Hi all,
Is there any function/BAPI/BADI to check budget on particular cost element in any cost center? The requiement is to check budget in one of the customized ABAP program.
Regards
N|S
Thanks for your reply Eli.
Actually, the requirement is to simply have a function to check if budget is available to particular cost object (say cost center in our case). We have Expense GL Account 900101001, which is configured as cost element as well and we use to post through cost center 800101001. The cost center is being derived through OKB9. Now, the requirement is whenever user post aforementioned expense, the availability of budget should be checked.
This use to happen in any standard transaction code, but as we have developed our own TCode for particular functionality, we need to have budget check function.
Further, FM is also activated, so I think i', using the right word Budget, as Fund center is also created similar to the name of cost center.
Hope the requirements are clear
Thanks!
BR
Similar Messages
-
Report Painter values are not populating for a particular cost center
Report Painter(GR55) values are not populating for a particular cost center for the months of April 1 2011 where as for May onwards values are displaying correctly..We have check the transaction code KSB1 for this cost center there are some values posted for the period of April..
Can any one help me to find out where exactly the issue is and how to resolve the same..Please check your variables in your report.
-
For display budgeted amount in cost center what is table in sap?
For display budgeted amount in cost center what is table in sap?
Hi,
Is it budget or planning ? Budget is in BPJA; while planning is mainly in COSS, but also in COSP.
Regards,
Eli -
*hw 2 find user id of budget controler in cost center master data using RFC
HI all ,
can anybody tell me which RFC call is used to determine the user id of the budget controller from the cost center master record.?????
urgennnnnnnnntttttttttttttttttttttt pllllllllllllllzzzzzzzzzzzHai.
it may help u.
Refer this link:
http://help.sap.com/saphelp_nw04/helpdata/en/22/042518488911d189490000e829fbbd/frameset.htm
check out the following link it might help you
http://help.sap.com/printdocu/core/Print46c/de/data/pdf/BCFESDE2/BCFESDE2.pdf
Re: RF screens development
Re: RF Transaction:Control Framework: Fatal Error GUI cannot be reached
regards.
sowjanya.b. -
Load the Budget value at cost center level only
Hello All,
Can we load the budget value at the cost center level only with out using cost element . I have seen that we can from actual to budget in Kp98 at the cost Center level.
Thanks ,
KrishnaHi
There is a work around...
You can create one Statistical IO for each cost center and upload your budget in it...
Keep the same nomenclature for IO as the Cost center i.e. If cost center name is 123456, have the same name for IO as well
In Substitution OKC9, you can use a Field to Field Mapping and populate same IO as the Cost center no in the posting or you can also use exit RGGBS000
br, Ajay M -
Budgeting on account & cost center level
Hi ALL, My company is planning to implement SAP in the near future and I'm taking the SAP course now. According to what SAP instrcutor said, budgeting cannot be done on account & cost center level. In my company, our current practice is to record all budget figures under account & cost center level and for every expense (invoice or journal) input, account & cost center would be the mandatory fields so that budgeting can be monitored in such level.
Can anyone tell me how this can be handled in SAP?HI
DONT TRUST that type of words.
i hope that your instructer is not a real time guy.
we have to do Budgeting at cost center lavel in Cash Budget management. why because that is (Cost Centyer)Orgnisational level Responsibility Area
and item level in Funds mangement.
But for every expence you want do the budget you have to implement Funds mange ment Module.
then your item level budgeting will be solved.
Thanks & Regards
Mala K Reddy. Vundela -
Getting Cost Center Does not exist error when executing BAPI_ACC_GL_POSTING
Hi Champs,
I am getting Cost Center Does not exist error when executing BAPI_ACC_GL_POSTING_CHECK.
But when I checked for the particular Cost center, it is mapped to the same company code the program has got executed.
Example:
Cost center 1000/150402 does not exist on 17.11.2009.
Cost center 1000/150402 does not exist
Cost center 1000/150402 does not exist on 17.11.2009.
Cost center 1000/150402 does not exist on 17.11.2009.
Please let me know if you have any guess on this. It is very critical issue for me.
Thanks for all your help in advance.
With Best Regards,
Ravi kanth YechuriUse 0000150402 not 150402 .
Rob -
Tables for BUDGET & ACTUAL - COST CENTER
Hi
I want to know what are the table in which the actual and the budget for the COST CENTER are stored....
Regards
SAP4MEHi Eli,
Thnx for the reply.i have already checked those mentioned by u.
My req is that i want to pull the DATA for developing a report of ACTUAL and BUDGET for a particular cost center o range of cost cost centersfor a range of period.
But in the table mentioned by,how can i will come to know,to which cost center ,what is budgeted and the actual .
Please give some details.
Regards
SAP4ME -
How to get Cost centers a below a cost center from hierarchy using ABAP
Hi !!
I am currently developing a user application wherin i need to give a dropdown help to the users for cost center field.
How ever I need to give him those cost centers in the help which are lower to the cost center to which he is assigned .
For example he is at department level which has cost center '90000' he should get the cost centers of the offices assigned to that department in the hierarchy .Also cost centers of various lower nodes which might have been assigned to these offices and so on so forth .
How can I get those cost centers which lie lower to a particular cost center in the hierarrchy using ABAP ..as I am in to BSP application and have access using ABAP.
thanks in advanceBSPIAN,
usually there will be a hierarchy table where the cost center hierarchy is stored. see if you can find that table.
To go about the same , activate the datasource for cost center hierarchy from business content
Execute the datasource in RSA3
do a background SQL trace and you will find the necessary table for the same.
Hope it helps..
Arun
Assign points if helpful -
Particular GL acc to Cost center
Hello,
Can anyone let me know how to see a particular GL acc has assigned to particular cost center or profit center?
Regards
AnifiHi ,
It is not mandatory that, G/L account should be assigned to particular Cost center only. The same G/L can be used for many cost centers, profit centers.
Through OKB9, it is fixed for CostcenterG/L or profit centerG/L or etc.. For that the table is TKA3A.
For G/L + Profit center center combination, you can check 3KEH transaction code.
There is no specific Where Used List for G/L.
I hope, it helps -
Respected Gurus,
what is the procedure of budget consideration in cost center,types of budgets.
regards
janakinldy check the sap note SAP Note 68366 - Active Availability Control for Cost
Centers
Symptom from SAP note as cited above
The standard SAP R/3 System has no active availability control for cost
centers. You can exceed the cost center budget without corresponding
messages
Solution part of sap note
The SAP R/3 System's active availability control is for individual
measures, meaning job orders and WBS elements only.
If you want availability control for postings to cost centers, use the
following indirect solution for primary postings:
o Create a statistical job order for a cost center or cost center
group and enter the cost center budget as a budget for this job
order. Then activate availability control for the job order.
o By using a customer-defined substitution in CO (transaction OKC9),
you can ensure that the statistical job order is posted
automatically if a manual posting is made to one of the cost
centers. The budget of the statistical job order is checked during
posting. If you exceed the budget, a corresponding message appears.
- Note: Substitution does not work for automatic allocations --
assessment, distribution, imputed cost calculation, and so on.
If you use Release 3.0D or earlier, also refer to note 45226. -
Cost Center Budget-Cost element wise
Dear SAP Gurus,
My client needs to create cost center budgets cost element wise. For e.g. Salary paid (code 430000) in Development Cost center (code 9901).
We now use KPZ2 to create cost center budgets and KP06 for cost element planning. Kindly guide.
Regards,
SivaHi Ramesh,
Thank you for the reply. I did suggest them to use KP06 but they require some sort of validation when posting an expense (cost element) to and cost center.
For e.g. If the travel budget for Marketing cost center is $1000, they need the system to prevent posting once that amount is exceeded.
Any help in this regard would be appreciated.
Regards,
Siva -
Budgeting for Cost center in KPZ2 tcode
Hi Friends,
I have a requirement stating to create the cost center and do the budgeting for that cost center.
This has to be done using BAPI / FM.
Can anyone help me out in finding out the BAPI / FM .Try those BAPI
- BAPI_COSTCENTER_CREATEMULTIPLE Create One or More Cost Centers
- BAPI_COSTACTPLN_POSTPRIMCOST Primary Cost Planning: Postings (sample report RK_BAPI_POSTPRIMCOST)
Regards,
Raymond -
Hi All,
How can we budget for a cost center.
We want the system to stop on 95% of budget(cost center).
At 95 % system should give an warning message that "budget is almost exhusted" and at 99% an error message.
How can we do this in the system.
Do revert
RegardsHi,
As mentioned here, there is no budget management for cost centres, but you can do the following:
a) define statistical I/O with a link to a true cost centre
b) define budget for these I/O according to your requirements
c) define a validation which will stop posting to the relevant cost centres without I/O
Thus, you will get a control over your cost centres.
Regards,
Eli -
G/L Account determination for cost center
Hi,
When we issue the material with movement type 201 or when we do 202, we enter the cost center in the MB1A, then ref. to this cost center how to determine which G/L account is updated, and if we want to know how much is total goods issue is done for a particular cost center which g/l account to be check.
regards,
zafarsystem check the setting in Define Account Grouping for Movement Types
for movement type
201 what is account modifier its VBR
then it check material number and takes valuation class
then it goes to OBYC and check the gl account under GBB
and looks for Gl account for VBR and valuation clases
and pick up the Gl accoun
hope its clear now
and in case of PO
the logic for gl account determination for account assigned po is as below
for cost center u give K
for this K it goes in Maintain Account Assignment Categories and check what is Acct modification it is generally VBR
then it check if u have given material number and takes valuation class and if material ordered is with out material code then valuation class is blank
then it goes to OBYC and check the gl account under GBB
and looks for Gl account for VBR and valuation clases in case on manteria number
or VBr and Blank entry for valuation class
and pick up the Gl account
Hope now its clear
Maybe you are looking for
-
How can I delete photos from my iPad without affecting my journal in iPhoto?
Hi, I have recently been on a long trip creating a journal in iPhoto as I go, uploading many gb of photos using the camera connection kit. I love the way I can view my journal and tap on photos to see them in full screen and maximum quality. I am now
-
I will be traveling in China with my iPad2 and want to use hotel wireless. It requires a sign-in with user name/password. Can I use an Airport Express for this purpose? How do I set it up for that? I have an old Express (pre-2007); can I use it or d
-
How do I get iPhoto from the app store for my OSX Lion 10.7.5 Macbook??
Hello, I have an older macbook which I was able to install OSX Lion 10.7.5 onto, and it works good with this setup. However I wanted to have the iPhoto app from the App Store installed on my Macbook, but looking in the App Store it says that iPhoto i
-
Invoice idoc cannot be processed
Hi All, i hope you can help me out with this. The problem is that we cannot process an invoice idoc because the condition type is not allowed on the idoc. Can you please explain to me why idoc do not allow this condition type? This only happening in
-
SES integration with Oracle WMS
1) How do we dispatch the events from the SES database (SDR, EDGE SCHEMA) To the EBS WMS Module, such that when an item in an order is scanned using RFID, the Order should automatically be ship confirmed in WMS? Regards Balaji [email protected]