Display the PO in the capacity leveling

Hi,
in the capacity leveling CM21 there is a table section.
In the table section I get Production order and planned order.
I just want to display the production order in this sections or in the oders pools.
How can I customize the system.
Thanks
Dede

Hi
Use CM25 and the selection profile you can select order.
Thanks
S.Murali

Similar Messages

  • Capacity leveling - Priority logic

    Can anyone explain the logic of SNP Capacity leveling order prioritization when set with ‘No priority’?
    I have tested this with ‘No priority’, but the system is applying priority by ‘order size’ on the net demand in a bucket (considering demands not fulfilled in backward propagation).

    My question is about the capacity leveling profile that you define in SPRO / main menu / during leveling in planning book. In the profile, we can define one of the following for priority
    - No priority
    - By order size
    - By product priority (from product master field in SNP2 tab)
    My question is related to the first option of 'No priority'. When using that option 1, system behaves as if option 2 (Order size) is chosen. I want to know the standard logic that should be applied by the system.

  • Capacity Leveling Problem

    If I have an order that requires 85 hours of production, and the work center responsible only has available capacity of 14 hours per day, how can I divide up the order in a Capacity Leveling Planning Table (CM22)? When I dispatch the order, it automatically overloads the work center instead of spreading itself out over several days. When I created the production order I gave it a start date 2 weeks away from the finish date. Yet in capacity leveling, when I dispatch the order, it only goes to one day and overloads the work center by several hundred percent?
    Basically, how can I take this single order and divide it up over 7 days in Capacity Planning?

    In both the "strategy" box of CM22 and the "capacity" tab of CR02, I have made sure that the relevant boxes for finite scheduling were checked.  However, the system still overloads the work centers.  This would mean that there is a 'finite' capacity in each work center and that each center cannot be overloaded, but my work centers still load themselves to nearly 1000% capacity!  Why is this?  How can I make sure that when a work center reaches capacity, it's quantities flow into the next available slot?  
    How can I spread the requirements over a period of several dates and not just one?
    Edited by: Cameron on Sep 21, 2009 3:08 PM

  • Capacity leveling profile

    Hello ,
    When the t/c cm21 or cm22  is excecuted , which 'overall profile' does the system select ?
    Where do we define this.
    Regards
    ShankarR

    Hi,
    T,code:OPDQ,OPDE,
    Most of the settings are under "'capacity levelling and extended evaluation'" in SPRO
    Hope it helps
    THNX
    HKR

  • Resource scope when performing capacity leveling with Optimization method

    Hello,
    Can anyone tell me if, when performing the Optimization method in Capacity Leveling for transportation resources production resources are validated? I am currently testing this and I found out that if the capacity variant of the production resource is no 00, 01 or 02 the system will give an error message when trying to level a transportation resource, the message indicates that there is no available capacity for the production resource.
    When reading documentation in help.sap it appears to me that Capacity Leveling should only focus on the resource to be level not in other resources and in this case my transportation resource has available capacity that shouldn't be affected for master data errors of production resources...
    Could somebody help me clarify this issue?, I have already open a message and they suggested me to change the capacity variant of the production resource, evidently when I do this everything works but I still don't understand why capacity leveling, with Optimization method, of a transportation resources is checking on production resources.
    Thanks!
    Erika

    Hello Ian,
    I am not talking about the SNP Optimization Run that is certainly manipulated by the constraints that you update on the optimization profile; in this case "Capacity Leveling with Optimization Method" the constraints are automatically set by the system and what I need to know is if these constraints are considering not only the resource that is to be leveled (in this case the transportation resource) but also the production resource.
    Sorry but your answer does not correspond to my request, because you are talking about the Planning Optimization run and I am talking about  "Capacity Leveling with Optimization Method".
    Erika

  • Reg. Capacity levelling for the maintenance order

    Hi all,
    I am using SAP R3 ECC6.0.
    I have created a maintenance order with order type PM01(Internal).In this order i have assigned Work Center 1 with the Work center category as Labour.And i have assigned 2 operations for this Work center in the maintenance order with the total hours of 60 HRS. and i saved this order & made the status to release.
    Then i went to Tcode CM33 and there i inputed the Work center name and executed it.It opens a Graphical View.But in that view my order no is not displayed .Previous order no. which is there already for that Work center is shown there.
    What could be the Reason.
    As an alternate checking i went to T code CM31 order view.There i Inputed my order no. and executed it but it throws a message
    "No Capacity requirements were found in the evaluation period"
    "No work centers or orders were found"
    What could be the reason.
    Tell me how to overcome this issue.
    More over i want to make dispatch in the capacity levelling.
    Thanks in advance,
    M.Badrinarain.

    hi badri,
    are you checking in the same period ? and next check ur overall profile and time profile assigned to ur overall profile .... u will find order no , operation no .... and once u dispatch operation status gets DSPT .
    regards
    pushpa

  • Display the totals only at Material level in ALV

    Hi........,
    I am calculating the subtotals and totals. I am having the columns Company Code , Plant and Material etc.
    First I did sort on table as :
    gr_sorts = gr_table->get_sorts( ).
      gr_sorts->add_sort( columnname = 'C_CODE' subtotal = abap_true ).
      gr_sorts->add_sort( columnname = 'WERKS-WERKS' subtotal = abap_true ).
      gr_sorts->add_sort( columnname = 'MATNR' subtotal = abap_true ).
    After that I am doing the aggregation like this :
    gr_agg = gr_table->get_aggregations( ).
      gr_agg->add_aggregation( 'QUANTITY' ).
      gr_agg->add_aggregation( 'QUANTITY1' ).
      gr_agg->add_aggregation( 'DELTA' ).
    It is displaying the totals and subtotals at each Company code , Plant and Material level.
    But I want to display the totals only at Material level.
    Guide me on the same.
    Reply me as early as possible.
    Thanx,
    Jay
    Edited by: Alvaro Tejada Galindo on Feb 14, 2008 11:08 AM

    Replace your code for sorting
    gr_sorts = gr_table->get_sorts( ).
    gr_sorts->add_sort( columnname = 'C_CODE' subtotal = abap_true ).
    gr_sorts->add_sort( columnname = 'WERKS-WERKS' subtotal = abap_true ).
    gr_sorts->add_sort( columnname = 'MATNR' subtotal = abap_true ).
    with the code given below.
    gr_sorts = gr_table->get_sorts( ).
    gr_sorts->add_sort( columnname = 'C_CODE' subtotal = abap_false ).
    gr_sorts->add_sort( columnname = 'WERKS-WERKS' subtotal = abap_false ).
    gr_sorts->add_sort( columnname = 'MATNR' subtotal = abap_true ).
    Hope this helps. Reward points if helpful.
    Thanks,
    Balaji

  • Running latest Audition CC on Yosemite.  Audio track is displaying, I can see the levels as I scrub but NO sound to headphones. WHY?

    Hi,
    I am Running latest Audition CC on a 2009 MacPro running the latest Yosemite.   I can see that  the audio Audio track is displaying, I can see the level rise and fall as I scrub but I can hear NO sound to headphones. WHY?
    I have checked the MacPro's system preferences and clicked through the Audition settings but I can't see where the output to device ( headphones) might be muted.  What am I missing?
    Thanks

    TexasPengr wrote:
    The signal level input registers on system preferences>sound>input source, but no matter what I do, I can't get Garage Band to recognize a signal input.
    set it in GB:
    http://www.bulletsandbones.com/GB/GBFAQ.html#selectinterface
    (Let the page FULLY load. The link to your answer is at the top of your screen)

  • IPone 6, iOs 8.1.2 when removing the phone from the charging does not reflect the increase in the percent charge level , by reconnecting displays correctly

    when removing the phone from the charging does not reflect the increase in the percent charge level , by reconnecting displays correctly

    Addendum
    Last night charging for around 3-4 hours only charged a dead phone by 55% then left it to charge overnight
    Today the battery dropped from 6:15 am full charge to 53% at 10:38 am at time of writing this with
    1 phone call out for 30 secs
    1 incoming missed call,
    Whatsapp fetched around 10 msgs
    Email fetched around 20 ermail from 4 accounts but not viewed yet on phone

  • CRM :B2B: Want to display Message in the Order Basket: at Item Level

    Hi all
      I wanted to add some Message for every Product(item) being added into the Order Basket of the B2B (E-Commerce) application.
    Hopefully i found a Badi at the ABAP Layer (CRM_ISA_BASKET_ITEMS) and implemented the interface CHANGEITEMS_BEFORE_IL(code added to display a sample text).
    I am successful in adding TExt at the Top of the Basket. But my requirement is to add the Text for every Product present in the Basket !!!!!
    Any Help please !!!!! 
    Many Thanks
    KK
    Message was edited by: KK

    Hi
      Go to COMM_PCAT_ADM.Select Catalog type Both and choose details screen.Select S5 Text determination procedure for items.
      SPRO>CRM>BASIC FUNCTIONS>TEXT MANAGEMENT>DEFINE TEXT DETERMINATION PROCEDURE>SELECT THE ROW WITH A TEXT OBJECT>PCAT_CTY>DIALOG STRUCTURE CALL UP THE PROCEDURE AREA.Select the row with text determination procedure s5 ,In the dialog strurcture ,call up the definiton of procedure area.Select text type.
    I hope it helps

  • How to display DVD timecode to the frame level?

    I know you can advance frame by frame with (assumes DVD
    object is called "mydvd")
    member("mydvd").frameStep(1)
    but.......how do see what frame you see the frames in the DVD
    controller object?
    The DVD object only shows to the nearest sec it seems. Can I
    change this or make a text field that will do it?
    When doing trace (member("mydvd").currentTime), the command
    only shows to the nearest sec. (even though it has the "00" and the
    end for frames.....example 115 sec. = 11500
    I tried this for a custom text field:
    member("mytextfield").text = "" &
    member("mydvd").currentTime
    but this does not work ....it gives an error I was kind of
    expecting to see at least the results of a trace command
    It is strange that you can control a DVD frame by frame by
    not view the frame you are actually on...there has to be a way
    right?
    any help would be great!!!
    thanks

    Anybody have any ideas on this?
    I was thinking that if I could get below to work:
    member("mytextfield").text = "" &
    member("mydvd").currentTime
    then I could create a button that would step a frame and
    would make the text result, (text result + 1) to show a somewhat
    more accurate timecode as I click.
    However this could be off as much as 29 frames if the
    playhead was at 04 sec 29 frames and it reported back 04 sec. as I
    believe it does (at least for reporting back timecode)
    any ideas on you to read the DVD timecode and place into a
    text field....wish I could just add frames feature to the DVD
    control component.
    Kyle

  • Work schedule display in capacity leveling cm25

    Hello,
    In our company we have created a work schedule (tcode OP4A) and have associated to a work center (tcode IR02).
    However, capacity leveling (tcode CM25) doesn't display the work schedule associated to our workers in the graphical planning table.
    Do you have any idea how to solve this problem?
    Thank you very much,
    Óscar

    It could be issue with your over all profile..
    Use - Over all profile SAPPM_G001  
    Overall prof: SAPPM_G001           PM: Ind.cap/tab/day/avail.lab./norm.schd
           Select.profile:                     SAPPM_S001      PM: Tab/work center/lab/
           Control profile:                    SAPPM_C004      PM: Capacity planning table individual
           Time prof:                          SAPPM_Z0T1      PM: Tab. short-term (1 month)
           Evaluation prof.:                   SAPPM_A001      PM: Plant maintenance
           Strategy prof.:                     SAPPM_T002      Lead time sched. backwards
           Capacity planning table (tab.form): SAPPM_R001      PM: Plant maintenance/Individual caps.
    Note: Don't modify the Standard profile .

  • EPM 2013 Report is displayed as cut off and shows less than half the width of the report in IE 10 and IE 9.

    EPM 2013 Report is displayed as cut off and shows less than half the width of the report in IE 10 and IE 9.  This issue occurs for some users only.I tried the same url in google chrome and is working fine.
    Can you please help.
    Please find the attached screenshot.

    Hi BJ1986,
    According to your description, I think this issue is caused by the IE browser that runs the report. To trouble shoot this issue, I suggest that we can try to clear internet temporary files, cookies and others in IE browser. And also add this site
    as a trusted site in IE browser to check this issue again.
    If this issue is still existed, it can also be occurred due to the setting or third party add-ons of Internet Explorer (IE). In this scenario, you can try to run IE in compatibility mode to check the issue again. Or I suggest that you can refer to the
    steps below to troubleshoot the issue:
    Click Tools -> Internet options.
    Switch to the Security tab, click Local intranet, and then select Default level.
    Switch to the Advanced tab, and click Restore advanced settings.
    Temporarily disable third party add-ons. For detailed steps, please see the link below: 
    http://windows.microsoft.com/en-IN/internet-explorer/manage-add-ons#ie
    Hope this helps.
    Thanks,
    Katherine Xiong
    Katherine Xiong
    TechNet Community Support

  • REQ: Add 'Fit-width' or 'Fit-visible' view mode, in which the zoom level is automatically set based on the width of the _current_ page.

    Currently, the default zoom level when viewing a page of a PDF file is automatically calculated based on the width of the "widest" page of the document. This means that, if the document contains one page that is wider than the others or is in landscape orientation, then the default zoom, when viewing all the other narrower pages, is set in a way so that the page does not use the full width of the screen. This results in very poor experience, because the zoom level and the visible area of the page have to be constantly adjusted for each page. The latest update (at the time of writing) has added some extra view modes, but not the much needed 'Fit width' or 'Fit visible'.
    Personally, I can find no reason valid enough to justify the lack of such a view mode. Automatically setting the zoom level based on the width of the current page so as to take advantage of the full width of the screen should be a must have feature for mobile devices, if not the default behavior. The current default behavior regarding the zoom level is pretty much useless, even on 8"/10" screens. There should be a view mode in which the full width of the screen is always used to display the document.
    Examples of documents for which the Adobe Reader for Android provides a poor reading experience are:
    documents which contain some of their pages in landscape orientation.
    publications which, apart from the main content, also contain the full front and back cover in a single page (usually first page which is much wider than the content pages) or any other extra pages like cards or application forms (that are meant to be printed) which usually use an A4/Letter page size etc.
    documents which have been cropped by external utilities or scripts so as to eliminate unneeded white margins (in some cases not all pages have the same width).
    Please consider fixing the default behavior in future releases of the Reader for Android or add a 'Fit width' or 'Fit visible' view mode.
    Thank you in advance.
    Message was edited by: George Notaras
    Improved descriptions of example documents.

    To add to this, if you prefer you can separate your JavaScript from your JSF pages.
    Add a folder (I named mine 'js') to your application's ViewController project's public_html folder.
    Via JDeveloper, create a new JavaScript file inside your newly created folder and place your JavaScript functions inside it.
    You can then 'load' the .js file using the method Shantala described, with the addition of an added 'source' property to the af:reference tag.
    (This can also be a URI reference to a JavaScript file hosted on a web server)
    <f:facet name="metaContainer">
      <af:resource source="/js/myJsFile.js" type="javascript"/>
    </f:facet>The benefits of this 'split' are cleaner JSF page source and also code-highlighting and formatting within the .js file making finding and fixing bugs in your JavaScript much easier.
    It appears however, that when using <af:resource> to load scripts, once the page has been submitted even once, the JavaScript is no longer available to the page. Which isn't very useful.
    A solution is to use <trh:script>.
    Add xmlns:trh="http://myfaces.apache.org/trinidad/html" to your <jsp:root> tag and install the library.
    then in place of the above code use:
    <f:facet name="metaContainer">
      <trh:script id="script1" source="/js/myJsFile.js"/>
    </f:facet>Now after a page submit the JavaScript still functions.
    Edited by: Matthew Carrigy on 12/08/2009 10:39

  • How to remove the 1st level folder under the main ones at each level

    In the normal mode, either in the Content Areas section or in your Folder Portlet on your page -
    all the sub folders are rendered in blue, and then under each one, its corresponding sub folders are also rendered in smaller font.
    Is there a way to disable this feature, so that one would only see the current folder's children, and then you need to click on a specific child/node/sub folder to see its children and so on.
    I would like to remove this default behavior of displaying the children of all the subfolders while you are in a specific folder.
    regards
    -Ananth Makaram

    In the normal mode, either in the Content Areas section or in your Folder Portlet on your page -
    all the sub folders are rendered in blue, and then under each one, its corresponding sub folders are also rendered in smaller font.
    Is there a way to disable this feature, so that one would only see the current folder's children, and then you need to click on a specific child/node/sub folder to see its children and so on.Yes. In 309, this setting is configured through the style attached to the folder. Edit the style,
    go the layout tab, select the "Sub Folder" region and set the folder level display setting.
    By default, it is set to "2".