Does material status control MRP running?

Hi experts
May I just check if material status could conrol the MRP running?  LIke we setup some parts as Y0- obsolete. but we found it still could generate Pr or Plan order....
So does material status control the MRP running? Could we let obsolete part not run by MRP?
Thanks
Alice

Hi,
In addition to Mr.Brahmankar mentioned ways, you can exclude material from MRP run by selecting Procurement Type as No Procurement in MRP-2 View in Material Master.
Also you can select X-plant / Plant specific Material status as :
01     Blocked for procment/whse to block materila from MRP run.
Hope this helps.
Revert if any doubt.
Regards,
Tejas

Similar Messages

  • Material Status Control

    Hi All
    I create a new transaction type in inventory and Check Status Control to enable material status control for this transaction type. but it is not apper on Material Status Control form.also i set the profile option INV: Material Status Support to yes
    cooperation will be greatly appreciated
    Essam

    Hi,
    In addition to Mr.Brahmankar mentioned ways, you can exclude material from MRP run by selecting Procurement Type as No Procurement in MRP-2 View in Material Master.
    Also you can select X-plant / Plant specific Material status as :
    01     Blocked for procment/whse to block materila from MRP run.
    Hope this helps.
    Revert if any doubt.
    Regards,
    Tejas

  • Follow-UP Material Functionality  into MRP Run

    Hi
    i wanted to just know anout the Functionality of Follow up material into MRP run .
    how it would be help in case of MRP run , if i will use Follow-up Material.
    Rgds
    Pankaj Agarwal

    Hi
    i wanted to just know about the Funtinality of Follow up material into Specialy MRP run.
    Whether system will consider the parrallal Material Stock and Open PO if we are considering the
    A (1 nos) FG is having X (1 nos) Material  is current part and Y is followup material for the Same with Indicator 1.
    Suppose X-200 nos and Y -700 nos (Open PO also 200 nos)
    then after MRP run suppose for A  FG requirment is 1500 than is system will consider the Y-700 + Y-200(Open PO) and give the PR for X is only 400.
    Regards
    Pankaj Agarwal

  • Purchase order status in MRP run

    Hi Gurus,
    I have a doubt in MRP run.
    While doing the MRP run, can there be any open PO s or is it mandatory to close them.
    Can you also please suggest me on how to run the MRP.

    Hi,
    MRP Run
    Purpose
    The Material Requirements Planning (MRP) function enables you to plan material requirements for complex manufacturing processes. You use the MRP Wizard to create and run MRP scenarios. The MRP Wizard generates recommendations for the production and purchasing orders required to produce the final product on time and in the required quantity. You then use these recommendations to create production and purchase orders in the Order Recommendation Report.
    The order recommendation cannot be issued for requirements that happened in the past (before the present day). Since the purchasing or production process cannot be completed in time, the MRP does not mix the real past data with new recommendations for the same period.
    Prerequisites
    ●     You have defined the
    ○     Planning system
    ○     Procurement method
    ○     Order mutliple
    ○     Minimum order
    ○     Lead time
    See also: Item Master Data, Planning Data Tab.
    ●     You have set the time interval between orders. See also: Define Inventory Cycles.
    ●     You have defined the appropriate items as non-production bills of materials (if required). See  also: Item Master Data, General Tab.
    ●     You have defined default warehouses. See also: Define Warehouses.
    ●     You have defined forecasts. See also: Forecasts.
    ●     You have selected the Consume Forecast option to make the system exclude existing sales orders from the forecast. If this is not selected, the forecast considers existing sales orders as an additional requirement. See also: Sales Order.
    ●     You have set the planning definitions. If you chose Consume Forecast, you have defined the consumption method, days forward and days backward. See also: General Settings, Inventory Tab.
    Process Flow
           1.      Start the MRP Wizard.
           2.      Create a new MRP scenario or select an existing one. (See also: MRP Wizard: Select New or Existing Scenario.)
           3.      Define the parameters for your scenario, such as the planning horizon and item details.
    You also choose your display preferences. (See also: MRP Wizard: Scenario Details.)
           4.      Define the data sources for requirements that you want to include in your MRP scenario.
    For example, you define whether you want to consider the existing stock or the minimum stock level. You can also include a predefined forecast. (See also: MRP Wizard: Data Source.)
           5.      Save the scenario or run it.
    After you run the scenario, the system displays the MRP Results.
    If there are red figures in the result table, solve the problem and re-run the MRP.
           6.      Analyze the MRP results. You can display the final stock quantity before the MRP run or after it.
           7.      Save the recommendations and exit the MRP Wizard.
    Result
    After completing the MRP Wizard, you still need to create the purchase and production orders in accordance with the MRP recommendations. See also: Order Recommendation Report.
    Hope this will help.
    Reward Point if helpful
    Thanks,
    Raja

  • "Generic" material master in MRP run

    Hi
    Our business users want to use MRP to manage the stock of materials such as circuit breakers. There are however many manufacturers/types and while a certain specification is required, they would be happy to purchase from a variety of suppliers whose products could be different from one another.
    Would it be possible to use MRP to do this, and how could that be achieved?
    The process envisaged would be something like this:
    Material number xxxxx with MRP settings defined; stock falls beyond prescribed level.
    System must generate requisition indicating requirement for circuit breaker in general
    Procurement must get quotations from variety of suppliers (as per tender and procurement policy) based on minimum specification.
    Quotations received must be evaluated and based on price/quality, the supplier selected and order placed.
    Item must be received against specific material number yyyyy for that supplier's circuit breaker.
    Any suggestions much appreciated.
    thanks and regards, Lara

    you can only receive an item which is specified in the purchase order.
    if the purchase order has XXXX then you cannot receive YYYY, you have to receive XXXX and then either use a 309 movement to get it to YYYY, or even better using a production order to make YYYY from XXXX.
    Further if you plan XXXX and procure YYYY, then this order does not reduce the requirement for XXXX, and the next MRP run will give you again a requisition for XXXX.

  • Secondary packing material procurement through MRP Run

    Hi
    Is it possible to procure Secondary packing material through MRP Run. Material type of Secondary packing material is VERP. In MRP view we defined MRP type as VB and reorder point also set.

    Hi
    the MRP run would create a procurement proposal if the stock has fallen below the re-order point. The procurement proposal needs to be a purchase requisition if procurement should start immediately (see Creation indicators for the MRP group). Further, you need to set the "automatic purchase order" indicator both on the material (purchasing view) and on the vendor. In the MRP run, the system also needs to be able to assign a vendor (i.e. through a source list). Then a purchase requisition is automatically converted into a purchase order on creation.
    Good luck
    Eivind

  • Issue with BOM Status in MRP Run

    Dear All,
    I have a BOM structure and BOM status as attached below.
    In this case, system is generating the PR's for all three components correctly while i run MRP (MD51). But when i convert planned order to production order for "Assembly" & "BOM", it is coping the components for Assembly correctly but not for "BOM".
    If i maintain the BOM status as "4" for "BOM", then the components are copied into Production Order but i am getting double PR's as the BOM is exploding two times.
    As per my requirement BOM should be exploded only one time ie. for "Assembly" and component should be come in Planned order for "BOM".
    Please tell me where is the problem..
    Regards,
    Rao

    Dear Rao,
    assembly and Bom have the same type of production order?
    In the production order type which application is contained? PP01?
    You should check the explosion setting in the profile order and the setting of application of the Bom.
    if you can send me screen shot of the planned order of the Bom (components details).
    Thanks
    Daniele 

  • How MRP Run exclude QI Stock Type of a Raw Material SLOC?

    Dear all
    Fact:
    All of our raw materials must be subject to quarantinee upon GR. We have Storage Location of Raw Material: RMSL
    In Material Master of that Raw Material
    We are using the "SLOC of EP" (MRP View 2) to put the defaulted GR SLOC. And we also make use of the "Post to QI Stock" in View: Purchasing.
    Upon GR:
    During GR, the Raw Mat SLOC (RMSL) will be copied from "SLOC of EP" of the material master data, and it will be posted to the stock type "QI STOCK".
    Problem:
    However, when the MRP Controller run MRP, it will take the QI Stock Type of Raw Material SLOC into account.
    Is there anyway we can exclude the QI Stock Type of Raw Material SLOC from MRP Run?
    I have read from some threads to suggest to post it to the Quarantinee SLOC. We prefer not to create another Quarantinee SLOC (QISL) which will be filled in SLOC of EP and then after passing QC, we perform Transfer Posting from SLOC: QISL to SLOC: RMSL. We have a few Raw Material SLOCS and we do not want the Warehouse guy to get confused which Raw MAterial SLOC to choose upon GR. Rather, we prefer it to be defaulted in the "SLOC of EP" in the material master.
    Please advise.
    Edited by: Daimos on Jul 13, 2009 1:16 PM

    Hi,
    Generally MRP consider stock from all the storage location when run the MRP for Plant level for material.
    However we can exclude the particular storage location from MRP Run, for those following settings to be done.
    Go to MRP-2 View of material master and select the storage location to be excluded from MRP. (Press Shift +f1 ex .sloc2) As per your case it should be RMSL
    In that MRP view go to Storage location MRP Tab.
    And assign u201CSLoc MRP indicator = 1 (Storage location stock excluded from MRP)u201Dand save.
    Now run the MRP, stock from sloc2 will not be considered to create-planned order.
    Please try this and revert back.
    Cheers,
    Kumar.S

  • MRP Run - Planning file entry Issue

    Dear All,
    We are facing one problem in MRP Run. We run MRP in the background for a plant (MDBT) System is not creating planned order for few component. I have checked all relevant setting. I found that planning file entry is missing. I would like to know that how system can miss the material? How system creates & delete planning file entry ? I have some data related to this.
    Last MRP run date is 22-04-09
    PIR changed date on 30-04-09
    MDRE Run on the 30-.4-09 at night.
    MRP Run on 02-05-09 at night.
    Problem reported that no planned order for the material on 07-05-09.
    We have huge number of material so its difficult to check all material individually whether MRP run happend or not ?
    Please let me know the possible reason for this.
    Thanks & Regards
    Kundan Kumar

    Dear,
    If you carte materaial or uplod materail before activation plant for MRP this may be the cause for this.
    Planning File creates all the materials relevant for the planning run.
    The planning run and the scope of the planning run (which materials are planned in which planning run) are controlled by the planning file.
    For planning file entry use the following transactions,
    MD20 : Create planning file entry
    MD21 : Display planning file entry
    MDAB : Set up planning file entry in background
    MDRE : Check planning file entry Please run this in it will solve your problem
    All materials assigned with MRP are automatically entered in planning file entry.
    Depends on changes in material planning or in proposal , system will create planning file entry.
    When MRP run system will consider only which materials having entry in above contents of planning file entry. After MRP run system delete the planning file entry. And again material gone the changes like GI GR on any other demand  then system generate planning file enty again.
    Hope it will help you to understand basic concept.
    Regards,
    R.Brahmankar

  • How to restrict RESCHEDULING after MRP run ?

    Dear All,
    We r using prodn. strategy 30. We don't take MRP run for finished material. First we create production orders for finished material & then we take MRP run to create planned orders for semifinished material.
    After MRP run , production orders of semifinished material of previous month gets rescheduled . How to avoid this ?
    We created production orders of NOV2007.
    When we take MRP run today i.e. SEPT2007  to create planned/prodn orders of OCT2007 m/c shop plan. It shows wrong results. It is not giving right requirement for blanks .
    PL' answer.

    Hi,
    In OPPQ/OPPR increase the tolerance value to a high value.
    The system compares this value with the ( order finish date - reqmts date) and if it is greater the system do reschedules.
    Ex tolerance value -
    2
          diff bet ( order finish date - reqmts date )  -
    5
         the system reschedules.
        so increase the tolerance value to 5 and see the results. The system does not
        reschedules.
    OR in OPPQ disable the indicator for production order
    Regards,
    nandha

  • Multiple planned orders in MRP run

    Hi All
    I have a requirement where I need to create multiple planned order for the same material during MRP run. I understand that once I run MRP a planned order creates. If I run again for the same material, the quantity will be changed for the same planned order. Do we have any configuration so that system creates multiple planned orders for same material for each MRP run.

    Hi Adithya
    Planned orders may be changed by MRP until they are firmed. Therefore, what you need to do is to firm the planned orders after the MRP execution.
    You can use for example, transaction MD19 to mass firm planned orders after each MRP run.
    Otherwise, you can user BAdI MD_PLDORD_CHANGE to automatically firm the planned orders created by MRP.
    BR
    Caetano

  • DURING MRP RUN MATERIAL IN QI STATUS HOW TO GET MATERIAL OUT OF QI

    HELLO EXPERTS:
    DURING EVERY 24 HOUR MRP RUN 1 OR 2 MATERIALS SHOWS AS BEING IN QI STATUS WHEN IN RESTRICTED STOCK..... MY UNDERSTANDING IS MATERIAL IN RESTRICTED STOCK IS NOT IN QI.....CAN YOU EXPLAIN WHY

    Dear in SAP generally there are 3 stock statuses are in use most of the time they are Unrestricted,Blocked and QI stock.
    When you have activated any inspection setup in MM QM view based on the setup when you do any movement for that material it will create an inspection lot with stock posting to QI,based on your results you can send that QI stock to unrestricted or blocked through Usage Decision(QA11).
    Now during MRP run if you don't want to consider the QI stock for net requirement calculation check this badi as in standard SAP You would be able to define only the following stock types not available for MRP run.
    1. Stock In Transit
    2. Blocked Stock
    3. Restricted Use stock.
    This you need to configure in OPPQ transaction in the available stock section for the plant.
    So in standard it is not possible to restrict QI stock from not considering as available stock, if required you need to look for Implementing BADI "MD_CHANGE_MRP_DATA ", please check with your technical consultant(Abaper).
    Cheers
    KK

  • Vendor not assigned to PR when doing a MRP run

    I am doing an MRP run for creating purchase requistions
    However the vendor is not getting assigned to the PR.
    I have the vendor defined in the source list (made it fixed) and also created info record.
    However when i run the MRP the PR is created but the vendor is not assigned to the PR.
    Also how can create the PO automatically from the MRP ?
    Also where can i see the time frame setting for Processing PR to PO?
    Thanks

    Dears,
    I'm faced to the same kind of problem...
    The process is an inter-company PR.
    The MRP of our plant creates PR for the other plant, these PR are type "MFS" (because of customizing with the tcode OPPR, in order to manage MRP group in the material sheet MRP1)
    We have maintained the info-record and the source list, and the extra-purchasing view of the vendor (the plant we send the PR).
    When we launch the MRP, the systems creates the PR and we get them in the dynamical status of stock (tcode MD04). In this list, the vendor well appears on the rigth of the screen. So, it seems that the source list is well managed
    BUT, when we have a look into the PR (tcode ME53N), the vendor doesn't appear in the source list sheet. :-((
    Please, tell me what could be the reason of this stange fact ? (the field is not invisble customized...)
    FYI, we get the same result with material without MRP group, and PR type NB
    Thanks for your support,
    BR,
    Tony

  • Consideration of stock of discontinued FG or trading material during MRP Run

    There is an functionality of follow up material for component. I would like to know if there is any similar option available for finished goods or trading materials.
    I am doing procurement planning for externally procured Trading materials. Now my previous material A is being replaced by material B. Therefore all the planned independent requirement is available in system only for B. But still there is some stock available for material A. How can it be considered during MRP run for material B.
    Example,
    Material A:
    On Hand Stock = 100
    Planned Independent Req. = 0
    Material B:
    On Hand Stock = 300
    Planned Independent Req. = 1000
    In this case if we run MRP for material B, how we ask system to plan Purchase Requisitions for 600 instead of 700 for material B, considering stock of material A.

    Hello
    Please refer to the following SAP note:
    43636 - Discontinued parts
    This note provides a detailed explanation of the system standard design of the usage of discontinued parts with material requiremenst planning and the most common questions about this issue.
    The following information is provided on this note regarding the PIRs:
    2. Planned independent requirements and forecast requirements are not redirected.
                  Explanation: Planned independent requirements after the effective-out date are not redirected but are provided with an exception message in the MRP list stating that they cannot be included in the availability check. Planned independent requirements and forecast requirements are therefore displayed in the MRP list and in the stock/requirements list. However, they do not influence planning
    BR
    Caetano

  • MRP Run with User Exit key for Follow up material

    Dear Gurus,
    I want to run MRP only for followup materials by using User exit key. For example i have a material X(with discontinued Indicator as 1) and it's follow material is Y.
    So we have a user exit key as ZFL, with coding as shown below. Now when i run MD01 with user exit key ZFL and parametre as 1, it only runs MRP for material X and not for material Y. What else we need to do so that when i run MD01 with user exit key ZFL, it shoudl consider both X and Y. 
    WHEN 'ZFL'.
    DATA : BEGIN OF ITAB5 OCCURS 0,
    KZAUS LIKE MT61D-KZAUS,
    END OF ITAB5.
    TRANSLATE USER_PAR TO UPPER CASE.
    SPLIT USER_PAR AT ',' INTO TABLE ITAB5.
    IF ITAB5[] IS INITIAL.
    EXIT.
    ENDIF.
    CLEAR: NO_PLANNING, STOP_PLANNING.
    READ TABLE ITAB5 WITH KEY KZAUS = MT61D-KZAUS.
    IF SY-SUBRC <> 0.
    NO_PLANNING = 'X'.
    ENDIF. 

    Hi Kumar,
         You can use either MRP Type, MRP Controller, MRP Group in this user exit to control the MRP run. For these set of Materials you have to assign any of same value or at least differentiate these material from other material. Then only you can control the MRP by using this user exit even though if you use different MRP Group and MRP Controller. In User Exit, you may have to add your dependent material's MRP Group/MRP Controller. Make sure that these set of materials are different than all other materials.
    If you don't have any plan to run MRP for other materials then as per Ajit suggestion you make that material's MRP type as "ND". But, in your business case they may want to activate the MRP for all the material not now but may be latter.
    Thanks