dear plm consultant,
I am facing problem in c project costing,
When  i try for calulate costing.
I get the cost revenue rates screen.but in that screen revenue rates are not comes that field come blank.and cost of the resoure are come negative form.
e.g. 560- in such fasion cost disply
I am unbale to trace this error. please help for same .
piont will be reward for help full answer
sunil jawalkar
[email protected]
Message was edited by:
        sunil jawalkar

Hi Suny,
I have the same problem as you, do you help me to understand how fix it?
Thanks in advance,
Sara Gil

Similar Messages

  • Cost / Revenue rate for resources - cProjects 4.0

    Having done the required accounting configurations, I get to see the the cost and revenue rate at the cProjects front end, defined (configured) in the system. I am also able to overwrite the system configured values and have my own. However, when I save, the system throws an error message - 'Cost / Revenue rate not defined for role / resource.'.
    Where could I be going wrong??

    Hi
       Swayam,
    please check the following setting in configuration .
    collabration project-
          --Connection to External System
              --Account Integration
                --Define Cost/Revenue rate
                  --Replicate Cost/Revenue rate
                    --Replicate Accounting-Relevant charac.
                      --Make setting in the ERP system
    Do this configuration setting
    This will definetly solve u r problem.

  • Cost/revenue rate E_MOE_DEC, 00000000: unit of measure PDA does not exist

    Dear community,
    I am still working on SAP PPM FICO & CATS integration.
    I can't replicate my cost/revenue rate in the ECC system.
    There is the error message : Cost/revenue rate (name of the cost/revenue rate) : unit of measure PDA does not exist
    Does someone know what PDA is ?
    I customized the units with FTE.
    Thank you in advance for your help.
    Best,
    Cassoké

    Hi Cassoke,
    Through analysis found that you need to define 'Units of Measurement' PDA which is linked to the capacity unit 'FTE'.
    Just check whether you have the PDA unit of measurement in tcode-CUNI or under SPRO-->PPM-->Portfolio Management-->Global Customizing-->Global Settings-->Define Units of Measurement.
    Select dimensions 'Time' and click on 'Units of Measurement' and if no PDA entry is there, create an entry(Attached screenshot for your reference).
    Hope this helps.
    Regards,
    Ravi

  • Error to replicate cost/revenue rates

    Hi,
    Error regarding replicate cost/revenue rate .
    We use PLM Dev server and gives RFC R/3 100 Dev and R/3 410 Quality server.
    We use Project suit 4.0 and ecc 6.0 versions
    We are tried to make account integrations between c project and R/3system 
    When we try <b>to replicate cost/revenue rate</b>
    Form PLM Dev to R/3 Dev 410 it works fine (but Quality server is not modifiable)
    So I try to do same PLM Dev to R/3 100 Dev it gives error
    <b>Function Module “DPR_REPLICATE_RATES “Not found</b>
    I check function module in R/3 100 Dev and 410 Quality it is present in the both client.
    But when I check it in PLM Dev 100 it shows function group DPR_CALC does not exits.
    Then what is exact problem? Please help for same, if problem in PLM dev 100 then how it transfer cost /revenue rate to R/3 410  and not for R/3 100 Dev.
    We check RFC CONNECTION IT WORK FINE
    thanx
    <b>sunil jawalkar
    [email protected]
    9890960640</b>
    sunil jawalkar

    Hi.
    This is difficult to answer without seeing the system. I just can guess:
    - An easy thing would be that the function module just isn't activated. You go to transaction SE37 in PROD and look it up.
    - If you cannot find the function module it might have been lost in a transport. You check the object catalog entry of the function module: R3TR FUGR DPR_CALC first. You go to transaction SE03 and check in DEV and Q if the object is in a request or task and look up its status there.
    By the way: The function module is part of cProjects. Has it been implemented in your PROD already?
    Best regards.
    Jens Schmid

  • Cost/revenue rate

    Hi all,
    I have created 4 nos. cost/revenue rates. While replicating,  they four are having different status than other. Can anyone tell me about this status? where to maintain/change the status?

    Hi Yogesh,
    Please explain your issue in detail.
    Amit
    Edited by: Amit Sawant on Apr 10, 2008 4:24 PM

  • Error Landed Cost - Customs rate not valid (SAP B1 9.0 PL10)

    Hello experts,
    We would like your advise on the following issue.
    We are currently using SAP Business One 9.0 (PL10) and we are trying to add a Landed Cost document, but the following error occurs:
    Customs rate not valid.  [Landed Costs - Rows - Duty Rate]
    The SAP Note: '1928862 - An Error occurs when adding Landed Costs', which describes the error, is listed in the References section of PL09 and PL10 upgrade. However, the error still occurs.
    Any advise on how to solve this issue?
    Kind Regards,
    Vassilis Korolis

    Hi,
    Is it happening for same scenario has mentioned in SAP note? If yes, raise ticket to SAP support.
    Thanks & Regards,
    Nagarajan

  • Cost / Revenue for Project Role Types

    Dear All,
    I need your suggestion on cost / revenue rate for multiple project roles type of the project elements. I am defining various project roles such as account manager / project manager / Team leader / Team members etc. which will be assigned to project. There will be different cost / revenue hourly rate for each role type. I have defined hourly cost / revenue rate for organisation management. But i oberved that hourly rate is getting copied to all type of role in project & the same is update as planned cost.
    Request you to suggest how to mainatin different hourly rate for various project roles in side project.
    Thank you in advance.
    Regards,
    Ranjan

    Hi,
    Make sure you have done following settings
    SPRO>Collaboration Projects >Connection to External Systems>Accounting Integration>Define Cost/Revenue Rates
    here you define Cost revenue rates
    Now i feel you have assigned these rates in define Task types in SPRO>Cproj>structure>define task types
    in this case it ll take same cost revenue rates.
    you remove these
    and in SPRO >Collaboration Projects > Resource Management>Basic Settings for Project Roles> Role types
    assign the rates.
    clear the browser Cache, cookies.
    Make sure you log off and then try to create new Project with the settings
    It shd help.
    P.s. Zhenbo plz correct me if im wrong...
    Niranjan
    Award points if useful.

  • Evaluation - Cost/Revenue Costing for Project

    Hello,
    executing the evaluation "Cost/Revenue Costing for Project" I get no results. Could someone tell me where the values for this report come from? Can I find somewhere a list with all the evaluations (except the one like completed checkpoint items, ... which are really self explaining) and the source of the shown values?
    Thx, Max

    Hi,
    I hope that you have assigned Cost revenue rate to Roles.
    Check in spro> cProjects> Evaluation--> Define extract layout, Iterator for the specific layout RES_PART, Object and attributes.
    Also check in Define evaluation assigned extract layout to Evaluation is correct which is defined in earlier step.
    Regards,
    Karan Hon
    Award if useful..

  • Incorrect cost/revenue value show in cProjects

    Hi all,
    I'm working with cProjects and PS.
    The problem is: costing value showed in cProjects is incorrect(it’s 10 times bigger than that value in PS), however the value showed in PS is correct.
    For example:
    1 engineer has cost/revenue rate : 10usd/15usd /Hour
    He work 10hours for a Task
    in PS (ECP, CJ40,..)we will see the cost/revenue is: 100usd/150usd
    however in cProjects (Tab: Accounting) we will see the cost/revenue is: 1000/1500
    Please help me to solve that problem, it's very urgent.
    Thank you very much
    Duc Nguyen

    HI Duc,
    It sounds like a curreny problem with the  decimal place, would you please check the customizing item :
    SAP NetWeaver -> General Settings -> Currencies -> Set Decimal Places for Currencies
    Please check in BOTH systems (cProject & ERP), if there is any difference for the USD?
    Kind regards,
    Zhenbo

  • Migration of costs & revenues of open projects

    Dear All,
    I am new to CO & migrating the costs & revenues of open projects from old SAP system to new SAP system.
    For costs & revenues of open WBSs/Network activities, we have three programs:
    1. primary costs extraction & upload
    2. secondary costs extraction & upload
    3. revenue data extraction & upload
    For primary costs, i am referring to table COSP and secondary costs COSS.
    Incase of secondary costs, i am not sure what all the values i should consider
    In COSS - i have cost center allocations - which need to be migrated through KB21N, with total qty & UOM
    and also i have network activities settlements...do i need to consider this as well to get the value matching with WBS value in CJI3.
    If yes, how do i migrate the network settlements? definetly not through KB21N.
    Kindly clarify as i am not able proceed further on this.
    Thanks in advance
    Gangadhar

    When you say migrating from old SAP system to new SAP system,  do you mean, you are in a upgrade project? If it is an upgrade project, you need worry to transfer data. The technical upgrade would address the need of data migration.
    If it is entirely a new different system and you are planning total re-engineering, you may only want to post primary costs and redo the allocations and settlments.

  • KKA2 Error-Assign a revenue element to a line ID in the assignment

    Hi Gurus,
    We are trying to run KKA2 on WBS element & we are getting an error as
    Assign Revenue Element to a Line ID in the assignment
    We have already checked OKG5 and the necessary Sales revenue elements are assigned to a line ID.
    The exact SAP error message is as follows:
    Assign revenue element to a line ID in the assignment
    Message no. KJ 723
    Diagnosis
    Revenue element cannot be assigned to a line ID in the assignment rules of results analysis. If no revenue element in indicated, this is because no revenue element was found in the invoicing simulation.
    The complete term with which no line ID could be found in the assignment is as follows:
    / / / / / / /E/ / /2010/006/
    The words or letters enclosed by slashes describe, in order, the following:
    /Cost element /Origin group/ Cost center/ Activity type/ Business process/ Debit-credit indicator/ Variable-fixed indicator/ Apportionment reason/ Accounting indicator/ Fiscal year/ Period/
    Procedure
    Make the necessary changes to the rules in the assignment in Customizing for results analysis.
    Appreciate your help on this..
    Thanks & Regards
    Kumarpal/Advait.

    Hi
            In case of Projects (WBS Elements) Result Analysis Key you have Fifteen types of "Results Analysis Methods" is there for Projects we can use only 1,2,3 or 6 for WBS Elements.
    (01) Revenue-Based Method with Profit Realization,
    (02) Revenue-Based Method without Profit Realization
    (03) Cost-Based POC Method
    (06) POC Method on Basis of Revenue Planned by Period
    Please go through SAP library
    http://help.sap.com/saphelp_di471/helpdata/EN/90/ba6f6b446711d189420000e829fbbd/frameset.htm
    Period-End Closing in Product Cost by Sales Order: Scenario -->Results Analysis -->Results Analysis Methods
    Please study the methods and use as per your requirement. First method is good. Please check your end. Is that method helpful for you?
    Regards

  • Pricing error in customer invoice-"Error in converting exchange rate from to RUB"

    Hello Friends,
    Please help me to solve the below issue .
    When user created customer invoice, system showed pricing error for last line item . The error was for cost condition type which did not determined any value and had "Red" indicator . The error message is -"Condition ZXXX: Error in converting exchange rate from  to RUB" . Message No.V1208 . User could save the invoice but accounting doc was not created .
    In this case-->
    -Document currency is RUB
    -Currency RUB updated in customer master .
    -Currency RUB updated in material master .
    -Con.origin is A for this condition type .
    Please tell me why this error message occurred ?
    Regards,
    Sandeep N.

    Hi,
    Below are the screen shots for OB22 and invoice :
    Regards,
    Sandeep N.

  • Transfer cost & revenue to internal order defined inthe service order.

    Dear Experts,
      On release, service order creates internal order that collects cost & revenue for the job. My requirement is to transfer these costs & revenue to a different internal order through crm order itself. In CRM order there is option to assign the account assignment object as " Internal Order ". This is under tab Account Assignment. Here we can enter any internal order no.
    On saving order doesnt throw any error message. But Cost & revenues are not transafered to the I/O mentioned in the CRM service order.Is there any config. setup missing or should we look for BADI enhancement.
    Can anyone help me in fixing this issue Plz. Your early response would be most appreciated.
    Thank U,
    Regards
    Devika.S

    Hi,
    Just to get cleared, have you set up a Billing Engine in CRM and also the Administrate Console for Billing to flow in CRM with Middleware settings + Item Category (Billing Relevance)
    Cause the above are very necessary for your requirement.
    Apart from those, in ECC, you need to maintain values  under
    IMG>Integration with other mySAP.com components>CRM>Settings for Service Process>Billing Integration
    Hope this information helps, as I am assuming it that others are maintained by you.
    Regards,
    Madde

  • Project WBS element cost allocation

    Dear All,
    In a project we have created 10 WBS elements out of which one is used for common expenses and rest other or individual works carried out in the project. Now i want to allocate the Common cost of one WBS element to other nine WBS elements.
    Can anybody explain how this can be done and is there any possibilites of costing gets doubled in the project if the cost transffered to other WBS elements.
    Thanks and regards

    Thanks for the reply,
    I have another query also, i had transferred the WBS element cost to other WBS element cost in the same Project.Whether it will double the Revenue or Cost incurred
    For ex, WBS Element A got 100 and i had settled to WBS Elements B and C , now B and C got 50 50 each
    now my project will have
    a) WBS Elements A-100, B-50 and C-50   or
    b) WBS Elements A-0, B-50 and C-50 ,  for my understanding option (b) will be right. Your views pls
    Edited by: aspirefico on Apr 30, 2009 12:59 PM

  • Error regarding cost center while posting migo

    Dear sap experts
    I am getting this error message
    COST CENTER A123/A123 IS BLOCKED AGAINST REVENUE POSTINGS ON 29/12/2010
    where A123 is cost center as well as controlling area.
    I have some more doubts
    WHETHER PROFIT CENTER SHOULD BE CREATED FOR THIS.
    TO CREATE PROFIT CENTER PROFIT CENTER GROUP SHOULD BE CREATED BUT I AM GETTING ERROR
    WHILE CREATING PROFIT CENTER GROUP. HOW TO SOLVE THIS
    THANKS IN ADVANCE

    hi
    I followed your reply but now I am getting this error
    COMPLETE   PA    TRANSFER STRUCTURE   FI
    How to overcome this.... any idea
    waiting for the reply
    bye

Maybe you are looking for

  • Onrelease gotoandplay PLEASE HELP!

    I am new to CS4 and actionscript 3.0. I am developing a flash website for a friend of mine as a favor. Ive been stuck with a small problem for a day and a half already. I am used to the oldschool flash MX 5.0 and actionscript 1.0 where you could simp

  • Intel 17"imac vs 2ghz g5 powermac

    So I'm in the market for a desktop. I'll be doing a number of things with the computer. Alot of important, sensitive material from corporate office (financial spreadsheets etc) however I'm still in denial and expect to unleash my fury in a few online

  • WPA2 Enterprise connections don't work

    Hi everyone, Configuration: MacBook Pro 7,1, 2,4GHz, Mac OS X 10.6.5. Three user accounts (one for me, two for friend's backup), two of them have admin rights. I'm using one of these accounts. I'm having a strange issue with *WPA2 Enterprise*-based a

  • Opening PDF Documents

    Since downloading Adobe X1 - I am unable to open some PDF Documents - anyone any advice for me  (I am not particularly computer literate)

  • Cannot display the iRecruitment page

    Dear Expert We are facing a issue in iRecruitment. When we go to our career website following error occurs. Error: Cannot Display Page You cannot complete this task because one of the following events caused a loss of page data.Possible Causes: You h