Hi,
When doing the cost element/activity type planning upload via KP06, can I assign only one characteristic in the element definition level?   Because I want to put in the excel upload layout  the cost elements, cost centers and activity types.  But ECC 6.0 is allowing only one characteristic in the element definition level.  Has anyone encountered this problem?
Thanks and best regards,
Thess

Hello,
This is controlled by planning are in your planning profile. You need to use "Cost ctrs: Cost element/activity inputs" planning area for this purpose.
Hope you are conversant with Integrated excel upload.
To do integrated excel upload of cost center plan data.
IMG ==> Controlling ==> Cost Center Accounting ==> Planning ==> Manual Planning User Defined Layouts - Create your own layout or copy from standard layout and change it.
IMG ==> Controlling ==> Cost Center Accounting ==> Planning ==> Define User Defined Planner Profiles
Copy the SAPALL to ZSAPALL. You cannot change SAPALL as it is standard.
In ZSAPALL planner profile, select proper planning area and enter your layout.
Tick Integrate Excel.
Once the popup for KP06 comes, you need enter the data and save it. It would generate the file name.
With the same file name you need upload the plan data by using KP06.
In KP06
Extras ==> Excel Planning ==> Upload
Select the file as prepared in accordance with format at the time of generating the file name.
Hope this solves your problem.
Please let me know if you need futher help.
Regards,
Ravi

Similar Messages

  • BAPI for  ""Change Cost Element / Activity Input Planning ""

    Hi
    Is there any BAPI for  ""Change Cost Element / Activity Input Planning "" ( TC KP06) as there is BDC for that but is goes through lot of steps . ( TC OKKS, KP04, KP06 )
    So if any one know the BAPI for the same please let me know,  and if possible send me your code also it will be really help full.
    Regards

    o   OBJECT_INDEX - Index uniquely identifying the row and thus the           
        object. The index must be greater than zero and may only appear once     
        in the table. If the index does not exist in INDEXSTRUCTURE, the row     
        is ignored.                                                                               
    o   COSTCENTER    - Cost center that includes the activity.                                                                               
    o   ACTTYPE       - Activity type that includes the activity. You must       
        fill this together with COSTCENTER. You only need it for an activity     
        input that is activity-dependent.                                                                               
    o   CO_BUSPROC - Business process that includes the activity.                                                                               
    o   ORDERID       - Order that includes the activity.                                                                               
    o   WBS_ELEMENT  - WBS element that includes the activity                                                                               
    You may fill one object only,for example COSTCENTER, CO_BUSPROC,             
    ORDERID, or WBS_ELEMENT.                                                     

  • Activity Type Planning, Cost Center Planning

    Hi Friends,
    I am learning SAP Controlling. I have few doubts.
    1. Activity Type planning (or) Activity Dependent Planning (Cost Center +Activity
       type) both are same.
    2. Cost Center Planning (or) Activity Independent Planning (Cost Center + Cost
        Element +Activity type) both are same.
    Thanks,
    Rams.N

    Activity Planning and Cost planning are different. The first in quantity planning, while Cost planning is Dollar Planning.
    While planning cost ($), you can mention, if such cost is activity dependent or not.
    The purpose is to derive an actitivity price. This is derived by dividing, the cost by the activity quantity. If a cost center has more than one activity, then the cost need to be associated with the activity. This is where we require to identify, if a cost is activity dependent or not. When you mark a cost as  an activity dependent, that cost is fully cosidered while deriving the associated activity price.
    The activity independent cost are split amongst activities to derive the price for each activity. This step is done before the activity prices are computed.

  • KSPP error: Plan/SOP order &: Reference to cost center/activity typ

    Dears,
    I need to know how to correct the error: "Plan/SOP order &: Reference to cost center/activity typ" that I received when I run the KSPP.
    Error code kp603.
    Thanks in advance
    KR
    Vincent

    Hi everbody,
    I found that when we have a formula in Resource -> Costing view but no quantity ( zero ) in Standard Value for operations (Master recipe) then we face the error.
    Other tips could be found in sapnote 1770587 and sapnote 380282.
    I hope this help to solve the issue.
    Regards

  • Activity Type Prices upload

    Hi Experts,
    I am uploading the Activity Type planning through LSMW and I recorder the the same in LSMW and when I am doing this it is saying that field BDC08 for Variable price cannot maintained.And when in source fields step I cannot fins any field for this.
    So how to ulpoad the Activity prices ? Is there is any method for doing this in SAP Conrolling ? If it is available give me the steps by steps for this.

    Hi Edukondalu,
    Normally it is not suggested to use LSMW for Planning Data Upload for Cost Element and Activity Planning in Cost Center Accounting.
    There is "Excel Upload" menthod available which standard SAP feature. You will need to create Planner Profile, Planning Layouts etc.
    Pls find the detailed procedure below for Excel Upload for cost element planning...
    CREATE LAYOUT : (Example of cost element planning layout) KP65
    1. Create cost center element planning layout:
    2. To insert new lead column:
    i) Press New Lead column and select the required column. As shown in screen shot below.
    ii) Click Lead column and select name and characteristic (to view both the field name and description).
    iii) Click confirm to save.
    3. For general data selection : click on general data selection button (Filter Symbol).
    The following screen ( Fig C ) appears. Select the fields required and press confirm.
    Then follow previous step to add new lead column.
    4. Save the layout.
    USER DEFINED PLANNER PROFILE: KP34
    1. New Entry: Give profile name and description. Then save the profile.
    2. Select the newly created profile and press General Controlling. Fig E appears. Select the planning area for which layout has been created. (In this case Cost element/activity planning). Select QUDK from selection list (i.e. the basis for distribution of the total cost over each period). Save the planning area.
    3. Select the newly created planning area and press Layout for controlling. Fig F appears. Select the layout to be attached to the planning area and check the integrated box. Save the layout.
    4. Select the newly created layout and press default parameters.
    5. Give the Version, period from and to, year, cost center, activity (if activity dependent), element. Check the form base button and press overview screen.
    6. Save Generic Name of file. (eg. Planning*.txt).
    7. Save file description.
    8. Save excel layout.
    9. Copy the file to another excel sheet and save as planner1.xls. In this file give the plan amounts and save in txt form with same name.
    10. Go to KP06 T/Code.
    11. From Menus select extras - excel planning u2013 Upload.
    12. Give path or file name. Choose the file description and execute. The file will be uploaded in system.
    Hope this will help you...Pls revert back for further assistance...
    Srikanth Munnaluri

  • Master record for cost center/activity type

    Hi all;
    How create a master record between an cost center and activity type?
    Thank you

    Hi
    You can create master data between cost center / activity type.
    You can link the two by planning for activity qty the combination of a cost center / activity type in KP26. Then you do a detailed planning for costs for the cost center / activity type / cost element in KP06.
    I hope it is clear..
    Regards,
    Suraj

  • Delete cost element in KP06 planning

    Dear all,
    I am facing the issue in cost run:
    Our scenario is like below we done cost element planning for cost center activity type cost element combination(kp06) due to mistake user defined the cost element which is not relevant for activity price calculation after that i run the plan price calculation(KSPI) here i found the warning  message  "Cost element is not assigned to cost component structure, if i will ignore this message my cost component view and itemization view won't match. So i deleted the cost element value from KP06 , but when i execute the kspi same message is appeating.
    1) Please advise me how to delete the cost element from kp06 resulting it wont appear in kspi.
    Regards,
    Ravi.

    Hello Ravi,
    I repeatedly used the following programms Ajay might refer to.
    First guess: xx29 might help.
    "Best practice?": I would not call it best practice. At least it is SAP-reports and not
    customer-specific reports.
    I hope it helps.
    With kind regards
    Thomas
    RKPLNC18
    RKPLNC19
    RKPLNC25
    RKPLNC27
    RKPLNC23
    RKPLNC29
    RKPLNC39

  • Activity type planning error

    we want to CO planning for cost center/ activity type labor,but in kP06, it asks for cost element. how can we do planning without cost element
    also
    second error says:Cost center C231000 has none of the activity types used here
    Message no. K8102
    Activity type LABOR not planned on any of the cost centers used here
    Message no. K8103
    when I check activity type setting, it is: activity type category:1, price indicator:1
    how can I change activity type and cost center to allow kp06 posting

    Hello
    You have to enter the plan against the cost element in KP06.
    Check if the activities are assigned to work centers and work centers are mapped to cost centers. Also in the activity master You allow the cost center category in which the cost center C231000 is created. You may enter * in the field CCtr. category.
    Sangram

  • CATS INTEGRATION WITH PP AND PM MODULE ( TO FIND ACTUAL MANPOWER COSTING THROUGH ACTIVITY TYPE)

    Hi Experts,
    We have a scenario like, Client wants to track the actual manpower costing through activity type ( Ex: How much hours an employee worked on a particular work center to produce an “X” product, So that his actual cost should be loaded on that product.
    We have employee ( 1. Staff 2. Worker 3. Contract labor employee and apprentice from third party roll and staff and worker we plan to go with negative time management and for contract labor and apprentice will go with through cats.
    Since we are not going to run the payroll for contract labor employee and apprentice, we just maintaining the employee data as a group ( Ex: Group A,B,C etc.. Each group consists 20 or 30 employees, According to system each group as one employee and according to us each group consists as 20 or 30 employee.
    The Activity type as well cost center will be created by Co module, the same will be assigned in info type 0315, but still i want more input from experts on the same, since i am new to cross application time sheet configuration, could any one help me out to find the actual manpower costing in a better way.
    Regards,
    Prem

    Hi Experts,
    Can any one please reply on the same.
    How to arrive the exact manpower costing through activity type ?..
    Regards,
    Prem

  • KP26 Activity type mass upload

    How to upload details of cost center/activity type for current fiscal year?
    while production confirmation following error came
    *"a master data for cost center/activity type exists only for the year 2010"*
    Thanks&Regards
    selva

    Inform your CO colleague to do the same. It is not a PP activity to upload rates.
    But if you're the CO person & want to know how to do it, then do a search in CO forum, there will be quite many threads on it.

  • Costing varient/Activity types tab

    hello gurus,
                    in costing variant/activity types tab my strategy sequence is 1.plan price for the period and 2.actual price for the period.here my question is from where the system will pickup these prices.please explain this
    thanks
    rihana

    Hi Samaar,
    Based on this configuration, system will read the Planned Price or Actual Price of the Activity Types maintained in the recipe.
    You can see these Planned Prices & Actual Prices of the Activity Types  using T-Code # KSBT
    Regards,
    Pandu

  • Table for cost center / activity type prices

    Can someone give me the table name where cost center/activity type prices are stored?
    Regards,
    Manohar

    hi,
    for cost centers
    table name  =  CSKSZ
    field name =  KOSTL
    Activity prices
    table name = RKPLN
    field name =  TKF
    HOPE IT HELPS
    regards
    sayeed

  • Routings and activity types planning

    hi,
    can any body explain how we will fix values for acitivities like set up time, processing time etc.. in the routings. whether the cost center-activity price planning fixed first or standard values for activities would be fixed first.
    thanks in advance
    Robert

    Rob
      if you have the workcenter with the activities defined in teh costing view it means that you have carried out the price planing for the activities for the Cost center within  a controlling area. after that while creating the operations in routing you can see activities defaulting in operation details.
    So do carryout KP26 first and then go for routing.
    Hope this helps
    SK

  • PS: planned costs by activity type

    Hi experts,
    I have a problem about an activity type.
    I have created an activity type and planned it on a cost center. This activity type is inserted in a work center with standard formala key "SAP003".
    I insert my activity type in an internal processing of WBE and I calculate costs for this internal processing.
    When I see the cost report of internal processing, the system returns this message: "No costs were calculated for the activity".
    Why? Is it correct?
    Thank you
    Nicola

    Hi Ashish Jain,
    I have planned activity type/price with the transaction KP26, but the system doesn't return any value in planned costs of WBE.
    Why?
    Thanks
    Nicola

  • Actual activity price does not exist for cost center / activity type

    Hi,
    We are trying to upload the time sheet related data(number of hours an employee workred on a project) ect from Non SAP to SAP.
    We have used a customized program and have loaded the data from se38.
    All this HR data will be saved in CAT2
    Later we transfer the time related data into SAP FI/CO using CAT7.
    +When  tested  with a couple of employees time sheets, they got uploaded in SE38 proerly and when transfered it through CAT7 it was properly taking the hour*rate is cost and was reflecting in the respective cost element.
    For a few time sheets in SE38 we were getting an error saying that the cost center(100501)/ activity type(EAT001) does not exist for 2010.
    Hence we have taken, FY 2010, the cost centes and activity types in KP26 and have given the planned Activity as 1. No planned cost in KP06.
    We have run the price calculation forr the FY 2010.
    Then we were able to uplaod the time sheets, but when we tried to transfer the data through CAT7, it throws an error saying no activity price exist for cost center 100501/ activity type EAT001. If I ignore the warning an proceed, no amount is being calculated.
    When uploaded employee time sheets before, all the cost were getting claculated and were entering into  the respective cost elements, but now no amounts are being calculated and it is taking Zero.
    When checked the previous years data i.e, 2009 all amounts are fine, in KSII I can see the activity quantity filled with some numbers in 2009, where from are they comming? I have checked KBk6 nothing was mentioned.
    PLease assit
    Regards,
    shilpa

    Hi
    I never used CAT* though, but the error means that you need to maintain a activity price in KBK6 (Actual price)
    Regards
    Ajay M

Maybe you are looking for

  • Regarding CLOB datatype handling in forms6i

    hi everybody, i created a table with two fields 1.sno number datatype 2.pic BLOB datatype. i created a datablock based on the above table.At the same time i placed one button for file open dialog box and i am selecting jpg files and placing that into

  • Sy-ucomm for a button

    Hi Experts, Can anyone please tell me about the sy-ucomm for message button in ME22N transaction and then one more button Repeat Output. My requirement is i have to re send an IDOC when someone changes the PO and press the repeat output. For this i a

  • My document did not convert correctly.  Can I fix it in the PDF version?

    My document did not save as it was originally written.  Can I fix it once it has been changed to a PDF?

  • Error in JDBC

    I have got error message by JVM as follow Connection reset by peer: JVM_recv in socket input stream readThere are no recordsjava.sql.SQLException: Connection reset by peer: JVM_recv in socket input stream readProcess Exit... any body can tell when th

  • ERROR at line N

    If I run the following plsql in sqlplus, /** Comment BEGIN FETCH l_cursor INTO abc ROLLBACK; END; it will report SQL> /****************************************************************************************************************** SQL> /** SQL> /*