Hi Experts,
I am unable to cancel business completion of a PM order as the options are greyed out. The PM order is closed in normal way, still I don't see the options for cancelling or reversing the business completion.
Can some one help on this. I checked the previous posts.
Thanks
Surya

I have the same issue with all status under order - functions- being grey'ed out and unable to change.  I have done SU53 and trace, it is not an authorization issue, seems to be related to this one order.  In test system I ran the RIORD* programs and they all said they order was fine.
We have an open reservation against the work order that we would like cleared, so want to cancel business completion.  Any help would be greatly appreciated.

Similar Messages

  • Cancel business completion

    Hi experts
    Any one can help out, how to cancel the bussines completion if the PM order is closed on the last financial year , i.e 2008-2009 and now need to re-post some activity against that order.
    Is this can be done through authorization and what could be the authorization object.
    Regards
    N.Saidasan

    Execute the Transaction IW32 and check
    choose Order - Functions - Complete -  Cancel business completion. 
    if menu is greyed out, execute the transaction  /NSU53 to check the authorisation
    may be S_USER_GRP object missing in your profile. Ask security / Basis to add.
    otherwise use Firefighting ID to cancel the business completion.

  • Unable to cancel Business Completion

    Hi all,
    I need your inputs in this Issue.
    I have an Order which has system status 'CLSD MANC NCMP NMAT PRC'. Now the user want to reverse the CLSD & TECO and put back the Order in REL Status. Issue is that system is not allowing to reverse/cancel the Business Completion.
    There are other Orders in the same plant with same Order Type. I'm able to change the Status there as required.
    The only difference I saw between the Order which has the problem & other Orders is that there is no Settlement Rule (SETC is not in the System Status) defined for the Order (the one I want to put back to REL).
    In customization, Creation of Settlement rule is defined as mandatory for Release of the Order for this Order Type. The default Settlement receiver is CTR (Cost Center).
    I'm surprised to see this as all along I've been under the impression that a Settlement rule is mandatory for release or at completion.
    I'm sure this is not a standard behaviour. Is there a way to change the status.
    Regards,
    Ajai

    Hi Ajai,
                You are correct, if the settlement rule is defined in the to be mandatory for release then the system Automatically Creates the Settlement rule from the Master, but if the settlement reciever is not found then it ask for the same, and wont allow to save.
    I guess in that case the settlement rule must have been created and then removed from the Order once the order is released.
    can you just check the Chnage Log for the Maintenance order
    follow the path
    Extras-->Document for Order->Changes.
    check out for all the AFIH Entries.
    Hope it helps you.
    Regards,
    Yawar Khan

  • I downloads the latest iTunes software update and it properly installed.  But,  I cannot close the window showing it was completed and the blue completion bar is full but cannot cancel or close it either.  Any ideas on how to clear that out and close the

    I downloaded the latest iTunes software update and it properly installed.  But,  I cannot close the update window showing it was completed and the blue completion bar is full but cannot cancel or close it either.  Any ideas on how to clear that out and close the window.  Tried to quit on both the big window and the software update title in the menu bar.  No luck.

    Tried that by shutting down via the power button only as the normal shutdown was nixed by the open window issue.  It did not help.  Found a very similar question in the discussions and it recommended "Force Quit".  That worked and the update works normal and the window is gone.  Thanks!

  • HT4061 Ios7.04 update to ipad2. Will not let me continue the set up after trying to join a wifi network. Cannot cancel or start again. Cannot even switch off iPad. If you hold home button it says setup not complete continue? But it will not let me continu

    Update to iOS 7.04 on ipad2. The set up screen appears but it will not let me continue the set up. It will not let me get to the next screen after choose wifi network. It is if I am stuck on the choose wifi network page. Cannot cancel or continue. Cannot switch it off. Holding home button brings set up is not complete message. But it won't let me continue. Please help. What else an I try to get through the set up?

    You are now stuck at step 14.
    Software update
    1. Settings>General>Software Update
    2. Download software
    3. Agree to Terms and Conditions
    4. Select "Install"
    5. Verifying update
    6. Apple Logo + progress bar
    7. Black screen
    8. Apple Logo
    9. Apple Logo + progress bar
    10. Apple Logo
    11. Slide to setup
    12. Update completed
    13. Tap "Continue"
    14. Choose a Wi-Fi Network
    15. Update iCloud; enter iCloud password
    16. You will be prompted to setup iCloud Keychain
    17. You will be prompted to "Create a Passcode"
    18. Select "Don't Add Passcode"
    19. Welcome to iPad (Get Started)
    20. Home Screen

  • Unable to cancel busines completion

    Hi Guus
       Order is closed, Status is CLSD, Iam unable to cancel this status ,
    When I go to function--> cancel the business completion system throws an error as
    Technically complete not allowed.
    I know its not possible , is thier any way to cancel this, either through user exit or some Tcode.
    regards
    Krish

    Hi Pete
    Error is
    "Technically complete" is not allowed (ORD 600036803)
    Message no. BS007
    Diagnosis
    The current status of object 'ORD 600036803' prohibits business transaction 'Technically complete'.
    Procedure
    To process business transaction 'Technically complete', you first have to change the status of object 'ORD 600036803' to allow the transaction 'Technically complete'.
    This gives you an overview of the system and user statuses that affect the transaction. A transaction can only be executed if there is at least one status that allows it and there is no status that forbids it.
    Transaction analysis
    regards
    Krish

  • 5320 cannot cancel single sms entry in call log

    Hi,
    I've a problem, my nokia 5320 (s60 3rd) cannot cancel a single entry from sms log. The only solution I have is to cancel the complete log (calls as well).
    Reading the forum I understand it's a limit of s60, someone is suggesting codes (but I really don't know how to use them) and someone else is suggesting a software (but they never mention the name).
    Can someone be so kind to give me the name of a s60 application (if free better..) able to perform this task?
    Thanks
    Max

    this cant be done
    If  i have helped at all a click on the white star below would be nice thanks.
    Now using the Lumia 1520

  • My iPad gets stuck...cannot cancel or send message in mail

    My iPad gets stuck...cannot cancel or send message in mail

    Try closing the Mail app completely and see if it works properly when you re-open the app : from the home screen (i.e. not with the Mail app 'open' on-screen) double-click the home button to bring up the taskbar, then press and hold any of the apps on the taskbar for a couple of seconds or so until they start shaking, then press the '-' in the top left of the Mail app to close it, and touch any part of the screen above the taskbar so as to stop the shaking and close the taskbar.
    If that doesn't work also do a reset : press and hold both the sleep and home buttons for about 10 to 15 seconds (ignore the red slider), after which the Apple logo should appear - you won't lose any content, it's the iPad equivalent of a reboot.

  • Cannot cancel

    Hi, we are currently helping other customers in line ahead of you. We'll be with you as soon as possible.
    While you wait, you can try our community forumswhere experts are online 24/7.
    My experience with Adobe support earlier today,  unresoved, below:
    (I would appreciate if someone can cancel my subscription without taking money from me, thank you)
    You are now chatting with Neha. To ensure we stay connected throughout our interaction , please don't click on the 'x' in the chat window. Doing so will disconnect our chat session.
    Neha: Hello! Welcome to Adobe Customer Service.
    Neha: Hi Micha.
    Micha Oelsner: Hi
    Neha: I understand that you wish to cancel the subscription.
    Neha: I'll be glad to check and help you with that.
    Micha Oelsner: Yes please
    Micha Oelsner: What do I need to do?
    Neha: I have checked and seen that you have purchased Adobe ExportPDF Annual on Mar 10, 2013.
    Neha: May I know the reason for canceling the subscription.
    Micha Oelsner: Yes, I couldnt figure out how to cancel in time
    Neha: Okay.
    Micha Oelsner: That program does not work. Any documents I tried to convert from PDF into ie word, did never convert correctly. So I stopped using it and certainly don't want to pay for another year for a programm that does nor work for me. I am on Windows 7, 64 bits and use open office. That might be the problem.
    Neha: Okay.
    Neha: Please give me 3-4 minutes to cancel the subscription for you.
    Micha Oelsner: I also don't have the time to get to the bottom of why it is not working. I was not aware of the subscrpition automatically carrying on and did not know Adobe can just try take money off my CC without first invoicing me or something. And as mentioned I couldnt figure out how to cancel in time, and also saw the email from Adobe too late! (I was moving from one city to another in February, so my emails piled up
    Micha Oelsner: Oh, ok, if you can cancel the subscription for me, great! please do
    Neha: Micha I see that you need to update the credit card details if you wish to cancel the subscription. I request you to please update your credit card details so that I can cancel your subscription.
    Micha Oelsner: My CC details have not changed. What do you mean update?
    Micha Oelsner: The reason the payment did not go through is that I have no funds in my CC
    Neha: Micha I cannot cancel your subscription until your credit card details is not updated.
    Micha Oelsner: Explain what you mean with that, because my CC details as they are on your system have not changed...
    Neha: Micha that is for CC subscription. The subscription that you are referring is for Adobe export PDF.
    Micha Oelsner: Now I am confused. So what exactly do I need to do now?
    Neha: You have contacted us to cancel your Adobe Export PDF subscription and i checked that you need to update your credit card details in order to cancel your subscription.
    Micha Oelsner: How do I do that? Where do I go? Is there a link?
    Neha: I'll provide you the steps to update the credit card details.
    Micha Oelsner: ok
    Neha: 1:Sign in to Creative Cloud @ creative.Adobe.com . Click My Account.
    Neha: 2:Under Plan Information, click Edit Payment Info.
    Neha: 3:Enter your password, click Verify, and then enter the new payment information.
    Micha Oelsner: Under my subscription, is says edit billing. Is that what you refer to?
    Neha: Yes, you are correct.
    Micha Oelsner: But that makes no sense,my CC details have n ot changed. So how do I change them if they have not changed???
    Neha: I am sorry Micha I cannot cancel your subscription until you change you credit card details.
    Micha Oelsner: Change them to what if they are the same as before???
    Neha: Please update it.
    Micha Oelsner: Must I make invent new CC details?
    Micha Oelsner: You have tried to take money off my CC. The reason it did not work is NOT because my CC details changed, it is because there are no funds
    Neha: Okay. You can contact us back once you have funds and we will be able to cancel your subscription.
    Micha Oelsner: I am not paying! I dont want the subscripotion!
    Micha Oelsner: Why would I pay for a whole year that you are cancelling anyway!
    Micha Oelsner: I am shocked at Adobe's way of making business. I will rather cancel my CC and get a new one so that I never hear from Adobe again and so that you can never access my CC account again.

    Hi Micha O,
    As you want to cancel Export PDF, annual plan there will be no charges for the subscription according to the below mentioned link:
    http://helpx.adobe.com/x-productkb/policy-pricing/cancel-subscription-acrobat-online-servi ces.html
    You may also contact our Customer Support:
    http://www.adobe.com/support/download-install/supportinfo/
    Thanks!
    Gurleen
    Message was edited by: Gurleen_K

  • You cannot cancel a change request with status New.

    We're just starting to dive into SCSM. We created a test Change Request and now want to delete / cancel it. When we try, we get a message
    "You cannot cancel a change request with status New."
    Is there an easy way to remove this?
    Orange County District Attorney

    Hi, a Little late but..
    This is a problema from your 3 scsm services, maybe in your principal or secundary server.  You must to restart services in an special order and delete application cache.
    Please review
    http://www.systemcentercentral.com/scsm-2012-tip-all-workflows-stuck-in-new-status-and-never-completing-issue-and-workaround/
    it Works!
    If you have principal and secondary do it in both servers.
    I think this problem is for bad performance in databases and application, so review your hardware design, and logical, so review workflow performance too.
    For items when state new, you must change it to inprogress with smlets

  • Cannot do a complete backup

    I have Elements 10 on Windows 7.  When I try to do a complete backup to an external hard drive, I see "calculating total media size" and the execution bar stops at 96% and nothing else happens.  I have waited for an hour, nothing.  My CPU usage meter shows no activity.  It is like it is hung up.  I cannot cancel, I have to click the x button.  At some point in the past this wroked since I had three complete backup files on my external drive (which I deleted before doing this).
    What's wrong?

    Hi Michel,
    MichelBParis wrote:
    I am a regular reader of the LR forum where you find lots of computer experts and I have still to read a complaint about the database engine choice.
    That's an interesting point, and I freely admit I don't know if the problems seen here with catalogs are due to:
    The SQLite database engine itself.
    The design of the Organizer's database structure.
    The program code used by Organizer to manipulate its data.
    MichelBParis wrote:
    In my experience, the usual advice to run 'repair' and 'repair anyway', inherited from the days of Access, are only 'placebos' and I have never been of any use. (Always in my own experience).
    I don't know what the Organizer's "repair" does, so I share your scepticism about that function -- it's never helped with issues we've seen here.  The "optimize" function, however, is valuable and has always been valuable, even when using Access.  The reason is that when a database is told to "delete" a record, for performance reasons the record is simply marked as "no longer available".  The physical space occupied by that record's ones and zeros is still there on disk.  With time, if a lot of records are deleted there are accumulated a lot of "dead" areas that affect performance.  "Optimizing" rewrites the physical ones and zeros, physically removing the "deleted" records and moves the remaining ones and zeros on disk to create contiguous used areas on disk.  (This is why "optimizing" is also called "compacting".)  With "personal" databases like Access and SQLite, that optimization must be initiated manually, but "enterprise class" databases like MS SQL Server (and MS SQL Server Express) and Oracle and IBM's DB2 are server-based database engines and can perform that database maintenance automatically.
    MichelBParis wrote:
    I am a regular user of John R Ellis's psedbtool, and I consider that integrating some of his diagnosis and repair tools instead of fancy automatic processes would be a welcomed progress.
    That's pretty much the same point I'm making.  There are huge advantages to having a database engine running as it's own separate process.  One of those advantages is that the database engine can constantly run its own optimization and integrity-checking processes against the databases that are connected to it.
    Here's why I'm so enthused about "enterprise-class" databases (and MS SQL Server Express in particular):
    The way I see it, any free open-source database (like SQLite) by definition, does not make a profit for its developers.  The quality of that database is determined by the skill of the developers, their dedication, and how much time they can afford to spend on it.  On the other hand, major databases like MS SQL Server, Oracle and DB2 generate hundreds of millions of dollars in profits for their respective companies.  Therefore, they will have the most knowlegeable and skilled developers available in the world working full-time on those databases.  Those databases are used for extremely critical applications like credit card processing on a global scale, so those databases will incorporate the most advanced and reliable features known to man.
    If I can have a choice of databases for my personal use, it would be foolish not to choose the most advanced and reliable one.  Each of those companies offeres an entry-level database, and in the case of MS SQL Server, MS is aggressively promoting the free "Express" version as an "entry-level" database in order to impress users with its features in the hope that they will later spend the money on its flagship database.  That's why the free "Express" version uses the same database engine as the "big" SQL Server.
    So, I enjoy using MSSSE for my personal projects, and I sleep well at night knowing I've got something at the top of its class.  For our image cataloging purposes, there is the example of this program, whose "Pro" version allows the use of other database engines:
    http://www.cerious.com/thumbnails.shtml#standard
    I'm surprised that feature has not been implemented by Adobe, especially for Lightroom.
    Ken

  • Whr we do the business completion other than in IW32

    Dear PM Gurus,
    my client requirement is Accounts / Finance departments do the Settlement for TECO orders, after settlement clients requires Business completion should done by Accounts department. How i have to give this authorization i know CO99 which should used to Collective Closing of the orders. Is there any other t.code ? In IW32 we can give authorization but is there any choice to operate only Business completion action only? is it possible can we restrict for other activities? and one more thing i want to restrict to cancel the TECO and Business completion is it possible ? if possible in which way we can restrict this functionality? its mandatory for my business.
    thanks in advance to all PM Experts
    regards
    jalu

    hi
    create one role with following values and assign to finance users.it will allow only to do completion.also check with your securiy team as well if anything missing.
    Authorization object:I_VORG_ORD(PM: Business Operation for Orders)
    Field name:BETRVORG
    Field value-BABS(Complete)

  • Business Completion Importance

    Hi Expert,
    Can anyone explain about maintenance order "business completion" importance?
    Why business completion need to done after order settlement? and what the impact(s) that might happen if we do not perform business completion?
    Please help
    Thank you
    Rgds,

    Hi Micheal
    Business Completion is done to ensure that no more costs are expected for the Order & it is financially closed
    After Business Completion , the Order cannot receive any further postings
    It is a requirement from Controlling view point.
    For more clarifications / understanding kindly refer [here |http://help.sap.com/erp2005_ehp_03/helpdata/EN/5b/ae39634b8611d182ba0000e829fbfe/frameset.htm]
    Regards
    Jignesh

  • IPad is "frozen" whilst in Draft email. Cannot cancel, delete nor get back to my emails. Help !

    IPad is "frozen" whilst in Draft email. Cannot get back to my emails, cannot cancel Draft. Help.

    First, try a system reset.  It cures many ills and it's quick, easy and harmless...
    Hold down the on/off switch and the Home button simultaneously until the screen blacks out or you see the Apple logo.  Ignore the "Slide to power off" text if it appears.  You will not lose any apps, data, music, movies, settings, etc.
    If the Reset doesn't work, try a Restore.  Note that it's nowhere near as quick as a Reset.  Connect via cable to the computer that you use for sync.  From iTunes, select the iPad/iPod and then select the Summary tab.  Follow directions for Restore and be sure to say "yes" to the backup.  You will be warned that all data (apps, music, movies, etc.) will be erased but, as the Restore finishes, you will be asked if you wish the contents of the backup to be copied to the iPad/iPod.  Again, say "yes."
    Finally, if the Restore doesn't work, let the battery drain completely.  Then recharge for at least an hour and Restore again.

  • PR Marked for deletion after Business Complete

    Hi gurus,
    My PR created from work order are marked for deletion after business complete and/or why is it being marked for deletion?
    the requirement is to not mark it for deletion. is this possible?
    Thank you.

    Dear,
    Technical confirmation is followed only after all confirmations and GR/GI and reservations posted which means that the work has been completed on ground.,The remaining Capacities, reservations, partial confirmations, Open PR's(Not processed into subsequent material documents like RFQ/Quotations, PO) Open PO's get cancelled as soon as you TECO the Work order. so this clearly states that all your PR's ad PO's are delted at TECOstage much before settlement and Business Completion is done.
      If you want ur PR's not to get cancelled then you can lock the PR's and then TECO the work order. However this lock will prevent PO creation.The best way to do this is to give  a user status and hold the PR from getting deletd. User status can be provided at PR or Work order level.