Confirmation date - Strategy grp 50

Hi, can anyone advise why when we use strategy grp 50 'Planning without final assembly' for MTO scenario, the confirmed date/lead time in the SO is based on the inhouse production time only?
When i use strategy group 20 'Make-to-order production', the confirmed date/lead time in SO is based on inhouse production time + GR processing time.
Can i know why the difference in th delivery scheduling?
Thanks
Peter

Hi PP,
The following links may help to clarify your doubt:
[Strategy type|http://help.sap.com/saphelp_46c/helpdata/en/e0/71bb169c9f11d191920000e8a5f6e6/frameset.htm]
[Availability check|http://help.sap.com/saphelp_46c/helpdata/en/cf/70124adf2d11d1b55e0000e82de178/content.htm]
Regards,
Abhee.

Similar Messages

  • Confirmed date in sales order influenced by planned order dates

    Hi,
    My requirement is that the after the MRP is carried out and planned order is generated, the changes in the dates of the planned order, when carried out, shall accordingly influence the confirmed date of the sales order line item when the availability check is carried out in the sales order.
    Say, the sales order has confirmed a line item for 25.05.2009. Once the MRP is carried out and planned order is generated and owing to unavailablility of a component, the planned order date (finish date) is manually re-scheduled to say 28.05.2009. My requirement is that the sales order confirmed date shall accordingly be re-scheduled when the availability check is carried out.
    Additional Info : Strategy Group - 20,
                           Make-to Order scenario is employed,
                           Standard Item category TAN,
                           Requirement Class - 040.
    Is this possible in standard SAP? If not, please suggest any custom developments that may be required. Looking forward for helpful replies.
    Do revert back if more info required.
    Regards,
    Anil Kumar

    Hi Anil,
    As Suggested in Above reply to your question.
    If Materail component was not available and due to that you had to reshedule the planned order date manually, that definately will affect the material availability date, but i think if material availability will be run once again in Sales Order it will determine the new material availability date, and i dont think there is any need to carry out any enhancement.
    Guru's Please correct me if I am wrong.
    regards,
    Paresh

  • Open Purchase Orders Report with Confirmation Dates

    Hi Friends,
    I have searched a lot for the following need and I have found nothing. I was wondering if there ia any report that I can show the scheduled delivery dates from a Purchase order. I have seen in ME2L that by placing EINT in scope of list I can see the schedule lines. However, if there is a new delivery date due to supplier confirmation that have been placed in PO with the indicator AB this is not appeared. At the same time if there is a partial quantity that has already been delivered then it does not appear as well. So, I need a report with all the scheduled delivery line plus the open quantity.
    Many Thanks in advance,
    Ioannis

    It is very strange. Because what I see is that in this report the confirmation date is not appeared although the schedule line is appeared. Then If I go to change the confirmation date in PO for second time then it is appeared. I have no idea why this is happening

  • Conversion of Sales Orders with Original ATP Confirmation Dates/ Quantities

    Hi
    Please suggest best practice to maintain ATP confirmation dates/ quantities during sales order conversion. We have committed schedule lines in a legacy SAP system. Now we want to maintain the exact same dates/ quantities when loading these dates into the new SAP system.
    We will not have supply (inventory/ orders) loaded at the time sales orders are loaded.
    Thanks
    Rishi Menon

    Hi
    I will suggest to turn-offthe Transfer of Requirement & Availability Check from the Schedule Line (VOV6). And then make your BDC to upload the Sales Order of Legacy System in SAP.
    While creating the BDC recdord the consider the Schedule line date and quantity.
    Regards,
    Amitesh Anand

  • PO Confirmation Date (OA) & Inbound Delivery Date  Report

    Dear All,
    Please let me know SAP Standard Report
    PO Confirmation Date (OA) & Inbound Delivery Date  Report
    Regards
    Amey

    Hi,
    I guess ME2A will give u unconfirmed orders that require a confirmation, but have not yet been confirmed according to the dates configured for your monitoring period. First, ensure that you have such an order
    Also, ensure that your confirmation control (OMGZ) has BOTH a value in Monitoring period AND Reference date.
    Pls chk note for more information.    https://service.sap.com/sap/support/notes/500502
    BR,
    Krishna

  • Material Confirmation date in future though the material is in stock

    Dear Gurus,
    Please tell me why the system is giving the material confirmation date in future though the matl is  available in stock.
    System creating two schedule lines one for 15/10 (15 oct) and the second one with the confirmation of quantity on 22/11 (22 Nov) as I have enough stock than the required for this order. In MRP1 view of same  matl Master of same material delivery planning time is 28 days. and in MRP3 view the Replenishment lead time is 20 days.  please tell me what date system considering to shift  the confirmation date in future. the factory calender has Sat-sunday off.
    please tell me the possible reasons for confirmation date change.
    regards,
    Sandesh

    Hi ,
    Please check the  value at MM03-> Sales: General plant Tab ->Availability Check is '02'.
    u201802u2019 will consider all the u2018Individual Requirementsu2019 done before and during the creation of Sales order for the combination of respective Material & Plant.
    Even though Material stock will be visible for you at MMBe for respective plant double click on the Quantity, it will show you multiple Row with one of it will be " On Order Stock" these are the other orders for which Quantity is already confirmed but respective PGI is not yet done.
    The next schedule line date always generated based on the Factory calendar (based on Holidays/Weekly Offs if any).
    AT MD04 Tcode, based on the selection made at Material master for Availability Check you could see all the requirements related to Goods Issue Sales Orders , STO & Production Orders for Goods receipts.
    Hope this will solve your query.
    With Best Regards,
    RB.

  • Availability Check : Confirmed Date in Sales Order.

    Hello Gurus,
    I have an issue with the availability check.
    Scenario :
    Customer has created an order for quantity 800 on 26th of Feb and accordingly when created the order go confirmed for 17th of March.
    The specific quanity(batch) of 800 was released from Quality to unrestricted on 27th of Feb.
    And Now that the stock is in unrestrictd the customer wants to deliver this material before 29th of Feb as against the 17th of March confirmed date.
    When we try to re run the availability check, since there are other open orders and deliveries against the material system proposes a new confirmed date alltogether which is still further ahead of 17th.
    Can some body advice me as to how do i ensure that the particular quantity can be sold before 29th.
    I have also tried running Backorder processing and Rescheduling which failed, It might also be because i might have not run them properly as i am new to the concept of backorder processing and rescheduling.
    Please guide me to correct this step wise.
    Thanks.

    please try as below:
    Back order processing is a functionality in SAP where you can change the committments and over-ride the blockage of stocks marked against sales documents/deliveries. For e.g. you receive an order from a very important customer for material "A" but the entire quantity of A is committed to another customer "B" via earlier sales orders and this is where BACK ORDER processing helps you to change the committment and shift stock due for B to A. This is the benefit of this funtionality.
    OMIH - Checking rule for updating backorders
    OPJL - Define new checking rule
    OPJJ - Define scope of check
    V_RA - Backorder Processing
    Data selection:-
    Sold-to-party Customer code Mandatory
    Sales Organization Mandatory
    Distribution Channel Mandatory
    Division Mandatory
    Changed confirmed quantity :-
    Tick the material you want to changed and click the Back order button Confirmed quantity that still can be changed are highlighted.
    V.15 - Backorder List
    Sales Organization Mandatory
    Distribution Channel Mandatory
    Division Mandatory

  • Delivery date to be replaced by Confirmation date automatically.

    Hi All MM gurus,,
    I want to do a setting in the Purchase order in such a way that if there is inbound delivery created or say buyer created a confirmation manually in the PO.
    The confirmation tab delivery date should replace the delivery date in the Delivery schedule tab automatically.
    The buyer should not go and change the dates in both the places.
    Is there any standard setting for this or else what all configuration needs to be done.
    Thanks  in advance
    Sagar

    Hi,
    Thanks for the reply.
    No this issue is not MRP revalant,
    When the confimation comes from vendor , we change the confirmation tab as well as the  delivery date in the line item and We send the PO back to vendor again with the new delivery date.
    Now here the buyer has to change the dates twice.
    Is there a std setting by which we can get once the confirmation date is changed it will change the delivery date automatically.
    Thanks again
    Sagar007

  • Purchase order Confirmation data from SRM to MM

    Hi,
    I am trying to send Purchase order Confirmation data from SRM to MM via PI. In SRM portal i am able to see that the data has been send successfully. But i am not able to receive any data in PI nor iam able to any messages going from  SRM in SXMB_MONI.
    Please help me.
    Thanks & Regards
    Kasturika Phukan

    Hi,
      In SRM check in sxmb_moni is there any queue is blocked.
      If not then,
      Check your proxy settings.Select Go To and check connection Test.
      Go to sm59 and check H type RFC destination is maintained.
      Go to sxmb_adm check the Global setting value,
      Application system,dest://RFC destination is maintained.
      In XI,
      Go to SLD.
      Check Technical system (client with logical system) maintained.
      Check Business System maintained with role of application system,Related integration engine
      maintained.
    Regards,
    Prakasu.M

  • Schedule line confirmation date for 3rd party sales( non stock item)

    Hi ,
    While creating an sales order i have a stock  item and 4 non stock items . All the non stok items are similar to 3rd party sales as they are services . While created the sales order for the no stock item the confirmed schedule date is given as 12 days in the future or in one case after month .
    Can  someone please help me in understanding how the dates are being calculated . I havent created any PO for the non stock items.
    I would like the confirmed date to be picked as the system date.

    Hi,
    There can be multiple reasons for this.
    You have not mentioned the material type. Anyhow, first check Material Master 
    Purchasing view> GR Processing Time field
    Sales / general Plant > Set up time and processing time field
    If MRP views are maintained
    In MRP2 View > Scheduling.
    In case you do not want availability check to be carried out
    Untick Availbility check and TOR check boxes in VOV6 for the schedule lines determined for these materials.
    Hope this helps.
    Regards,
    Sharan

  • Confirmation date in vendor evaluation

    Hi Gurus,
                   Can you please let me know the settings to be maintained to get a score for the sub criteria Adherence to confirmation date during vendor evaluations.
    I've already maintained the purchasing org config settings like weighting and point scores for the automatic criteria.
    But when I run a vendor evaluation there is no score coming out for the sub-criteria Adherence to confirmation date.
    I'm using the confirmation control key One day acknowledge and confirmation category AB (Order acknowledge). Please let me know if anything is missing out
    Regards,
    Ashwin.

    Ashwin
    Our company has the same issue, did you find a solution to this problem?
    Thanks
    Brad

  • Report on confirmation date

    Hi,
    Iam looking for a report which shows the PO date , PO delivery date , confirmation date & GR date. I can find a report for all except for the confirmation date. Any update on this is highly appreciated.
    Regards
    Sudhakar

    Hi,
    ME92F (Check SAP Note 500502 - FAQ: Order acknowledgments in the purchasing) for more details.
    ME2A will give you unconfirmed orders that needs to be confirmed.
    Hope this helps!
    Reetesh

  • Vendor Evaluation- Confirmation date Adherence

    Hi Team
    In vendor evolution I am using Delivery as my main criteria and Confirmation date Adherence as sub criteria and assigned weighting 1 .  I have also entered the % and scoring both positive and negative.  But when I am using T code ME61 system is showing scoring 0 for Confirmation date Adherence.
    I have tried all option Confirmation date change in PO and GR still I am not able to see scoring in Tcode ME63. All other criteria is showing correctly, please let me know if I am missing any important step.
    Thanks
    Sanjay

    Sanjay
    Did you solve this issue?  From what I have researched in SAP the confirmation date is only used on a advance ship notice, is this what you are measuring?
    Our company would like to measure against the order confirmation type "AB" not the delivery conformation "LA"
    Any suggestion on using the order confirmation in this measure would be appreciated. Is it possible?
    Thanks
    Brad

  • Vendor evaluation - Confirmation Date

    Dear all,
    am trying to run vendor evaluation for - confirmation date..
    i have create a new confirmation  spro - MM -purchasing - confirmations - define external conf , setup conf  control
    i have included this confirmation in the PO ..delivery date in po item line is 23.06.2014.. delivery date in conf in item details 22.06.2014  GR date is 23.06
    when i run vend evaluation, 4 Adher. to Conf. Date is coming zero ---
    can you pls advise what could be the reason...  is my understanding to this Subcriterion is correct

    Hi,
    As an example its not available, nor tried self. As a common rule - if a main criteria created and sub criteria exists, when you run evaluation for main - excluding a stage of sub is not possible.
    Secondly try transaction code: ME6C
    Help says: Set this indicator if you only want to display those vendors that do not have
    an evaluation for certain main criteria. When you click on Execute, a screen allowing you to choose one or more main criteria appears. The missing evaluations for these criteria are then listed.
    here you can selection option to include/exclude evaluation.

  • Vendor Evaluation - calculating score for subcriteria Confirmation date

    Hi,
    I have configured vedor evaluation with subcriteria Confirmation date with B
    But while maintaing vendor evaluation ,system is not calculating score.
    As per my understanding system compares the date of inbound delivery and actual GR date.
    Can somebody help me on this how system calculates score or what is missing.
    Thanks & Regards,
    Charudatta

    Hi,
    Look at this article, it explains how it is calculated.
    [http://help.sap.com/saphelp_erp60_sp/helpdata/en/8d/b985b0414511d188fc0000e8322f96/frameset.htm]
    Thanks.