CM01 / capacity planning / generate graphic automatically ?

Hello experts,
we have implemented the capacity planning for our production.
The processes are working fine.
But I've got the following requirement to solve:
Is it possible to generate the graphical views from CM01 every day automatically in background jobs and send them to printers or email-accounts (nice to have)?
Thanks a lot for your answers.
Regards
Markus

Dear,
Yes it is possible to generate the graphical views from CM01go toGraphic--standard overview.
But automatic in background it is not possible.
Hope clear to you.
Regards,
R.Brahmankar

Similar Messages

  • Customize CM01 Capacity Planning

    Hello,
    I am new in PP module and have no PP functional to discuss. I need help about CM01.
    Can I customize T-Code CM01, start from the selection-screen ?
    Any exit so that after i push download button, it will save to my ztable and print a smartforms instead download it to excel ?
    Thank you very much for your kindly help.
    Erick

    Dear,
    Yes it is possible to generate the graphical views from CM01go toGraphic--standard overview.
    But automatic in background it is not possible.
    Hope clear to you.
    Regards,
    R.Brahmankar

  • How is Reqmts calculated in CM01( capacity Planning: Detailed Capacity List.

    I believe Reqmts is the difference between the 'To be confirmed' and 'confirmed hours'.
    If let suppose standard hours for a part to be manufacture is 100hrs and we have already work 52 hrs off 100hrs then if i go and look up this order in CM01 then the Reqmts should say 48hr (100-52).
    But when I am going to CM01 it still saying 100 hours which is not correct. Can some one help me solve this issue

    Hi Pankaj,
    Once confirmation is done, hours must be deducted and it should show the remaining hours in CM01 based on the below settings in work center/resource in Capacity tab.
    Control: Calc. of Remaining Req./Duration After Confirmation
    Controls how, after partial confirmations the
    Remaining capacity requirement and
    Remaining duration in a rescheduling is calculated.
    The following are possible:
         Formula-Related: The remaining requirement / remaining duration of a
         partially confirmed operation is determined when the formula defined in the work
         center is evaluated. It is the remaining quantity and not the operation quantity
         that is taken into account after the confirmation.
         Completely for Partial Confirmation: The remaining requirement /
         remaining duration is reduced completely when there is a partial
         confirmation.
         Completely for Final Confirmation: The remaining requirement /
         remaining duration is reduced completely when there is a final confirmation.
         There is no adjustment through partial confirmations.
         Proportional to Service: The remaining requirement / remaining
         duration of a partially-confirmed operation is reduced proportional to the
         service that is assigned to the relevant capacity segment in the work center in
         your record type group.
    Dependencies
    When there is a final confirmation the remaining capacity requirement of the
    operation is always completely reduced.
    Please check your settings accordingly.
    Thanks.

  • Operations are not getting despatched in capacity planning table

    Hi Experts,
    I am using capacity planning table (Graphical) to level the capacities and sequence the process orders. The start date of my orders are very well in future and sufficient capacities also is available in resources. But when I go to CM25 and select one order and click on despatch, system is not despatching it. This is the case for almost all the overall profiles.
    The surprising factor is, this function was working fine earlier without any issues. I havent done any changes in configs which will affect capacity planning.
    What can be the reason for this? Any thoughts please?.
    One more thing. Is there any option to avoid the capacity planning step if Iam using R/3 and manage it by some other way?
    Appreciate your earlier reply
    Thanks & Regards
    Prathib

    Most likely you didnt define the rowsource key properly. Please look under <install>/errors folder for any file there.
    Also, please read the documentation. There is information there about how to troubleshoot a loading problem. Please always read the documentation and we would appreciate feedback on the documentation.
    http://download.oracle.com/docs/cd/E17236_01/epm.1112/iop_user_guide/frameset.htm?launch.html

  • Plant Maintenance: Capacity planning CM01/ CM07

    Hi
    In capacity planning CM01, the standard sap shows all the maintenance orders which have system status created. But we would like to look at onlly the released pm order in the standard overview list and detailed capacity list. Please let me know if there is way we can configure it.
    Thanks

    Hi Nayan202,
    You could configure desired "selection set" T.code "CSM1" and then assign this to appropriate "Selection Profile" under initial set.
    Hope this helps.
    Shahnawaz

  • Maintenance Work Center : Capacity Planning CM01

    Hello Gurus,
    We are using T-code CM01 to determine the Requirements / RemAvailCap of the Maintenance Work Orders in a given Maintenance Work Center.
    After executing CM01, the detail capacity list contains Not Scheduled orders( CRTD )and  capacity of these not Released orders also taking into consider.
    How to restrict CM01 Order selection based on the work order System status or User status ?
    I found below discussions on SCN but couldn't get precise answere.
    Plant Maintenance: Capacity planning CM01/ CM07
    Configuring profiles in CAPACITY PLANNING (CM07)
    Please help.
    Thanks in Advance
    Ashok M

    There are a few ways:
    Create a new status profile via BS42 and assign the REL status only (see image 1). Then in the CM01 display screen, use menu path: Planning->Selection->Order and enter the status profile created above (see image 2)
    Create a new selection combination via OAP0. In the CM01 display screen, use menu path: Planning->Selection->Combination and enter the selection combination created above (see image 3)
    The above settings can then be defaulted via the various capacity planning profiles.

  • Maintaining work center list in Capacity Planning: Selection List in CM01

    Hi,
    Where can find the config route in SPRO for maintain work center into the Capacity Planning: Selection List in CM01?
    Thanks a lot!
    Min

    Mandy,
    Couple of combinations you should check,
    1. First try to identify "Selection Profile" which is used. In "CM01" go to menu Planning->Profiles->Selection Profile.
    2.Check the defination of this profile using transaction "OPA2". Here you need to look for "Work center Set" which is assigned.
    3. Now look at the defination of the workcenter set using transaction "CMS3", here is were we define as how the list is to be fetched.
    Hope this helps....Reward your points and close the thread if so,
    Regards,
    Prasobh

  • Capacity planning CM01 not displaying PM Order capacity

    Hi experts,
    I have created one order with the work center and defined operations...... but i am not able to see the CAPACITY REQUIREMENTS in the capacity planning (CM01)............
    Please suggest me what should  i do for this.............

    Hi Maheswaran,
    Thanks for the information , in configuration "Capacity Requirement Planning" have been maintained and now i am getting the CAPACITY REQUIREMENTS and CAP. LOAD also .........................but there is one problem i.e. when i am seeing the capacity planning (CM01) , IT IS NOT SHOWING THE VALUES ON THE DAY WHICH IS WORKING actually according to factory calendar FRIDAY and SATURDAY are holiday, but it is showing the value on SATURDAY and not showing the value on THURSDAY that is today........Please see the screen shot also......
    what should i do.......

  • Machine capacity planning and efficency

    Dear Guru,
    I have number of machines and i want there individual capacity and efficency can we see that by any report or any tcode to see all capacity of machine.What is capacity leveling.
    Is thee any configuration for capacity planning.
    Thanks in advance

    Hi, the following configuration steps involved in the capacity planning: SPRO --> IMG --> PRODUCTION --> CAPACITY REQUIREMENT PLANNING Capacity Requirements Planning: 1) Define time units 2) Define Capacity Category 3) Set up Capacity Planner. 4) Define parameters 5) Define Standard value key. 6) Define Move time matrix. 7) Define Setup matrix. 8) Define Control Key. 9) Define Shift Sequence. 10) Define Key for performance efficiency rate. 11) Define Formula parameters. 12) Specify Scheduling type. 13) Set up Production scheduler group 14) Select Automatically. 15) Define Scheduling parameters for Production orders 16) Define Scheduling parameters for networks. 17) Define Reduction Strategies planned/ production orders. 18) Define Reduction Strategies for network/process orders. 19) Define Control Profile. 20) Define Selection profile. 21) Define time profile. 22) Define Evaluation profile. 23) Define Strategy Profile. You can follow these above configuration steps in capacity planning Yes you need to active your all work center for the finite scheduling at the bottom of capacity view. Use all standard SAP configurations, Capacity Leveling Profile. Define time profile in OPD2. Define the strategy profile in OPDB Define the Overall profiles in OPD0. Then only you need to to active your all work center for the finite scheduling at the bottom of capacity view in work center.(CR02) Then run MRP with scheduling- 2 Lead time scheduling and capacity planning.(MD02) You will get your capacity requirement in CM01, or CM25/CM21. In rem you can use MF50. -
    OR refer below steps Capacity Planning Evaluation: Use this procedure to Evaluate the Capacity of a Work Center (Resource). The same transaction will be used for finding out the Capacity Overload on the Work Center Select Logistics -> Production -> Capacity Planning -> Evaluation ->Work Center View ->Load and go to the Capacity Planning Selection screen (CM01) Through capacity planning : Standard overview :System will show week wise overload in Red Color. If there is no overload then system will show in the normal color. Date wise Capacity can be overviewed. If there were capacity overload, system would show with Red Color indication and Percentage overload can be viewed. Through capacity planning : Standard overview: Details: Date wise, planned process order wise capacity requirement. Through capacity planning : Standard overview: Graphical: Yellow Color indicates capacity lying un-used. Red Color Bars is the indication for Capacity Overload and Blue Color Bars indicate for Capacity available Use this procedure to Level / Schedule the Capacity of a Work Center Capacity Planning - Levelling/Scheduling: Select Logistics ->Production->Capacity Planning -> Levelling -> Work Center View and go to the Planning Table (Graphical) screen (CM21) Key Points u2022 This would be used for Shop floor production scheduling u2022 Capacity Scheduling is mandatory for correct results of Master Production Schedule and Material Requirement Planning For settings: Define formulas for resources: (OP54) IMG -> Production Planning For Process Industries -> Master Data ->Resource->Capacity requirements planning->Formulas for resources->Define formulas for resources. For formula parameters for Resource/workcentre:(OP51) IMG -> Production Planning For Process Industries -> Master Data ->Resource->Capacity requirements planning->Formulas for resources->Define formula parameters for resources-> Standard Value u2013 Define Parameters (OP7B) IMG -> Production Planning For Process Industries -> Master Data ->Resource-> General Data -> Standard value -> Define Parameters Define standard value key(OP19) IMG -> Production Planning For Process Industries -> Master Data ->Resource-> General Data -> Standard value -> Define Standard Value First configure the below settings in the capacity Planning. 1) Define time units Path : SPRO ->Production-> Capacity Requirements planning ->Master Data-> Define Time units (OPCF) 2) Define Capacity Category Path : SPRO ->Production ->Capacity Requirements planning->Master Data-> Capacity Data ->Define Capacity category. 3) Set up Capacity Planner. Path : SPRO ->Production ->Capacity Requirements planning -> Master Data->Capacity Data -> Set up Capacity Planner 4) Define parameters Path : SPRO->Production ->Capacity Requirements planning -> Master Data ->Work Center Data->Standard value ->Define Parameters (OP7B) 5)Define Move time matrix. Path : SPRO -> Production-> Capacity Requirements Planning -> Master Data-> Work Center Data -> Define Move time Matrix (OPCN) 6) Define Setup matrix. Path : SPRO -> Production ->Capacity Requirements Planning -> Master Data -> Routing data -> Define Setup Time Matrix 7)Define Control Key. Path : SPRO-> Production-> Capacity Requirements Planning -> Master Data ->Routing data -> Define Control Key(OPCG) 8) Define Shift Sequence. Path : SPRO -> Production-> Capacity Requirements Planning -> Operations -> Define Shift Sequences (OP4A) 9) Define Key for performance efficiency rate. Path : SPRO-> Production -> Capacity Requirements Planning -> Operations-> Available Capacity-> Define Key Performance Efficiency Rate (OPDU) 11) Specify Scheduling type. Path : SPRO ->Production ->Capacity requirements Planning->Operations->Scheduling ->Specify Scheduling Type (OPJN) 12) Set up Production scheduler group. Path : SPRO ->Production->Capacity requirements Planning -> Operations -> Scheduling -> Set up Production Scheduler Group (OPCH) 13) Select Automatically. Path : SPRO -> Production -> Capacity Requirements Planning ->Operations->Scheduling ->Task List Type-> Select Automatically (OPJF) 14) Define Scheduling parameters for Production orders. Path : SPRO -> Production ->Capacity Requirements Planning-> Operations->Scheduling -> Define Scheduling Parameters for Production orders (OPU3) 15) Define Reduction Strategies planned/ production orders. Spro-> Production->Capacity reqirements planning->operations->Scheduling->Reduction strategies->Define reduction strategies planned-/production order 16) Define Reduction Strategies for network/process orders. Spro-> Production->Capacity reqirements planning->operations->Scheduling->Reduction strategies-> Define reduction strategies for network/process order 17) Define Selection profile. Spro->Production->Capacity requirements Planning->Evalution->Profiles-> Define selection profiles Hope clear to u. Regards Alok

  • Setting needed for Capacity Planning.

    Hi PP Gurus,
    I want to know what setting we have to do for capacity planning.
    what I know is:
    1. W/C should be set for finite scheduling.
    2. In scheduling parameters for process order tick "Generate capacity Requirement".
    This both setting are made in my scenario, but it is'nt loading the work center fot that week.
    Any other setting nedded?
    Thanks, in advance.

    Dear ,
    You need to have following set up at basic level frist before you perfomr the capacity requirement planning  :
    1.In OPKP-Define Production Scheduling parameter -Availability check -Confirm Capacity and also Finite Scheduling chekc box ticked .
    2.In OPU3/OPU5-Define Scheduling Parametesr -you should mark the following
    1.Automatic Scheduling check box should be marked
    2.Scheduling Log check box should be marked -generate in case there is a scheduling error due to capacity over load .
    3.Scedulinga and Generate Capcity should be ticked .
    3.In OPJK Imaintain check capacity with SAPSFCG013 overall profile and set indicator -1 -Release Order -by user decision if capacity is insufficient
    4.Work Center - Define the capcity planner group,activate checkbox Relevant for Finite sceduling,on the capacity header define the shift timings,break timings and unit of measure,no of individual capaity, enter formula for scheduling in capacity view.
    5.Routing - enter the values for the standard values. Use control key with scheduling and CRP activated .
    6. OPD0 and have the following set up  : Overall profile : SFAPSFC015 --Inside the over all profile I have the following set up
    1.Selection Profile -SAPSFCS013 SFC: Order view, standard overview
    2.Control Profile : SAP___C004 : Gen Capacity Availability Check for 1.5 months
    3.Time Profile : SAP___Z006 : Gen Capacity Availability Check for 1.5 months
    4.Evalution Profile : SAPSFCA013 : Gen Capacity Availability Chek =3.0D
    5.Strategy Profile : SAPSFCVER1-Gen Capacity availability Check
    6.Period Profile : SAP___P001 -Weekly period
    7.List Profile : SAPSFCI001-Production Planing
    Check all of them in place .Then you can go ahead with Capacity Req.Planning -Evalution and Leveling -CM21/CM22/CM05/CM07  etc.
    Refere the below theread for farther reference :
    Capacity problem in production order
    capacity planning
    Hope this will be useful .
    Regards
    JH

  • Constraint capacity planning for Un-Routed items in ASCP

    Hi All,
    Is there any possibility to create constraint capacity planning for items which do not have routings in ASCP?
    I tried by setting Bill of Resources (BOR) in Aggregatin tabbed region in Plan option. But i could not get an expected result. Kindly help me out in this.
    regards,
    Murlai R
    Edited by: user10942922 on Mar 27, 2009 9:30 AM

    Dear ,
    To answer the question for Capacity requirement planning on sales order I would say that MRP does  only materials planning based on demand and reciept  but never does Capacity Requirement Plannig .MRP generates Planned Order  and susequently , production order can be genreted and farther you can carry out capacity requirement planning based on the work cente available capacity , requirement and load for those MTO orders .
    But there are SAP business suit like APO-SNP APO PPDS which carriy our details scheduleing and caapcity check based on the demand situation : Sales Order ,Independent Order  and does capcaity vaialbality chek for those demands while planning .
    Now , here is the answer of your question :
    1) Can Capacities are Scheduled as per priority given in SO automatically. : Not possible  through  SAP MRP but in APO-PPDS, APO-SNP-CTM , Herustic model .
    2) Can revised availability dates will be reflected in SO. : It can be reflected as per the ATP chekc , Replishmenet Lead  Time and re-scheduling horizon maintained in OPPQ-Carry all overall plant parametres.
    3) Which reports will be useful for understanding consolidated availability date of material for given sales order/s. : You can check through MD04/MD05 or in sales order -Availaibility check -Schedule Line -Availaibility date .
    Hope your are clear about the requirememt .
    Regards
    JH
    Edited by: Jiaul Haque on Jun 5, 2010 1:59 PM
    Edited by: Jiaul Haque on Jun 5, 2010 1:59 PM

  • Repetitive manufacturing - CM01 Capacity Requirement

    Hi All,
    I configured repetitive manufacturing process with lead time scheduling.
    Conf. at OPU5 is set as below
    Rate.plng horzn  - 999
    SelID:rate plng -  02
    Scheduling u2013 X (selected)
    Generate Capacity reqs. u2013 X (selected)
    Scheduling level  - Via Rate based scheduling
    Adjust dates u2013 Do not adjust basic dates, dep reqmt to operation dates 
    For capacity scheduling u2013 Always basic dates, dep. Reqmt to operation dates 
    I run MRP (MD02) with option - Lead Time Scheduling and Capacity Planning
    I could see required capacity is calculated at tab u201CProduction Ratesu201D & also in menu Planned order >> Goto >>Capacity leveling.
    we are unable to view Capacity requirement in CM01 transaction & in planning table MF50.
    Regards

    Hi,
    Select the correct profile in CM01.  Menu->Planning->Profiles
    Thanks

  • Capacity planning issue

    Dear all
    My customer has two actor types: project managers PM and 7 work center managers WCM, with strong antithesis: PM looks at project quality and productivity; WCM looks at his resources capacity planning.
    Every PM defines wbs basic start / finish dates with appropriate, large and comfortable time lag. Into this time lag, during the capacity planning, the WCMs can set definitive activity start / finish dates, by their needs (and with user status communicates to PM the happened choice) .
    The generic project is composed of more wbs elements and 7 networks: all activities of a generic network are assigned to only one work center. Every lowest wbs element has only one activity.
    Every PM plans dates (large and comfortable) and efforts on network activities; schedules via bottom up and copies wbs scheduled dates on basic dates. After, CP sets the top down scenario and save the project. In IMG, network profile, the type of checking during top-down time scheduling is u201CEu201D:  exit with error (transaction code OPUU).
    Every WCM using transaction code CM01 doesnu2019t see the WBS constrains. So doesnu2019t know the wbs dates range. Moreover the WCMs donu2019t like a dashboard like CM01 because it is not user friendly. They prefer a graphical dashboard. 
    My personal idea to resolve this issue is use transaction code CM21 or similar with the display of wbs time lag. Is it possible?
    Is there anyone who could help me, please? I am also interested in other technical solution.
    Thanks in advance.
    Salvo50

    Venky,
    1) Sales order when enter in the system can perform the capacity availability check ?
    Not in ECC/R/3.  However, in APO this is possible.
    2) The delivery dates & confirmation in the sales order is on what basis?
    Depends on how you have configured your availability check.  There are a number of possibilities.  Many companies confirm MTS orders to Total Replenishment Lead time in the Material master.  Other companies leave the orders unconfirmed until Planning has created supply elements (production orders).  
    As far as the delivery date is concerned, it can also start with the confirmed material availability date as calculated by ATP, and then additionally schedule in the warehouse pick-pack-load times, and route transit time (the time it takes to move the shipment from your loading dock to the customer's location.
    In 'Assemble to order' (a special version of Make To Order) it is possible to confirm to the scheduling time of the supporting Finished goods production orders combined with the availability of the components of the FG production order.
    In R/3, some companies will confirm the MTS sales order to a date that is farther into the future than the actual estimated process time including capacity backlog.  Then, they run MRP to create planned orders.  Then, they run Capacity leveling.  Then, they run BackOrderProcessing (rescheduling) of the sales orders to re-confirm to the planned or production orders that have been capacity leveled.  In this way, Sales orders are indirectly confirmed to capacity.
    Consult with your local SD and PP ATP experts to discover the options available.
    Rgds,
    DB49
    Edited by: Dogboy49 on Jan 6, 2010 10:37 PM

  • Capacity Planning vs. Capacity Leveling

    My production facility is looking to divide up our shop floor by work centers.  There are about 20 individual work centers that are composed of 10 people each.  Each material we make is divided up into 3 operations which go through 3 separate work centers.  Each operation has a corresponding work center that it goes through.
    Right now we are unsure which program suits our needs better, Capacity Planning or Capacity Leveling.
    Our goal is to measure each individual work center (not the workers that make up the work center).  Each work center has a specific goal involving the number of materials they can produce, whether or not they reached that goal and by how many.
    In a nutshell, we want to be able to measure how long it took each work center to reach their individual goals by the materials they produce.
    This is all about measuring the individual work centers and how efficient they are.  Our goal is to be able to utilize this data within SAP.
    What is the difference between Capacity Planning and Capacity Leveling, and which would better suit our goals?
    Our production facility is not very complicated and we're looking for something simple and basic within SAP to accomplish these goals.
    All help is appreciated.  What would be your recommendations for this type of situation?

    HI
    Capacity evaluation
    In the capacity evaluation, available capacity and capacity requirements are determined and compared with each other in lists or graphics.
    Capacity leveling
    The objectives of capacity leveling are:
    Optimal capacity commitment
    Selection of appropriate resources
    In most applications, you can use two types of planning table (graphical and tabular versions) to display the capacity situation and to carry out capacity leveling.
    In some applications such as Repetitive Manufacturing (PP-REM) or Sales and Operations Planning (PP-SOP), there are application-specific planning tables for capacity leveling.
    T codes for Capacity Planning
    Work Center view - Capacity Evaluation
    CM01 - Load
    CM02 - Orders
    CM03 - Pool
    CM04 - Backlog
    CM05 - Overload
    Capacity Leveling
    CM21,CM22, CM27,CM28.
    Hope it will help u
    Regards
    Anupam Sharma

  • Planned order splitting during capacity planning

    Hello,
    anybody plese help me during the capacity planning in T.code.CM31 i want to split a planned order and want to assign alternative sequence. how can i do this and the capacity should be reschedule automatically to my requirement date. i am using backward scheduling.
    plese suggest immediately
    Thanks and reagards
    Bhakta

    Dear Bhakta
    MRP does not perfom any Capacity Requirement Planning .While  you are executing MRP with Lead Time Scheduling , MRP proposes Planned Order Dates based on the Routing Operation Timing not based on the Work Centre available Capacity because in SAP Std R/3 we did not have scope to check the finite scheduling and capacity requirement chek .MRP assume that Work Centre has infinite available capacity .
    In MRP run , it will give you Detail scheduling of the Operation in Planned Order -Detail Scheduling tab  and copied the routing , BOM as master data .When you convert that Planned order to Production order , it will copy the Routing details based on the Order Type denpendt Parameters -OPL8-Routing -Alternative sequnce  and Automatic selection -3 option
    Thats why we have Capacity Requirement Planning  for Detail Capcity check and production order scheduling  .
    Note : Earlier to my first  reply , please note that you have option in CM21  enter sequence number  at order level which may applicable to you .CM21-Work Centre -exectute -Select the Order from order pool -Goto Order -Sequence number maintainence
    This number( sequence number operation /order )  that can be assigned to production orders or planned orders at the level of the task list header and is therefore valid for all the operations in an order.
    Hope this is clear .Revert if you nees farther help
    Regards
    JH
    Edited by: Jiaul Haque on Jul 5, 2010 3:32 PM
    Edited by: Jiaul Haque on Jul 5, 2010 4:01 PM

Maybe you are looking for

  • Can't Install SQL Server 2012 in Windows 8.1 Pro

    I have Visual Studio 2010 Ultimate installed on my unit. I tried installing SQL Server 2012 and it failed because I don't have the SP1 for VS2010. I installed SP1 successfully, but now I can't install the SQL Server 2012. Error says: Managed SQL Serv

  • Non-English artist name sorting

    Hello! I just bought my iPod Touch today, and it's my first ever iPod so i'm still getting used to it. I have a question, though, regarding how artists are sorted. I bought my Touch in Japan (finally found a store with stock!), and I would say 90% of

  • Mac Os 10.4.11 and firefox

    MacOsX 10.4.11 my latest version. Guess I will not be able to use firefox as my other software will not go with 10.5 and above. Can not stop the firefox popup from constantly asking me to upgrade. I like firefox, any other solutions?

  • Header data not coming from vendor master when creating SA using BAPI

    Hello, I am creating SA using BAPI_SA_CREATE. I am passing the vendor code and other header related data in the header table of the BAPI. SA is created successfully with all the data that is passed to the BAPI. Now if the payment term and inco terms

  • User tables documentation

    HI can anyone please share the user table documentation. Thanks