Currency issue in Local PO in SRM ( SRM 4.0, Ext. Classic scenario)

Hello SRM community,
       There is contract exist at a Product category level which is created in currency Euro & can be used by both local as well as well global purchasing org. for subsequent PO releases( Call off).
We are using extended classic scenario, SRM 4.0. before explaining the scenario, here is what we have maintain for a vendor in BBPMAININT
Let say..
Vendor(Business Partner)             Purchasing org.                     Currency
100168                                         Global Purchasing org.     Euro
100168               Local Purchasing Org                SEK
Now there are two scenarios in this
Scenario No.1
When Strategic purchaser directly creates any purchase order release for Local purchasing org. with reference to above created contract
& if he chooses Euro as a currency, system throws a warning message as "Currency Euro in Purchase order is different then the PO currency SEK of vendor.
but still he manage to order the PO Euro.
Scenario No.2
If strategic purchaser creates shopping cart for local purchasing org. where S/C currency is Euro & assign above contract as a source of supply.
Local PO gets created but the system swaps the currency in PO automatically to SEK which is nothing but the currency available for Vendor/Pur. Org combination
in BBPMAININT.
Why there is this difference in behaviour.
I mean, when you directly creates a PO release wrt contract, system allows you to select currency other then the one maintain in BBPMAININT for Vendor/PUr.Org combination however if you try to create a SC for Local pur. org  with contract as a valid source of supply then system overrides the SC currency with the currency maintain in the BBPMAININT for  Vendor/PUr.Org combination
We would like to know if there is any way possible by which we can maintain SC currency in PO & should not allow system to
swap it with what is being maintain in Vendor/Pur.Org combination in BBPMAININT.-
is there any Badi available where we can change this behaviour..& if poosible a way of approach to do it through Badi....
Any help is well appreciated with full rewards to valuable suggesation.
Regards
Bharat Morajkar

Hi Bharat,
You can use the BADI <b>BBP_DOC_CHANGE_BADI</b> to make changes to the document, after user entry and before saving the document to the database.
BBP_SC_CHANGE method can be used for changing shopping carts.
Hope this works in your case. Try it and let me know.
Rgds,
Teja

Similar Messages

  • R/3 Backend PO in SRM for Confirmation in Ext. classic scenario

    Hi,
    We are on SRM 4.0, Extended classic scenario
    User created STO(Stock transport order) in backedn R/3(Not in SRM) and is visible in "Confirmation /GR services" in SRM.
    But when user tries to do confirm it the items are not available and confirmation is not possible in SRM.
    Is there anything missing in the system ? Please suggest
    Best regards,
    Sambit

    it should be updated by running standard progarams which updated the status of the corresponding documents in R/3

  • Output(print out) in SRM for backend PO in Classic scenario

    Hello,
    My requirement is to take print out for the backend PO created thru shopping cart in classic scenario.
    i know for extended classic scenario Actions works as in that case PO is created locally and then replicated.
    But in the classic Scenario where the PO is in backend, can we take print out in SRM becasue the detials of that Po is available in SRM to in Fllow up documents in SRM 5.0.
    is there any standard way available to achieve that.
    Thanks
    Robin

    Hi Sarabjeet,
    It does not make sense to print PO from SRM in classic scenario because there is no PO in SRM at all !
    In classic scenario, PO is created only in the backend.
    Only shopping cart is created in SRM.
    Kind regards,
    Yann

  • SRM MM-SUS for Direct Material ( i.e. Ext Classic Scenario)

    Hi Friends,
    We are planning to have the Classic Scenario in SRM 7.0  with  SUS. So it will be SUS-MM scenarion and it supports only for Classic Scenario,
    But when there is a case of Direct Materials [ Manual or through PDP ( Ext Req) ], it is SAP by defaullt setting that , system determine Extended Classic Scenario.
    Now , if SUS-MM supports only to Classic scenario ,then we can collaborate the Orders of Direct Material genereted through Ext Classic Scenario in SUS ?
    Confused over these contrast . Can any one suggest that how to get both one in SUS-MM  ?
    Thank you in advance.

    Hi Alex,
    Thanks for reply.
    It seems here is some confusion. PDP of Dircet Material is standard SRM secarion where we can soure the requieremnets generted in various SAP Module like PS, PM , SD, APO..etc. So We just hav eintenstion to source the requiermnet in Sourcing cockpit to create the PO .
    Okay. For time being , forget the PDP of Direct Material.
    Just take the Direct  Material ( For which we mention inventory or we procure for stock) only.
    By SAP standard / defualt setting  , for Direct  Material , local PO is generted ,althoug we have mentioned Classic Senrion setting for the same . And it is Extended Classic Scenarion. Right!
    At another side , it is SAP standrad that SUS-MM senarion support for only CLASSIC SCENARIO.
    Then , my conern is  how we can send these Local orders for dircet Material to Supplier via SUS ? Wether it is not possible ?

  • GOA + Local Contract distribution to R/3 in Extended Classic Scenario

    Dear SRM Gurus,
    System Information: SRM Server 5.5   EBP5.5
    Technical Scenario: Extended Classic Scenario.
    Q1) We have created a Global Outline Agreement in EBP. We want this to be distributed to R/3.
    But when we click on distribute, it does not get distriduted to R/3 ???  Is there any IDOC to be maintained----wich one ??
    Please guide me as to how can we go ahead with this.
    Best Regards,
    ANIL RAJPAL.

    Hi Anil,
    The IDOC to be maintained is: BLAREL
    For detail information you can visit the links.
    http://help.sap.com/saphelp_srm50/helpdata/en/00/f5c93f4d903b1ce10000000a114084/content.htm
    https://websmp104.sap-ag.de/~sapidb/011000358700002529571998/blarel02_d.htm
    Also you can have look at notes:
    643823
    953269
    671764
    641919
    Pls let me what all configuration you have done for GOA functionality so that I can suggest you something specific.
    Best Regards,
    Amit
    Do reward the points if ans is helpful!!!

  • Use of Purchase info records in SRM SC in Extended Classic scenario

    Hi All,
    We have implemented SRM 7.13 with Extended classic scenario. If we have Purchase info record in SAP ECC for the material, it gets populated in SRM SC in Source of supply Tab but the price of Purchase info record does not get updated in the SC line item.
    Can anyone let me know which configurations is required to fetch the Purchase info record price or we need to have a customization to achieve this.
    Thanks,
    Ankur

    HI Ankur
    when you say the price did not get updated did you check the sequence which is used for price determination ?
    1. User entry
    2. Contracts
    3.  Info record
    If still you think it is an issue please check the report  EBP_GET_BACKEND_PRICES and let me know if your problem gets fixed?
    Regards
    Vinita

  • Extended classic scenario in SRM 7.1

    Hi colleagues,
    we want top use SRM 7.1 with extended classic scenario and we want to create POs in SRM and reflect them in ERP backend. The question is it possible somehow to change those POs aftewards (e.q. add confirmations, transportation costs, etc...) in ERP? Or is there any way to trasnfer POs in hold status from SRM to ERP and then change them in ERP?
    Thanks and regards, Anton

    Hi Anton,
    PO is created a in SRM as local and a copy( copy does not contain the entire PO info, only the useful for the backend) is being sent to R3.
    DO NOT try to search a workaround for modification in the backend..sooner or later you will be incurring in incosisnten data and misalignmentes.
    SRM is the PO golden source.
    Thanks and Regards,
    Abraham

  • PO text transfer to Back-end in case of Extended Classic Scenario in SRM 4.

    Dear experts,
    My system is in SRM 4.0 in Extended Classic Scenario. We use in the PO internal note text and vendor But thses texts are not transfered to Back-end.
    Is it normal?
    Do I need to customize something?
    Can it be achieved by BADi? How then?
    OR is it only possible from SRM 5.0?
    Thanks in advance
    RD

    Yes you can do this. Implement BADI BBP_CREATE_BE_PO_NEW, Refer parameter IS_SC_DOCUMENT>LONGTEXT,  and CS_PO_DOCUMENT>IT_PO_ITEM_TEXT. Map the exact text-id of the R/3.
    Note: if this BADI is not present, use BBP_CREATE_PO_BACK
    Regards, IA

  • SRM & SUS in Classic scenario

    Hello SRM Gurus,
    I would be great if you could give your overview for below my quires.
    I have good idea of SRM with SUS for extended classic scenario.  But how would be the communication between SRM and SUS in Classic scenario. Because the PO will be created in backend.
    Now my question is in Classic scenario,
    What is the use of SUS in classic scenario?
    How the PO will be transfer to SUS system? Does the PO data from SRM or ECC?
    What is the communication data between SRM and SUS?
    Kindly provide me above information and also your thoughts.
    Thanks.
    Regards,
    Magesh.

    Hi Mahesh,
    If you are using SRM7.0 & ECC EHP4 version with classic scenario then you can user configuration gudie "Plan-Driven Procurement with Supplier Integration: Configuration Guide" (Release SRM4.0).
    But following keys points are to be noted for SRM7.0:
    1. "PO" and "service entry confirmation" will be handled using XML messages.
    2. To send PO's using XML messages to SUS from ECC activate the workflow in SWETYPV transaction by falging "Linkage activated" for object BUS2012(CHANGED & CREATED) for workflow ws3800008.
    3. take the help of PI consulatant to enalbed the PI messages to send PO and Serivce confiramtion bewtween SUS and ECC.
    ERP     PurchaseOrderERPRequest_out_V1                          PurchaseOrderERPRequest_In_V1                          SRM
    SRM     PurchaseOrderERPConfirmation_Out_V1     PurchaseOrderERPConfirmation_In_V1                         ERP
    SRM     ServiceAcknowledgementERPCreateRequest_Out     ServiceAcknowledgementERPCreateRequest_In     ERP
    ERP     ServiceAcknowledgementERPConfirmation_Out     ServiceAcknowledgementERPConfirmation_In     SRM
    ERP               ServiceAcknowledgementERPCancellationNotification_Out                                                                                    ServiceAcknowledgementERPCancellationNotification_In     SRM
    With Regards
    Manjunath

  • Currency configuration in classical scenario

    Hi all,
    I am working on a SRM 3.0 in a classical scenario. I checked at IMG (SAPWAS->General Settings->Currencies) that there are lots of customizing that can be done here (currency codes, decimal places, exchange rates, quotation, expiring curencies, etc...).
    I want to know if it is required to set this customizing in a classical scenario or this should be done only in the backend. Also, please inform if there is a minimum config that can be done in EBP.
    Very thanks in advance.
    Renato Lazaro

    Dear Experts,
    Kindly help me to resolve above issue on SRM PCard Deplyoment
    Thanks & Regards,
    Manish

  • Extended Classic Scenario - PO Update issue

    Hello experts.
    We are working with SRM 5 in the extended classic scenario and we have a serious problem in a productive environment for the following case.
    (01) We create a purchase requisition (PR) in R/3 with several items;
    (02) We send PR to the SRM generating a shopping cart;
    (03) The buyer creates a PO for all items from the shopping cart;
    (04) The PO is transmitted to R/3;
    (05) For some cases buyer changes the PO wich is sent back (updated) to R/3;
    So far so good. The problem happens when some item in the request already has GR or Invoice. In those cases when the PO is updated on SRM, its transmission to R/3 does not occur, generating an error log that can be seen in transaction RZ20 of SRM.
    I understand that if any GR or Invoice exists for the item it can no longer be modified, but is it expected that no other item can also be modified from SRM? What is the expected behavior for this case?
    Moreover, even if the GR and Invoice have been canceled, we are still unable to update the PO in R/3 from SRM. Is this a expected behavior? It was our understanding that the PO should be updated if all incoming documents (GR, Invoice, SES ..) were completely canceled.
    We appreciate any help on this matter.
    Thanks and Regards,
    Evandro Miasato

    Hi, Masa,
    Thank you for your advice,
    I set the method U:Print Using Berkeley Protocol, after that
    in  trx. SP01 I have the Error Status on Composite Document -
    Status Incorrect (Reason Unknown).
    Best regards,
    Guzal.

  • JPY Currency issue in SRM 5 Limit Items

    Hi
    We are having an issue JPY Currency issue in SRM Limit Items (550 SP 13).
    Basically the currencies like JPY, KWR where there are no decimals causes value to be multiplied by 100.
    There are lot of notes and threads on JPY currency issues.
    But I have not found one that helps fix SRM Limit Items.
    Let me know if there is a note or thread that talks about it.
    We are on SRM 550 SP 13.
    Thank You
    Nikhil

    see MDM forum

  • Unable to create Local PO's in SRM

    Hi,
    Earlier, we working with Classic and Local scenerio's. Now we activated Extended classic for certain product categories.
    Issue: we unable to create Local PO's - we getting error message that
    1.Account system (SRM) differ than target system (R/3)
    2.Sytem asking us to enter Plant .However, if we enter the plant , getting another error message that material not maintained in the plant (R/3).
    It seems ,eventhough it is Local category system promting as a backend proct category.
    Could you help us?
    Harish

    Hi Harish
    You can create a local PO for local product categorybut that same material group must exist in r/3 system  which you created in SRM.
    there are some instances , for eg.
    001- material group in r/3 same you can create 001 product category in srm .
    but wherever you mentioned product category originated logical system as SR logical system.
    for eg define product category settings source system as Local SRM logical system and target system as r/3 backend system.
    hope you understand.
    Try for product category dont try for product . (only special request.)
    regards
    muthu

  • Parallel currency 2nd local currency issue

    Good morning everyone,
    I am handling and issue wherein I am finding a difference in the FS10N GL line items.
    Background-
    1. Doc currency, 1st local currency and 2nd Local currency are the same i.e USD.
    2. When I see any GL account in FS10N I dont see any issues but for the GR/IR GLs.
    It was seen when F.19 was run while analysing GR/IR clearing accounts.
    I have 3 GLs that I am investifgating-
    GR/IR exp offset oth- P& L type
    GR/IR -analysis adj - Other  -B/S type
    Vendor control -Other - P& L type
    All the above mentioned are GR/IR relevant accounts.
    Need help On?-  Inspite of the Doc currency, 1st local and 2nd local currency being USD; the 2nd local currency shows a different value for some line items.
    Although Doc and 1st local currency are always same.
    Please assist.
    Thanks & regards
    Rajdilip
    9920845568

    Hi Madhu,
    I did not yet close the Defect but had to raise a query with SAP about the same.
    I do not really know the symptoms of your issue yet.
    What I have done is -I got the Business run F.13 for all old uncleared stock for all previous years that do not make sense to be still available uncleared in the system.
    Then get the open items identified by the Business so that we can decide if we can clear the unclearable open items that we encounter after running F.13 and use MR11 this time but with careful selection and approval.
    Once the available open items are in manageable numbers the performance of F.19 will increase.
    Also, you may think about implementing 2 notes after checking if they are already there in your system via transaction SNOTE-
    1058971 and 1233775.
    If you still have queries upon this, do let me know and I shall try to cater better understanding upon the same.
    Thanks & regards
    Dilip Raja

  • Invoice in foreign currency: Different local currencies issue

    Hi there,
    We have two company codes 1000 & 2000 and we have a business requirement that Company Code 1000 needs to make purchases on behalf of company code 2000 using a cost object (cost center 20001234) under company code 2000.
    Company Code 1000 – local currency USD
    Company Code 2000 – local currency CAD and currency of cost center 20001234 is CAD. (We are using ECC 5.0)
    We are running into an issue (Different local currencies USD CAD) when we try to post the vendor invoice in foreign currency. This error happens only when a GR (goods receipt) and IR (invoice receipt) being done on different dates, and the exchange rate changed between these dates.
    Any help / pointers will be appreciated.
    Thanks in advance!

    Hi Ravi,
    I have already configured purchase price variance account but still an error appears: "Inconsistent in FICO document: difference in first local currency".
    Please take note the PO is charge to an asset account and usually any exchange rate difference should be charge to same account which is an asset account right? If the result of the difference is positive the systems allows the difference posting to the asset account but if the difference is a negative value above error appear.
    Please assist me on this issue; any help would be highly appreciated.

Maybe you are looking for

  • Bex Query in ABAP report

    Can i call a BEx query in ABAP report and display in ALV grid. if so please give me the syntax. Thanks Akila.R

  • App update wont update

    When i try and update the apps on my iPad they try and update and then a note comes up to say account not valid for use in german store. I am on the new Zealand store. Cant change store on the ipad so made sure im on the right store on my computer bu

  • Macbook numbers 2.1(436) will not open the project from Numbers APP on iPad 2.1(1129) .  The error is "index.html is missing"

    I updated the numbers APP on my iPad to 2.1(1129) and my Macbook numbers 2.1(436) will not open the project.  The error is "index.html is missing". I think I am having compatibility issues also with my numbers files but the symptom started last week.

  • Printer and airport in the same hub

    This worked 2 days ago- but that was before the ISP put in a new satellite dish and the airport needed to have an IP set manually- now it doesn't work and I'm trying to find a solution in system preferences.. First off the printer is fine- the lights

  • How can I have iTunes quit changing what I put in for my zip code

    My credit card only accepts five numbes. When I put my zip code into iTunes it add the other four. That does not match what my bank has and it tells me that I have to enter my security code. This has been going on for five days. Apple Tech Support ha