Cancellation of Production Order confirmation (CO13) not generating TR/TO

Hi,
We are facing a typical issue in the PP-WM interface. When we create an order and confirm it (partial confirmation), the Goods movement happens (261 mvt type) as desired and the TO is created and confirmed in the background.
But, when we try to reverse the movement type (cancelling the production order confirmation using CO13) then there are no TRs or TOs generated in the background (for movement type 262).
When I manually try to post a material document for 262 movement type, it creates a TO in the background (as per the configurations that I maintained) but this does not happen when movement type 262 is called using PP interface.
The movement type configurations are all done for Automatic TR and TO generations - this works with normal IM process (when we manually post using MB1A transaction) but not with the return Goods movement happening with PP.....here, the material comes back to the interim storage type 914. We then need to create a TO manually and confirm it to take the stock back in to the original storage type and bin.
We want that when a process order confirmation is cancelled then the materials should be posted back in to the original storage type and bin (from where the material was issued against the order).
For Info: COGI shows no errors during the 262 movements, also, material document is generated for 262 movement type but no TR/TO generated.
Is there any configuration that we have missed?
Thanks and Regards,
Shankar

Hi,
Yes, you are correct in the understanding that the system creates quants in 914 when the production order confirmation is cancelled. But, it does not generate any TR or TO in the background to post the stock back into the original storage type.
Can we not use the put away strategies so that the system determines where to place the material? My query is that despite all the configurations for automatic TO creation and confirmation for movement type 262, it does not generate a TO (or TR) in the background when a production order confirmation is cancelled using CO13.
However, if I manually post a material using MB1A for 261 movement type and reverse it using 262, it generates a TO and confirms it as per the setting in configuration.
The same thing does not work when we run it through PP (CO11N and then CO13).
Any suggestions on how to approach this and where to check for missing configurations?
Thanks and Regards,
Gaurishankar

Similar Messages

  • Price difference on cancellation of production order confirmation

    Hi,
    We are having a material which is maintained at price control "S". We have created a production order for the material. In due course of business, we did confirmation for say 100 pcs of the material. However, immediatly on confirmation, we realized that we do not need to do the confirmation & hence we did the cancellation of the production order confirmation using CO13.
    On doing the production order confirmation cancellation, we observed that the system has posted some amount to "price difference account"
    We also observed that once in a while this kind of entries do get posted.
    It is requested to please let us know in why system is behaving this way?
    We have checked SAP Note no 216080 "Price difference when reversing GI for S-Priced material" & SAP Note no 215980 'Price difference during GR for the production order". However we are not convinced that these could be the reason for the price difference.
    Thanking you in anticipation
    Regards
    Santosh Kumar Agarwal

    Hi,
    Yes, you are correct in the understanding that the system creates quants in 914 when the production order confirmation is cancelled. But, it does not generate any TR or TO in the background to post the stock back into the original storage type.
    Can we not use the put away strategies so that the system determines where to place the material? My query is that despite all the configurations for automatic TO creation and confirmation for movement type 262, it does not generate a TO (or TR) in the background when a production order confirmation is cancelled using CO13.
    However, if I manually post a material using MB1A for 261 movement type and reverse it using 262, it generates a TO and confirms it as per the setting in configuration.
    The same thing does not work when we run it through PP (CO11N and then CO13).
    Any suggestions on how to approach this and where to check for missing configurations?
    Thanks and Regards,
    Gaurishankar

  • Mass cancellation of production order confirmation

    Hi All,
    Wrong confirmation is posted with no cost control key. But the operation is relevant to cost.
    Now we have to cancel all the wrong confirmations & re-confirm with a correct control key.  Is there any way to cancel confirmations in mass??
    Pls reply...

    Dear Srijit,
    There is No Std T-code for Mass Cancellation of Confirmation
    Either go with LSMW or BDC
    Regards
    Madhu

  • Production order confirmation document

    Hi All,
    After carrying out production order confirmation, material document generated is not displayed at the front end.Instead we get messege that "confirmation of order XXX is saved".We have to view that in MB51/COOIS .
    How to display confirmation material document number ( Not confirmation number ) in the front endscreen. This is required as user can write down document number at the time of confirmation for his record.
    Whether there is any option?
    Regards,
    Milind.

    Hi,
    Do the below given settings to print your confirmation document after you confirm the production order.
    Go to OPJ8, check on print confirmation.
    Now you do the confirmation. You will get the confirmation slips.
    Thanks
    Muthu

  • Changr HU quantity generated via PRoduction order confirmation

    Hi gurus,
    I have created GRN of 112 quantity via production order confirmation.
    My plant andstorage location is Handeling unit managed so with GRN handeling unit gets generated.
    but packing had done for 1 quantity only.
    now how to change this quantity?  I tried HUCANC t code and gave the HU number but system is giving error that HU can not be cancelled.  first cancelled material document
    but GRN has made 112 quantity which is correct then how HU got packed with 1 only?
    I stuck up pls help

    when I am trying to change Hu in humo i am getting following error
    Storage type 111 does not allow repacking - HUs cannot be changed
    also getting following error if I am changing the quantity or emptying the Hu
    Handling unit 10016000800120555 has status "cannot be changed" - Process cancelled
    Edited by: vrunda on Jul 9, 2010 10:57 AM
    If I tried to delete
    Handling unit 10016000800120555 contains items that cannot be deleted
    Edited by: vrunda on Jul 9, 2010 10:58 AM

  • Production order status was not changed to 'CNF' after final confirmation.

    Hi guru.
    I experienced very special case that production order status was not changed to CNF after final confirmation.
    I did final confirmation and canceled confirmation. (CNF -> REL)
    And I did final confirmation again because of fixing activity quantity.
    the strange thing is that production order status wasn't changed from REL to CNF.
    I did  confirmation again with 0 activity, thereby  I solved this problem
    BUT i don't know why this case happened.
    Please, explain the reason.
    Thanks.

    Hi,
    As per my observation, their is not any change in the status of the order REL with confirmation CNF, instead of this, it has change from CRTD & then to TECO.
       Sequence of the status of the order as below
    1) CRTD MANC NMAT SETC
    2) REL  NMAT SETC - Changes from CRTD to REL after releasing of the order
    3) REL  CNF  PRC  CSER ERTR OPGN SETC -  After confirmation, it updated after the order REL status.
    Rgd,
    Chetan

  • Need help on Production order confirmation cancel issue

    Hi,
    I need your help regarding Prduction Order issue.
    We have created Production Order and issued raw materials and we done paritial confirmation also. Now the order status is PNCF.
    After that we notice that it was wrong confirmation so we went CO13 we cancel those confirmations.
    But in our zprogram still those order is showing as paritial confirmation order.
    I need in which SAP table confirmation status stored and what will be the production order status after cancel the confirmation.
    and in which table cancel production order confirmation data will be availiable.
    please guide me
    sateesh

    HI,
    There is No Standard Status for Reversing or cancelling the Confirmation.
    Generally, When you confirm the status PCNF or CNF gets active.
    When you reverse it theybecome inactive.
    also let us know, whether You cancelled or reversed the confirmation or revesed the GI postings.
    If you have reversed the GI postings using Reverse Movement type or Materail documents, it is possible to have the PCNF order status unchanged.
    Regards
    Ratan
    Edited by: Ratan on Aug 28, 2009 7:23 PM

  • Production order confirmations to BW

    Hi,
    Does anybody know if it is possible to take production order CONFIRMATIONS (Fertigungsauftrags Daten auf Ebene Rückmeldungen) to BW via standard routines? In LBWE (with 2LIS_04_P_ARBPL, ...) it does not work.
    Would appreciate any idea ...
    Thank's Markus

    i don't think we are getting that from standard DS. I will tell you our set up. Workcenter will assigned from the Planed Order.
    Comming to your cases... check the DS once again. I will check it out. If you are not getting the values for work center where it is confirmed.
    Create a Generic DS. i can guide to generate a DS and for delta handling.
    1. Create a Generic Extractor for Master Data.
    2. Provide Table Name "AFRU".
    3. save the DS. click on Generic Delta Provide the field "ERSDA" and select the Calender Day. it will pick up the Delta records.
    Any questions let me know. If you reslove this with creating Generic DS please update the thread.
    All the best.
    Regards,
    Nagesh Ganisetti.

  • Batch Determination at the time of Production Order Confirmation

    Hi,
    I am working with Batch Determination at Item Level.
    I already have configured system to generate Batch Automatically at the Time of Production Order Release.
    But now i want to generate Batch Automatically at the Time of Production Order Confirmation
    Please help me with the necessary Configurations which would be required into achieving the same.
    Thanks in advance.
    Harris

    Hi,
    I have maintained the same for my Order Type in OPJ2 but still the same is not being picked at the time of Order Confirmation and it is being put to COGI mentioning the error as No batch specified in production order
    Also if i try to Manually Select the Batch through in Goods Movt. of CO15 it is giving a msg that No Strategy could be found.
    I have done following settings:
    1. Have maintained Condn Records in MBC1 for the component whose batch is to be determined.
    2. In material master in MRP2 Batch Determination: 2
    3. In OPL8: Batch determination search procedure
    4. In OPJ2: BD ticked for that relevant Order Type
    5. In OPKP: Automatic Batch creation kept as BLANK.
    Please support
    Thanks
    Harris

  • Serial Number. Production Order Confirmation. GR. UD. Sales Delivery

    Hi Gurus,
    Please help on this issue to get any user exits .....
    As part of Serial number management, we have a certain issues on serial number confirmation, goods receipt from production order and quality inspection with UD.
    Master data:
    Finished product material master, Workscheduling view, Serial number profile maintained " ASRN"
    Process flow:
    1) Avalon Specific Serial numbers generation for finished goods through production order release status.
                  (A11206000001)
                                        A  - Avalon
                                        1   - PCB Unit 1
                                        12 - Year 2012
                                        06 - Week
                                        000001 - Running serial number for the week.
    2) Production order confirmation through CO11n transaction.
    3) Production order Goods receipt through MIGO transaction against order.
    4) Quality Inspection with Usage Decision through QA32 transaction.
    5) Goods Issue for Delivery.
    SAP Product Error:
    1) System does not track and control the operation wise confirmed serial numbers during order confirmation.
    2) System does not track and control the finally confirmed serial numbers during order goods receipt.
    3) System does not track and control the last goods receipt qty in Usage Decision.
    4)  For semi finished product, if we maintain serial number profile in workscheduling view, system is not showing goods issue material list in Co11n transaction for the finished goods.
    5) Interfacing the serial number reading scanner with SAP,  is not working without entering material number and serial number manually.
    6) System does not tracking and controlling the last Usage Decision done serial number during Goods issue to Sale order Delivery.
    Regards,
    Santha

    Hi Santha,
    This is a bit vast, but I'll try to address at least some of the issues:
    1- serial number in operation confirmation is not possible, for the reason that serailization is part of stock management, and as WIP in an order, this is not stock yet. Actually you cannot confirm the manufactured material either, and those 2 go together.
    For tracking specificly WIP, there's something called WIP batches; you may look into it to see if you can use it.
    2- during GR system will propose those SNs that you have defined for the order at release or creation.
    3- ?
    4- GI in CO11N is provided only for BACKFLUSHED material components. Serialized materials CANNOT be backflushed.
    5- You can use a barcode reader to read the serial number (instead of keyboard entry) when cursor is on the right field in the respective screen.
    6- ?

  • URGENT: Prob with Production Order Confirmation

    Hi Gurus,
    I have a problem with Production Order Confirmation.
    When I am confirming a Prod Order and if the components present are more than '999', then error is being thrown and Material Document Number is not being created.
    I want to split the records into 500 slots and pass them at a time for the creation of the Production Order so that it doesnt throw me an error while creating a Material Document No.
    While saving the Production Order confirmation order, it should split the records into 500 slots each and then create Material Document No for each slot.
    Can anyone please help me out in this regard, how to solve this.
    Thanks & Regards,
    Harish Kalla

    Hi Harish,
    This problem is addressed in OSS Note : 36353
    The Symptom reads like this
    ==========================================================================
    When you post documents using the AC interface (from SD, MM or other applications), items appear in the FI document which are identical in all or in almost all fields.
    This can also cause error message F5 727 ("Maximum number of items in FI reached"). The system issues this error if more than 999 items occur in an FI document.
    ===========================================================================
    This Note is an elaborate one..
    Hence, go through this and ask your FI Consultant to help you in this regard.
    All the best..
    Regards,
    Siva

  • Measuring point update by production order confirmation

    Hi friends,
    I created a prt as equipment and assigned it to the routing. I created a production order and when i confirm the same i am getting following error as:
    Document MeasUnit has a different dimension to the characteristic unit
    Message no. IR071
    Diagnosis
    The measurement unit on creation of the measurement document must have the same dimension as the measurement unit of the characteristic of the measuring point.
    In this case, the measurement unit % does not suit the character unit EA of the measuring point 103.
    System Response
    Processing will not be continued.
    Procedure
    Use the possible entries help.
    Please suggest the solution.

    Hello Sir(s)
    i have gone through entire post for the subject related to measuring point auto update from production order confirmation.  I have tried the same but i dont know what i am missing.
    if i put some value like 1 or 2 and appropriate UOM then only my measuring document is being updated with the same value not with the actual confirmed quantity..  i have already maintained standard formulla in prt view.
    my basic requirement is to get actual value of produced quanity as counter update. means if 20 pieces have been produced and confirmed in co11n, then counter must bhe updated with the value of confirmed quantity.
    please advice what value should i put as usage in routing master to get actuall counter update.
    Will Highly appreciate your quick reply.
    Snapshots
    Regards.
    Mohammad.

  • Restricting Good Receipt Unless Production Order Confirmed

    Hi
    Experts,
    I want to Restricting Good Receipt Unless Production Order Confirmed
    I am doing following thing but the error is occured.
    Use Tcode BS02 ( Customising USer status profile).
    2. Select the order type which you want to configure (eg:PP000001) and choose "Details" button.
    3. In the User status table do the following:
    a. In the status no field type"1" , status field "Sta1", short text"GR not allowed",  lowest no "1",  Highest No "2". Mark a tick in the initial stats check box.
    b.Next line, type status no field "2" ,status field "sta2", short text"Gr allowed", lowest no "2" , highest no "2".
    4. Select the STA1 line and choose details. select the "create"button.select the "GR for prod order", mark "forbidden
    radio button" and "set radio button".
    5. Select the STA2 line and choose details. Selct the "create"button. select "confirm order", mark "permitted radio button" and "set radio button". Next choose "GR for prod order" , mark "permitted radio button".
    6.Save.
    Create a prod order and check whether the required scenario is working.
    I have created user status profile as PP000001   GR
    ERROR
    First define allowed object types
    Message no. BS218
    Diagnosis
    The object types for which a status profile may be used define which business transactions are included in business transaction control.
    Procedure
    First define for which object types this status profile can be used.
    What is object type how to define?
    Thanks & Regards
    Pert

    Hi,
    Refer to the below thread which addresses the same need:
    Re: GR not allowed :BS02
    Revert if you face any issues.
    Regards,
    Vivek

  • Production order confirmation problems

    My production facility has been having problems for years centered around the production order confirmation process.  My colleagues and I are considering submitting an OSS note to SAP, but figured that we should present our problems in these forums before making that next step.
    Here are some individual issues which I believe may be related.  All of these issues occur off and on at random.  They will typically occur when more users are working in the SAP system or when SAP is running slow.
    - When an order is confirmed and a label is printed, sometimes the quantity on the label will be incorrect.  Sometimes no label will print out at all.  When the order is unconfirmed and then reconfirmed again, a label prints out with the correct quantity.
    - When a confirmation is unconfirmed, the unconfirmation will not backflush the associated materials correctly.  Sometimes this error will appear in CO1P for us to re-confirm, but not always.
    - Sometimes confirmations will only backflush certain materials and not ALL the components within the production order.  When the confirmation is unconfirmed and then reconfirmed again, the confirmation will backflush all materials correctly.
    These problems occur at random intervals and never present the user with an error.  Close to 100% of the time all the confirmation issues will be corrected by simply u201Cre-doingu201D the confirmation as we did the first time (no changes in the process).  Only the second time around there will not be any issues.  This leads me to believe there is some internal issue with SAP, perhaps involving which tables CO11N pulls from when a confirmation is made.
    Any and all help is appreciated.  We currently run the AFS version of SAP.  This is my last stop before submitting an OSS note.

    Hi,
    I have not worked on AFS, so consider the below as a pointer which might help:
    When you post confirmations & notice that the components are not being backflushed, check in COGI it could be that there are some incorrect goods movement. You will be required to clear these entries from COGI.
    I suspect that you notice these because, the confirmations are being posted even before the stock for the same has been received & hence the issue with labels as well.
    Do a check on the above, if it resolves the issue, then i would suggest re-design the process to ensure you do not have COGI or COFC entries.
    Also do a search in OSS for AFS specific notes on confirmation.
    Hope it helps.
    Regards,
    Vivek

  • Error during Production Order Confirmation

    I get a real wierd error during production Order confirmation.  The error message is
    "Additional items are not allowed
    Message no. ZOAL010"
    Can anyone throw some light on this?
    Regards
    Raj

    it is not std SAP message.
    you can check the user exit for confirmation.
    check in transaction code CMOD/SMOD for CONF*