Incorrect cost/revenue value show in cProjects

Hi all,
I'm working with cProjects and PS.
The problem is: costing value showed in cProjects is incorrect(it’s 10 times bigger than that value in PS), however the value showed in PS is correct.
For example:
1 engineer has cost/revenue rate : 10usd/15usd /Hour
He work 10hours for a Task
in PS (ECP, CJ40,..)we will see the cost/revenue is: 100usd/150usd
however in cProjects (Tab: Accounting) we will see the cost/revenue is: 1000/1500
Please help me to solve that problem, it's very urgent.
Thank you very much
Duc Nguyen

HI Duc,
It sounds like a curreny problem with the  decimal place, would you please check the customizing item :
SAP NetWeaver -> General Settings -> Currencies -> Set Decimal Places for Currencies
Please check in BOTH systems (cProject & ERP), if there is any difference for the USD?
Kind regards,
Zhenbo

Similar Messages

  • Cost / Revenue rate for resources - cProjects 4.0

    Having done the required accounting configurations, I get to see the the cost and revenue rate at the cProjects front end, defined (configured) in the system. I am also able to overwrite the system configured values and have my own. However, when I save, the system throws an error message - 'Cost / Revenue rate not defined for role / resource.'.
    Where could I be going wrong??

    Hi
       Swayam,
    please check the following setting in configuration .
    collabration project-
          --Connection to External System
              --Account Integration
                --Define Cost/Revenue rate
                  --Replicate Cost/Revenue rate
                    --Replicate Accounting-Relevant charac.
                      --Make setting in the ERP system
    Do this configuration setting
    This will definetly solve u r problem.

  • COGS Value showing as null for Projects

    Hi All,
    We have a report called Revenue Report. In this report we track the revenue and cogs value for both OM orders and Projects. We are able to see th cogs value for OM order(i.e. sales order)but not for projects. We are using OOTB out of box mapping(i.e.SDE_ORA_GLCOGS) for populating cogs value.So we have approached oracle team to address this issue. Please find the below reply from Oracle. Can somebody help me how to calculate COGS value for projects.
    BIApps 7.9.6.x do not support the integration of Project and COGS out of the box. If you have cogs trx from Projects and would like to extract these trx, you can customize the SDE sql.
    [OOTB sql in SDE_ORA_GLCOGS]
    WHERE
    MMT.TRANSACTION_TYPE_ID IN (15, 33, 10008) AND
    (MMT.TRANSACTION_ACTION_ID,MTA.ACCOUNTING_LINE_TYPE ) IN
    ((27, 2), (1, 36), (36, 35))
    MMT : MTL_MATERIAL_TRANSACTIONS
    MTA : MTL_TRANSACTION_ACCOUNTS
    15 = RMA Receipt (Return Material Authorization)
    33 = Sales order issue (Ship Confirm external Sales Order)
    10008 = COGS Recognition
    (27, 2) = (Receipt into stores, Account)
    (1, 36) = (Issue from stores, Deferred Cost of Goods Sold)
    (36, 35) = (COGS Recognition, Cost of Goods Sold)
    These are OOTB default values to extract the cogs trx for sales order etc. These are configurable. You can add/modify these values as needed. You can check the OLTP MTL module for the meaning of each values

    Please do not post duplicates -- COGS Value showing up as null Projects

  • Error to replicate cost/revenue rates

    Hi,
    Error regarding replicate cost/revenue rate .
    We use PLM Dev server and gives RFC R/3 100 Dev and R/3 410 Quality server.
    We use Project suit 4.0 and ecc 6.0 versions
    We are tried to make account integrations between c project and R/3system 
    When we try <b>to replicate cost/revenue rate</b>
    Form PLM Dev to R/3 Dev 410 it works fine (but Quality server is not modifiable)
    So I try to do same PLM Dev to R/3 100 Dev it gives error
    <b>Function Module “DPR_REPLICATE_RATES “Not found</b>
    I check function module in R/3 100 Dev and 410 Quality it is present in the both client.
    But when I check it in PLM Dev 100 it shows function group DPR_CALC does not exits.
    Then what is exact problem? Please help for same, if problem in PLM dev 100 then how it transfer cost /revenue rate to R/3 410  and not for R/3 100 Dev.
    We check RFC CONNECTION IT WORK FINE
    thanx
    <b>sunil jawalkar
    [email protected]
    9890960640</b>
    sunil jawalkar

    Hi.
    This is difficult to answer without seeing the system. I just can guess:
    - An easy thing would be that the function module just isn't activated. You go to transaction SE37 in PROD and look it up.
    - If you cannot find the function module it might have been lost in a transport. You check the object catalog entry of the function module: R3TR FUGR DPR_CALC first. You go to transaction SE03 and check in DEV and Q if the object is in a request or task and look up its status there.
    By the way: The function module is part of cProjects. Has it been implemented in your PROD already?
    Best regards.
    Jens Schmid

  • Evaluation - Cost/Revenue Costing for Project

    Hello,
    executing the evaluation "Cost/Revenue Costing for Project" I get no results. Could someone tell me where the values for this report come from? Can I find somewhere a list with all the evaluations (except the one like completed checkpoint items, ... which are really self explaining) and the source of the shown values?
    Thx, Max

    Hi,
    I hope that you have assigned Cost revenue rate to Roles.
    Check in spro> cProjects> Evaluation--> Define extract layout, Iterator for the specific layout RES_PART, Object and attributes.
    Also check in Define evaluation assigned extract layout to Evaluation is correct which is defined in earlier step.
    Regards,
    Karan Hon
    Award if useful..

  • CO-PA Cost Component do not match with Standard Cost Component Values

    Dear Members,
    The CO-PA Cost Components (as mapped through KE4R), do not match with Standard Cost Component values for the Group Currency. In local currency the values match.
    System is correctly picking up VPRS value, both in local currency and Group Currency, which is equal to the total of Standard Cost Components however, it is the Value Fields linked to the Standard Cost Components in Group Currency that do not match.
    In KE40, the Indicator is 4:Released Standard Cost Estimate matching Goods issue Date.
    I have verified KEPH/CKMLPKEPH tables. The values are same as that of VPRS.
    Any help/clues?
    Regards
    Satya

    Hi,
    In case of billing documents the group valuation approach is managed in the data structures of the legal valuation in additional value fields. To control costs and revenues in the different views separately, you must create additional value fields and assign them to the data structures.
    The field contents must be filled via the CO-PA user exit, they cannot be entered by assigning conditions to value fields. The profit center valuation is updated in a separate ledger. No separate value fields are necessary.
    The exit to be used is function module 'EXIT_SAPLKEII_002' ( enhancement COPA0005 ). Within the exit you have the complete SD data avaialble in the tables 'T_ACCIT' and 'T_ACCCR'. The conditions can be found in T_ACCIT and the corresponding values ( linked via 'POSNR' ) in table T_ACCCR. The PA line item and the corresponding SD item in table ACCIT
    can be mapped via the line item field 'RPOSN' and the field 'POSNR_SD' in table ACCIT.
    regards
    Waman

  • Transfer cost & revenue to internal order defined inthe service order.

    Dear Experts,
      On release, service order creates internal order that collects cost & revenue for the job. My requirement is to transfer these costs & revenue to a different internal order through crm order itself. In CRM order there is option to assign the account assignment object as " Internal Order ". This is under tab Account Assignment. Here we can enter any internal order no.
    On saving order doesnt throw any error message. But Cost & revenues are not transafered to the I/O mentioned in the CRM service order.Is there any config. setup missing or should we look for BADI enhancement.
    Can anyone help me in fixing this issue Plz. Your early response would be most appreciated.
    Thank U,
    Regards
    Devika.S

    Hi,
    Just to get cleared, have you set up a Billing Engine in CRM and also the Administrate Console for Billing to flow in CRM with Middleware settings + Item Category (Billing Relevance)
    Cause the above are very necessary for your requirement.
    Apart from those, in ECC, you need to maintain values  under
    IMG>Integration with other mySAP.com components>CRM>Settings for Service Process>Billing Integration
    Hope this information helps, as I am assuming it that others are maintained by you.
    Regards,
    Madde

  • Migration of costs & revenues of open projects

    Dear All,
    I am new to CO & migrating the costs & revenues of open projects from old SAP system to new SAP system.
    For costs & revenues of open WBSs/Network activities, we have three programs:
    1. primary costs extraction & upload
    2. secondary costs extraction & upload
    3. revenue data extraction & upload
    For primary costs, i am referring to table COSP and secondary costs COSS.
    Incase of secondary costs, i am not sure what all the values i should consider
    In COSS - i have cost center allocations - which need to be migrated through KB21N, with total qty & UOM
    and also i have network activities settlements...do i need to consider this as well to get the value matching with WBS value in CJI3.
    If yes, how do i migrate the network settlements? definetly not through KB21N.
    Kindly clarify as i am not able proceed further on this.
    Thanks in advance
    Gangadhar

    When you say migrating from old SAP system to new SAP system,  do you mean, you are in a upgrade project? If it is an upgrade project, you need worry to transfer data. The technical upgrade would address the need of data migration.
    If it is entirely a new different system and you are planning total re-engineering, you may only want to post primary costs and redo the allocations and settlments.

  • Incorrect costing sheet in service orders

    Hi All,
    We have one issue with service orders (T-code: IW32 ) setup.We have processed many service orders in system
    and recently we came to know that there is incorrect cost sheet derived into all the service order from the defaulted cost values of plant and order type.
    Now we want to do the proper setup for correct costing sheet for that plant and order type relationship .
    Can you please help us of  process setups to follow to correct the costing sheet for this requirement and what is the impact on posted service order with incorrect service orders.
    Thanks
    Rishai

    Hello Risha,
    Me also facing a similar issue
    Can you please share the solution for this thread
    Thanks,
    Satya

  • Comparing transaction summary against target revenue values

    Hi,
    We have a powerpivot model that contains transactions and revenue amounts by year, quarter and product. Each product has a defined revenue target for each year and quarter, which are contained in a lookup table.
    We've created a pivot table that does a simple summary of total revenue of transactions, summarized by product, year and quarter. We want to also display a column that shows the target revenue for each product, by quarter and by year, which is available
    in our other table.
    We've been able to successfully "lookup" the target revenue values however, we are unable to get the information to aggregate successfully for each quarter/year and product due to the fact that it is pulling the target value for each transaction.
    Below is a mockup of a pivot table that we would like to see. We have been able to get the summary by quarter/product for each transaction really easy. What has proven to be challenging is getting the target revenue information to display. The closest result
    we have been able to achieve is by doing a lookup on the revenue target data and displaying the "max" value, which will correctly show the max by quarter. However, the subtotal and total amounts for the targets are using the max value, and thus not
    providing a sum of revenue targets for the product by year or by quarter. Thanks in advance for any help

    Nevermind, I was able to find an answer here:
    https://social.msdn.microsoft.com/Forums/sqlserver/en-US/7d06ff1b-04fd-496e-9286-4babd0c9beb9/lookup-from-aggregation?forum=sqlkjpowerpivotforexcel
    This solved my problem.

  • BO Webi report hierarchy with measure values showing more(almost double value) compare to BW Bex report

    Hi,
    In our BO Webi report hierarchy with measure values showing more(almost double value) compare to BW Bex report. Can any one please help on this.
    Is it BW problem or BO problem?
    I checked in some other threads but it's not given solution.
    Thanks,
    Manjunatha

    Hi,
    Is it BW problem or BO problem? : BO
    is it causing problem with hierarchly data only ?  without hierarchies data is matching or not?
    Post same in SAP BusinessObjects Web Intelligence  .
    Thanks.

  • Net value showing negative in excise billing for free goods items

    Dear All,
    Need value suggestions in business scenario.
    While issuing Free goods to customer in excise billing ,Net  value of ZTNN item showing negative
    Inserted R100 % condition type above Tax condtions.
    MRP is statistical and accessable value is calculated on MRP.
    How to  solve the above issue.
    Due to the Net value showing negative for Free of charge in excise billing,qty value  displaying twice the unit price value in printing
    Thanks & Regards
    H V Kumar.

    Hi
    It is depends on your pricing procedure how you defines.
    Kindly check once again in your pricing procedure.
    Test the cycle once again without entering the R100 condition type in sale order line item and check the next value.
    After enter the R100 condition type check the base value to calculate the Amount.

  • Main Item net value showing as zero by condition type R100.

    Hi Experts,
    I am configured free goods, maintained condition record for exclusive free goods.
    but in sales order free goods item is not populating and when i see the analysis the requirement 55 not met.
    I removed the requirement 55 and i saved it.
    Still in the sales order the  free goods exclusive item not populating.
    and i find that main Item net value showing as zero by condition type R100.
    Why system showing the main item amount as zero by condition type R100?
    Thanks in advance.

    HI ram reddy
    you have to maintain R100 requirement -55 it should be there
    also Alternative Condition Base value - 28(100% discount)
    check your main pricing procedure having conditon type R100 or not if it is not there then maintain
    conditon record in VBN1 for NA00 check all the setting(calculation rule)
    activate free goods pricing correctly(NA0001)
    save it now try
    Regards,
    Krishna.
    Edited by: kris_hna on Jul 14, 2011 11:13 AM
    Edited by: kris_hna on Jul 14, 2011 11:31 AM

  • Material Attribute value display based on cost center value

    Hi,
    Is it possible to display the material attribute value based on cost center value. I mean for some cost centers I would like to display the value of other characteristic in place of material attribute. I am trying to create a query on MP.
    Any info in this regard will be appreciated.
    Thank you.
    Harshan

    Hi Adi,
    In Rows, Create a struture. Using New Selection, You can restrict the New Value to the cost center (Restrict again on those some cost centers) and material. And for this New Characteristic, you can have a attribute.

  • Assign direct material cost to value field in copa while issue to Prod orde

    Dear All,
    My requirement is like this:
    There are some 16 material groups from A to P each containing some materials(finished goods).
    I want to allocate overhead to different material groups(Charecteristic in copa) in COPA using the periodic assesment cycles. I am able to allocate overhead(admin & sales cost) to different value fields in copa from different cost centers.
    I want to analyse the product cost and also the profitability of each material group in COPA using Report painter. Iam able to pull all the costs which i assign to value fields using assessment. But, i am NOT able to get the direct material cost which is issued to production orders using BOM.
    My question is whether we can assign the direct material cost to any user defined value field(material cost value field) while the material is being issued to production orders. Is there any automated way where we can directly assign the direct material cost to value field in copa while issuing the material to Production orders.
    Pls explain me whether we can do it. if yes how?
    Thank you very much in advance.
    Regards,
    Vishnu
    VST-IT.

    PA is a Profitability analysis tool. That means it gets updated when a sale is made, not before. (Except for settlements and assessment of overheads.)
    Goods issues for production gets updated in CO-PC, and needs to be analysed there. If you don't, you loose all the inbuilt tools for variance analysis, cost estimate comparisons, Wip Calculation etc. To the best of my knowledge, a Profitability Segment cannot be used as a cost object in Production Planning, because amongst others, you need to be able to capitalise the produced materials to stock at the end of the production run, or to WIP at the end of the Financial period,which is not possible with PS.
    Similarly, overheads are recorded in CCA and needs to be analysed there.
    If one goes against these big groupings in SAP, you always run into problems.