I am involved in a ramp up project.
I created a project in solman in SOLAR_Project_Admin. I am tryinig to select the business scenarios from BPR but i am unable to view the BPR structure in the SCOPE tab (Template selection within that). I need to select few scenario say, Finance and Procurement.
Could anyone help me? what are the dependcies for this task. what are the steps i need to ensure before doing this? anything in system landscape? how do i select the business scenario for the project i created?
solman 7.0 and ECC 6.0 being used.
appreciate your inputs
Drake

Hi Drake,
You will be able to select business scenarios with transaction SOLAR01 (Business Blueprint).
SOLAR_PROJECT_ADMIN is used for project admin setup. You can also choose from template projects or roadmaps.
Regards,
Ruediger

Similar Messages

  • Business users select whom to route dynamically

    Hi,
    Can BPM help in the following scenario:
    1.Bussiness users assign to who all(which users) from the roles in the next step (BPM model step)will the task be assigned.
    2.Suppose there is a select box in which bussiness users selects user to whom in the next step the job is assigned.

    Hi,
    This can be done by modifying the UI for the Business user so that they can view who all user are there in a particular role and can select the user and assign the work item to selected participant.
    Steps to follow:
    1) Make column called Assigned To: and add a component called list box/drop down list box where you need to fetch the participant w.r.t a particular role
    Note: make sure that only the business user can view this new column put some validation logic
    for each person in Fuego.Lib.Role(roleName : <Parametric Role>, parameter : <parameter to Parametric Role if present>).participants do
         if person.enabled then
              for each element in person.roles do
                   logMessage "participant id and Name: " + element.name     + "Id: " + element.id
                   //add the participant id/name into a list
              end
         end
    end     
    Iterate the list and display into your combo box drop down list - in jsp/BPM presentation
    2) When the business user select the user/participant and submit the work item should be assigned to the selected participant.
    Participant.next = “<Selected_Participant_Id>”;
    Hope the above will help you
    Bibhu

  • 3.3.8 Create a Business Scenario Configuration

    Hi,
    I am trying to create Business Scenario Configuration via the SCL SOAMANAGER site.
    I click New, key in STARTER_SERVICES as the name and then proceed Next.
    I click on Add, the Search page is displayed.
    But I only have the option to search by Service. The guide states to change it to search by ServiceGroup.
    I dont have that option.
    Is there another way of doing this?
    Thank you in advance.
    Haridev

    Hi Haridev,
    all these steps should be taken care of by the installation Wizard.
    However, if you want to do it manually, then make sure that you are in Step 3 Consumer Side. Click on Add and a new Window should open. In here the "Search By" field has "ServiceGroup" selected by default.
    My guess would be that you are still in step 2 "Provider Side" where you can only search for Services.
    Regards,
    Holger.

  • Business Scenario Communication State = Failed

    Hello Guys,
    I try to configure Business Scenario Communication in NWA. I got Failed State once I activate it.
    I have set the communication profile in NWA and now I want to configure business scenario communication, my problem is here that I don't find Service Definition which I want to use. Even though, I have publish the service in Service Registry it shows the service in SR. But it doesn't show me in Business Scenario Communication configuration.
    In Business Scenario Communication configuration, Service Group is found which I have selected. This service group I have created at the time of creating Model in Webdynpro by using WSDL link. Once I activate the Business Scenario Communication configuration it shows me FAIL in STATE column.
    Do you have any idea??
    Regards,
    Naeem

    i close this thread. I need to open the other one.

  • Sol. Landscape - Business Scenarios from Temp. Project: Compare & Adjust ?

    Hi,
    In SOLMAN_DIRECTORY, within Business Scenarios, if I were to copy Business Scenarios from a Template Project, is it supposed to help me use the 'Compare and Adjust' functionality ?
    I see the icon for this utility, but invariably greyed out at all levels.
    The idea is to hold Template Project as the master content provider, even for Support side.
    The workaround could be (yet to fully test) to use a Maintenance Project, to compare and adjust and check it in again.
    Any ideas welcome - especially, on why the 'Compare and Adjust' icon appears greyed out, in the Solution.
    Best regards,
    Srini

    Hi Andreas,
    The news that your colleague has tested it successfully is very encouraging and gives me hope.
    That's the way I was testing as well, with limited success. I couldn't finish testing because the the buttons for Check Out/ Check In Requests disappeared from SOLMAN_DIRECTORY suddenly. Then, I got into SAP Notes search etc.
    Can you/ your colleague please confirm if my following understanding is correct and suggest changes where it's wrong:
    (1) First, create a Solution and Maintenance Project in the same project language (to get the KW context right)
    (2) Create a few Business Scenario Names in Solution Directory (e.g. Procure to Pay, Order to Cash etc.)  - as manya s required
    (3) Later, assign the Maintenance Project concerned to the Solution, in the tab 'Solution Settings'
    Note: (2) is done before (3) since the assignment of a Maintenance Project renders the section greyed out. If it is greyed out, there is nothing to check out at the first place.
    (4) Check out the Blank Scenarios to Maintenance Project
    (5) In SOLAR_PROJECT_ADMIN, I would have already pre-selected the relevant scenarios under 'public' Templates, so that they are available in Maintenance Project's SOLAR01/02 under the Business Scenarios folder
    (6) Now, when I open the Maintenance Project in say SOLAR02, it would list me the scenarios copied from Template in the usual way (as in say, any normal Implementation Project), and below those folders, it would also list the 'Checked Out' name sake Scenarios from the Solution Directory
    (7) I will 'copy' and 'paste' the right Business Processes from the first set of Scenarios (from Template Project) into the Solution Directory blank Scenarios -  while doing so, I will retain the right to 'refer' documents and not copy them
    (8) I would Check In the structure back into Solution Directory
    (9) In say, a months time or so, the Process in Template Project have undergone changes (more process steps added under a process, more documents added/ removed/ changed etc.)
    (10) I would open the Maintenance Project after running SA_PROJECT_UPGRADE for the maintenance project.  I would do the 'Compare and Adjust' function in the regular Scenarios to get the content adjusted

  • B2B OCI - One Step Business Scenario

    Hello Experts,
    I'm currently implementing an OCI "One Step Business" Scenario where our catalog is included in a customer's SRM system.
    I would like to know which XCM and Shop Scenario is the most adapted for this case. Because "OCI" often refers to integrating a customer's catalog in our webshop which is not the case here.
    Do you know a link which explains in details the different B2B shop scenarios? (HOM, Business on Behalf, etc.).
    Many thanks,

    E-Commerce OCI "interface" can work two ways.
    1 In the normal E-Commerce scenario, you are a "selling" organization. You are maintaining the product catalog external to the CRM system. Your customers can order products from this external Catalog in to the E-Commerce (ISA) cart and order. CRM E-Commerce application transfers items from this external catalog into its cart using OCI. In this scenario this is behaving as a OCI Client.
    2 If you are doing what is called "One-Step-Business" using E-Commerce, then you are still a "selling" office and integrating your E-Commerce system to your customer's SRM (EBP) system. You are maintaining your Product Catalog in the CRM system. Your customer is large, do lot of business with you and they would like "_automatic_" integration of your E-Commerce system's catalog "directly" into their Buying system (SRM). In this scenario also, OCI comes into play and the existing OCI framework will "transform" the normal E-Commerce catalog into "OCI server" mode.
    You are asking about scenario (2). In this scenario, the buying customer will start their purchase from their SRM system. When they want to buy a product from you, their SRM configuration will "launch and login into" your E-Commerce application and display the Catalog and Cart. Once they have selected their products from catalog and added to their basket, they can "Transfer" the contents to their SRM Purchase Order.
    The transferred "order" will be stored in the CRM as a "Lean quotation". If you "fully" implement the one-step-business, you have to configure for Lean Quotation and as per SAP you may also need SAP-PI solution.
    For scenario (2) there isn't any XCM configuration setting to do. However, the buying organization (your customer) will need your input to set their SRM hook to your webshop. If they also want additional attributes to be shared, then your customer will need to do some ABAP programming in the SRM system as well as some Java changes in your CRM Webshop.
    Easwar Ram
    http://www.parxlns.com

  • Business Scenario ( Mix of MTO & MTS) how to configure

    Hi,
    Our customer has a business scenario , which uses a combination of make against order and make to stock. In its case 90% of production is against make to order and 10% is against make to stock.
    Its requirements are that in case of make to Order scenario it should be able to know which production orders have been created against a particular sales order and the manufacturing variance at the time of order settlement should flow to COPA under specific sales order.
    In case of rest of 10% production it should have the flexibility of producing material as made to stock.
    How to fulfill the above requirements , pls provide details answers , helpful answers will be awarded points.
    Regards
    Milind Nair

    Hii Milind,
    What you can do is to check your consumptions of orders. In order to that you can select either single strategy or more than one strategies. As I saw that you receive your sales order for 90% sales, then you can choose different strategy and for purely make to stock for your 10% of sale, you can choose different strategy. For more documentation please refer to the following link:
    http://help.sap.com/saphelp_47x200/helpdata/en/cb/7f9b7043b711d189410000e829fbbd/frameset.htm
    cheers!!!
    kapil

  • Create new Tabs in business scenarios

    Hi,
    Short question, is it possible to create extra tabs in the business scenario's of a project? Next to General documentation and project documentation we want to create additional Tabs since the Tabs present do not cover all our documentation needs.
    Is this possible?
    Thanks
    Tom

    Hey Tom,
    Unfortunately its not possible to have additional tab in Business scenario of the project.
    Additonal tabs is possible only for selected business transaction types.
    This could be done using EEWB tcode.
    However EEWB does not support this screen enchancement on Projects.
    To sum up, its not possible.
    Hope this clarifies your queries ...
    please reward for usefull answer.
    Regards
    Anand.

  • Solution not allowing us to import business scenarios from Project

    Hi,
    We have a Solution that we are trying to update with a project which has gone live.
    I have gone into the "Change Solution Directory" area and clicked on Business Scenarios.  However, the Insert/Delete Row icons are greyed out and I can't click on them (and yes, I am in Change mode).
    Any suggestions on why this is happening?
    Regards
    Shaun

    Hi Shaun,
    Goto Solman_directory - select solution. right side in Solution setting check if the below checks are done,
    "Enable Checkin/checkout of Solution structure"
    "Send email after check-out status change"
    "Enable change Request Managent"
    "Enable History"
    Also check if any of the business process is Checked out i.e showing Right Arrow in the tree.
    If this is the case it causes Lock on the solution as you have checked out the structure element into a maintenance project,
    This could cause you such practical problems .
    Regards
    Sonal Kumar

  • Business Blueprint -  Restricting authorization at Business Scenario

    Hi All,
    We would like to restrict authorizations at a Business Scenario level, say FI module users are restricted to update only their documents and only view SD documents.
    Can anyone let me know if this is possible?
    Thank you for your time.

    Hi Guys,
    Blueprints are available online!!
    Go through the links
    The Blue print for Business Inteligence:
    http://help.sap.com/bp_biv335/BI_EN/html/Business_Blueprint.htm
    Now if you are looking the Blueprint for any other modules, Select from the list
    http://www.sap.com/services/servsuptech/bestpractices/index.epx
    regards
    Happy Tony
    <b>Points == Thanks</b>

  • SOLAR01: Business Scenarios

    Hi,
    I am getting the error when I do the following:
    1.) Go to a project in SOLAR01
    2.) Highlight "Business Scenarios"
    3.) Go to the Structure tab and source set to business process repository, open the input help
    4.) From the "Buinsess Process Repository Selection Help" screen, select SAP CRM-->Field Applications
    Error: Error while removing contexts.
    Message no. SOLAR_MESSAGES031
    Please help urgently.
    Thanks,
    Rinkal

    Hi,
    The BPR-content is stored within software component ST-ICO,
    if you run Function module SOLAR_BPR_F4 in test mode with
    I_STRUCT_TYPE = BMBSL
    than you can see, this is what you should be seeing.
    mySAP SRM
    Catalog Content Management
      SAP SRM 6.0,SAP NETWEAVER 2004S
      SAP SRM 4.0,SAP NETWEAVER 04
      SAP SRM 3.0 (WITH SAP EBP 4.0),SAP R/3 ENTERPRISE 47X110
      SAP SRM 3.0 (WITH SAP EBP 4.0)
      SAP SRM 2.0 (WITH SAP EBP 3.5)
    These contents is delivered with patch 8 of component ST-ICO
    note 629829 describes, how to download the most up to date Solution
    Manager content from Service Marketplace
    Also check note :1327596
    Normally this error disappear when ST-ICO is upgraded.
    Hope this helps.
    Regards,
    Shyam.

  • Business scenarios for daily, weekly and nightly loads!!

    Can any body tell some Business scenarios for daily, weekly and nightly loads where we monitor the loads in Production support.
    Regards
    srikanth.ch

    Hi,
    It all depends on your business needs. In general on daily basis you will load the SD and MM which will cover all the stock and sales done for day. Generally most of the clients use Lo Cockpit extraction for both the modules. FI chains will run on month end for example the AP(Accounts Payable),AR(Accounts Receivable) chains will be run on the month end.
    Some SD datasources : 2lis_13_vdhdr, 2lis_13_vditm, 2lis_13_vdkon - all these to pull billing related data
    Some MM Datasource : 2lis_03_bx and 2lis_03_bf.
    Regards,
    Harish Raju

  • Variable declaration in BEx - Business scenario's

    Hi,
        I need some documents about all kind of variable declaration with some example business scenarios in MM, FI-CO modules.
    will assign you a reasonable points
    Regards,
    Pooja.S

    Hi Pooja,
    The processing type of a variable may be varies from business requirement.
    In general we will use the processing type:
    Replacement Path : If you specify a variable as a characteristic value, you do not have to specify a text for the characteristic value right away. Instead, you can fill the text field dynamically and specifically for the characteristic that you use for the variable when you execute the query. To do this, define a text variable with automatic replacement.
    [http://help.sap.com/saphelp_nw70/helpdata/EN/bd/589b3c494d8e15e10000000a114084/content.htm]
    Authorisations: If the user belongs to Asia PAciffic region and he must see only details of his region then we can create a variable Region vt Processing type Authorisations so that he vl able to see only that region's data.
    [http://help.sap.com/saphelp_nw70/helpdata/EN/44/599b3c494d8e15e10000000a114084/content.htm]
    SAP EXIT: If you want to define a query that only ever displays the data from the current month, drag the delivered variable “current month” (technical name 0CMONTH) for the characteristic “calendar year/month” (technical name 0CMONTH) into the query filter.
    [http://help.sap.com/saphelp_nw70/helpdata/EN/f1/0a5702e09411d2acb90000e829fbfe/content.htm]
    Customer Exit: You want to use one characteristic value to calculate a second characteristic value. The InfoProvider only contains the calendar day. However, you now also want to display the cumulated value for the relevant period (beginning with the first day of a quarter) in a query.
    For the first day of the quarter, use a variable with customer exit processing. If you now enter the current calendar day (for example, 06/19/2000), a start date of 06/01/2000 appears in the customer exit, and the cumulated value of this period can be displayed.
    [http://help.sap.com/saphelp_nw70/helpdata/EN/f1/0a56f5e09411d2acb90000e829fbfe/content.htm]
    I hope this helps you.

  • Authorization for specific business scenario or business step in solar01

    Dear all,
    we have an issue regarding solution manager blueprinting management restricting an access to specific nodes. Our goar is to have several substructures devided by modules like: FI, SD, PS and etc. And each team member according his position in a company should have an access only to his substructure and all the related documentation below that. Saying an access means a change mode not a display access.
    Please find the steps have been performed during the configuration of project below:
    All the configuration around system landscape has been done properly.
    A new project for solution was created in solar_project_admin.
    A correct logical componens has been assigned.
    All the required users have assigned as a team members of a project.
    At the projec. team member tab a box has been checked in for: restrict changes to nodes in project to assigned team members.
    A proposed structure of nodes has been created within Tx solar02.
    The right team members have assigned to specific node. So that only they suppose to have a change permission within that nodes. All others read only access.
    Every user has sap_solar01_all role assigned to him. We have tryed assigning varios roles according to  http://help.sap.com/saphelp_sm310/helpdata/en/db/a1033b2a98f46ae10000000a11402f/content.htm
    However as a result we are having a change permission allowed for every node within the structure. Like FI responsible member can access to any node from a tree. And he can make a change for SD related documentation.
    Please assist regarding this issue.
    Kind regards,
    P.S.
    I found a thread with a similar problem which was solved by activating a checkbox which is already activated in our system and actually doesn't solve that problem for us.
    Authorization for specific business scenarios in Solar01/02
    Edited by: Artjoms Nikulins on Mar 11, 2010 3:37 PM

    Hi
    As far my knowldege goes this is not possible to do within same project or making the same.
    You can have project specific access given to member but you cannot go module wise authorization.
    Ofcourse there satellite system authorization will be different but not in solman.
    In addition check this security guide
    https://websmp104.sap-ag.de/~form/sapnet?_SHORTKEY=00200797470000075728&_OBJECT=011000358700007187872005E
    Hope it ans ur query.
    Regards
    Prakhar
    Edited by: Prakhar Saxena on Mar 12, 2010 3:22 AM

  • How to connect steps in business scenario

    Hello,
    After creating a project in Solution Manager, creating a business scenario in that project and creating a custom business process in my scenario, Iu2019ve defined the necessary steps that I want in my process. These steps involve 2 different logical components, a component specified for a SAP XI/PI system and a logical component for SAP ECC system.
    The business process will involve interaction between the two logical components where Idocs will be exchanged. My first issue is, in transaction SOLAR01 when I click the tab Graphic, Iu2019m able to see the two separate components each with their steps but with no connection or relation between them or with any step order.  Where can I define the order and flow for the steps in the business process? After defining the flow, will the connections be presented in the graphic?
    One other question, if this business process involve interfaces, should I define this as a business scenario or as an Interface Scenario? What is the main difference between these two objects? Canu2019t I have only business scenarios and define the steps as interfaces?
    Thank your for the attention.
    Best regards,
    Goncalo Mouro Vaz

    Hello,
    please be aware that only business process maintained in the operations part of SAP Solution Manager. i.e. the Solution Directory, are available for Business Process Monitoring. Processes defined within SOLAR01 are in the project part and hence not directly available for monitoring. But those processes can be copied into the Solution Directory.
    For BPMon only "Business Scenraios" are of interest. "Interface Scenarios" need not be maintained but can be used for additional documentation purposes.
    Please refer to http://service.sap.com/bpm > Media Library > Technical Information > Setup for Interface Monitoring.pdf
    You may also visit the FAQ page http://wiki.sdn.sap.com/wiki/display/SM/FAQBusinessProcess+Monitoring
    Best Regards
    Volker

Maybe you are looking for

  • Tax statement item missing for Tax code XH

    Hello, We are trying to release on SD Invoice to accounting and we are getting the following error: 'Tax statement item missing for TAx code XH'. Message no. FF805'. Has anyone seen this error before in this situation?  If so how did you fix it pleas

  • Query not executing on production but on dev server

    Hi, I have few queries which are running in less then a second in development server but couldn't get executed on production server in three hours. Production box is much heavier then the development server. I have verified the init.ora parameters. b

  • Stock inconsistency

    Hi All, Previously we have stock at plant and storage location level. We reversed the stock to acivate the batch management. For meterial there is no stocki n MMBE at plant and storage location level. And i checked in MD04 there also stock is 0. In C

  • Text Box Value in the Query Bind Parameter

    Hi I have to use text box value in the query bind parameter Thanks to help...

  • Printer MP480 - How do we reset printer for jammed paper when it is NOT jammed?

    My printer is stuck on clear jammed paper message.  But there is no jammed paper.  How do I reset printer so I can proceed to print?