Check point in fund management for budget and creation of po

I have a Budget for a perticular expenses say Rs 100000/-, so the po should not be created for more than Rs 100000/- as per the budget. but the po is been created for more than the budget amount.
pls. let me know where the check point has to be maintain.
Thanks
Santosh Visave
Moderator: Please, search SDN

Hi ,
First of all as a primary step you can do the following :
1. is the commitment item getting derived in the PO.
2. Is the commitment item non statistical ( means you have not put the tick on statistical commitment item ) in FMCIA .
3. check the budget amount via the report FMRP_RW_BUDCON for the budget amount and released amount .
Hope this would help .
Cheers ,
Dewang

Similar Messages

  • Funds Management with Budget Control System (BCS) submodule

    hi sap gurus
    can any one give me the details for the
    Funds Management with Budget Control System (BCS) submodule   
    if any material pls send to my mail id : [email protected]
    its very urgent pls
    thank you

    Hi,
    Try executing FMAVCREINIT report and check if the problem persists.
    Regards,
    Eli

  • Schedule manager for budget cycle

    Hi,
    I have a requirement from client where they want to configure a schedule manager for budget cycle and link it to a transaction code.So whenever a user logs into the schedule manager he gets an update as to when he has to update the budget.This is more of calendar( timelines guidence) requirement.They do not want the system to update the budget cycle automatically.
    The idea is to ensure that user has the authority to maintain budget cycle at the same time the timelines are maintained by system.
    Can this be done through schedule manager ? if yes can some hep me with config.
    If no, then is there any other alternative to this.
    Thanks in  advance for your help.
    Regards
    Pranay

    Hi ,
    Please note that I want the Schedule manager for following activites.
    GL PLANNING: GP12N, GLPLUP, GP12NA
    DBC planning via KE13N, KEPM, KE30
    STRUCTURE COST PLANNING VIA KP06.
    The client wants to maintain the calendar for this planning processes and track their status as well.
    Please let me know as to how can this be configured.
    Regards
    Pranay

  • Trying to load a Dreamweaver CS5 extension called Image Show Pro to mac operating system 10.9.2. Trial version worked fine, but when I try to load full version, Adobe Extension Manager crashes.  I have downloaded new Extension Manager for CS5. and still c

    Trying to load a Dreamweaver CS5 extension called Image Show Pro to mac operating system 10.9.2. Trial version worked fine, but when I try to load full version, Adobe Extension Manager crashes.  I have downloaded new Extension Manager for CS5. and still crashes. Anybody else experience this? email:[email protected]

    Hi bigd_bud,
    Can you see if the solutions in this post help?
    Re: Adobe Extension Manager crashes on mac 10.8
    Thanks,
    Preran

  • Can u tell me any predefined BAPI for change and creation of Material

    Hi,
        Can anybody tell me  predefined BAPI for change and creation of Materialmasterand Pricing?
    Thanks & regards,
    Gopianne.

    you can use the BAPI to BAPI_MATERIAL_SAVEDATA create as well as to change material master.
    When changing material master data, you need enter only the material
    number.
    In the header data, you must select at least one view for which data is
    to be created. Depending on the view selected, you must maintain other
    required parameters. If you do not enter values for all of the required
    parameters, the method is ended with an error message.
    The corresponding fields in the tables (such as CLIENTDATA) must first
    be supplied with data by the calling program. An indicator must also be
    set for each of these fields so that the data is written to the database
    by the method. This requires the calling program to supply the
    corresponding field with the indicator in a checkbox table (for example,
    CLIENTDATAX). Checkbox tables exist for tables that do not contain any
    language-dependent texts (MAKT, MLTX), International Article Numbers
    (MEAN), or tax classifications (MLAN). Several data records for a
    material can be created in these tables.
    regards
    vivek
    reward points if it helps

  • I want to use my Time Capsule as a central 'hub/hard-drive' in order to keep all my working files in one place. I then plan to use my laptops/desktops as peripheral devices for editing and creation of these files. Is it possible? Create a personal cloud?

    I want to use my Time Capsule as a central 'hub/hard-drive' in order to keep all my working files in one place. I then plan to use my laptops/desktops as peripheral devices for editing and creation of these files. Is it possible? To create a personal cloud?
    Can someone advise as to whether i can do the following:
                                Future Internet connection -------------------TIME CAPSULE (containing all files) -------------- Backed up on the WD 2T Hard-drive I have
                                      (not connected yet)                                         I                                                          (*connected to timecapsule physically)
                                                                                                            I
                    I                                         I                                                I                                                              I                                                I
          Macbook Pro                             iMac                                       HP (PC)                                             OLD Macbook Pro                         iPhone
    (used for remote working)       (Used for home working)     (used for heavy CAD and rendering)    (not being used for anything at the moment)        (& iPods)
    I am looking to have all my files in one place as i am hopelessly disorganised. I know the online clouds are a good solution (used Dropbox at work and uni for 3 years) however i am wanting to create my own 'dropbox/icloud' at home. So whenever i get back home with my laptop, any work i have been working on whilst out that day is updated to the timecapsule, and then ultimately as i turn on the other devices, they update to those newer versions of the files. Please tell me that the 3TB time capsule i have can do this, otherwise it feels rather overpriced as a wireless storage device?
    Another note (to those in the know) If i am to be working on large files (REVIT/SOLIDWORKS/KEYSHOT/CREO/AUTOCAD) - is the timecapsule connection good enough to support editing and updating these files?
    I know i may be asking a question that many have before, but as a bit of a technical novice I wanted a clear-cut answer to my specific circumstances. Your help is greatly appreciated.
    (*can i use this WD hard-drive that is connected to the Time Capsule as a back up? so that the time machine back-ups/any back ups are also backed up onto this one? can the WD be a backup for the TC?)
    Kind Regards
    Joe

    The diagram was supposed to look more like this......
    Internet ---------TIME CAPSULE(containing all files) --------WD 2T Harddrive
                                                I
         I                           I                          I                            I                                   I
    Macbook Pro         iMac                 HP (PC)            OLD Macbook Pro           iPhone
    Sorry!
    Regards
    Joe

  • Exclude budget update in Funds Management for particular FI document type

    HI FM gurus !!
    We have an issue in FM .We do the service entry for Transporters for the whole years charges at one time . ( for some reason it cant be done for the month) So we have to pass the FI entry for the Prepaid Expenses. But when we do this entry in FI  corresponding effect goes in FM and the Budget for this committment item gets INCREASED. THIS WE DONT WANT since this temperorily available budget may get used for other things. This is the background .
    so All we would like to do is to prevent the budget update in FM for this Prepaid entry. How can we do this ? is there any config or BADI ?
    PLEASE ADVICE

    Its been resolved..
    For budget not being available for consumption after being posted through FMBB th issue was in my AVC profile. and for the second part where budget was not consumed after invoice being posted through FB60 the issue was in my fiscal yeas variant year shift. the posting was taking plane in the wrong fiscal yeas hence consuming budget for that particular fiscal year and not of the year i intended to post to. Thank you so much fpr approving my query
    Regards,

  • Funds Management for all transaction

    Hi
    I have activated funds management. I want this only for checking budget for non-assigned PO.
    But it will ask comittment items for all business transactions like FI / MM / SD,etc
    What settings needs to be done for the same so that other transactions are affected. Please help

    Hi,
    Bear in mind that the minimum account assignment that must be provided in case of FM, is funds center and commitment item, this is required for postings, budget, avc and so on.
    Funds center can be a combination of cost centers that you should have filled in your PO.
    To be able to derive automatically funds center from the cost center, use FMDERIVE transaction creating  a derivation rule that connects cost centers to the funds centers.
    The FM derivation tool can only be used for deriving Funds Management account assignments. Additional information is
    available in note 881202.
    I suggest you to read also the documentation available in the following menu:
    SPRO -> Public Sector Management -> Funds Management Government -> Prepare Funds Management Installation
    It is only a text document but with links and with all the necessary instructions to start FM in your company.
    I hope that this helps you.
    Best Regards,
    Vanessa.

  • In Funds Management-Assigned budget is more than the release

    Hi Experts,
    We have Funds Management active and in few cases the assigned budget is more than the released budget for a funds center and commitment item. We observed that the material consumption (stores requests) entries get posted even when there is no released budget.
    Can you suggest ways to control the posing of material consumption entries when there is no released budget in Funds management.
    With Regards
    ACR.Ruben

    hi
    Try there is a USER _EXIT for Material consulmption for the Movement type 261 GI to Production .
    Extension SAPLFMFA, component EXIT_SAPLFMFA_001
    through this you can stop the Material consumption additions to fundcenter through the commit ment item.
    Thanks & Regards
    Mala K Reddy

  • Funds Management for PO

    Hi
    I want to do commitment (for budget check) for PO. This commitment i require for PO only. Not for other transactions like FB60, F-53, etc.
    But its asking me commitment item for each and every item. Let me know how to bring it only for PO and de-activate for other transactions.
    Let me know the link or steps

    make this commitment item is required entry for all filed status groups, assign this commitment item in fs00, to make commitment items automatically, you can do it in FIPOS, after that create a derivation strategy for 'GL and Commit.item, do the required settings for activity groups and assign it in available control. if your budget is limited to few gl accounts, make all other items as statistical. but what ever you do, you have to create at least one derivation rule to do budget after activating FM.
    regards,

  • Funds Management-Transfer Budget

    Hi!
    We implemented Funds management-budget Control System.
    Following process is not working properly.
    when we transfer budget from one  fund center to another fund center, the system is not checking the budget available on sender fund center.
    budget is being transferred from sender fund center even that fund center have zero budget to another receiver fund center.
    plz guide me, if we missed any configuration or any other?
    Thanks

    Dear Muralidhar !
    In Budget Control System, there is no need of budget profile. Budget profile are maintained in Former budgeting.
    Any How, I checked the budget profile. it is fine.
    Thanks
    Message was edited by:
            MSiddique

  • Funds Management - Release Budget

    Hi,
    Regarding Funds Management:-
    I have activated Funds Management and configured completely.
    But I want a Budget Type which i need to release the Budget on Monthly Basis.
    Will the Standard allow this ?
    If so what is the Configuration Needed and What is the User Part in It ?
    regards
    N.Kumar

    I believe, I answered that in your previous thread.

  • Funds Management - Current budget Vs Consumable budget

    Hello -
    I have posted a budget entry document with budget category 'payment' and posted few commitments and actuals , when I run the Budget Consumption oveview report - budget amounts  are shown under the column ' Current Budget' not under consumable budget and nothing is shouwn under consumed budget as well. Where as I have posted an entry document for budget category ' Commitment' earlier, thats being shown under consumable budget and all budget consumptions are recorded. Both the entries are made with one document type which is assigned to 'automatics release'. I am using update profile 102 - PB , inv, posting date. What is that i am missing ?
    Thanks in advance
    CHris

    Hi Chris,
    I suppose that you are using BCS, if not, kindly let me know.
    Can you please inform your EA-PS package? In addtion, can you please confirm if the report that you are using is transaction FMRP_RW_BUDCON? If you are using this one the value columns of this report are the following:
    Consumable Budget =  from availability control
    Consumed Budget =  from availability control
    Available Budget = Consumable Budget - Consumed Budget
    Current Budget = from budgeting
    Commitments and Actuals
    Therefore you can check each field with the table values.
    For AVC fields (that check the value from availability control) you should check the value from the report in table FMAVCT.
    Current Budget from your budget transaction or reports.
    Commitment and Actuals from table FMIT.
    Let me know your comments about these information. I hope it helps you.
    Best Regards,
    Vanessa Barth.

  • Funds Management for PO with reference to a PR

    Hello,
    I'd like to check the system's behavior on the next issue:
    Letu2019s say I have a funds reservation for $18,000,000.00 and I create a purchase requisition with one item with reference to this funds reservation for an amount of $17,000,000.00.
    Then I create a purchase order with one item, making reference to the purchase requisition for $10,000,000.00.
    At the moment I have availability in the reserve of $1,000,000.00 and a commitment (also pre-commitment) of $17,000,000.00 ($10,000,000.00 from the purchase order and $7,000,000 from the requisition).
    If I later (after I had saved) try to update the purchase order item increasing its net value, for example in more than one million (exceding the reserve's available amount), the systems generates an availability control error indicating that I donu2019t have enough funds in the funds reservation (which its true).
    My question concerning the systemu2019s behavior is, doesnu2019t it recognize the fact that the PO is referenced to a PR, therefore being able to consider also the remaining amount of the PR as a funds source for the increased value of the PO item (instead of only the reservation available amount)?
    If I make a new PO with reference to the same position of the PR, I can do it for the whole available value (funds reservation + PR), and the system makes the necessary reduction for the PR at funds level.
    However, as I mentioned before, if I increase the value of the PO item it only recognizes the available amount in the funds reservation as a funds source to AVC check.
    Iu2019d like to know if this is a right behavior and if there's a way to make the system use the amount commited in the Purchase requisition, to be able to increase the item in the PO, making the necessary reduction in the PR and funds reservation (BUT RECONIZING BOTH FUNDS RESERVATION AND PURCHASE REQUISITION AS POSSIBLE SOURCE OF FUNDS FOR THE INCREASE, INSTEAD OF ONLY THE AMOUNT AVAILABLE IN THE RESERVATION, DURING THE AVC CHECK).
    In the activity "Define Activation of Availability Control" is specified "Active with usual check logic".
    Kind regards,
    Edited by: Víctor Domínguez on Mar 9, 2009 7:20 PM
    Edited by: Víctor Domínguez on Mar 9, 2009 7:21 PM
    Edited by: Víctor Domínguez on Mar 9, 2009 7:21 PM

    Thanks for your answer, but I'm using type C (Active with usual check logic) for the fiscal year in question (2009).
    But the system is only checking the available amount in the funds reservation when I increase the value in the purchase orde item, it doesn't try to decrease the value of the purchase requisition, which still has a $7,000,000 commitment, in order to be able to use that as funds to be able to increase the value in the PO. That's what I don't know if it's a normal system behavior or it could be something in the customizing to help me solve this issue (bear in mind that I'm updating the purchase order, because when I create the PO there's no problem or even creating a new one with reference to the PR, it let's me use not only the amount available in the funds reservation, but also the commitment in the PR as available funds for my PO).
    I wouldn't want to decrease the value of the purchase requisition to be able to increase the availability in the funds reservation (so I could increase the PO item value), because it has been released and approved. And I can't either fix the "closed" indicator on the requisition to release commitment, because the remaining value of the requisition could be used to create other purchase orders.
    Edited by: Víctor Domínguez on Mar 9, 2009 10:04 PM

  • Check GL(Bank) account balance for banks and stop payment if sufficient

    Hi Experts
    Requirement is to check GL account balance for bank account and check whether enough balance exists for effecting payments. In the absence of insufficient bank balance, payment should not be effected. Balance needs to be check either manual cheque payment or automatic payment program.
    Please provide best solution.
    Regards

    Hi,
    Requirement is very clear,
    this is critical requirement, normal situation nobady update values in Available amount every day in FBZP
    If you want to impliment this reqirement, discuss with technical person (ABAPer) to impliment BADI functionality.
    As a functional consultant you have to tell the technical person,
    1 - Create Z internal maintanance table. for house bank & Company code againest available amount.
    2 - During payment (FB01,F-53,F-48,F-58 & F110) system need to Compare table Vendor open Item (BSIK) and Z teble balances, if Z table balance is less than table (BSIK) value system stop the process else system process for payment.
    for better clarification discuss with technical expert.
    Regards,
    Viswa