Cost centres change

Dear experts,
Our client is changing the existing cost centres and they are uploading new set of costcentres.
Can any one explain me what way it will effect in MM module.
For exapmple If any opened PO's, then what is the impact.
thanks in advance,
Reagards,
Krish

Hi Krish,
It depends on the scenario your client would like to follow.
It will most likely be all the new Shopping carts that will be created hence forth should use the newly craeted cost centers.
In all possibility you should close all the existing open documents to avoid any issues later on.
The cost centers will be blocked for the time being for further usage.
Hope this makes you more clear and helps in understanding the issue. Clarifications are welcome.
Award points for helpful answers.
Rgds,
Teja

Similar Messages

  • Retro payroll processing for org unit cost centre changes

    Dear All,
    We have created some new cost centres and assigned  it to relevant org units . when we run payroll , retro run is happening from the period we changed the cost center and assigned the new cost centre to the org units . please suggest a solution
    regards
    Tressya

    Hi Tressya,
    changes in IT0003 won't affect retro calculation, since you have already created result periods for retro calculation. The payroll programm will detect this and allways will repeat the retro unless you delete those results first.
    Try TR PU01 during correction - then clear Earl.pers. RA date  by PU03 (PA30 won't work here)
    After that you hou'll have to repeat payroll run for effected employees to get new results for actual period only.
    regards
    J.

  • How to change validity period of cost centre or activity type

    Hi
    How to change validity period for an Activity type or Cost centre?
    Can we change the validity period once created?
    regards
    Prakash

    Please note this can be done.
    Go to Edit Cost Center
    Goto Edit, Analysis Period.
    Create a new validity period say today until 3112999
    Change the data you want and save.
    When you go into the CC again it will show two validity periods.

  • Way to mass change cost centre in positions

    Hi Experts
    We have a scenario, where the client i srequired to change the cost centre for multiple positions. Is there any report by which this can be done at one go.
    Regards
    Saurav

    First of all, u r talkin abt positions and cost centers....
    i would like to know ... how u mapped ur Costcenters to Positions ?
    did u maintain relationship thru Org Unit ? realtion ship A011 ?
    Then simple change Cost Center of Units accordingly, this would take hardly 10 min.
    Otherwise, use BDC to change the relationship for each position....from the date of effective.
    Option Move in PPOME is very useful for mass changes... like selecting n number of positions together and moving to required units
    Regards
    ...Sadhu

  • Change the profit centre in the cost centre master after a year

    Hi All,
    Could you'll please let me know whether it was possible to change the profit centre in the cost centre master and if i did what will be the implications.
    Thanks and Regards,
    Vandana

    Refer transaction code OKEG.
    You can maintain master data for cost centers, cost elements, activity    
    types, and business processes with time dependencies. You can make        
    changes at any time for any given time interval. Data storage also takes  
    place with a time reference. In this way, a master data record can have   
    multiple database records storing different information.                                                                               
    The smallest interval is one day. To ensure data consistency, you cannot  
    change each field daily. The timeframes in which you can change a field   
    depend on the field functions, which are fixed by the system and cannot   
    be changed. Master data maintenance includes an automatic check for each  
    field's time-based consistency, resulting in individual time-based        
    maintenance for each field.                                                                               
    The following dependencies are supported:                                                                               
    o   Not time-based                                                                               
    o   Day-based                                                                               
    o   Period-based                                                                               
    o   (Fiscal) year-based                                                                               
    This function provides an overview of the time dependencies of           
    individual master data fields during master data maintenance, along with 
    checks and storage of consistency timeframes. You find this information  
    in the "Time dependency" column.                                                                               
    If you use fields requiring characteristics greater than one day and     
    which are changed for the system lifetime of the object, the system      
    automatically creates a new database record for this processing          
    interval, and changes the time-based validity of existing records. The   
    change is logged in the master data record with the time reference.      
    However, a great number of changes in multiple timeframes will result in 
    a correspondingly great number of data records.                                                                               
    Fields which you can change freely (indicated in the DAY column) can     
    possess different time dependencies only if you mark them additionally   
    as historically relevant. This activates the time-based updating for the 
    records.
    Object 1000 has one master data record created with a fiscal year of 12 
    periods and the cost center name AAAAAAAAAA. During master data         
    maintenance, you change the cost center name in period 5 to BBBBBBBBBB. 
    The system reacts with one of two options.                                                                               
    o   "Name" is marked as historically relevant. The existing master data 
         record for periods 1 - 12 must now become three records:            
         1000   01-04   AAAAAAAAAA                                           
         1000   05      BBBBBBBBBB                                           
         1000   06-12   AAAAAAAAAA                                                                               
    o   "Name" is not marked as historically relevant. The existing master  
         data record remains intact, with the name changed for the entire    
         existence of the record:                                            
         1000   01-12   BBBBBBBBBB
    Edited by: Ravi Sankar Venna on May 19, 2009 4:03 PM

  • BAPI for cost centre create/change

    Hi,
    Is there a BAPI for Cost centre create and change?
    Thanks in advance.
    Regards,
    Arun Mohan

    Hi Ravi,
    My system is 4.6B.
    I found BAPI_COSTCENTER_CREATEMULTIPLE,
    but the BAPI for CC change is not present.
    Is there any other BAPI for CC change?
    Arun

  • Cost centre mass changing

    Hi
    I have arount 800 cost centres from 3 different co.codes A,B,C. which are to be changed to co.code D from the beginning of the new year.
    i m trying to do through collective processing but what about profit centres attached to those cost centres.
    there are some postings in it which do not allow me to change the co.code in profit centres . how do i do mass changing for them

    Hi Milind,
    Good evening and greetings,
    Normally from the controlling aspect it is better to clear of the balances lying in the Profit Centres before you do the mass change so that in future there would be no need for reconciliation.  Considering that, you can do a mass change of Profit Centre using KE55 and if you want to change the company code assignment in Profit Center you can use KE56 for changing the same.
    Anyhow if you are going to process this from the new year, then clear off the balances to a dummy profit centre and do the mass change.
    If the answer found useful, please reward points.
    Thanking you
    With kindest regards
    Ramesh Padmanabhan

  • Change Profit Centre in Cost centre

    Hello Experts,
    I have to change profit centre in cost center (postings have been done on cost centre), how can I do ?
    Thanks in advance.
    Regards,
    Catherine

    Hi,
    Once you post transaction to the Cost Center, we can not change Business Area or Profit Center assignment for the same Fiscal Year.
    System will allow changes for the subsequent Fiscal Years though.
    You cannot really reduce the number of Cost Centers. However we can restrict the validity period though. You can delete the Cost Center validity for the dates that do not have transaction with in the same Fiscal year as well.
    Hope this helps
    Regards,
    Som

  • How to change validity from.. to dates in cost centre(production) ?

    Dear All,
    We have created cost centre(production) on current dates ? Due to this,
    We were unable to maintain activity price for work centre.
    Message is telling us to maintain activity price for current fiscal year.
    How to change validity from date in production cost centre(KS02) ?
    Appreciate valuable inputs.
    Jeyakanthan

    Dear ,
    1.Go to Transaction Code KS02 - change cost center and in the next screen go to Menu bar > Edit > Analysis Period.This will pop up another window - in this you can change the analyis period and save it.
    2.Or Use the tcode OKEON from the hierrachy choose the cost center in the basic data tab u will see one button named Validity period.Change the validity there.
    3.You can do it using 'KSH2' transaction.Open the hirarchy and select your cost center. now select the business area and new hirarchy node where you want to move it. and click on 'INSERT AT LOWER LEVEL' to move the cost center from one business area to another.
    Try and check
    regards
    JH

  • Is it possible to change the cost centre assigned to profit centre?

    hi all ,
    We have a requirement to change the old profit centre which was assigned to cost centre , with the new profit centre ... is it possible ? ... is there any problem in doing so ?... what will be the effect of this ? ...
    thank u ... in advance

    Hi,
    u can only change the cost center assigned to profit center before any document posting,
    If even single document is posted or any other postings has done then u cannot change it.
    Regards,
    Pavan.

  • Change to settings on Cost centre master record

    what problems may happen if change the lock indicator settings on cost centre -  currently a flag is in the actual revenues - need to post to this with a cost element set up as 11 revenues (in error) -

    hi
    The locking indicators will works as under
    1. If the locking indicator is on then it will not allow to post revernue. But still this can be posted statistically.
    2. If the indicator is removed then you can post actual values.
    You can change these indicators any time and it will not have any negative impact on old transactions.
    This may help
    Regards
    Shantanu

  • Change cost centres for train crew personnel

    What is the impact if we change train crew personnel cost centre's within a same company code to another cost centre with another business area?
    Edited by: Annelize Meyer on Feb 2, 2009 7:20 AM
    Edited by: Annelize Meyer on Feb 2, 2009 8:10 AM

    The challenge is the following;
    Personnel has been created in a business area "COAL" and linked to payroll area S2. We must move these traincrew personnel to business area "BATX" but payroll area S1.
    1. What is the FI and HR implication?
    2. Do we have to create new posts on HR within BATX? If so, how can we do this programatically?
    3. Can we link the cost centre hierachy to the new BATX cost centre and will we be able to post at month-end to FI?

  • Change the Cost Centre

    Dear Sap Guru,
    My user book  the entry with Cost center but after that he knows  that book wrong Cost Centre. Now how I can change it the cost center only in this entry.
    Regards,
    Ankita

    Hi,
    You have to either reverse the original document and post ot again with right cost centre or make internal posting in CO (KB11N)  between the cost centres. In the first case, you will have the update in FI and CO; in the second only in CO.
    Regards,
    Eli

  • Cost centre Name Change

    Hi Experts,
    i have few cost centres i want to change the name of these cost centres.
    For exp-
    Cost centre name       -  GSMPTA35
    Description                 - GSM FWP
    how can i do it. please advice

    You can use KS02 or OKEON to change the name.
    I hope it is really the name and not the technical name that you want to change, because the technical name can not be changed.

  • Changing cost centre

    hi all, hope not put my question on wrong sub forum,
    i realized this day that my journal is wrong at the cost centre,
    i want to edit or adjust the journal..
    how to do that
    thank you
    Search SDN

    You have two options:-
    (1) Reverse that document and create a new one with correct cost center. (This is recommended to ensure the document tracability.)
    OR
    (2) Create a cost document in KB11N to transfer the cost from wrong cost center to correct cost center.
    Regards,
    SDNer