   we have a finish material ,which can be manufactured using 3 different work centers.Then I create 3 production versions to link each work center .
PV1   Routing 1(work center1)   BOM 1    production line:work center1
PV2   Routing 1(work center2)   BOM 1    production line:work center2
PV3   Routing 1(work center3)   BOM 1    production line:work center3
   Is it possible to create a batch job to dispatch planned order between work centers in CM40?I am able to manually dispatch planned orders between different work centers in CM22..
   CM40 use the same selection/strategy profile as CM22 and the planned orders are dispatched to other period if current period get overload..But I expect CM40 to dispatch the planned orders to other available work centers..Anyone has any suggestions?
   thanks very much..
Edited by: Monst Yang on Jan 10, 2012 9:59 PM

Hello,
With CM40 also you can dispatch planned orders as like CM22
Please look into the below link for more functions performed with the transaction:
http://help.sap.com/saphelp_46c/helpdata/en/f3/0869a3a6ae11d183d00000e83235ee/content.htm
Hope the information was useful
Regards,

Similar Messages

  • To split an operation quantity in a single production order into different work centers.

    Detailed Process:
       Our client have 17 factories. Inside each factory there are 15-20 Sewing lines (Work Centers). In each line 15-20 machines (individual capacities) are there. The standard manufacturing scenario practiced here is MTO. Merchandisers create sales order and allot it to a particular plant. Now line level planning happens inside the factory. Based on the order delivery date to meet the requirements they split the production order and allot it to several sewing lines (work centers).  In SAP we can have work around solution to partially convert planned order to production order and allot it to particular line. The challenge here is to have same production order number which can be allotted to several sewing lines with a mandatory option to enter the quantity for each sewing line
    We have proposed alternative and multiple routing for converting planned order into number of production orders but the solution was not meeting their requirements.
    Please provide your valuable opinions on this issue.

    Hi,
    Please explore the option of using the concept called Parallel sequence in routing...
    Check the below thread...
    parallel sequence in Routing
    Routing - Parallel Sequence
    Hope this helps
    Thanks
    Kumar

  • Can't dispatch planned order (LA), but can dispatch production order

    Hello,
       I'm new to capacity planning and all of the related configuration screens.  I'm probably missing something simple.  We've configured our work centers and routings.  We've configured our production order types (tcode OPU3, type US01) and planned order types (tcode OPU5, type LA) so that all create capacity requirements and are relevant to 'detailed scheduling'.  Requirements are being generated for production orders and planned orders.  We can see correct setup and production times in the graphical planning table CM21.
       Here's the problem: When we try to dispatch a planned order, nothing happens.  There is no error, but the order is not dispatched.  If we convert the planned order into a production order, accepting all SAP proposed defaults, and then try to dispatch the production order, it works fine.
       What configuration are we missing?  My first thought was to look in OPU5 for order type LA.  In the detailed scheduling section, scheduling horizon is zero (is this Ok?), SelID: Detailed is 01, 'scheduled' and 'generate capacity reqs' are checked.
    Thanks,
    Randy

    Randy ,
    Please analyse the below note related to your issue.Hope this will help you to sort out the problem.I have cheked the configuration area.I hope u are correct .In fact , it may related to your production version if you do automatic dipatch.Please reade the note and come back.
    If an error arises when automatically dispatching planned orders (for example, a capacity overload at a work center) then the system schedules the affected planned orders to another production line.This function is available in both types of planning table. It is of interest for all areas that use planned orders, for example in repetitive manufacturing or in MRP/MPS. It can also be used in production control when later converting planned orders to production orders.
    this function the following conditions must be met:
    The dispatching function Change production version on error must be set in the strategy profile.
    The original work center
    must be entered in the production version of the material as the production line (not necessarily in the current production version).
    can only be assigned to one operation in the routing for this production version
    The alternative work center can only be assigned to one operation in the routing for the alternative production version
    If an error arises the system copies the production version with the version key that is next alphanumerically into the planned order. The planned order is rescheduled with this production version. However, it is not dispatched to the new production line but remains in the pool. In this way you can dispatch the rescheduled planned orders together with other planned orders in the pool to the new production line.
    To give you a better overview and to improve handling you should choose a sort key with which the planned orders in the pool are sorted according to work center and, for example, latest start date. All orders that are to be dispatched to a production line are then placed next to one another in the pool. If an error arises during automatic dispatching to the new line every planned order affected is rescheduled with the next production version
    . If the conditions are not met then the following occurs depending on your settings in the strategy profile:
    Dispatching is terminated
    Dispatching to the same work center is continued and error messages are written to the planning log
    You can only dispatch main operations with this function, but not sub-operations. Operations are always dispatched with the full quantity to the new work center
    Reward point if useful
    Regards
    Jia

  • Dispatch planned orders CM25

    Dear experts,
    Is it possible to dispatch planned orders in the capacity planning board CM25?
    In which profile do I change the settings to make this happen?
    Many thanks,
    Tim
    PS: will award points!

    the following  profiles can be used for viewing capacity over load
    SAPSFCG001     SFC: View work center/capacity (2 graf.)
    SAPSFCG002     SFC: View work cntr./capacity (tabular)
    SAPSFCG003     SFC: View order/capacity      (tabular)
    SAPSFCG004     SFC: View order/capacity     (graphical)
    SAPSFCG005     SFC: View Individual cap.    (graphical)
    SAPSFCG006     SFC: View work cntr/ind.cap.  (tabular)
    SAPSFCG007     SFC: View order/individual cap. (graph.)
    SAPSFCG008     SFC: View order/individual cap. (tabul.)
    SAPSFCG009     SFC: View line               (graphical)
    SAPSFCG010     SFC: View setup optimize     (graphical)
    SAPSFCG011     SFC: View work center/capacity (3 graf.)
    SAPSFCG014     SFC: GANTT view wkcntr/capacity (3 grph)
    SAPSFCG015     SFC: Evaluation, standard overview
    SAPSFCG016     SFC: WC/Capa (2 temp.save graphical)
    SAPSFCG020     SFC: Standard overview in work cntr view
    SAPSFCG021     SFC: Standard overview in order view
    SAPSFCG022     SFC: Standard overview in indiv.cap.view
    SAPSFCG023     SFC: Standard overview + actual cap.rqts
    Usually the following std profiles are used.
    SAPSFCG021     SFC: Standard overview in order view
    SAPSFCG022     SFC: Standard overview in indiv.cap.view
    <b>Dispatch of capacity is carried out in the following transaction</b>
    CM21, CM22
    CM27, CM28
    CM31, CM32

  • BAPI or FM to DISPATCH PLANNED ORDERS

    HI Gurus,
    We have a requirement to automatically dispatch planned orders instead of manually going to CM25/CM21 screen to manually do it.
    Is anybody aware of any BAPIs, FMs or anything to be able to dispatch planned orders.
    I was going to use BDC but the table control has restricted me to do this.
    Thanks for you help.

    Hello Basil,
    I am looking for the same solution, can u plz update if u hav some information how to approch for the requirement.
    Thanks in Advance.
    Adar

  • How to generate SNP planned order with different category

    Our SNP system receives Forecast and Salse Order from DP system.
    and we'd like to generate SNP planned order with different category..for example, 'AI' for Forecast Demand and 'AL' for Sales Order..
    currently, If we run CTM, system generate SNP planned order with the
    same category 'AI'..
    another system(APS) in Our company receives planned order from SNP
    and they want to receive planned order for forecast and planned order for sales order seperately..

    It is not directly achievable however can be done through BADIs and two CTM profile. I am assuming that sales orders are planned ahead of Forecast demands. So have two CTM profiles - one for Sales Orders (regenerative mode) and the other for Forecast Demands (net change mode). You may have to invoke two BADIs in the first run for Sales Orders - one that changes master data by putting a temperory Forecast Horizon in SNP2 tab (BADI /sapapo/ctm_matloc). The other BADI (BADI /sapapo/ctm_orders) changes the ATP category just before saving. in the second run though you just need to run the latter BADI by saving it in the ATP category required. BADIs can be invoked based on CTM profiles used.

  • Tcode CM25:BDC or function module to dispatch planned orders

    Hi all,
    Could you please suggest a BAPI/FM for CM25 -dispatching the planned orders.
    While i try BDC, it requires the line selection for dispatch,which does not get captured in recording.
    Can anyone throw light on this or suggest any alternative.
    thanks
    kiran
    Moderator message - Cross post locked
    Edited by: Rob Burbank on Oct 23, 2009 11:28 AM

    reposting it

  • BDC for CM25 tcode or a function module to dispatch planned orders

    Please suggest a way for BDC of CM25 tcode as the selection of planned/process order in the tcode is not captured in recording.
    or provide FM/BAPI for dispatch of planned orders.
    Moderator message - Cross post locked
    Edited by: Rob Burbank on Oct 23, 2009 11:27 AM

    reposting it

  • Different Work Centers

    Hi,
         I have 5 work centers for producing same final goods.  I want to produce FG against production order at user desired work center. for ex work center 3.  Where i have to assign these all work centers and option of choosing in production order?

    Hi,
    Pl. check in your production version, whether you get the result as<b> task list exists & BOM exists</b> after clicking the check tab for all production version, check the validity dates & lot size also.
    Also production versions should not be locked in c223.
    Also check in opl8 if you have maintained manual selection of production version for the respective <b>plant & order type</b>.If it is maintained, the system will pop-up a screen to select prod version during order creation.
    Regards,
    Senthilkumar

  • Function with production/planned orders of a work center or capacity

    Hi,
    does anybody know if a function exists which we could use in a tailor made report, which will list all production and planned orders for a given work center or capacity ?  The aim should be to create a report which is more or less equal to the capacity evaluation overviews in CM01-CM07, but then in ALV and with customer specific fields in it.
    Many thanks for any valuable feedback !
    Kristof Wylin.

    Will be done in another way.  Orders will be collected via KBED.

  • Single planned order for different sales order of same material

    hi frnds
    my client want that if there is two  or more sales order of same material in a specific period than he require single planned order during mrp run for that material or when if he enter same material in two different line in single sales order than mrp doesnt considered it line item aand produce single planned order for both sales order
    please help me out its very urgent
    thanks

    Hi,
    In Mrp 3 view set the availability check as 01 and in Mrp 1 view
    Keep the lot size as periodic lot size and try the same.
    Thanks,
    S.Nandhakumar

  • BOM for planned order in different plant.

    Hi,
    we have 2 plants: A and B. 
    Plant A creates a sales order for a configurable material (MAT_1). There is a BOM for this material. All the materials in this BOM should be sent from B to A.  B should purchase or produce these materials and then send them to A.
    Materials produced by plant B are also configurable materials and their components depend on the characteristics chosen for MAT_1.
    The thing is that the system generates a BOM for the sales order (and this bill is fixed throught transaction CU51). We would like to fix the complete BOM, not only in its first level, but also the components of the configurable materials through this transaction.
    The problem is that when we plan the materials in plant B in order to produce them, the system generate the planned orders but no material components are determined.
    How should I proceed?
    Thanks in advance,
    Luis

    Hi Luis,
    The header item A also manufactured in plant B and sent it to Plant A or the final product assembly is happening at plant A only ?
    The material A = B + C+ D , the components B, D is procured and C is produced at plant -B and send it to plant -A
    Material A & C is a configurable material , is it my understanding is correct ?
    In the super BOM according to the object dependcy assigned for the each component, BOM qty will get exploded accordingly
    and you can configure the special procurement key & assigned it to material master  to pass the requirement
    Rgds,
    R.Gopi

  • Creation Of A Single Purchase Requisition From Different Planned Orders

    Hi,
         After MRP run i get different Planned Orders for different raw materials . My requirement is that can i combine all the Planned Orders for diiferent materials into a single Purchase Requisition.This is a urgent requirement.
    If useful i will award points.
    Regards
    Jimmy

    Hi,
    it is not possible to combine with planned orders for different materials into single PR but differet PR can combine into a single Purchase Order.
    pls let me know any clarification.
    thanks
    mohan
    Message was edited by:
            Mohan Ramalingam

  • Planned order and Production order Not appearing cm21 transaction code

    Hi
    I have created a planned order for a material through MRP run
    As soon as the planned order is created its available in the cm21 transaction code . But once i dispatch the planed orders , the planned orders can be seen only as a BAR in the upper right side of the screen .
    1.Can any body please let me know how i can view the details of this dispatched planned orders in the same way when the planned orders were un dispatched ?
    2.If i create a production order manually or convert a planned order to production order i cannot see these production orders in cm21 neither on cm22 , can any body please let me know what i have to do so that i can view these production orders as well in cm21 or cm22 transaction code.
    Thanks and regards
    Sankar N

    Hi Pradeep
    I have checked the generate capacity requirements and it worked ,Thank you
    Presently i can view only the work centre details in cm21 screen extreme left , how can i see the details of the orders that are dispatched at this work centre ,in the similar way we see in the order pool, bottom left of cm21 screen .
    Thanks
    Sankar

  • Capacity Leveling in CM25 by Sequence Number in Planned Order

    Hello Gurus,
    I am having an issue with dispatching planned orders using tabular form.  We have to use the tabular form in order to be able to have our program select all planned orders.
    I have been testing and testing this trying to get it to work.  We have sequence numbers defined for our planned orders in the PLAF-SEQNR field.  When entering CM25, we are wanting to dispatch all of our planned orders at once and have them dispatched in the correct order by sequence number.  I have the Strategy Profile defined for Finite Scheduling, Plan. direction forwards, and no closing of gaps.  and I have my Dispatch Sequence layout key defined to only use the Sequence Number in the Planned Orders.
    We need to use the tabular form so we can select all planned orders.  I set up the requirements grouping to only include planned orders that are not yet dispatched.
    When I use the graphical form instead of tabular and I manually highlight all of the planned orders and dispatch then they are all in the correct order with all of the gaps are closed...which is what i want.
    However, I need to be able to do this using the tablular form.  No matter how I try to set up the strategy profile, it doesnt seem to work using tabular form.  They are dispatched according to start date with gaps in between the orders.
    Any help is greatly appreciated.
    I also have the following defined in Strategy Profile for Dispatching Control:
    Sort operation to be dispatched
    Consider operation sequence in the order
    Midpoint scheduling
    Thank you.
    Edited by: Kevin Gorman on Jan 14, 2009 8:19 PM
    Edited by: Kevin Gorman on Jan 15, 2009 3:26 AM

    Hi Vishal,
    I hope the below link will provide you need full information:
    http://help.sap.com/saphelp_470/helpdata/en/8a/a5a7674adc11d189740000e8322d00/content.htm
    Hope it clears your doubt.
    Regards,
    Madhu.G