Different Delivery Dates in STO's

Hi All,
At present in our system if the delivery dates is different in STO (Stock Transfer Order) it will create different Outbound Deliveries, In Practical Snenario, We are sending the stock from One Warehouse to One Store with different delivery dates,Our question is If We have created multiple STO's from One Warehouse to One Store with different delivery dates It needs to create only one outbound deliveryfor all multiple STO's.
kindly suggest how to create only one outbound deliveries for multiple STO's as We have same Vehicle for carrying the multiple STO's. from Warehouse to Store.
Note :- We are using the T-code VL10Fand VL10B for creating the outbound delivery against the STO'S.
Thanks & Regards,
Murali.M

Hi,
Go to customizing VTLA (copy control for deliveries). Then find at Header level the Source/Target that corresponds to your Replenishment Delivery.
And then go to Header Data transfer routine (I have routine 301 maybe yours is other) and put a Break Point in it. Then in VL10B select two STO's with different dates you would like to have their deliveries COMBINED and process with button "Background". The debugger should stop at your breakpoint.
manually replace LIKP-LFDAT for a common date (for example today) when debugging routine and see what happens.
This should result in a combined delivery with the date you specified in debugger
Best Regards,
Sebastián Ligueros
Alynea-MVC

Similar Messages

  • Combine stock transfer orders with different delivery dates into 1 delivery

    Hello,
    In transaction VL10B, the system normally combines stock transfer orders that have the same ship-to-party and same delivery date (if the combination indicator in the customer master specific to sales and distribution is checked). My business requirement is to combine stock transfer orders that have the same ship-to-party but different delivery dates. Is this possible through standard configuration? Is there a user exit that can allow this?
    At the moment the system is creating different outbound deliveries according to the delivery dates specified in the stock transfer orders.
    Please advice a solution.
    Regards,
    Felipe

    Felipe, please have a look at OSS note 386340, it may help to solve your problem about combining STO items with different delivery dates to one delivery (as I understand the code correction overwrites the delivery dates...).
    Edited by: Csaba Szommer on Jan 21, 2011 5:06 PM

  • Delivery Date in STO ( UB) & PO (NB)

    Hi, I have a question, delivery date in STO (UB documnet type) or PO ( Doc type NB) what it refer? ( item-->delivery date)
    I mean the date on which we are going to receive the goods or the date on which either vendor or supplying plant going to transafer or ship the goods?
    Since we are able to create outbound delivery in STO using VL10b transaction only if the delivery date in PO is greater than or equal to VL10b delivery date.
    Also let me know, how the delivery date will be determined in PO/STO automatically. when i enter the material , plant and qty automatically delivery date is getting determined?

    Hi,
    The delivery date is the date on which we receive goods.The process of delivery date determination is in the moment you enter a material number and hit enter, SAP moves the current date into the delivery date, and depending on planned delivery time of material master it add those days to the current date. If the data entered is sufficient to determine already the info record, then it takes the planned delivery time from there into consideration. Thanking you.

  • Partial Delivery in Sales Order with Different Delivery Dates

    Dear All,
              In Sales Order we need to specify the different delivery dates for the items ( Partial Delivery ).
    Ex: If I add one sales order for 20 qty of an item today.I need  to specify 5 nums to be delivered on immediately
    and next 10 qty i need delivered on after 15 days and rest of the remaining qty delivered on after another 15 days.
    How we configure in SAP B1 Sales Order.
    Please guide me.
    Thanks in advance.
    - Rajesh

    Enable 'Del Date' in Form Settings of the Delivery.
    In the First Row, select the Item, Qty 5 and type Del Date Immediately
    In the Second Row, select the Same Item, Qty 10 and type Del Date after 10 Days
    In the Thrid Row, select the Same Item, Qty 5 and type Del Date after 15 Days

  • Different Delivery Dates

    Hi All,
      I have a sales order for 100 qts. And th required delivery date given in the sales order is 30.05.2008.
    But this order will be delivered partially.
    Means on 30.05.2008 - 50qts, on 05.06.2008 - 40 qts and 08.06.2008 - 10qts to be delivered.
    My client want for these three partial deliveries three different delivery dates should be there in the order. And also my client want the report that for this one order, there are 3 deliveries and for these 3 deliveries 3 delivery dates should be there in report.
    How to configure this?
    Please guide me.
    reward points for helpful answer.
    Regards
    Ashis

    Hi
    Ashis
    Please use the table VBEP-EDATU and check VBEP-WMENG not zero. This way u can consider the field in yr report and u will get the report as per yr requirement.
    VBEP is table where u can see the schedule lines agaisnt sales order.
    If this slove yr problem please mark the forum as Answer with full point to me.
    Thx.

  • Standard PO with different delivery dates

    Hai All,
    Pls. clafiry my below query.
    e.g. my PR Qty may be 30 PC (in one line item)
    I want to create the PO in one line item with different delivery dates.
    Like: 10 PC 15.12.2008
            10 PC 20.12.2008
            10 PC 25.12.2008
    Rams

    Hi,
    In ME22N, on "Delivery Schedule" tab you can set manually on which dates the shipments should come.
    If you want to have the right date for the PO item, you should carry out your settings accordingly to get proper results after MRP run. However, you cannot set MRP (as per my best knowledge) to create several Delivery date for one PR - MRP will create a separate PR for each different date.
    Regards,
    Csaba

  • Combined delivery with different delivery dates:

    Combined delivery with different delivery dates:
    We are experiencing a problem when doing combined delivery from multiple orders of the same ship to party.
    All the requirements are being met (for the order combination) accept the Delivery dates.
    Sometimes an order Qty is confirmed on the 1at of a month , then the second order qty is confirmed on the 15th of the month.  But when we want to make the combined delivery , the delivery dates differ and the user has to go into the individual order ans changes the dates.
    Is there a way to make the combination, the system not taking in account the delivery dates? Because we have huge no. of orders to combine. Please guide.
    Regards,
    Mansur.

    Dear Mansur,
    I think there is no any solution exaclty map with your problem in standard SAP.
    Better you control based on the MRP type, not sure. And also check with availability check and tranfer of requirments.
    Thnx,
    Pratik

  • Users with different delivery dates

    Hi ,
    Two users entering a sales order with same master data of customer, material and quanty are having different delivery date at item level?
    Any reasons?
    Thanks,
    Pramod

    Hello Friend,
    The problem could be stock could be less and the first order would have blocked that stock so for the second order based on Material Availability Date in Sales Document Type, Scheduling in Material Master MRP2 View and Shipping Point Picking and loading time it is giving a different material availability date based on all these parameters.

  • Delivery is pulling items with different delivery dates from sales order

    hi all,
    i have a sales order with two line items with different delivery dates(eg 1st and 21st). material availability date for them is different. when i tried to create the delivery on 1st it is pulling the 2nd item whose delivery date is on 21st.
    where can i control this.
    thanks in advance
    harini

    Hi,
    let us take one example>materials A and B,
    A delivery date is 22.01.2008(maintained in schedule lines in SO)
    B delivery date is 30.01.2008(maintained in schedule lines in SO)
    now i want to deliver material A on 22.01.2008
    by default system will give you only material A in the item line
    material B will not be displaced in the second line item
    now i want to deliver material B on 30.01.2008
    by default system will show me material B in delivery line item
    if in case material A is not delivered then delivery will show you two line items
    i.e., Material A and B
    i think you have understood the difference
    regards,
    US

  • Program to update Delivery dates of STO based on Material availability

    Hi,
    We have requireement in which, we need to material availability check for the materials on daily basis. This is only for Stock Trasnfer orders.
    Suppose there is STO ( Stock Transfer Order) 1 that has been created for material M1 for qty 20. The scheduled delivery date for the material is tomorrow. Now I create another STO 2 today for the same material and same quantity. The scheduled delivery date that was proposed was 7 days from today.
    Some one deletes the STO 1. Now Material M1 with qty 20 is avaiable to use. I then go in the system, open STO 2 in change mode. Select the line item and click on Material availability check. When I do this, the new delivery dates are proposed.
    This is standard sap functionality.
    We have required to do this programmatically. Is there any standard SAP program which will check all the STO's by there creation date and do the material avaibility check automatically and re-set STO dates.
    Regards,
    Shahu

    Instead of all that, you could just use stock transport scheduling agreements.  MRP can update those automatically during its processing.

  • Planned order creation via MRP depends, If we change Delivery date in STO

    Hi,
    Planned order  creation via MRP depends, If we change Delivery date in Stock transfer Order.
    I created STO with delivery date as 31.1.2012 and when i checked MD04, i can see Planned order created on 27.2.2012 with the same above STO quantity .
    Now when i changed the delivery date as 30.1.2012 and runned MD03, and then checkd MD04, planned order disappeared.
    Why Planned order got created when STO delivery date was 31.1.2012 and when I changed the delivery date in PO, planned order disappeared.
    MRP profile details :
    Plnd delivery time   1
    GR processing time   1
    Planning time fence  38
    Tot. repl. lead time 38
    Can you please let me know why system is beaving in this manner?
    Regards
    Utsav

    Hi,
    Normally , MRP runs based upon the requirements.If your STO is created for a date , system checks through the availabiloty check wheather there exists any stock for that date to get deliverred in the supply plant .If there exists for that date the stock , planned order will not be created.If no stock available then a planned order will be created in MRP.
    cHECK the availability check parameters assigned to material master in supply plant.
    Regards,

  • Statistical delivery date on STO

    Hi,
    Can any one tell me the significance of a Statistical Delivery date on an STO. I can understand that we can measure the Vendor performance when it is relavant to PO but I am trying to understand the significance w.r.t. STO.
    Regds

    A STO is notthing else than a PO, it uses the the same maintenance transactions, hence it has the same fields, and some companies even want to evaluate their sister companies (because internal business is often done subordinate to business with  external customers, and may cause a lot trouble )

  • Delivery dates in STO

    Hi All,
               Please let me know how the delivery dates are getting calculated in STO while creating a STO in the shipping tab. What all parameters are considered while calculating the delivery date.
    Regards,
    Ashwin

    Hi,
    During the STO po creation process  system checks the avalability of the material in the supplying plant.in the check it will consider the possible incoming of materias like PO, ORDER etc in the supplying plant abd decides about the possible availability date in the supply plant.
    You would have observed a warning message while PO creation saying that 'material not available or psrtially available etc.
    This date is the base for the delivery by the supplying plant.Based upon this date system calculates when to deliver , transport,pack , etc in the supplying plant.
    please check the availabllity check at OMGN t code.
    Ofcourse system will take the deliverey date as per your wish with a warning message during creation of PO but may not deliverer at VL10G/B if there is no stock.
    Regards,

  • Same deliveries for different delivery dates on Po

    I have a requirement
    If we use standard SAP and have a purchase order with materials that have different planned delivery times, we are going to create multiple deliviers from the PO based upoon the delivery creation date calculation.   Since we want to ship all of these materials on the same delivery ,  we have an issue.
    Is there any workaround for this ? PL help me.
    Thanks.

    Hi,
    If you have a different delivery schedules for a material with the vendor you can go for Scheduling agreement which is good option for this.
    Because in PO if you maintain the delivery schedules in Item detail>Delivery schedule  there is no check for this delivery dates.You can inward all the stock in a single delivery which don't have a control on that dates.
    If you follow the Scheduling agreement then system will not allow you to post the stock unless the delivery date is valid.
    rgds
    Chidanand

  • Delivery date in STO b/w sloc

    Hi All,
    Need your help in understanding the delivery date prposed by SAP in ME21N for document type UB and stock transfer between sloc to sloc with delivery for a plant.
    Current stock in MMBE in issuing sloc is 34
    Also checked the stock requirement list and the requirement is 2 pc as of now.
    Data from config.
    1 Shipping point- Pick pack time / load time --route dependent
    2. Pick pack time/load time is 0 in route
    3. Transportation lead time is 0
    4. Transit time is 1 day
    5. Planned delivery time is 3 days
    6. GR processing time is 1 day.
    PO creation date is 5 april 2011
    As per the concept I know the below calculation should happen to find out the delivery date.
    Assumption: Commited date = material availability date
    material avalibility date(5 april 2011 should come but i dont know how 6 april is coming) + transprotation lead time (0 day) + loading time (0)+ good issue(5 april)+ transit time(1 day) + Planned delivery time (3 days)
    Delivery date should come as = 9 april but in system its coming as 8 april
    some checking rule is also assigned to material in mrp3 view

    Hi,
    The delivery date is the date on which we receive goods.The process of delivery date determination is in the moment you enter a material number and hit enter, SAP moves the current date into the delivery date, and depending on planned delivery time of material master it add those days to the current date. If the data entered is sufficient to determine already the info record, then it takes the planned delivery time from there into consideration. Thanking you.

Maybe you are looking for

  • How to deal with  this type of flash warning

    I develop a ocx for playing flash on web .Then I also place a swf that has encrypted on web,before it can be played it must retrive the need information form ocx for decoding.But when I play the swf on web,it will warning that Adobe Flash Player has

  • Necessary to "Update" old illustrator files?

    I have tons of files created in old illustrator 6.0 and now that I have a newer version of illustrator, specifically CS2, loaded on Mac OS X it's calling all of my illustrator files "Text Files." It says, "This file contains text that was created in

  • SAP WM Preallocated Stock Not bypassing GR and Putaway in GI Area

    Hi, I have maintained the following to bypass the put away into GI Area in ECC 6.0 1. Preallocated Stock maintained for the material in the Preallocated stock Table V_T310 using LT51. 2. Movement type 101 is set to consider the preallocated stock. I

  • Cost assignment search help not working

    Hi, I have looked in to the SD thread already, but none of the notes seems to be of interest as we are on support package of the notes!. Here is the problem, when trying to select cost assigment values, cost center and GL account search helps/f4 func

  • Edit the  results list in  sql developer 1.5

    Hi is there someone that know if it is possible to make a querry in sql developer and then edit in the results list? I have tryed but can not se how. In my company we are using both toad 9.7 and sql developer and the users would like to update the da