Change in Business Area in project structure

We use Project System to execute large turnkey projects. Due to recent
change in Organisation Structure , it is necessary to change the
Business Area field in Pending Projects. Is it possible to change the
field for pending projects. In some of the projects the networks are
released , the business area field is greyed out and not modifiable.
Can you suggest the solution in this case.
With Regards
BGLimaye

Hi
It's possible to change BA only if the option "Time-independent" is checked" in customizing for AA:
ORFA->Master Data->Specify Time-Independent Management of Org. Units
Visit:
http://help.sap.com/saphelp_470/helpdata/en/4f/71ec4c448011d189f00000e81ddfac/frameset.htm
Or refer  > chaning business area in asset master
Regards,
Zub

Similar Messages

  • Problem in changing the Business Area?

    Hi,
    I have a discoverer report where the eul folders are in one business are. Now I need to change the business area. By manage folder option I can do that.
    Now my query is as the business are is changed for the folder what should I do for the workbook. Do I need to recreate it because the business area definitions are changed.
    Could anyone please help....
    Thanks

    Hi,
    You don't need to change the workbook at all. However, make sure the business area security is correct so that the workbook owner can still access the folder. The workbook references the folder and so the folder will be shown in the new business area when you inspect the workbook items.
    Rod West

  • Change of Business Area in Cost Center

    Hi,
    We want to change the business area for the existing cost center from next fiscal year.
    Suppose i have a cost center 1001ADM with Business area 1000 and validity time is 01.04.2007 to 31.12.2999.
    Now i want to change the business area to 2000 for the existing cost center 1001ADM with effect from 01.04.2008.
    Regards
    Balaji

    Hi,
    Changing the business area is possible.  Go to KS02> Menus> Analysis period --> Give the new analysis period for which you want to change the field business area.
    Now give the new business area.  you will get a message changing this field will take time to check the dependent data.  Give 'Yes'.  It will check all the depending data and then change the field for the new analysis period.
    Good Luck!!!!!
    Thanks and Regards,
    Bhuvaneswari.S

  • Change of business area in direct table entry

    Hello All,
                 We are trying to change the business area in table MSEG by direct table entry through se16n.
                 But i am getting the error "GL account XXXXXXX not fouind in table SKA1."However when i check the table SKA1,entry XXXXXXX exists in table SKA1.The company has decided to change its policy and therefore they want to change the business area..Please tell me the procedure so that i can change the business area.
    Thanks,
    Saurabh Kumbhare

    Hi Pravin,
    First of all, do not change the values directly in tables.
    You want to change Business Area in MSEG but at the time document entry there may be other tables where this entry might have gone. So you need to identify all the tables before you do the change. Hence it is better to consult FI/CO team to find the solution from funtional side.
    However, still if you need to change the value then look for the GL A/C in table SKB1. Since SKB1 is company code dependent data you have to check if the said GL exists or not in company code contained in MSEG.
    Regards,
    Firoz.

  • Change of Business Area to Cost Center (my first thread , please help)

    Hi Everybody i'm Charmaine Leena Martin freshly certified  FICO consultant , this is my first thread i'm posting, please help me with the same.
    A wrong business area has been assigned to a cost center and postings have taken place in the same.
    while using t-code KS02: change cost center , for rectifying the business area , i get the following error:
    "Field change business area is not possible (transaction data exists)"
    so i've created a new cost center and assigned it the right business
    and using t-code kb61 : i have posted the documents to the new cost center
    at that time system generates a co-document automatically:
    But the accounting document of which transfer postings have taken place still shows old business area and cost center
    Please let me know why is it so ,
    and what has to be done with the CO document that gets posted automatically
    and is there any other way out of changing the business area without creation of new cost center
    Moderator: Please, search before posting

    Hi Leena
    Welcome to SDN
    Do KB11N to post the cost back to the Wrong cost center
    Do an FI Posting again Dr the Correct new cost center and Cr the Old wrong cost center
    This will match both FI and CO
    br, Ajay M

  • Changes in material transferred to project structure.

    Hello,
    It is required to track the changes made in material transferred to project structure alongwith User Name. (eg: Deletion of magterial, Incerease/decrease in qty etc)
    In assignments, we can only see the Username of the person who has  made the last change.
    Kindly help.

    Hi Nidhi,
    Please refer to SAP note : 1127691.
    In this note Point 5  CNEX0026 -- EXIT_SAPLCOMK_005 will help you.
    This user exit is used to check if there are any changes done to the material component in the component overview screen or the details screen of the material component.
    Regards,

  • Business Area in Enterprise Structure

    Can someone please explain the purpose of Business Area/Business Unit in the Enterprise Structure? I'm wondering, functionally, how it is different from personnel area and personnel subarea, as we use the PA and PSA to distinguish  between departments and business units, respectively. Are there integration differences, or is there not a significant difference?
    Thanks for any replies and help.
    -Nick

    Hey Nick,
    If you bring up the help on Business Area within the IMG, you get the following:
    Define Business Area
    Use
    In this section you create business areas. A business area is an
    organizational unit within accounting that represents a separate area of
    operations or responsibilities in a business
    organization.
    When defining a business area, you enter a four-character alphanumeric key
    and the name of the business area.
    In a client, you can set up
    several business areas to which the system can assign the postings made in all
    company codes defined in
    this client. To ensure consistency in document entry, you should give business
    areas the same name in all company codes.
    You make all other specifications for your business areas in the Financial
    Accounting Implementation Guide.
    So as this and Theo also indicated above, this is relevant for FI.
    Hope this helps!

  • Change of Business Area in Line item

    My client has posted many documents without assigning Business Area to each line item.  When they try to assign in the document overview, the field is grayed out.  Can anyone help me in sloving this issue.
    Lakshman

    Hi,
    BA is not allowed for change on already posted document, even if document change rule is maintained, and field status is correct. BA is one of the organizational units (like company code, profit center etc..) and these fields are not changable by system default.
    You must reverse the document with incorrect BA (trx. FB08) and post a new document with the correct BA.
    Best reagrds, Kyoko

  • Warning message should be raised when user changes Business Area in MIRO.

    Hello all,
    My requirement is,
    When in MIRO transaction, in details tab the BA (Business Area) comes from PO line items. When user changes this Business Area to some other value then the system should raise a warning message and continue with the transaction. It happens in MRHR transaction in 4.6. Now we are on ECC6.0 and user wants this functionality.
    So is there any configuration to be done or so I need to write User Exit?
    Please explain in details like where to make these config settings and all.
    Thanks in advance.

    Hi Harshal,
    Make use of  EXIT_SAPLMRMP_010 in Enchancement LMR1M001  User exits in Logistics Invoice Verification.
    Raise your warning message by validating GSBER present in structure in exit's FM : EXIT_SAPLMRMP_010
    hope this helps.
    Regds,
    abhee

  • Problem while changing Business Area in Cost Center Master Data

    I am having a problem while changing the Business area in cost center master data, the system does not allow to change the business area due to the following reasons;
    1.  The transactional data already exists for that cost center
    2.  The desired date required to be changed, falls between analysis period 01.01.2000 to 31.12.2999
    Can anyone help me in order to reslove this issue
    Thanking in anticipation
    Edited by: Arshad  Iqbal on May 24, 2010 2:10 PM

    Dear Dejan !!
    Thanks a lot for resolving my problem actaully i have tested the scenario in Testing Server by changing the fiscal year and the system allowed to change the business area before any transactional data posted.
    Thanks Once Again
    Regards
    Ch. Arshad Iqbal

  • Business area in FI changing without using substitutions

    Hi all,
      Is it possible to change the business area when we post a clearing document?
      For example, we need to pay the line item that have business area 3000. Then we use transaction F110 to create a payment then a clearing docuement will be created with business area 3000. Can we configure it to change to Business area 1000 when we do the payment.
      I tried to implement a FI substitution but Business area field cannot be changed(OSS Note 42615). we can do that by changing standard program but it is not recommended by SAP.
      Any idea on how to do this? Configuration, BTE or any user exits? Point will be rewarded for any helpful answer.
    Thanks,
    Chaiphon

    Hi,
       Post in   Expert Forums  » SAP Solutions  » ERP Financials  forum too, they may help you.
    Regards,
    Satya

  • Can business area change when we post a clearing document?

    Hi all,
      Is it possible to change the business area when we post a clearing document?
      For example, we need to pay the line item that have business area 3000. Then we use transaction F110 to create a payment then a clearing docuement will be created with business area 3000. Can we configure it to change to Business area 1000 when we do the payment.
      I tried to implement a FI substitution but Business area field cannot be changed(OSS Note 42615). we can do that by changing standard program but it is not recommended by SAP.
      Any idea on how to do this? Configuration, BTE or any user exits? Point will be rewarded for any helpful answer.
    Thanks,
    Chaiphon

    hi raj,
      Could you please explain more about assignment and substitution? did you implement this before?
      I am in doubt because OSS Note 42615 said that GSBER (Business area) must not be substituted. Therefore, if you implement it and there is no problem, I will do the same.
    Thanks,
    Chaiphon

  • Changing business area on a cost center

    We mainly use HR, but we use some FI/CO for accounting.  (I am no expert in FI/CO whatsoever - so please excuse any incorrect terms).
    Our users have entered incorrect business area to a cost center.
    This business area is now registered on employees, and payroll/posting has been run up unitil October 2010.
    If I try to change business area from 01.11.2009 (realize it is probably not good to change earlier due to postings); I get the following error message: "Field change Business Area is not possible (transaction data already exists)"
    In addition, the message says: If you still want to change the object, select a suitable change interval by choosing "Edit -> Analysis period...".  However, trying to change the analysis period I am told I have to choose year end.
    My questions are:
    1. Is there a way I can change business area from 01.11.2009 ?
    2. Is there a way to change area earlier - and if so, what are the impacts+
    I appreciate any help
    Kirsten
    Edited by: Kibo on Oct 11, 2009 2:44 PM

    Hi Kirsten,
    Normally, it's not possible to change business area during a fiscal year once there is already postings in this Fiscal Year.
    The reason is to make sure that there is no change within the fiscal year since you then would have different postings - cost center belonging to different business areas within the same fiscal year. Meaning that it is possible to change the business area for the next fiscal year like described in the long text of the error message KS134. The reason is that it is to avoid inconsistency update of the table (COSS, COEP, or COSP).
    Although, If the following requirements are met, than it is is possible to change the business area during a fiscal year with the
    help of the note 62716:
    1.  The change interval is set to period limits
    2.  There is no dependent actual transaction data in the change interval
        or afterwards.
    3.  There must already be an analysis period for the respective cost
        center which starts on the first day of the chosen period. If this
        is not the case, you can create one with 'Change cost center'
    If the requirements are met, you can run the report RKACOR06 in SE38
    safely. I recommend you to execute the report first with Test Run on
    your test system.
    Regards,
    Greta

  • Field Business Area in cost center cannot be changed

    Hello all,
    we would like to change the "Business Area FS" (OB65) field for our
    company code to required. But if we do that, we have issues with 2 of
    our cost centers (ks02, analysis period 01/01/10-12/31/10) that won't
    allow us to enter a business area.
    We get the following error message:
    NA KS134 Field change Business Area is not possible.
    Diagnosis: To ensure of existing data, you can only change object
    Business Area if no transaction data exists in the change period; that
    is, neither plan data nor actual data has been posted.
    I have checked with our accounting and the cost center report does not
    have any data in actual nor budget.
    Somehow I figured out that we do have an entry in table CEKO for this
    cost center for 2010. (se16n). I did some further research and tried to
    test report RKPLNC18 to delete this entry. But I get the message:
    the deletion could not be carried out. The following plan/actual
    records are available...
    Any suggestions?
    Thanks
    Anne

    Hi
    You can change the business area in cost center by changing the Analysis period. If there's any data exsist it is not allow you to change the business area. If else block or eleate the cost center and create a new one ( even though this might not permitted if  data exsist in related to cost center.
    Regards
    Kesharika

  • Cost Center validity period change & Business area assignment to cost cente

    We are facing with error KS134 - Transaction data already exists for the period.
    We tried to create new cost center with period split. But I am getting error KS133 - Deletion is not possible (dependent records exist in table ).
    Hence even creation of the new cost center is not possible. We alrady have Validity Period from 1.04.2005 to 31.12.9999.
    Is there any alternative solution ?
    Sumeet

    Hi Sumeet,
    The fields in Cost Center Master Data are "Time-Dependent" and you can see the Time-Dependency of each field in OKEG transaction code where you can find "Business Area" to be "Fiscal-Year" based.
    So, if at all you need to change the Business Area, it would be possible in next financial year only...
    And also, because, your Cost Center is defined from 01.04.2005 to 31.12.999, there is no way that you can change the validity period so as to create / extend in the same period-lap.
    I hope you got it...
    Srikanth Munnaluri
    Edited by: Srikanth Munnaluri on Apr 8, 2009 3:11 PM

Maybe you are looking for

  • Goods Issue using BAPI_GOODSMVT_CREATE movement type 541

    Hi     According to my requirement I need to do Post goods issue using BAPI_GOODSMVT_CREATE. But I am unable to do PGI . how to consume BOM details if batches are changed. please let me know what values I need to pass to BAPI . give with an example.

  • Providing ADF security  to fusion WebAppliaction (ADF 11g)

    I created ADF application contains single page . i am able to deploy this on standalone WLS10.3 But i need to provide the security to my application. I am reading the chapter : Enabling ADF Security in a Fusion Web Application in develpers guide. is

  • Report exceeded opened cursors limit

    Hello everyone, I'm building this report using ref cursors. I've following the steps in "Oracle 9i building reports" document. My report has 2 ref cursors with a data link between them. I'm suposing that a cursor is opened once for the main query and

  • Delete a "page" within pages

    I am desperate to delete several pages within a saved Pages document. The problem is: it appears all my pages are "merged" or something. When I click "View - Page Thumbnails" the thumbsnails do appear on the left. However, I cannot select ONE page to

  • Aperture 3 slow to import

    Why is Aperture 3 so slow to import! It can take five minutes to recognise just a few images on the Desktop and the fan whirls. This must be a bug!