5 NW SP 15, we use admin and client in spanish language see image attached
    All users see through BPC CLIENT for Excel in spanish mode both ID and descriptions but when we added new user it can´t, just it can see ID member. We refresh Dim Cache member from client side but nothing happens.
    We reprocess All dimensions through BPC Admin Client in spanish mode and doesn´t have any efect in dimension description?
    is there any issue with this?
    please give an advice to follow,
    Thanks for your answer.
    regards.

    Hi Roberto,
    thanks for your anwser
    We checked though BW and saw it that long descriptions were set in Spanish language key which is the same language as BPC for Excel was openend.
    As solution we checked at UJA3_USER_LANGU table, we notice that users in which descriptions are missing were registered in English language, therefore we deleted this user and its language and then was recreated those users through BPC ADMIN client.
    Thank you,
    Giovanni

  • Data missing in QA after BPC transport

    Hi,
    I have transported the Appset, the request transported successfull to QA from Dev with RC =0.
    however ceratin Input schedules, reports, Scripts are not visible in BPC QA. are we missing something?
    CV in Action Pane in QA says 'more' 'more'
    Do I have to make a copy of APSHELL in QA before I do the Appset transport for the first time?
    Please help

    No, you only need to configure it once and transport it throughout the landscape.  If you go to the class CL_UJT_TRANSPORTS_MGR and look at the UPDATE_CHG_TABLE method,  if there the below method call is on line 30, then you are safe.  Again, these TLOGOs are now handled by the framework, so it will add them in the table if they do not exist in the target system during import.
    lt_mandatory_tlogo = do_transports_dao->get_mandatory_tlogo( ).
    If you do not see this line of code, then I would say they DO need to be in the table in the target system.  It really depends on what SP level you are at.
    Regards,
    Rich Heilman

  • BPC 7M SP4 EVDRE missing rows - Error is  "1004-Selection is too large.}

    Hello,
    On a customer who installed BPC 7 Ms SP4 I have on client Exception log the error:
    ===================[System Error Tracing]=====================
    [System Name]   : BPC_ExcelAddin
    [Job Name]         : clsExpand::applyDataRangeFormula
    [DateTime]          : 2009-07-17 09:44:13
    [Exception]
           Detail<sg     : {1004-Selection is too large}
    ===================[System Error Tracing End ]=====================
    When I see this error there is an EVDRE input schedule expanding which have some of the rows missing rows descriptions.
    This means there is a gap of missing row header formulas stating from second row to somewhere in the middle of the report.
    If I reduce the number of the resulting rows for the same EVDRE input schedule results are ok.
    Do you know some setting to fix this?
    I tried increasing the Maximum Expansion Limit for rows and columns in Workbook Options without success.
    Thank you.

    Hi all,
    I have the same problem with 7.0MS SP07. With 59 expanded members it works. With 60 expanded members it fails.
    Mihaela, could you explain us what is the purpose of the parameters you talk about?
    thanks,
    Romuald

  • Missing Admin Console Tasks items BPC Administration

    Hi All,
    We use BPC version 5 for Microsoft.
    I have a user who has a problem with missing Admin Console Tasks items. Previously, she was able to access the items. Then she was assigned a new computer. After installing BPC (administration and Excel), now the items are missing. She could access BPC using Excel (normal tasks).
    Does anyone has observed and solved this problem before? I checked the Internet Explorer settings (security and Java JRE) and seem fine. Except the Java JRE is  bit old (1.6.0_03)
    Thanks.

    Hi Zikif Hamdy,
    It could be due to few possible reasons....so please check the following on her new computer.
    You can do the following using your login credentials - First (to find the issue).
    1) Go to client software center and click BPC Client Diagnostic
        Check BPC administration Client features. You will know whether you have all necessary softwares available on her new computer or not for installing BPC administration. If any errors it will generate error log.
    At the same time you will know whether you are able to access all BPC admin console tasks.
    2) Since she is using it for the first time on her new computer. You need to select correct AppSet & Application on current view. So that based on her security profile all necessary BPC admin Console tasks will be enabled.
    Hope this helps!!!

  • BPC 7.5: Hierarchy load fra BW. Missing "parent" nodes.

    Hi,
    i'm having problems uploading a 0profit_center hierarchy from  SAP BW to BPC.
    My problem is that the load fails due to missing dimensions members on profit_center in BPC. The missing members is the hierarchy parents, which are not a part of the masterdata on the infoobject "0profit_center"
    So for example I have a simple hierarchy:
    Parent1:
    -child1
    -child2
    -child3
    Child1-Child3 are masterdata on (dimension members) on 0profit_center. Parent1 is NOT masterdata. So the load will fail due to the fact that parent1 is not a dimension memeber in  'BPC' profit_center.
    Do I have to load the hierarchy table from BW to BPC (profit_center) in order to get the dimension members for the hierarchy ??
    Thank You,
    Joergen Dalby

    Hi,
    you need to use a formula to remove the spaces. Though not sure how to define it for hierarchy notes.....
    The formula can be defined in the conversion file.
    The formula is js:%external%.toString().replace(/s+/g,"")
    And your conversion file should look like (transposed for reading purpose).:
    EXTERNAL = *
    INTERNAL = js:%external%.toString().replace(/s+/g,"")
    FORMULA
    You can read more here:
    http://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/c02d0b47-3e54-2d10-0eb7-d722b633b72e?quicklink=index&overridelayout=true
    Under section 4.4.
    Hope this helps,
    jdalby

  • BEx 3.5 with SAP GUI 7.10 missing + sign expanding InfoAreas

    I am running SAP GUI 7.10 (patch 5) with BI 7 Addon (patch 3) and BW3.5 Add-on (patch 2)--all are the most current available at this time.  The client PC's are XP, Office 2003 SP3.  Also, to fix another error, I installed Office KB907417 per SAP Note 1025122.
    This problem only occurs when launching BEx Analyzer 3.5 via RRMX from the BW GUI, regardless of a BI7 system or a BW3.5 system.  If BEx 3.5 is opened directly via Start, Programs, Business Explorer, then the problem does not occur.
    The problem itself is that when selecting queries by InfoArea, the plus sign to expand the InfoArea is missing.  I am unable to highlight an InfoArea either.  However, if i click on one, although it does not highlight, if I use the + sign on my keyboard, it will expand.  Similarly, I can use the minus sign to collapse.
    This problem also occurs when selecting workbooks by role, and in Query Designer, when trying to expand dimensions and InfoObjects.
    For other information

    Our message was escalated and SAP (Walldorf) has responded that this is a "well known" issue that will be fixed in SAP GUI 7.10 SP8, due out in late May.  It should be available at the following link at that time:
    [http://service.sap.com/~form/handler?_APP=00200682500000001943&_EVENT=LIST&HEADER=&FUNCTIONBAR=&EVENT=LIST&ONR=01200615320200007657&NTYPE=T_CV_DELO&V=MAINT&TA=ACTUAL&AI=SWTYPSC|&AI=PECCLSC|OS&AI=PECU_OS|WIN32&AI=DELO|10002995]
    Our response also indicated that the developer erroneously indicated this was fixed in SP7, so you may see that somewhere, but it is not correct.
    Thanks,
    Jim

  • BPC 10.1 - Missing BW users

    Hi,
    I have installed BPC 10.1 When I try to assign the users to the ENVIRONMENT, BW Users are missing as in the bellow URL
    BPC 10.1 - Missing BW users
    Please help to resolve the issue.
    Regards,
    Suresh Linga.

    This is a known issue.Please refer to KBA 2036093 for details.

Maybe you are looking for